Page 1: Project Case Study

3/12/2014

Boxes Manufacture Project Case Study

Planning Engineer Website HTTP://WWW.PLANNINGENGINEER.NET/

Page 2: Project Case Study

Page 1 of 20

Table of Contents

1) Table of figures ........................................................................................................................ 3

2) Introduction ............................................................................................................................. 4

A) Project background ............................................................................................................. 4

i) Requirements Analysis: ................................................................................................... 4

ii) Design and concept: ........................................................................................................ 4

iii) Plan the project: .............................................................................................................. 4

iv) Materials procurements: ................................................................................................. 4

v) Boxes production: ............................................................................................................ 4

vi) Boxes assembly: .............................................................................................................. 4

B) Planning concept and software ........................................................................................... 4

i) Planning concept ............................................................................................................. 4

ii) External resources and software ..................................................................................... 4

3) Project scope statement.......................................................................................................... 5

A) Define project scope ............................................................................................................ 5

B) Project assumptions and constraints .................................................................................. 5

i) Quality ............................................................................................................................. 5

ii) Resources ........................................................................................................................ 5

iii) Scope ............................................................................................................................... 5

iv) Time ................................................................................................................................. 5

4) Work Breakdown Structure WBS ............................................................................................ 6

A) Decomposition .................................................................................................................... 6

B) WBS ..................................................................................................................................... 6

5) Project schedule ...................................................................................................................... 7

A) Define project activities ....................................................................................................... 7

B) Estimate activities duration ................................................................................................. 8

C) Schedule activities ............................................................................................................... 8

i) Sequence activities .......................................................................................................... 8

ii) Project Original Bar chart ................................................................................................ 9

iii) Project Revised Bar Chart: ............................................................................................. 10

6) Resource management plan .................................................................................................. 10

A) Types of resources ............................................................................................................. 10

B) Quantities of each type of resource .................................................................................. 11

Page 3: Project Case Study

Page 2 of 20

C) Project organization chart ................................................................................................. 12

D) Project resource histogram ............................................................................................... 12

i) Primavera resource histogram ...................................................................................... 12

ii) Microsoft Excel resource histogram .............................................................................. 13

iii) Microsoft Excel revised resource histogram ................................................................. 13

7) Cost estimates ....................................................................................................................... 14

A) Determining Project Budget .............................................................................................. 14

i) Original project budget ................................................................................................. 14

ii) Revised project budget .................................................................................................. 14

B) Project cash flow ............................................................................................................... 15

i) Original Cash Flow ......................................................................................................... 15

ii) Revised Cash Flow ......................................................................................................... 15

8) Risk management plan .......................................................................................................... 16

A) Identify risks ...................................................................................................................... 16

B) Perform qualitative risk analysis ....................................................................................... 16

C) Perform quantitative risk analysis ..................................................................................... 17

D) Plan risk responses ............................................................................................................ 17

E) Monitor and control risks .................................................................................................. 17

9) Communications plan ............................................................................................................ 18

A) Project Stakeholders.......................................................................................................... 18

B) Communications groups .................................................................................................... 18

C) Communications Information needs ................................................................................. 18

10) Quality plan ....................................................................................................................... 19

A) Plan Quality ....................................................................................................................... 19

B) Quality Assurance .............................................................................................................. 19

C) Quality Control .................................................................................................................. 19

11) Conclusions and recommendations .................................................................................. 19

12) References ......................................................................................................................... 20

Page 4: Project Case Study

Page 3 of 20

1) Table of figures Figure 1(Scope Decomposing) ........................................................................................................ 6

Figure 2(Project WBS) .................................................................................................................... 7

Figure 3(Activity List) ..................................................................................................................... 7

Figure 4(Activity Duration) ............................................................................................................. 8

Figure 5(Activity Sequence)............................................................................................................ 9

Figure 6(Bar Chart) ......................................................................................................................... 9

Figure 7(Revised Bar Chart) ......................................................................................................... 10

Figure 8(Type of Resources) ......................................................................................................... 11

Figure 9(Resources Quantities) ..................................................................................................... 11

Figure 10(Organization Chart) ...................................................................................................... 12

Figure 11(Primavera Resource Histogram) ................................................................................... 12

Figure 12(Excel Resource Histogram) .......................................................................................... 13

Figure 13(Excel Revised Resource Histogram) ............................................................................ 13

Figure 14(Project Budget) ............................................................................................................. 14

Figure 15(Revised Project Budget) ............................................................................................... 14

Figure 16(Project Cash Flow) ....................................................................................................... 15

Figure 17(Project Revised Cash Flow) .......................................................................................... 15

Figure 18(Qualitative Risk Analysis) ............................................................................................ 16

Figure 19(Quantitative Risk Analysis) .......................................................................................... 17

Figure 20(Communications Information) ...................................................................................... 18

Page 5: Project Case Study

Page 4 of 20

2) Introduction

A) Project background Our company Flexible Models (FM) awarded a project for the Research and

Development unit of the Property Development Department of the Government

(PDDG). The project is part of Seismic Zone Residential Construction

Improvement Program, and it is to manufacture and deliver boxes, which used on

a foundation of buildings. In order to deliver the final product, the project will pass

through the following stages:

i) Requirements Analysis:

Interview the project stakeholders and Product detail analysis to define the

project scope of work.

ii) Design and concept:

Perform the project design and execution method statement in order to plan the

project.

iii) Plan the project:

Develop the project plan; scope statement, WBS, schedule, resources, cost,

risks, communication, and quality plans as per the following sections.

iv) Materials procurements:

As per the project management plan, and the design, the materials procurement

should start to provide the materials required to manufacture the boxes.

v) Boxes production:

As per the materials delivery schedule and the project plan, the manufacture

should start to deliver the boxes on time.

vi) Boxes assembly:

As per the production schedule, and the project management plan, the boxes

should be delivered and assembled at the client's site as required.

B) Planning concept and software

i) Planning concept

Project planning concept is as per (Project Management Institute 2008) planning

process groups, tools, and techniques. However, the author used his own

experience to select the best techniques fits the project situation.

ii) External resources and software

The author used Microsoft Excel, and Oracle Primavera to perform the required

calculations and diagrams embedded in the final project document as figures.

Page 6: Project Case Study

Page 5 of 20

3) Project scope statement

A) Define project scope The project scope is to design, manufacture, deliver, and assembly cardboard or

metal sheet boxes, which will be used in the foundation of PDDG program.

B) Project assumptions and constraints This section include the assumptions and the constrains, which considered during

the project planning and execution as per the following:

i) Quality

The size must be 300 x 250 x 200 cm with a slot of 10 x 10 x 25 cm.

The tolerance on outer dimensions must be +/-2 cm.

The tolerance on dimensions of the slot must be 0 to -3 mm in width. In

short, the slot cannot be more than 10 x 10 cm.

It should be made of cardboard or metal sheet.

It should be made of small cubes of dimensions 5 x 5 x 5 cm.

It should be smooth in appearance.

ii) Resources

The following is the Labor rates:

Design department: USD 150 per day

Cutting department: USD 90 per day

Assembly department: USD 150 per day

Note: the given effort of resources is total number of resources to complete the

task not the daily manpower,

The following is the Labor rates:

USD 20 per industrial cardboard sheet

USD 25 per metal sheet

USD 10 per Standard cubes

iii) Scope

The boxes should be delivered and assembled at the client's site

iv) Time

The project completion date was revised because of the risk management.

See section 8-D.

The calendar used on oracle Primavera scheduling tool is standard 5-day

work per week except for task number A1150 “Shipment/Delivery” the

calendar used is 7-day work per week.

Page 7: Project Case Study

Page 6 of 20

4) Work Breakdown Structure WBS

A) Decomposition “Decomposition is a technique for subdividing the project deliverables into

smaller, manageable tasks called work packages” (Sanghera 2010, p97). The

project scope of work decomposed into work packages and groups as per the

following figure-1.

Boxes Project Decomposing

1 Requirements Analysis

1.1 Interview client stakeholders

1.2 Product detail analysis

1.3 Refinement of the final draft

2 Design and Concept

2.1 High level design

2.2 Details with operation designs

3 Production

3.1 Set up

3.2 Cutting and parts development

3.3 Sub-assembly 1

3.4 Sub-assembly 2

3.5 Sub-assembly 3

3.6 Assembly integration

4 Material

4.1 Cardboard sheet

4.1 Metal sheets

4.1 Cubes

5 Delivery

5.1 Pre-delivery

5.2 Shipment/Delivery—delivery takes 2 weeks by sea.

5.3 Implementation

Figure 1(Scope Decomposing)

B) WBS After decomposing the project into work packages, the WBS is created by Oracle

Primavera as per the following figure-2.

Page 8: Project Case Study

Page 7 of 20

Figure 2(Project WBS)

5) Project schedule

A) Define project activities After the creation of the WBS on Oracle Primavera, the activities were populated

under the related WBS as per the following figure-3

Figure 3(Activity List)

Page 9: Project Case Study

Page 8 of 20

B) Estimate activities duration In this process, the duration of each activity will be estimated. Since the “duration

estimate is progressively elaborated” (Project Management Institute., 2013), this

step could be revisited during the schedule activities, resource management, and

risk management to achieve the project deadlines. See figure-4

Figure 4(Activity Duration)

C) Schedule activities

i) Sequence activities

The activities is sequenced in Oracle Primavera by assigning the predecessor and

successor relationships as per figure-5 below.

Note: activity number A1040 “Details with operation designs” has a start-to-start

+ 2 days lag relationship with activity number A1030 “High level design” as per

statement “The task 'Details with operation designs' starts with a 50% overlap with

'High level design'”

Page 10: Project Case Study

Page 9 of 20

Figure 5(Activity Sequence)

ii) Project Original Bar chart

After sequencing the activities, Oracle Primavera represents the bar chart which

identifying the project critical path by the red bars as per figure-6.

Figure 6(Bar Chart)

Page 11: Project Case Study

Page 10 of 20

iii) Project Revised Bar Chart:

Because of the risk response in section 8-D, the project duration was changed to

mitigate the risks. Accordingly, the bar chart was revised as per figure-7

Figure 7(Revised Bar Chart)

6) Resource management plan

A) Types of resources The following figure-8 defines the type of resources associated with each activity

Boxes Project Decomposing Task

Duration

Resource

Type

1 Requirements Analysis

1.1 Interview client stakeholders 4 days Design

1.2 Product detail analysis 6 days Design &

Assembly

1.3 Refinement of the final draft 2 days Design

2 Design and Concept

2.1 High level design 4 days Design

2.2 Details with operation designs 6 days Design

3 Production

3.1 Set up 4 days Assembly

Page 12: Project Case Study

Page 11 of 20

Boxes Project Decomposing Task

Duration

Resource

Type

3.2 Cutting and parts development 3 days Cutting

3.3 Sub-assembly 1 6 days Assembly

3.4 Sub-assembly 2 6 days Assembly

3.5 Sub-assembly 3 4 days Assembly

3.6 Assembly integration 3 days Assembly

4 Material

4.1 Cardboard sheet sheets

4.1 Metal sheets sheets

4.1 Cubes pieces

5 Delivery

5.1 Pre-delivery 2 days

5.2 Shipment/Delivery—delivery takes 2 weeks by sea.

5.3 Implementation 7 days Design &

Assembly Figure 8(Type of Resources)

B) Quantities of each type of resource After defining the type of resources associated with tasks, quantity of each

resource is calculated as per figure-9.

Figure 9(Resources Quantities)

Page 13: Project Case Study

Page 12 of 20

C) Project organization chart Figure-10 represent the project organization chart as mentioned in the case study

Figure 10(Organization Chart)

D) Project resource histogram The author populated the Oracle primavera with the activities resources to

calculate the required work force per week, and then create the resource histogram

using Microsoft Excel for better presentation.

i) Primavera resource histogram

Figure 11(Primavera Resource Histogram)

Page 14: Project Case Study

Page 13 of 20

ii) Microsoft Excel resource histogram

Figure 12(Excel Resource Histogram)

iii) Microsoft Excel revised resource histogram

Because of the risk response in section 8-D, the project duration was changed to

mitigate the risks. Accordingly, the resource histogram was revised as per figure-

13

Figure 13(Excel Revised Resource Histogram)

Page 15: Project Case Study

Page 14 of 20

7) Cost estimates

A) Determining Project Budget

i) Original project budget

The author estimated the cost of each activity, and accordingly the project budget

using Microsoft Excel. The project budget is 36,960 $ as per figure-14

Figure 14(Project Budget)

ii) Revised project budget

Because of the risk response plan in section 8-D, Project budget was revised to

mitigate the risks associated with the project. The revised budget is 37,815 $ as

per figure-15

Figure 15(Revised Project Budget)

Page 16: Project Case Study

Page 15 of 20

B) Project cash flow

i) Original Cash Flow

The author populated the Oracle primavera with the budget cost of each activity

to calculate the weekly cash flow, and then create the cash flow using Microsoft

Excel for better presentation as per figure-16

Figure 16(Project Cash Flow)

ii) Revised Cash Flow

Because of the risk response plan in section 8-D, Project cash flow was revised to

mitigate the risks associated with the project. The revised cash flow is as per

figure-17

Figure 17(Project Revised Cash Flow)

Page 17: Project Case Study

Page 16 of 20

8) Risk management plan

A) Identify risks In order to establish the risk management plan, the project team should identify

the risks as the first stage (Wysocki 2012, p77). Accordingly, project team and the

project manager identified the following risks:

Risk Id R1: The Cutting and parts development task id A1060 required a

very skilled resource to meet the quality requirements.

Risk ID R2: Project materials could be damaged during shipment.

Risk ID R3: change in client requirements after the cutting stage.

B) Perform qualitative risk analysis

Risk R1 has a 0.7 probability and will delays the project by 6 days for every

day of delay in this task, which consider high impact assumed by 0.6.

Risk R2 has a 0.3 probability and 0.3 impact on the task cost.

Risk R3 has assumed probability of 0.5 and has impact on tasks (Set up,

and Cutting and parts development) by 1

The following figure-18 represent the qualitative risk analysis.

Figure 18(Qualitative Risk Analysis)

Page 18: Project Case Study

Page 17 of 20

C) Perform quantitative risk analysis Reference to (Berman 2007) p167 risk assessment, risks above 0.6 high and from

0.4 to 0.6 medium, and below 0.4 low, the qualitative risk analysis ignored the low

risks. The impact of the high and medium risks are calculated as per figure-19

below

Figure 19(Quantitative Risk Analysis)

From the quantitative risk analysis, the project budget increased by 855$, and the

task duration for tasks (Set up, and Cutting and parts development) increased by

2, and 3 days respectively. These changes reflected on the project management

plan.

D) Plan risk responses Because of the quantitative and qualitative risk analysis, the project completion

date, bar chart, resources histogram, budget cost, and cash flow plans were

changed and named “revised”.

E) Monitor and control risks Monitoring and controlling of risks is required to evaluate the risk response against

planned metrics. This process could result a development on the risk plan and

identify new risks during the progress of the project.(Kerzner 2009) p788

Although, risk R2 is low risk, but it should be monitored to avoid its impact. Other

Risks R1 and R3 should be monitored carefully because they have a big effect on

the project if they occurs. Project team should identify any new risks and keep

monitoring the three risks identified.

Page 19: Project Case Study

Page 18 of 20

9) Communications plan

A) Project Stakeholders In addition to the project team identified on the organization chart in section 6-C,

other external stakeholders is identified. Joseph Bukhmann, the chief editor of

Construction Consortium Journal.

B) Communications groups The project consist of three main groups:

FM Company group

Client Group

External stakeholders group.

C) Communications Information needs The following figure-20 represent the communication information between the

stakeholders on the project.

S.N Stakeholder Name Stakeholder

Group Type of information

Sequence of

Communicat

ion

Information

Delivery

Method

1 Roy Benjamin

FM Company

group product design alternate day Email

2 Michael Gartner

FM Company

group

detailed drawings

assembly drawings Weekly

Email & Hard

Copy

3 Philip Cloony

FM Company

group design drawings Weekly

Email & Hard

Copy

4

Jim Stanford

FM Company

group

vendor management,

market analysis,

contracting, and

procuring required

resources

Weekly Email

5

John Morris

FM Company

group

information on the

progress

project management

processes

Daily

Web-based

project tracking

system

Reports, and

Memo's

6

Caroline Smith

FM Company

group budget Weekly

one-on-one

meetings, and

telephone calls

7

Joseph Bukhmann

External

stakeholders

group

Progress, photos, and

project status Monthly

Email & Hard

Copy

8

Paul Lee

Client Group

progress of the

technical design

Progress presentation

Weekly

report

biweekly call

Email

Phone Call

Figure 20(Communications Information)

Page 20: Project Case Study

Page 19 of 20

10) Quality plan

A) Plan Quality The boxes manufacture project has a very tight scope constrains with very limited

tolerances. Therefore, the boxes quality should meet the quality constrains and

tolerances mentioned in section 3-B-i. In addition, a mockup of the boxes to be

manufactured in early stage of the project to perform a quality test, experiment the

manufacture quality procedures and to avoid risks of bad quality in the production

stage.

B) Quality Assurance During the manufacture process, and before proceeding with the second stage of

the manufacture, the first stage should be checked via inspection request and

verified by the QA engineer. This procedure will reduce the probabilities of quality

defects and if any defects discovered during the manufacture will be fixed in early

stage, rather than waiting the assembly stage to find out that there is a problem in

the boxes.

C) Quality Control During the manufacture process, the QA engineer should physically check the

quality of the product and sign inspection request for each stage of the

manufacture.

11) Conclusions and recommendations The boxes manufacture project represent a high value to the FM company

reputation since it is part of well-known program, and followed by the

Construction Consortium Journal chief editor Joseph Bukhmann.

The project quality requirement is very high, and therefore, the quality should be

effectively managed. The risks associated with the project increased the project

budget and duration. Accordingly, all the project management plan components

were revised to accommodate the risk response.

Project communication involves different parties. Therefore, the communication

information log is effective way of informing the stakeholders the required

information, by the time they need to know, and with the preferred communication

method. This communication plan will ensure the information flow, and will keep

all the project stakeholders updated.

The project management plan is a progressively elaborated document. It is

expected to be modified, and updated. Each change or update should be reflected

on the other elements of the project management plan.

Page 21: Project Case Study

Page 20 of 20

12) References

BERMAN, J., 2007. Maximizing project value [electronic book] : defining, managing, and measuring for optimal return / Jeff Berman. New York : Amacom, American Management Association, c2007.

KERZNER, H., 2009. Project management [electronic book] : a systems approach to planning, scheduling, and controlling / Harold Kerzner. Hoboken, NJ : John Wiley & Sons, 2009; 10th ed.

PROJECT MANAGEMENT INSTITUTE, 2008. A guide to the project management body of knowledge (PMBOK guide). 4th edn. Newtown Square, Pa.: Project Management Institute.

PROJECT MANAGEMENT INSTITUTE., 2013. A guide to the project management body of knowledge (PMBOK® guide). Newtown Square, Pennsylvania: Project Management Institute, Inc.

SANGHERA, P., 2010. PMP in depth, second edition : project management professional study guide for the PMP exam / Paul Sanghera. Australia ; Course Technology/Cengage Learning, 2010; 2nd ed.

WYSOCKI, R.K., 2012. Effective project management. 6th edn. Indianapolis, IN: Wiley.