Port of Savannah

MegaRail Project

Christopher B. Novack, P.E.Senior Director of Engineering and Facilities MaintenanceGeorgia Ports Authority

Page 2: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

GARDEN CITY TERMINAL

Savannah River • Dedicated container facility

• Terminal area: 1,200 acres

• Berthing: 9 berths = 9,693 ft

• Covered storage: 1.19 m sf

• 2 on-terminal rail yards

• 26 STS cranes + 4 in Dec 2017

• 146 rubber tired gantry cranes

Mason ICTF (NS)

Chatham Rail Capacity:

180,000 Lifts

Mason Rail Capacity:

400,000 Lifts

Need to increase capacity

to 1 million lifts with the

ability to build 10,000 foot

unit trains

Page 3: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation
Page 4: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Mason ICTF

Garden City Terminal

SR 25

12

3

4

5

1 Mason ICTF track expansion with 8 RMGs

Multi-rail connection between Mason and Chatham2

SR 25 Overpass3

4 Rail crossings over Pipemakers Canal

5 Chatham ICTF track expansion

•$126.7 million project

•$44 million funded thru Federal Grant (FASTLANE)

•Completion at the end of 2020

FY18 FY19 FY20 Total

$25.0 M $61.0 M $40.7 M $126.7 M

MegaRail Scope and Funding

Page 5: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Year 2000 – 940,000 TEUs

5

Intermodal Tracks within Marine Terminal

Page 6: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Year 2003 – 1.5 Million TEUs

6

Mason ICTF served from Foundation Lead,Stub-ended Facility

Page 7: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Year 2012 – 2.9 Million TEUs

7

Bourne Ave Grade Separation + South End Ladder & Connection to Foundation Lead, Double-Ended Facility

Page 8: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Intermodal Demand

8

730-915k

lift potential

at buildout

Page 9: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Existing Conditions – 2016

CSX & NS train building

9

Page 10: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation
Page 11: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Existing Road Crossings

11

• Based on 1 train in and out, includes road blockage

only

Street Blockage Time

Crossgate Rd. 1:00:00

Grange Rd. 1:21:00 + 40 min (switching)

Smith Ave. 0:35:00

Azalea Ave. 0:31:42

Herty Dr. 0:22:18

Rommel Ave. 0:21:24

SR 25 3:40:00

Page 12: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Existing Site Plan

12

Page 13: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Project Site Plan

13

Page 14: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Project Overall Site Plan

14

Page 15: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

8 RMGs

15

Page 16: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation
Page 17: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Proposed Road Crossings

17

Removed with

Brampton

Connector

4 Intermodal Crossings

Eliminated

Street Blockage Time

Crossgate Rd. 0:21:15

Grange Rd. 0:21:15

Smith Ave. 0:00:00

Azalea Ave. 0:00:00

Herty Dr. 0:00:00

Rommel Ave. 0:00:00

SR 25 0:21:15

* Based on 1 train in and out, includes road blockage

only

Page 18: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Schedule & Key Milestones

18

1a

3

4

5

1 2

Critical Path & Milestones

1b

2a

2b

Page 19: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Existing Terminal (Nov 17)

19

Page 20: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

3 NS Tracks in Mason (Aug 18)

20

1a

Page 21: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

NS West Bundle (Sept 19)

21

2

Page 22: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

CSX Tail Track & SR 25 (Dec 19)

22

3

Page 23: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

CSX East Bundle (Sept 20)

23

4

Page 24: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Connector & Tie-In (May 21)

24

5

Page 25: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Maximum Train Lengths

25

CSX 10,000’

NS 10,000’

Page 26: Port of Savannah MegaRail Project · 2017-10-27 · Year 2000 –940,000 TEUs 5 Intermodal Tracks within Marine Terminal. Year 2003 –1.5 Million TEUs 6 Mason ICTF served from Foundation

Georgia Ports Authority

Discussion and Questions