pickle mill

Upload: amol-pethkar

Post on 03-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Pickle Mill

    1/3

    MILLENNIUMS

    TEEL

    2006

    230

    AUTHOR: Peter Hopf

    Siemens AG

    ThyssenKrupp Stahl AG (TKS) is part of the carbon

    steel business unit of ThyssenKrupp Steel, which has

    been operating a tandem rolling mill in Dortmund,

    Germany since 1972. It produces quality steels primarily

    for the automotive industry, including an increasing

    proportion of the latest steel grades such as dual phase

    (DP) and transformation induced plasticity (TRIP) grades.

    Over the years, the company has been converting the mill

    in several stages to increase its capacity. An important

    step was coupling it with the pickle line in 1998. The

    companys next goal was to equip the mill to produce thesame high-quality steel as TKSs continuous tandem mill

    in Duisburg, commissioned in 2000.

    When Siemens started the TKS modernisation project in

    2001, the Dortmund plant had a mix of old and new

    components. The main drives were 30-year-old DC motors

    with analog controls. The converter-fed three-phase drive

    units in the coupling section dated back to 1997.

    Instrumentation made use of the latest 24V technology,

    but also included some old 220V sensors and the process

    peripheral equipment connected to the automation via

    hardware couplings and bus systems.

    Because of numerous minor conversions over the years,

    the plant was using a variety of different automation

    components, including automation technology from the

    1990s. What is more, there was no central computer for

    process automation; instead, the plant relied on several

    computers from different vendors.

    CONVERSION PLANNING

    Siemens started by performing a detailed on-site review,

    and then worked with TKS to devise the conversion

    concept. As much work as possible was performed during

    maintenance shutdowns to keep the main shutdown time

    as short as possible. The hydraulic, cooling and lubrication

    systems were converted in stages during maintenanceshutdowns before the main shutdown. Siemens also

    directly installed ET200 components in existing

    switchgear cubicles, preparing the ET200 on assembly

    panels that could then be installed in the old cubicles in a

    very short time during a maintenance shutdown.To minimise conversion time, the existing field bus was

    retained, even though it included parts from another

    manufacturer. Special bus connections allow the Simatic S7

    to operate the Interbus. Siemens simply unplugged the bus

    cable from the old automation device and connected it to

    the new Siemens automation system during the shutdown.

    In the coupling section, the three-phase supply drive

    systems from Alstrom were also converted to the Siemens

    bus standard quickly and easily by exchanging the bus

    interface for a standardised Profibus interface. The

    flatness measuring system was re-used by simply

    replacing the interface connection with a Profibus card.To minimise costs expensive main drive power

    components such as motors and thyristors were re-used

    whenever possible. By connecting the plants 30-year-old

    thyristors to new digital control system, a whole series of

    analog cubicles were replaced by a single cubicle for dual

    motor control.

    The DC supply systems for the pickle line and the

    Simatic S5 automation measurement and control

    systems were left unchanged. Siemens linked the

    tandem mills reused DC roller motors, including the

    reused thyristors, to new all-digital Simoreg devices. The

    old DC reeling machine, on the other hand, was

    replaced completely by two new AC reeling machines

    with an indirect converter. Exchanging the interfaces for

    Siemens components allowed the reused DC and AC

    drive systems in the coupling section to connect to the

    new automation system.

    The conversion also involved completely replacing the

    basic automation system of the coupling section,

    tandem mill and new run-out section, including all

    technological control systems. This required an interface

    between the remaining functions of the pickle line and

    the new basic automation system. A new model-based

    SIROLL process automation system that could handle

    the entire plant replaced the old process computers. Thisresulted in a significantly simpler interface design. All

    converted sections now feature standard display and

    diagnostic systems.

    With minimum downtime, Siemens modernised ThyssenKrupp Stahls coupled pickle line/tandemmill in Dortmund Germany, enabling the 30-year-old plant to rival the production quality of todays

    most advanced facilities.

    Modernising the coupled pickleline/tandem mill at TKS Dortmund

  • 8/12/2019 Pickle Mill

    2/3

    231

    MILLENNIUMS

    TEEL

    2006

    FINISHING PROCESSES

    SINGLE-OPERATOR CONTROL OF THE MILL

    All components are based on Simatic PCS 7 with WinCC

    as the standard control system for plant operation and

    fault diagnosis. The Simatic S7 provides control and

    regulation functions. New process peripheral equipment

    is connected via the ET200. The Simatic TDC automation

    system provides maximum computing power for

    technological control.

    Industrial PCs provide process automation. An open

    communications system exchanges data between the

    systems, using Profibus as field bus for peripheral

    equipment. Fast Ethernet serves as the process bus,

    backed by Simatic TDCs Global Data Memory for real

    time data exchange between the system controls.

    Siroll WinCC components were used for the joint display

    system, which features central power-up capability and a

    central signaling system that can be operated from anyplant monitor. The plant also relies on the versatile

    Siemens thickness control concept, which uses the

    extended mass flow technique to ensure tight tolerances

    under all operating conditions. The flatness control

    system makes use of neural networks that have a self-

    learning function, enabling them to adapt precisely to

    production requirements.

    Siemens paid particular attention to the design of the

    pickle line/tandem mills main control pulpit (see Figure

    1). The high degree of automation in all operating modes

    allows a single operator to control the intermediate

    section, tandem mill and reeling machine, up to the

    removal of the coil from the mill. The fault diagnostic

    system provides the operator with relevant information in

    an easily understandable form, supporting fast reaction

    to changing situations.

    INSTALLATION

    Integration tests using plant simulation are essential to

    success, especially in conversion projects. For theDortmund plant, Siemens exhaustively tested the entire

    automation system, including all control consoles, in the

    test department in Erlangen before shipment. Then, the

    r Fig.1 Main control pulpit

    a

  • 8/12/2019 Pickle Mill

    3/3

    MILLENNIUMS

    TEEL

    2006

    232

    FINISHING PROCESSES

    system was set up onsite in Dortmund two months before

    the main shutdown. This gave Siemens time to train TKSs

    operating and maintenance personnel. By carrying out

    ghost rolling with all production shifts, Siemens

    eliminated a host of problems that would otherwise have

    gone undetected until the plant was started up.

    Extensive preparation, proven systems, and expert

    installation management allowed the plant to start up

    ahead of schedule on 31 August 2003, after only a 34-

    day production halt. After a few days, the plant exceeded

    the planned production figures. Analyses in October

    2003 showed production quality levels comparable to

    those found in the most-advanced tandem mills. Figures

    2 and 3 show the mill.

    On 26 November 2003, a major fire destroyed the entire

    tandem mill area, interrupting acceptance testing. The

    blaze affected all five rolling stands, the ventilationsystem, the roller installation crane, and the hall roof.

    Twenty different companies and 350 employees worked to

    repair the plant. Siemens supplied all rolling stand control

    panels, plus decentralised process peripheral equipment,

    sensors and other components in the stand area.

    Renovation specialists from Siemens Industrial Services

    helped clean up all electrical equipment that was not

    directly affected. This made it possible to avoid downtime

    for many components.

    Original estimates suggested the plant would not be

    available for three months. However, the rolling mill

    started up again on 31 December, 35 days after the fire.

    Once production resumed in January, the acceptance

    tests were continued, with final acceptance in February

    2004. Now that the Dortmund plant been brought up to

    match the state-of-the-art standards of TKSs Duisburg

    facility, TKS has two pickle line/tandem mills advanced

    enough to meet any customer requirement. MS

    Peter Hopf is Project Leader, Siemens AG, IndustrialSolutions & Services, Erlangen, Germany

    CONTACT: [email protected]

    q Fig.2 View along the mill stands

    r Fig.3 Exit section of the modernised mill