permanente creek flood protection project: channel

20
Preconstruction public meeting Tuesday, April 10 from 7-9:00 p.m. 7 th Day Adventist Church Permanente Creek Flood Protection Project: Channel Improvements Your Safe, Clean Water vote at work

Upload: others

Post on 04-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Permanente Creek Flood Protection Project: Channel

Preconstruction public meetingTuesday, April 10 from 7-9:00 p.m.7th Day Adventist Church

Permanente Creek Flood Protection Project: Channel Improvements

Your Safe, Clean Water vote at work

Page 2: Permanente Creek Flood Protection Project: Channel

• Introductions

• Project Overview

• Channel Improvement Features

• Construction Overview

• Comments & Questions

Agenda

Page 3: Permanente Creek Flood Protection Project: Channel

The purpose of this presentation is to provide an update on the Channel Improvements Project as we enter the second and final year of construction.

Purpose

Page 4: Permanente Creek Flood Protection Project: Channel

Historical flooding

• 12 major floods in the past century

• Most recent major floods in 1995 and 1998

• Potential flood damages in this area are estimated in excess of $48 million (1999 value)

Page 5: Permanente Creek Flood Protection Project: Channel

Project objectives

• Provide one-percent flood protection to the citizens of Mountain View and Los Altos using a natural flood protection approach

• Protect Central Expressway and Middlefield Road

• Address deteriorating concrete channels

• Provide opportunities for environmental enhancements and trail extensions

• Minimize long-term maintenance costs

Page 6: Permanente Creek Flood Protection Project: Channel

Major project elements

A Levees and floodwalls

C Channel reconstruction

B

D

McKelvey Park

Rancho San Antonio Park

Flood detention areas:

The project will protect 2,200 parcels in Mountain View and Los Altos from a one-percent flood.

Light blue area shows the historical flood area

Page 7: Permanente Creek Flood Protection Project: Channel

Project schedule

Page 8: Permanente Creek Flood Protection Project: Channel

Channel improvements

Page 9: Permanente Creek Flood Protection Project: Channel

Channel improvements - Permanente

Page 10: Permanente Creek Flood Protection Project: Channel

Channel improvements – Hale

Page 11: Permanente Creek Flood Protection Project: Channel

Box Culvert Replacement

Page 12: Permanente Creek Flood Protection Project: Channel

Construction schedule

Construction Activity Estimated Dates in 2018

Channel widening site preparation Mid-April to May

Permanente special u-frameconstruction

May to Mid-October

Hale u-frame construction May to Mid-October

Box culvert replacement May to September

Separation wall at Arroyo Road September

Site restoration October – December

Page 13: Permanente Creek Flood Protection Project: Channel

What to expect during construction• Estimated 8 months of construction

• Work hours are 7:30 a.m. to 4 p.m., Monday through Friday

• Work between Mountain View Ave. and Valencia Ave. will mainly take place within the creek

• Mountain View Ave. between Raymundo Ave. and Arroyo Rd. will be closed to traffic for approx. 5 months while the culvert is replaced

• Temporary fencing and signs will be installed

Page 14: Permanente Creek Flood Protection Project: Channel

Channel Improvements: Construction Impacts

• Vibration

• Noise

• Dust

• Traffic

Page 15: Permanente Creek Flood Protection Project: Channel

Channel Improvements: Box Culvert Detours

Page 16: Permanente Creek Flood Protection Project: Channel

Channel Improvements: Construction Haul Route

Haul Route Map For Work Area #2&#3

Page 17: Permanente Creek Flood Protection Project: Channel

Outreach

• Public meetings

• Mailed notice

• Signage and flyers

• Website

• Email updates

• Fact sheets

• Media relations

• NextDoor

• Conference Calls

Page 18: Permanente Creek Flood Protection Project: Channel

For more information

http://www.valleywater.org/permanente-creek

•Sign up to receive project updates via email.

•View project reports, maps, history and other information.

Lotina NishijimaProject Manager

[email protected](408) 630-2795

Jose VillarrealPublic Information [email protected]

(408) 630-2879

Page 19: Permanente Creek Flood Protection Project: Channel

Reach us from your computer or smart phone

Page 20: Permanente Creek Flood Protection Project: Channel

Questions?