north san jose project. work began on this project in 1999, completed in 2001 work began on this...
TRANSCRIPT
North San Jose ProjectNorth San Jose Project
North San Jose ProjectNorth San Jose Project Work began on this project in 1999, completed Work began on this project in 1999, completed
in 2001in 2001 The transmission line installed called the The transmission line installed called the
Nortech-Trimble 115 kV line is 4.6 miles long Nortech-Trimble 115 kV line is 4.6 miles long and runs between PG&E’s Trimble Substation and runs between PG&E’s Trimble Substation and a new PG&E Substation called Nortech and a new PG&E Substation called Nortech Substation.Substation.
The conductor is 795 kcmil ACSS/Condor (54/7) The conductor is 795 kcmil ACSS/Condor (54/7) This project added new distribution capacity in This project added new distribution capacity in
the North San Jose area to remedy the area the North San Jose area to remedy the area deficiency caused by increased new constructiondeficiency caused by increased new construction
Why Horizontal Vee Why Horizontal Vee Insulators Were Chosen?Insulators Were Chosen?
Benefits of using a post insulator (no Benefits of using a post insulator (no insulator swing from wind) with longer insulator swing from wind) with longer span lengthsspan lengths
No insulator swing means less right of No insulator swing means less right of way had to be acquired for the way had to be acquired for the transmission linetransmission line
During construction, area land costs were During construction, area land costs were $1Million/acre$1Million/acre
Swivel post insulators used also provide Swivel post insulators used also provide tension relief between uneven spanstension relief between uneven spans
Construction Issues with Construction Issues with Horizontal Vee InsulatorsHorizontal Vee Insulators
Swivel post provided benefits noted Swivel post provided benefits noted previously but created a temporary previously but created a temporary problem for Constructionproblem for Construction
Insulator assemblies provided by Sediver Insulator assemblies provided by Sediver (MacLean Power Systems) had a pin (MacLean Power Systems) had a pin which prevented swinging of the swivel which prevented swinging of the swivel post during installation of stringing post during installation of stringing blocks and during conductor pullingblocks and during conductor pulling
Disadvantage listed by some Disadvantage listed by some manufacturers include concerns over pins manufacturers include concerns over pins not being removed during clipping and not being removed during clipping and prior to the line being placed into serviceprior to the line being placed into service
Other thoughtsOther thoughts
Line crews prefer removable pins on Line crews prefer removable pins on the swivel post type insulatorsthe swivel post type insulators
If pins are not present, crews can If pins are not present, crews can improvise methods to keep the improvise methods to keep the insulator assembly from swinging insulator assembly from swinging during conductor installationduring conductor installation
Pins, if provided, need to be removed Pins, if provided, need to be removed prior to line being placed into prior to line being placed into serviceservice
North San Jose ProjectNorth San Jose Project
Existing conductor Existing conductor transferred to new transferred to new steel poles to be steel poles to be used as a sock lineused as a sock line
Travelers installed Travelers installed in preparation for in preparation for sock line for new sock line for new second circuitsecond circuit
North San Jose ProjectNorth San Jose Project
Top and remove Top and remove wood polewood pole
Note existing dual Note existing dual OPGW fiber optic OPGW fiber optic system will system will remain on wood remain on wood poles to be poles to be transferred after transferred after 115 kV T/Line is 115 kV T/Line is builtbuilt
North San Jose ProjectNorth San Jose Project
Dot com boom Dot com boom occurred during the occurred during the permitting processpermitting process
Horizontal Vee Horizontal Vee insulators reduced insulators reduced the number of the number of structures, while structures, while reducing right of reducing right of way needs for new way needs for new T/LineT/Line
Project had permitting challenges due to its location Project had permitting challenges due to its location in close proximity to high tech building campusesin close proximity to high tech building campuses
Route was selected and permitting process began Route was selected and permitting process began prior to the existence of many of the office buildingsprior to the existence of many of the office buildings
North San Jose ProjectNorth San Jose Project
Steel pole Steel pole prior to prior to installation of installation of insulator insulator assemblyassembly
Close up view of horizontal vee with swivel post Close up view of horizontal vee with swivel post insulatorsinsulators
Sediver assembly used pins to limit insulator Sediver assembly used pins to limit insulator movement during stringingmovement during stringing
Pins were removed after clipping was completedPins were removed after clipping was completed
Line in serviceLine in service Close up view of swivel postsClose up view of swivel posts
North San Jose Project
North San Jose ProjectNorth San Jose Project
Questions/CommentsQuestions/Comments