ner300 offshore wind park “nordsee one” - europa · 1 ner300 offshore wind park “nordsee...
TRANSCRIPT
1
NER300
Offshore Wind Park “Nordsee One”Tobias Griesshaber
Shareholder representative of Innogy SE on behalf of project
Nordsee One GmbH
Brussels, 15 December 2017
22
• General project overview & timeline
• Project impressions
• Lessons learned
• Stakeholder management
• Permitting
• Financing & Innovation
• Risk management
• Movie about wind turbine installation in 2017
Agenda
33
General overview
Distance to shore 45 km
Water depth (LAT) 26 m – 29 m
Capacity 332 MW (54 x 6.15 MW)
Wind speed 9.8 m/s at hub height (90 m)
Yearly output 1.2 TWh
ShareholdersNorthland Power (85%) and
Innogy SE (15%)
NER300 funding EUR 70 mn
Lifetime 25 years
Commissioning 2017 Operation base
O&M route:
26 nm (48 km)
CTV 1.5 hrs
Nordsee One
44
Construction progress has just come to an endMost of the activities were performed within the schedule
2014 2015 2016 2017
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
100% Feed-in (only 18 days delay!)
Turbine Commissioning
Substation Topside Inst./Commissioning
Turbine Installation
Installation export cable
1st Feed-in
Substation Jacket Install
Actual vs. original (grey) planning
Last WTG section take-over
Cable Installation
Foundation Installation
Substation Topside Installation
Turbine Fabrication
Foundation (Basic Detailed) Installation
Permit: BSH Approval 2nd-3rd-4th
Financial Close FabricationFC assumption
Installation Commissioning
Cable Fabrication
Today
55
Ten years after project acquisition 332 MW are producing green powerFinancial and permit key milestones
• Acquisition of project rights by Innogy 2008
• Main Permit N1: April 2012
• Construction Permit Foundations: 03 December 2015
• Construction Permit Inter-Array-Cables: 25 April 2016
• Construction Permit Offshore-Substation: 08 June 2016
• Construction Permit Wind-Turbines: 03 March 2017
• Entry into operations: December 2018
requirement• NER300 Award by DG CLIMA December 2012
• FID by sponsors (incl. new sponsor NPI) December 2014
• Financial close with lenders March 2015
Thank
you!
66
• General project overview & timeline
• Project impressions
• Lessons learned
• Stakeholder management
• Permitting
• Financing & Innovation
• Risk management
• Movie about wind turbine installation in 2017
Agenda
1414
• General project overview & timeline
• Project impressions
• Lessons learned
• Stakeholder management
• Permitting
• Financing & Innovation
• Risk management
• Movie about wind turbine installation in 2017
Agenda
1515
Stakeholder ManagementUnderstand your stakeholders‘ needs
• Stakeholder analysis is an effort to understand motivation, benefits and pain points of affected parties.
• The right level of information and involvement will allow steering your project effectively through
challenging times, and be rewarding in good times.
As a consequence the support of the stakeholder will improve.
• Structure your stakeholder management by implementing the -Principle
A Single Point of Contact for a stakeholder or a group of stakeholders ensures one face to the
stakeholder, centralized data management and avoids ambiguous information.
Examples of key stakeholders for Nordsee One:
o Grid operator providing the electricity export connection to shore
o Equity investors
o Lenders via Facility Agent and their advisory group (technical, legal, tax etc.)
o Permitting authorities
o Public interest groups
S.P.O.C.
1616
Permitting (also applicable to public stakeholders, incl. the EU)Co-operate, communicate and stand by your word
Be predictable
In Germany, the permitting procedure is very comprehensive with involvement of the authorities at every
project phase. Projects need to pass several stage gates. Clearly defining and aligning milestones creates
a joint roadmap and provides planning security for all stakeholders.
Help the authorities to structure their resources to ensure the permit is issued when required.
Be open and transparent
In case things are going wrong or milestones are delayed, be as open and transparent as possible.
Authorities and public stakeholders support a change more smoothly if they understand why it is required.
Communicate transparently to avoid obstacles and ensure co-operation.
Take certain decisions early
The turbine type (here: 6 MW) is the central item to start with. This also applied to the NER300 funding
eligibility already back in 2011! The comprehensive permitting procedure – and EIB’s DD for NER300 –
involves metocean data, technology details and encompasses fabrication, transport and installation. As all
of the requirements are determined by the turbine, this needs to come first.
Predictability and reliability supports your project planning and execution significantly.
1717
Financing & InnovationDoes this go together well?
• Financing a mega-project (>1 bn€ CAPEX) is always a multi-variable moving target
• Banks & investors seek predictable conditions, ideally regulated returns and use of tested technology
• McKinsey found out that mega projects are delivered on average
o 1 year late
o 30% over original budget
• Nordsee One (1.2 bn€) did very well on
Scope (all assets are operational)
Time (less then 3 weeks delay compared to baseline)
Cost (within budget and contingencies)
But experienced
Quality issues: chosen foundation technology was innovative and – in hindsight – encompassed
some issues. Innovative blades turned out to require further design adaptations.
Financing seeks predictability and track record Innovation is new and usually radical change
More knowledge needs to be gathered and shared within and across the sectors
But there are limitations to linear thinking and transferability across sectors (onshore wind, O&G)
1818
Risk managementThe key to prepare for the known unknowns and navigate through uncertainty
• Risk?
Yield (un)certainty Offshore installation New technology
„The word 'risk' derives from the early Italian risicare, which means ‘to
dare‘ or ‘to circumnavigate’.
In this sense, risk is a choice rather than a fate.”
Peter L. Bernstein