Page 1: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

LS1 planning meeting

15.8.2013

Page 2: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Comments on LS1 schedule

• Schedule reviewed last week with Yann + TC… sequence after OD looked too squeezed therefore DCal SM installation delayed by one week (Joseph informed)

• Issues:– DCal installation DCal phone meeting 3rd September (tbc)– TRD SM insertion Bernd says realistically speaking we will have only three

SMs during LS1.– TOF slot depending on:

• Date completion LV modification BKF• Availability all rails (Yannick) + installation (10 SM must be moved)

• I hope we can finalize these details by beginning September.

15/8/13 LS1 planning meeting - A.Tauro 2

Page 3: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

15/8/13

LS1 plan 2013 Weeks

Remove plug, mobile shielding, open doors 8-9

Prepare for PHOS extraction, remove RB24 beampipe and PMD 10

Remove PHOS cradle and modules, transfer TOF crates on SF 11-13

Modify L3 services and install YP for TRD17 14

Modify L3 services, remove TRD17 and rework LV distr. TRD 7-8-10, DCal tests in SXL2 15-19

Modify L3 services, open low-beta and swap Q5L8 magnet, DCal tests in SXL2, new UPSes 20-23

Swap PHOS beams with DCal beams 25-26

Install DCal support structure and rails 27-30

DCal and PHOS services + complete support structure and rails 31-37

Open Days – 27-28-29/9 38-41

Install 2 1/3 DCal modules, new L3 ventilation ducts PX24 (Oct-Nov) 42

Install 3 DCal modules (C-side) and remove infrastructure (w45) 43-45

Rework LV distr. TRD11-15-16 46-48

TOF electronics repair 49-51

Xmas pause 52-1

DoneDoneDoneDone

DoneDone

Ongoing

Done

LS1 planning meeting - A.Tauro 3

Done

Page 4: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

15/8/13

Detailed plan till end of the year Weeks

Empty SA2 (SX2) + install new CR1 racks 30

Install new CR1 racks. DCal Al rails and I-side extensions 31

DCal Al rails and I-side extensions. Anti-collision system 32

DCal cabling, work at DCal support structure, clear SX2 hall for OD 33

DCal cabling, clear SXL2 for DCal SM storage, install 2 T0 racks (C33-34), reinstall CR1 rack door covers 34

Test anti collision system (Mon or Tue), CO2 cabling, arrival 4 DCal SMs (Tue/Wed) 35

Finalize DCal support structure (Mon-Wed), installation CO2 bottles C-side, maintenance TRD rotator, +1TRD (tbc) 36

Fix DCal rotator (Manoel), DCal installation platform, arrival dipole OD 37

Open low-beta and install scaffolding, PHOS and DCal cooling pipes 38

OD preparations - OD 39

Remove scaffolding (start Tue), remove ACR tables, remove portable chiller 40

Close low-beta 41

Install 2 1/3 DCal modules, PX24 scaffolding (L3 ventilation) 42

Modify DCal infrastructure, PX24 scaffolding (L3 ventilation) 43

Install 3 DCal modules (C-side), new L3 ventilation ducts 44

Remove DCal infrastructure and install TRD infrastructure 45

Rework LV distr. TRD11-15-16 and install TOF rails 46-48

TOF electronics repair 49-51

September

August

LS1 planning meeting - A.Tauro 4

October

Nov-D

ec

Page 5: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

15/8/13 LS1 planning meeting - A.Tauro 5

LS1 plan 2014 Weeks

Extend SAA3 shielding 2-6

Install top/bottom TRD counterweights 7-8

Remove comp. magnet and Suspend Miniframe 9-11

Install TRD12-13-14 with yellow platform (bottom) 12-14

‘Un-suspend’ Miniframe 15-16

Reinstall TRD17 17

Concrete walls & TRD installation frame 18-19

Install TRD4-5 (top) & counterweights 20-21

Remove TRD infrastructure 22

Reinstall ZEM and comp. magnet 23

Reinstall and bakeout RB24 beampipe 24-25

Install 4 PHOS + 3 DCal (A-side) supermodulesReinstall PMD

39-44

Close plug, L3 doors, reinstall shieldings 45-48 (Nov.) latest

Page 6: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Status UPS upgrade• CR1: done. 2 racks less than foreseen• CR2: done. Y row UPS, X-Z rows normal power. Replacement 32A -> 63A CB next week• CR3: 1-2 racks to be connected• CR4: done• CR5: CV cable to be installed---------Rack between EBD and EXD installed last week

To be done:• Interlock with SX2 ventilation • On-battery signal• False floor mezzanine• UPS support and false floor in front of UPS500

Project should be completed by end August

9/8/13 LS1 planning meeting - A.Tauro 6

Page 7: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Renaming CRs racks

• We have renamed all the CR1-4 racks, in order to:– avoid non-conventional naming (e.g. X01A, X01B…)– foresee place for non-installed racks

update CR drawings (Arturo, Maridor)update DCDB information (Andre, Mateusz)install proper labels (Andre, Fred)inform detectors (Andre)

15/8/13 LS1 planning meeting - A.Tauro 7

Page 8: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

ACR planningKick off meeting Wed 4th September 14:00

Before end August:• Remove personal objects (all subdetectors)• w34-35: move DCS, SLIMOS, LACS consoles and visitor token distributor to WR3 (upstairs) + key PAD/MAD• Remove screens and PCs (and WR1&2 tables)• Remove fire detection system (incl. piping)September:• w36 (Mon-Tue): remove Ethernet cables (MTE)• w37-38 (tbc): remove 220V cables (SPIE) + lightsOctober-December:• w40 (starting Tue 1/10): move ACR tables and chairs to SX2 (right after OD)• Remove ventilation outlets• Remove false ceiling, walls and doors. Install new windows• Install isolation panels and electrical ducts concealed in the plasterboard walls• Install false floor and cable traysJanuary-February:• Install 220V and Ethernet cables• Modify ventilation ducts (and unit)• Install new false ceiling and lights• Install fire detection systemMarch:• Install tables, WiFi, move consoles back in ACR, telephones• Finalize cablingApril-May:• TVs, screens and PCs• Contingency15/8/13 LS1 planning meeting - A.Tauro 8

Page 9: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Opening low-beta (w38)

15/8/13 LS1 planning meeting - A.Tauro 9

ALTEAD: remove blocks 9 to 24

Page 10: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

15/8/13 LS1 planning meeting - A.Tauro 10

Scaffolding 35 persons max.

Page 11: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

TE

NTLHC DIPOLE

Kidscorner

DAQ TOF

TRD

?

Cosmophone

ITS

Exh

ibit

ion

Control Room

Annex 4 – P2 surface entertainment area (SX2)

Restaurant

DCal ?

Shop

9/8/13 LS1 planning meeting - A.Tauro 11

DCS

Page 12: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Cooling

• All CP in stby (except SSD-SDD)• 1 chiller put in operation already this week. Primary cooling

stably back in w40• D.Piednoir absent till 9/9 contact Jani Lehtinen or Denis

Dumas if needed• Portable chiller needed by LHCb w40• Power cut (18kV) foreseen on 2-3/9 in order to make

electrical connections in SU2 Lonjon still to confirm

9/8/13 LS1 planning meeting - A.Tauro 12

Page 13: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Cabling• DCal:

– LV, Ethernet, HV ongoing. – Should be completed by next week however LV cable too short,

CH has ordered more.

• LV consolidation:– Restart next Monday, once Samuel is back– Charles-Henri to review schedule with Samuel

• CO2:– Started, will be finished by end August

Page 14: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

PHOS cabling & DCal

15/8/13 LS1 planning meeting - A.Tauro 14

PHOS cables and fibers below space-frame re-arranged such to be able to install DCal SMs.

Page 15: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Status CO2 project

• Cables bundle and minimax boxes done and at Cern• Cabling in progress from Cr5 to Ux25• Installation in October• Thermo cables ordered• Pyrotechnic valves at P2

• Bottles refilled installation in September• System installed before end of year

Page 16: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Status N2 project

15/8/13 LS1 planning meeting - A.Tauro 16

Page 17: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

SM

to

be

mo

ved

by

1m –

1.3

m i

n A

-sid

e d

irec

tio

n

SM

to

be

mo

ved

by

15cm

in

C-s

ide

dir

ecti

on

TOF interventions

Yannick informed. All rails should be ready before TOF intervention (November)

Page 18: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Rain - actions• Coming two weeks: GS to contact TSO in order to establish action

plan in case of rain • SXS2: roof inspected and cleaned last week (GS)• >>> ACR: GS will move pipe outside SX2 building <<<• P2: Vallier has intervened this week to clean both foul and rain

water networks now regular cleaning• Long term: modify and repair the P2 drainage network

– See R.Morton’s presentation at July LSC meeting:• http://indico.cern.ch/getFile.py/access?

contribId=3&resId=0&materialId=slides&confId=264805

9/8/13 LS1 planning meeting - A.Tauro 18

Page 19: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Gas

• Still in the process of searching and fixing leaks on SF6 and C2H2F4 lines (DT and MEF).

• SG2: scales (C2H2F4 and i-buthane) will be installed next Monday.

• Ar dewar re-connected, will be put in service in the coming weeks. Then the N2 dewar will be removed (September).

• SF6: heater will be installed around SF6 bottles (already done in CMS) this winter.

9/8/13 LS1 planning meeting - A.Tauro 19

Page 20: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

Access and perturbations

• The UMTS equipment covering ALICE lift and cavern will be replaced and upgraded to HSPA+ the 15th August.– The UMTS900 services in the cavern could be disrupted during 30 minutes.– The work will be performed at the surface in the SD.– The GSM and TETRA services wont be affected.

• Test 18kV 2-3/9 will stop UX racks (tbc)

• Les tests secours CERN seraient maintenus au 3 septembre 2013 de 7h00 à 7h10.

• Les tests auto-transfert seront probablement planifiés mi-septembre après la remise en service de la liaison MP2 (de nouveau en panne depuis vendredi dernier 9 aout 2013…)

15/8/13 LS1 planning meeting - A.Tauro 20

Page 21: LS1 planning meeting 15.8.2013. Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore

AOB

• Leak rack A21 water stopped. Issue: relief valve hidden below cables. Action: Philippe to check with Andre next Monday

• CV promised to fix leaks along ITS ventilation duct CR5->UX. Nothing done yet.

• Fan replacement for Wiener and CAEN (April) Andre to contact concerned detectors.

• ADAM: signal ON/OFF. Request sent to Jacopo/Donatella

15/8/13 LS1 planning meeting - A.Tauro 21