life covenant church complaint

Upload: howard-friedman

Post on 02-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Life Covenant Church Complaint

    1/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 1

    IN THE UNITED STATES DISTRICT COURTFOR THE NORTHERN DISTRICT OF NEW YORK

    LIFE COVENANT CHURCH, INC.

    Plaintiff,

    v. CASE NO. ___________

    TOWN OF COLONIE, TOWN OFCOLONIE PLANNING BOARD, PETERSTUTO, TIMOTHY LANE, LOUISMION, SUSAN MILSTEIN, BRIANAUSTIN, CRAIG SHAMLIAN,KATHLEEN DALTON, JOSEPH

    LACIVITA, MICHAEL C. MAGGUILLI,REBEKAH NELLIS KENNEDY.

    DEMAND FOR JURY TRIAL

    Defendants.

    PLAINTIFF S ORIGINAL COMPLAINT

    Life Covenant Church, Inc., (LifeChurch) the Plaintiff in the above-entitled and

    numbered case, files this Original Complaint against Defendants Town of Colonie (the Town) ,

    Town of Colonie Planning Board (Planning Board), Peter Stuto, Timothy Lane, Louis Mion,

    Susan Milstein, Brian Austin, Craig Shamlian, Kathleen Dalton, (collectively, the Planning

    Board Members), Joseph LaCivita (Planning Director) , Michael C. Magguilli (Town

    Attorney) , and Rebekah Nellis Kennedy (Assistant Town Attorney) and would respectfully

    show the Court as follows:

    I.

    NATURE OF ACTION

    1. This action arises out of LifeChur chs continual efforts to obtain land use

    approvals from the Town to construct a new church facility and associated parking on its

    property. The Town through its Planning Board, Planning Board Members, Town Attorney, and

    1:14-CV-1530 (LEK/RFT)

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 1 of 30

  • 8/10/2019 Life Covenant Church Complaint

    2/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 2

    Assistant Town Attorney (collectively, the Town Officials), has unreasonably delayed the

    review and approval of Life Churchs zoning requests in violation of federal and state law.

    LifeChurchs zoning requests have been los t in a bureaucratic maze as the Town and Town

    Officials have routinely made conflicting requests and continued to unnecessarily delay in

    requesting and reviewing materials prior to the Plann ing Boards consideration of LifeChurchs

    zoning requests. LifeChurch has reasonably responded to the Town's requests. However, it is

    clear based upon the Town s and Town Official s actions and unreasonable delays that any

    additional attempts to accommodate the Towns and Town Officials requests would be futile

    and LifeChurch's zoning requests have been and will continue to be improperly delayed so as toeffectively be denied.

    2. The Towns and Town Officials unreasonable delays, obstruction, and hostility

    towards LifeChurch have inflicted immediate injuries and have placed an unjustified substantial

    burden on LifeChurchs practice of religion and have applied this burden in a manner that has

    discriminated against LifeChurch as a religious organization. Moreover, this suit seeks relief

    from the clear and purposeful deprivation of LifeChurchs rights to freedom of religion ,

    assembly, speech, and association. In this action, LifeChurch alleges that the Towns and Town

    Officials actions violate the United States and New York Constitutions and the Religious Land

    Use and Institutionalized Persons Act of 2000, 42 U.S.C. 2000cc et seq . (RLUIPA). As a

    result of the Towns and Town Offici als unlawful actions, LifeChurch has suffered and

    continues to suffer damages.

    3. LifeChurch also files this action for injunctive and declaratory relief to, inter alia ,

    compel the issuance of all approvals and permits to allow it to construct its new church facility

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 2 of 30

  • 8/10/2019 Life Covenant Church Complaint

    3/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 3

    on its property. LifeChurch also seeks compensatory damages and the recovery of its reasonable

    and necessary attorneys fees .

    II.

    JURISDICTION AND VENUE

    4. Pursuant to 28 U.S.C. 1331, 1343(a)(3), and 1343(a)(4), and under 42 U.S.C.

    2000cc et seq. , this Court has jurisdiction over Life Churchs claims arising under federal law.

    This Court has jurisdiction over the requests for declaratory relief pursuant to 28 U.S.C. 2201

    and 2202. This Court also has pendant jurisdiction and supplemental jurisdiction over all state

    law claims under 28 U.S.C. 1367(a).

    5. Venue is proper in this District pursuant to 28 U.S.C. 1391, as the events or

    omissions giving rise to this action occurred in this District and the property that is the subject of

    the action is located in this District.

    III.

    PARTIES

    6. LifeChurch is a non-profit corporation organized under the laws of the State of

    Oklahoma and duly authorized to do business in New York.

    7. The Town is a municipal corporation organized under the laws of the State of

    New York. The Town may be served with service of process by serving its clerk, Elizabeth A.

    DelTorto at Memorial Town Hall 534 Loudon Road, Newtonville, NY 12128, or wherever she

    may be found.

    8. Town of Colonie Planning Board is municipal land use review board authorized

    and created by NYS Town Law 271. The Town of Colonie Planning Board may be served

    with service of process by serving its Chairman, Peter Stuto, at 347 Old Niskayuna Road,

    Latham, New York 12110 or wherever he may be found.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 3 of 30

  • 8/10/2019 Life Covenant Church Complaint

    4/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 4

    9. Upon information and belief, Peter Stuto resides at 19 Newell Ct., Albany,

    NY 12204-1227. Peter Stuto is a member of the Town of Colonie Planning Board. Mr. Stuto

    may be served with service of process at his residence or wherever he may be found.

    10. Upon information and belief, Timothy Lane resides at 7 Sage Ct., Albany, NY

    12204-1404. Timothy Lane is a member of the Town of Colonie Planning Board. Mr. Lane may

    be served with service of process at his residence or wherever he may be found.

    11. Upon information and belief, Louis Mion resides at 1 Altamont Ave, Albany,

    NY 12205-3605. Louis Mion is a member of the Town of Colonie Planning Board. Mr. Mion

    may be served with service of process at his residence or wherever he may be found.12. Upon information and belief, Susan Milstein resides at 6 Sage Hill Ln, Albany,

    NY 12204-1334. Susan Milstein is a member of the Town of Colonie Planning Board. Ms.

    Milstein may be served with service of process at her residence or wherever she may be found.

    13. Upon information and belief, Brian Austin resides at 14 Starboard Way, Latham,

    NY 12110-1306. Brian Austin is a member of the Town of Colonie Planning Board. Mr. Austin

    may be served with service of process at his residence or wherever he may be found.

    14. Upon information and belief, Craig Shamlian resides at 25 Carriage Hill Drive,

    Latham NY 12110-4946. Craig Shamlian is a member of the Town of Colonie Planning Board.

    Mr. Shamlian may be served with service of process at his residence or wherever he may be

    found.

    15. Upon information and belief, Kathleen Dalton resides at 54 Laura Drive, Latham,

    NY 12110-2308. Kathleen Dalton is a member of the Town of Colonie Planning Board. Ms.

    Dalton may be served with service of process at her residence or wherever she may be found.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 4 of 30

  • 8/10/2019 Life Covenant Church Complaint

    5/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 5

    16. Upon information and belief, Joseph LaCivita resides at 9 Belleauwood Cir,

    Watervliet, NY 12189-1229. Joseph LaCivita is the Director of Planning and Economic

    Development with the Town. Mr. LaCivita may be served with service of process at his

    residence or wherever he may be found.

    17. Upon information and belief, Michael C. Magguilli resides at 23 Newell Ct.,

    Albany NY 12204-1226. Michael C. Magguilli is the Town Attorney. Mr. Magguilli may be

    served with service of process at his residence or wherever he may be found.

    18. Upon information and belief, Rebekah Nellis Kennedy resides at 4 Marriner Ave.,

    Albany NY 12205-2906. Rebekah Nellis Kennedy is the Assistant Town Attorney. Ms.Kennedy may be served with service of process at her residence or wherever she may be found.

    19. Each of the individual defendants is named herein in his or her official capacity

    only.

    IV.

    STATEMENT OF FACTS

    20. LifeChurch is a religious organization that provides Christian American

    Evangelical faith services and faith oriented instruction classes to members of the Capital

    District community-at-large. LifeChurch presently provides faith worship services for church

    members in their 10,000 square foot facility, which is located at 560 Sand Creek Road, Village

    of Colonie, New York. This facility contains approximately 180 seats for its worship services.

    The current facility also contains four classrooms for children to attend Sunday school classes

    during worship services. The facility also has an associated parking lot that contains only 82

    parking spaces.

    21. Life Churchs membership has been rapidly growing, more than doubling in the

    past five years, and its attendance requirements exceed the capacity of its current facility. The

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 5 of 30

  • 8/10/2019 Life Covenant Church Complaint

    6/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 6

    inadequacies of the current facility have prevented LifeChurch from performing tasks that it

    believes are mandated by God, including expanding LifeChurchs membership and discipling to

    more members about the Christian faith. Additionally, the lack of adequate parking has

    prevented some current members from attending regularly scheduled religious services.

    LifeChurch thus requires the construction of a new facility to accommodate its existing and new

    members and to exercise its religious rights. The new facility would also enable LifeChurch to

    provide additional faith services and instruction not available at its present facility.

    22. Worship sites ( e.g., churches, temples, cathedrals) are essential to most religious

    groups, including to LifeChurch and its members. Beyond serving as a meeting place for groupworship and religious services, the sites themselves are sacrosanct, and they serve as symbols of

    the tenets and beliefs which are observed, practiced and taught by religious groups such as

    LifeChurch. Preventing a religious group such as LifeChurch from building a necessary worship

    site fundamentally and substantially chills and inhibits its ability to practice its religion.

    23. In order to further fulfill LifeChurchs Christian purposes, LifeChurch purchased

    property located in the Town of Colonie (the Property), to construct a new church facility with

    appurtenant religious education and training rooms and associated parking (the Project). The

    Project would contain a 36,601 square foot facility for worship services, 8 religious education

    and training rooms, and 457 parking spaces, which would allow LifeChurch to accommodate its

    growing membership.

    24. LifeChurchs Project, and its eventual operation of religious facilities upon the

    Property, will substantially affect interstate commerce.

    25. In order to develop the Project, LifeChurch commenced the site plan review and

    subdivision process. Pursuant to the Towns Zoning Code, the first step in the site plan review

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 6 of 30

  • 8/10/2019 Life Covenant Church Complaint

    7/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 7

    and subdivision process is the submission of a Zoning Verification request to the Towns

    Building Department. The purpose of the Zoning Verification is for the Towns Building

    Inspector to determine if a proposed project complies with applicable zoning and to determine

    what type of approvals are required.

    26. On March 21, 2013, LifeChurch submitted a Zoning Verification for its Project to

    the Town s Building Department.

    27. Upon review of the application, the Towns Building Inspector informed

    LifeChurchs project engineer, Sipperly and Associates (Brian Sipperly) , that he had a concern

    regarding access to the Property. Access to the Property on the submitted plans showed access by utilizing an existing easement along a private road known as Moffat Lane. Moffat Lane is

    physically located upon the parcel adjacent to LifeChurch which is owned by the United States

    Postal Service. Moffat Lane is a paved private road utilized by the United States Postal Service

    for ingress/egress to its facility located on the United States Postal Service s property. The

    Property is adjacent to Moffat Lane and is benefited by a filed and recorded access easement

    over Moffat Lane.

    28. The Towns Building Inspector informed Mr. Sipperly that the Town would

    accept Moffat Lane as LifeChurchs means of access provided that its plans were revised to

    show a cul-de-sac being constructed at the end of Moffat Lane.

    29. Upon submission of plans incorporating the revisions demanded by the Town

    showing Moffat Lane as the means of access with a terminal cul-de-sac to be constructed by

    LifeChurch, the Zoning Verification was approved for the subdivision portion of the application.

    However, the Zoning Verification for the site plan was denied because LifeChurch s proposed

    building exceeded the allowable square footage in the Office-Residential District, which is the

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 7 of 30

  • 8/10/2019 Life Covenant Church Complaint

    8/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 8

    zoning district where the Property is located. As a result, application for an area variance was

    required.

    30. On April 8, 2013, LifeChurch filed an application for an area variance for

    allowable building square footage with the Towns Zoning Board of Appeals (ZBA) . The

    matter was scheduled to be on the ZBAs agenda for its regularly scheduled June 6, 2013

    meeting. Approximately one week prior to the meeting, the Town informed Mr. Sipperly that

    the matter was being removed from the June 6, 2013 agenda based upon a paperwork mix-up in

    the Town Attorneys office pertaining to the State Environmental Quality Review Act. The

    matter was rescheduled for the August 15, 2013 ZBA meeting.31. On June 12, 2013, less than one week after the LifeChurch matter was removed

    from the ZBA agenda, one or more Town Officials informed Mr. Sipperly that the Town would

    not accept the plans showing access to the Property by means of the access easement across

    Moffat Lane. The Town took the position that the Property was landlocked and, in order to

    utilize the easement across Moffat Lane, application must be made for an Open Development

    Area ( ODA ) approval pursuant to NYS Town Law 280-a.

    32. In response, on August 15, 2013, LifeChurch submitted a request for an ODA.

    On August 8, 2013, LifeChurch also filed a complete application for site plan and subdivision

    approval with the Town.

    33. Shortly after this submittal, the Town Attorney questioned whether an ODA

    would be required because the Property had frontage on a public street, Watervliet-Shaker Road.

    The matter was then placed upon the September 10, 2013 Planning Board agenda for sketch

    review.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 8 of 30

  • 8/10/2019 Life Covenant Church Complaint

    9/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 9

    34. Soon thereafter, the Town Attorney informed LifeChurch that the Town Planning

    Board would not consider an ODA for the Property. On October 13, 2013, a meeting was held

    with NYS DOT to discuss access from the parcel directly to Watervliet-Shaker Road. A revised

    site plan was submitted showing access directly from Watervliet-Shaker Road. The request for a

    two lot subdivision was withdrawn.

    35. At the ZBAs December 19, 2013 meeting, the ZBA granted the area variance to

    allow for a 36,601 square foot building. Mr. Sipperly immediately requested that the site plan

    application be placed upon the Town Planning Boards January 21 , 2014 agenda. However, on

    January 3, 2014, Mr. Sipperly was informed that the resubmitted site plan application, previouslyfiled back on November 6, 2013, was incomplete. The Towns P lanning staff also requested a

    meeting to discuss the proposed access via Watervliet-Shaker Road.

    36. At a meeting held on January 8, 2014, Town Planning staff informed LifeChurch

    that they preferred access from Moffat Lane rather than access from Watervliet-Shaker Road.

    LifeChurch requested that the matter be placed upon the January 21, 2014 Planning Board

    agenda and that it would submit a revised plan showing Moffat Lane access for discussion at that

    meeting. On January 13, 2014, Mr. Sipperly submitted revised plans showing Moffat Lane as

    the access point.

    37. On January 17, 2014, in response to LifeChurchs email to the Town confirming

    that the Project was on the January 21, 2014 Planning Board agen da, the Towns Planning

    Director, Joseph LaCivita, informed LifeChurch that the Town Attorney pulled the matter from

    the agenda. In response, LifeChurch contacted the Town Attorney who stated that he had

    questions as to whether the proposed use constituted a church because, to him, it appeared to be a

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 9 of 30

  • 8/10/2019 Life Covenant Church Complaint

    10/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 10

    commercial television broadcast studio. LifeChurch provided documentation to the Town

    Attorney proving that the proposed use was a place of worship.

    38. On March 10, 2014, upon completion of additional traffic analysis, an updated

    complete application package was submitted to the Town. Mr. Sipperly requested the matter be

    placed on the next Town Planning Board agenda. However, Mr. Sipperly was informed that the

    application was rejected because the title block on the plan merely stated a wrong location for the

    Project.

    39. On March 31, 2014, Mr. Sipperly received correspondence from the Town

    Planner, Mike Lyons, that the application was complete and being placed upon the TownPlanning Boards meeting agenda for May 6, 2014.

    40. On May 1, 2014, Mr. Sipperly was informed that the matter was being

    rescheduled to the May 20, 2014 agenda because the Town had insufficient time to review

    recently submitted traffic data. However, on May 15, 2014, LifeChurch was again informed that

    the matter was being pulled from the May 20th agenda and not being rescheduled based upon

    Town discussions with DOT personnel who preferred access from Moffat Lane instead of the

    proposed new curb cut. At approximately this same time, the Town Designated Engineer issued

    a memo stating their recommendation that the Project be accessed via Moffat Lane. As a result,

    LifeChurch requested an immediate meeting with all parties to resolve the conflicting messages

    being received from the Town s officials.

    41. On May 22, 2014, LifeChurch attended a meeting along with the Project

    engineers Lynn and Brian Sipperly. In attendance was the Assistant Town Attorney, the Planning

    Director, and Mike Lyons, the Town Planner. At this meeting, Mr. Lyons and the Assistant

    Town Attorney advised LifeChurch to submit another request for an ODA to utilize Moffat

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 10 of 30

  • 8/10/2019 Life Covenant Church Complaint

    11/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 11

    Lane. One or more Town Officials agreed to make the request for the ODA. The Town had in

    effect backtracked back to where the Project had been in August 2013 wherein they made the

    same recommendation (which was ignored by the Town). LifeChurch requested that, in the

    event that the ODA was again refused, then the matter would be placed upon the next available

    Town Planning Board agenda for review showing direct access to the public street. Town

    Officials present at the meeting agreed to this alternative course of action in the event the ODA

    was again refused.

    42. On June 19, 2014, the Assistant Town Attorney informed the project engineers by

    email that the Town Planning Board would not hear the ODA request. As a result, LifeChurchsought clarification as to the reason and received no response. LifeChurch informed the Towns

    Planning Director that it was being forced to resort to litigation to compel the Town to place the

    matter on an agenda to be heard. LifeChurch sent a chronology of the above referenced events to

    the Planning Director to demonstrate how egregiously it had been treated. On July 23, 2014,

    LifeChurch contacted the Towns Planning Department and was informed that the matter was

    being placed on the August 12, 2014 Town Planning Board agenda.

    43. On August 12, 2014, LifeChurch was before the Towns Planning Board for a

    sketch review for the second time, the first of which took place nearly one year before. At this

    meeting, LifeChurchs engineers demonstrated that LifeChurchs proposed driveway location

    fully complied with New York State Department of Transportation regulations and standards

    pertaining to separation distances between driveways and intersections. At this meeting, the

    Towns Planning Board raised three items for the first time in again delaying the process in

    denying the sketch plan submitted on behalf of LifeChurch. Each of these three new items could

    have and should have been raised well before now, if they should have been raised at all.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 11 of 30

  • 8/10/2019 Life Covenant Church Complaint

    12/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 12

    44. The Town then advised LifeChurch that it would be on the Town Planning

    Boards agenda on September 23, 2014. However, on September 17, 2014, the Planning Director

    advised LifeChurch that its matter could be placed on the Town Planning Boards October 7,

    2014 agenda but not the September 23, 2014. In response, on September 22, 2014, LifeChurch

    sent a demand letter to the Town advising the Town and Town Officials that their continual,

    unjustifiable delays were violating LifeChurchs constitutional rights and substantially burdening

    its religious exercise. Additionally, LifeChurch advised the Town that if it was not placed on the

    October 7, 2014 agenda and if all of its requests were not approved at that time, then it would

    consider any further efforts as futile and it would proceed accordingly. Moreover, LifeChurchstated that any further delays or requests for additional information would further illustrate that

    the Town was merely seeking to delay LifeChurchs approvals indefinitely and that LifeChurch

    would treat such action as a denial of its requests.

    45. Even after LifeChurch provided the Town with notice of its unconstitutional

    deprivations and violations of RLUIPA, the Town did not place LifeChurch on the Town

    Planning Boards agenda for October 7, 2014.

    46. Subsequent to the Towns receipt of the letter setting forth the Town s and Town

    Officials RLUIPA violations, LifeChurchs application was placed upon the Planning Boards

    October 21, 2014 agenda for continued sketch review. At this meeting, LifeChurchs attorneys

    and engineers presented its application. Numerous attendees of LifeChurch also addressed the

    Planning Board explaining the role of LifeChurch in their lives as well as its role in the local

    community.

    47. As a result of the testimony provided to the Planning Board at this meeting,

    Planning Board members requested tha t Town staff and the Towns outside engineer meet with

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 12 of 30

  • 8/10/2019 Life Covenant Church Complaint

    13/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 13

    LifeChurchs representatives so that any outstanding issues could be addressed and the matter

    brought back to the Planning Board for concept acceptance of the site plan.

    48. On October 23, 2014, a meeting was held between LifeChurchs representatives

    and the Planning Director along with representatives from the Towns outsi de engineering firm.

    LifeChurch was informed by the Towns outside engineers that the purpose of the meeting was

    to gather information because the outside engineers were meeting that evening with members of

    the Town Planning Board.

    49. LifeChurch received no word on the discussion held or outcome of the meeting

    held with the elected officials.50. When LifeChur chs representatives inquired as to the status of being placed upon

    the Planning Boards agenda, they were informed that the Towns outside enginee rs had not been

    working on the Project because the escrow account that LifeChurch had provided to the Town to

    pay for the costs of the outside engineer needed to be replenished. LifeChurch immediately

    rectified this situation but was told by the Town that it was too late to be placed upon the

    December 2, 2014 Planning Board agenda. LifeChurch was informed by the Town that it could

    possibly be on the December 16, 2014 meeting agenda provided that the Planning Boards

    comments had been addressed.

    51. LifeChurchs attorneys then contacted the Towns engineer and inquired if

    anything further was required from LifeChurch in order for the outside engineer to complete

    their review in time for the December 16, 2014 agenda. They were informed that only an

    environmental assessment form needed to be submitted, however, the requested document had

    already been provided to the Town by LifeChurch a week before the request from the Towns

    outside engineer.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 13 of 30

  • 8/10/2019 Life Covenant Church Complaint

    14/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 14

    52. On November 20, 2014 , LifeChurchs attorneys received a memo from the

    Towns outside engineer stating that approval of the project will hinge on ODA approval by

    the Town Planning Board; a concept recommended and supported by the outside engineers. This

    is the same type of approval that LifeChurch had twice sought from the Town Planning Board to

    no avail.

    53. When seeking clarification on the memo, the Towns outside engineer offered to

    meet to explain their position. This meeting occurred on November 25, 2014.

    54. At this meeting, LifeChurch was given a list of approval conditions that the

    outside engineer stated he was going to recommend to the Town be conditions of any ODAapproval. Thes e conditions attempted to regulate critical aspects of LifeChurchs worship

    services and religious activities, including the number of worship services and the time for those

    worship services. A true and correct copy of the memo setting forth the conditions is attached

    hereto as Exhibit A. LifeChurch informed the outside engineer that a number of the conditions

    appeared to be unacceptable and would likely be rejected by LifeChurch leadership.

    55. When Town Officials were informed that the proposed conditions were not

    acceptable to LifeChurch, LifeChurch was told that it would not be placed upon the December

    16, 2014 agenda without accepting the conditions set out by the Town's outside engineer. See

    Exhibit B. On December 15, 2014, LifeChurch confirmed from the Town s website that

    LifeChurchs application was not on the Town Planning Boards December 16, 2014 meeting

    agenda. On December 16, 2014, one or more of LifeChurchs attorneys or representatives

    attended the Town Planning Board meeting and LifeChurchs zoning request was not on the

    agenda.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 14 of 30

  • 8/10/2019 Life Covenant Church Complaint

    15/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 15

    56. As a result of t he Towns continual delay tactic s, LifeChurch had no other option

    but to seek the Courts intervention.

    57. LifeChurch has no plain, adequate or complete remedy at law to redress these

    violations of its constitutional rights, and this suit for injunction, declaratory judgment and

    damages is its only means of securing complete and adequate relief. No other remedy would

    offer LifeChurch substantial and complete protection from the continuation of the Town s and

    Town Officials unlawful and unconstitutional acts, policies, and practices. By their

    longstanding hostility and bias against LifeChurch and its pending application, the Town and

    Town Officials have demonstrated that, without the imposition of preliminary injunctive relief,the continuation of proceedings before the Town Planning Board will be interminable and futile.

    58. LifeChurch has sustained an immediate, irreparable injury because of the Towns

    and Town Officials delays and unlawful burden they have placed on LifeChurchs exercise of

    religion. The Towns and Town Officials continual delay, hostility, and obstruction has caused

    LifeChurch to incur damages including unnecessary engineering and attorneys fees and

    expenses caused by the Town and Town Officials. LifeChurch will also continue to incur

    significant expenses for repairs and maintenance to its current facility that would not be

    necessary if it was allowed to timely begin the Project. As such, in addition to the substantial

    burden being placed on LifeChurchs religious exercise, it has and will continue to incur

    damages as the result of the Towns and Town Officials actions.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 15 of 30

  • 8/10/2019 Life Covenant Church Complaint

    16/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 16

    V.

    CAUSES OF ACTION

    COUNT I

    Violation of RLUIPASubstantial Burden

    (42. U.S.C. 2000cc(a))

    59. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 58.

    60. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to the free exercise of religion, as secured by RLUIPA, by imposing and

    implementing land use regulations that place a substantial burden on Life Churchs religious

    exercise without a compelling governmental interest. This substantial burden affects, or removal

    of that substantial burden would affect, interstate commerce.

    COUNT II

    Violation of RLUIPANondiscrimination

    (42. U.S.C. 2000cc(b)(2))

    61. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 60.

    62. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to the free exercise of religion, as secured by RLUIPA, by imposing and

    implementing land use regulations that discriminate against LifeChurch on the basis of religion

    or religious denomination.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 16 of 30

  • 8/10/2019 Life Covenant Church Complaint

    17/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 17

    COUNT III

    Violation of RLUIPAEqual Terms

    (42 U.S.C. 2000cc(b)(1))

    63. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 62.

    64. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to the free exercise of religion, as secured by RLUIPA, by imposing and

    implementing land use regulations that treat a religious assembly and institution on less than

    equal terms with a nonreligious assembly and institution.COUNT IV

    Violation of RLUIPAUnreasonable Limitation

    (42 U.S.C. 2000cc(b)(3)(b))

    65. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 64.

    66. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to the free exercise of religion, as secured by RLUIPA, by imposing and

    implementing land use regulations that unreasonably limit religious assemblies, institutions, or

    structures within a jurisdiction.

    COUNT V

    Violation of the United States ConstitutionFree Exercise of Religion: First and Fourteenth Amendments

    (42 U.S.C. 1983)

    67. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 66.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 17 of 30

  • 8/10/2019 Life Covenant Church Complaint

    18/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 18

    68. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its free exercise of religion, as secured by the First Amendment to the United States

    Constitution and made applicable to the States by the Fourteenth Amendment, by substantially

    burdening LifeChurchs religious exercise without a comp elling governmental interest, by

    discriminating against LifeChurch, and by intentionally and unreasonably inhibiting its right to

    construct a place of worship on its Property.

    COUNT VI

    Violation of the United States ConstitutionFreedom of Association: First and Fourteenth Amendments

    (42 U.S.C. 1983)69. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 68.

    70. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to freely associate for the purposes of religious exercise and for intimate association

    as secured by the First Amendment to the United States Constitution and made applicable to the

    States by the Fourteenth Amendment, by prohibiting LifeChurch from associating on its

    Property.

    COUNT VII

    Violation of the United States ConstitutionFreedom of Speech: First and Fourteenth Amendment

    (42 U.S.C. 1983)

    71. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 70.

    72. By intent and design, churches are expressive in nature. Among other things, they

    are architectural statements to the surrounding community of the churchs belief in God and in

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 18 of 30

  • 8/10/2019 Life Covenant Church Complaint

    19/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 19

    the necessity of looking to God for inspiration, guidance and salvation. The interior of a church

    is used for the expression of religious messages to church members, guests and casual visitors

    alike.

    73. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right, secured by the Free Speech Clause of the First Amendment to the United States

    Constitution and made applicable to the States by the Fourteenth Amendment, to express itself

    on matters of religion by, inter alia , discriminating against LifeChurch based on the religious

    nature of its expression, by unreasonably inhibiting its right to freely express its faith to its

    worshipers and the community, and by applying various land use regulations so as to delay,obstruct and unreasonably deny LifeChurch the ability to use its Property for expressive

    purposes.

    COUNT VIII

    Violation of the United States ConstitutionFreedom of Assembly: First and Fourteenth Amendments

    (42 U.S.C. 1983)

    74. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 73.

    75. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to free assembly for the purpose of worship, as secured by the First Amendment to the

    United States Constitution and made applicable to the States by the Fourteenth Amendment, by

    prohibiting LifeChurch from peaceably worshiping in a location where similar groups would be

    (and are) permitted to peaceably assemble.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 19 of 30

  • 8/10/2019 Life Covenant Church Complaint

    20/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 20

    COUNT IX

    Violation of the United States ConstitutionEqual Protection: Fourteenth Amendments

    (42 U.S.C. 1983)

    76. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 74.

    77. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to equal protection of the laws, as secured by the Fourteenth Amendment to the

    United States Constitution, by discriminating against LifeChurch and treating it differently from

    other similarly situated individuals or entities without a rational basis for the distinction.COUNT X

    Violation of the United States ConstitutionDue Process: Fourteenth Amendment

    (42 U.S.C. 1983)

    78. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 77.

    79. LifeChurch has the right, secured by the Due Process Clause of the Fourteenth

    Amendment to the United States Constitution, to a fair decision-making process and an impartial

    decision-maker before being deprived of the right to use its property for religious purposes.

    Specifically, LifeChurch has a procedural due process right to a land use review process that is

    non-discriminatory, unbiased, not unduly burdensome, and proceeds in a reasonably expeditious

    and fair fashion.

    80. By intentionally manipulating the land use approval process to create patently

    unreasonable delays, and by the other conduct alleged above, the Town and Town Officials have

    deprived and continue to deprive LifeChurch of its right to procedural due process.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 20 of 30

  • 8/10/2019 Life Covenant Church Complaint

    21/30

  • 8/10/2019 Life Covenant Church Complaint

    22/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 22

    COUNT XII

    Violation of New York State ConstitutionFreedom of Speech: Article I, Section 8

    85. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 84.

    86. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right, secured by Article I, Section 8 of the New York State Constitution, to express itself

    on matter of religion by, inter alia , discriminating against LifeChurch based on the religious

    nature of its expression, by unreasonably inhibiting its right to freely express its faith and to its

    worshipers and the community, and by applying various land use regulations so as to delay,

    obstruct and unreasonably deny LifeChurch the ability to use its Property for expressive

    purposes.

    COUNT XIII

    Violation of the New York State ConstitutionFreedom of Assembly: Article I, Section 9

    87. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 86.

    88. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to free assembly for the purpose of worship, as secured by Article I, Section 9 of the

    New York State Constitution, by prohibiting LifeChurch from peaceably worshiping in a

    location where similar groups would be (and are) permitted to peaceably assemble.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 22 of 30

  • 8/10/2019 Life Covenant Church Complaint

    23/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 23

    COUNT XIV

    Violation of the New York State ConstitutionEqual Protection: Article I, Section 11

    89. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 88.

    90. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of its right to equal protection of laws, as secured by Article I, Section 11 of the New York State

    Constitution, by purposefully and systematically discriminating against LifeChurch on the basis

    of religion in the Towns and Town Officials application of various land use regulations, which

    discrimination has resulted in the abridgement of LifeChurchs rights to freedom of religion,

    freedom of speech, freedom of association, freedom of assembly, and due process.

    91. The Town and Town Officials have subjected LifeChurch to a degree and

    duration of scrutiny which far exceeds that to which they have subjected similarly situated

    institutions. By imposing, implementing, and manipulating land use regulations in the manner

    described above, and by the conduct described above, the Town and Town Officials have

    deprived and continue to deprive LifeChurch of its right to equal protection of laws through their

    irrational and wholly arbitrary conduct.

    COUNT XV

    Violation of the New York State ConstitutionDue Process: Article I, Section 6

    92. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 91.

    93. LifeChurch, as a religious institution, is entitled under law to the benefit of a

    presumption that its religious use is beneficial to the community at large and that any approvals,

    permits and/or variances it seeks in connection with its development of its Property will be

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 23 of 30

  • 8/10/2019 Life Covenant Church Complaint

    24/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 24

    granted, subject only to reasonably conditions imposed to protect the public health, safety, and

    welfare.

    94. LifeChurch is further entitled to a land use review process that is non-

    discriminatory, is unbiased, is not unduly burdensome, and proceeds in a reasonably expeditious

    and fair fashion.

    95. The Town and Town Officials have deprived and continue to deprive LifeChurch

    of due process of law, as secured by Article I, Section 6 of the New York State Constitution, by

    intentionally delaying and manipulating the land use approval process to deny LifeChurch the

    use of its Property, and by conducting the land use approval process in an arbitrary, biased,unauthorized, and illegal manner which is discriminatory, unduly burdensome, and anything but

    expeditious and fair.

    96. Furthermore, the Town and Town Officials have deprived and continue to deprive

    LifeChurch of due process of law, as secured by Article I, Section 6 of the New York State

    Constitution, by intentionally delaying and denying to LifeChurch a fundamental liberty interest

    by conducting the land use approval process in an arbitrary, unauthorized and illegal manner

    which is discriminatory, unduly burdensome, and anything but expeditious and fair.

    COUNT XVI

    Petition for Writ of Mandamus

    97. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 96.

    98. LifeChurch has been adversely affected by the Town s and Town Officials

    unreasonable delays. The Town and Town Officials have failed to perform duties enjoined upon

    them by law. The Town and Town Officials, rather, seek to impose conditions on LifeChurchs

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 24 of 30

  • 8/10/2019 Life Covenant Church Complaint

    25/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 25

    zoning request that regulate critical aspects of LifeChurchs worship services and religious

    activities, including the number of worship services and the time for those worship services. See

    Exhibit A. The Town has communicated that those conditions, as more f ully set forth in

    Exhib it A, must be satisfied before the Town will consider LifeChurchs site plan application.

    99. LifeChurch has satisfied all of the Towns and Town Officials reasonable

    requests. The cond itions set forth in Exhibit A, however, are arbitrary and capricious.

    100. There is no discretion available to the Town and Town Officials not to place and

    keep LifeChurch on the Planning Boards agenda, and all that is left for the Town and Town

    Officials to perform is a ministerial act. The Town and Town Officials have refused to performthis ministerial act. In the alternative, in the event that the Town and Town Officials have

    discretion to place LifeChurch on the Planning Boards agenda, their failure to place and keep

    LifeChurch on the Planning Boa rds agenda is an arbitrary abuse of their power.

    101. LifeChurch requests that the Towns conditions set forth in Exhibit A be

    annulled and LifeChurchs site plan application be approved. In the alternative, LifeChurch

    requests that this Court issue a writ of mandamus directing the Town and Town Officials to place

    and keep LifeChurchs site plan application on the Planning Boards agenda and the Court

    further order the Town Planning Board vote as to whether LifeChurchs site plan application be

    approved or denied.

    COUNT XVII

    Declaratory Relief

    102. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 101.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 25 of 30

  • 8/10/2019 Life Covenant Church Complaint

    26/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 26

    103. For more than twenty (20) months, the Town and Town Officials have unlawfully

    delayed and frustrated LifeChurchs efforts to gain the requisite approvals to develop its Property

    and begin its Project.

    104. An actual controversy exists between the parties involving substantial

    constitutional and statutory issues, in that the Town and Town Officials actions, both on their

    face and as applied, violate LifeChurchs rights under, inter alia , RLUIPA, the United States

    Constitution, and the Constitution of the State of New York.

    105. The foregoing dispute presents a real controversy which is now ripe for

    adjudication. Accordingly, LifeChurch seeks a declaratory judgment against the Town andTown Officials as follows:

    (a) A declaration that the Town s and Town Officials actions related to LifeChurch

    violate RLUIPA; violate LifeChurc hs freedom of religion, freedom of association,

    freedom of speech, freedom of assembly, equal protection and due process rights under

    the United States Constitution; and violate LifeChurchs freedom of religion, freedom of

    speech, freedom of assembly, equal protection and due process rights under the New

    York State Constitution.

    (b) A declaration that the Town s and Town Officials actions related to LifeChurch have

    unjustifiably substantially burdened LifeChurchs Christian practices in violation of 42

    U.S.C. 2000cc(a)(1).

    (c) A declaration that the Towns arbitrary and capricious conditions set forth in Exhibit

    A shall by annulled and LifeChurchs site plan application be approved.

    106. No prior application for the relief being sought herein has been made to this Court

    or to any other court.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 26 of 30

  • 8/10/2019 Life Covenant Church Complaint

    27/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 27

    COUNT XVIII

    Preliminary and Permanent Injunction

    107. LifeChurch incorporates herein by reference as if fully set forth below the

    allegations contained in paragraphs 1 through 108.

    108. The Town and Town Officials have deprived LifeChurch of the constitutional and

    statutory rights mentioned above by intentionally delaying, manipulating and thwarting the

    municipal approval process and by such other actions and inactions as alleged above.

    109. LifeChurch has been irreparably injured as a result of the deprivation of its

    constitutional rights.

    110. By reason of the foregoing, LifeChurch is entitled to preliminary and permanent

    injunctive relief, as set forth in its request for relief herein.

    VI.

    REQUEST FOR RELIEF

    WHEREFORE, for the foregoing reasons, LifeChurch requests that this Court grant the

    following relief:

    1. A declaration that the Town s and Town Officials actions related to LifeChurch

    violate RLUIPA; violate LifeChurchs freedom of religion, freedom of association, freedom of

    speech, freedom of assembly, equal protection and due process rights under the United States

    Constitution ; and violate LifeChurchs freedom of religion, freedom of speech, freedom of

    assembly, equal protection and due process rights under the New York Constitution.

    2. A declaration that the Town s and Town Officials actions related to LifeChurch

    have unjustifiably substantially burdened LifeChurch s Christian practices in violation of 42

    U.S.C. 2000cc(a)(1).

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 27 of 30

  • 8/10/2019 Life Covenant Church Complaint

    28/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 28

    3. A declaration that the Towns arbitrary and capricious conditions set forth in

    Exhibit A shall by annulled and LifeChurchs site plan application be approved.

    4. Preliminarily and permanently enjoining and restraining the Town and Town

    Officials and ordering prohibitory and mandatory relief as follows:

    (a) enjoining the Town and Town Officials from applying their laws in a manner that

    substantially burden Life Churchs religious exercise;

    (b) enjoining the Town and Town Officials from imposing or implementing State and

    local land use regulations in a manner which treats LifeChurch on less than equal terms

    with other similarly situated assembles, institutions, or entities;(c) enjoining the Town and Town Officials from applying State and local land use laws in

    a manner that prevent LifeChurch from associating for purposes of expressive religious

    activity;

    (d) enjoining the Town and Town Officials from applying State and local land use laws

    in a discriminatory manner, and otherwise enjoin the Town and Town Officials from

    preventing Life Churchs exercise of its constitutional rights;

    (e) c ompelling and directing the Towns Planning Board to issue all necessary approvals

    and permits to allow LifeChurch to develop the Project;

    (f) prohibiting the Town and Town Officials from impeding or interfering in any way

    with LifeChurchs actual development and construction of the Project; and

    (g) annulling the conditions set forth in Exhibit A that the Tow n seeks to impose on

    LifeChurch, or in the alternative, issuance of a writ of mandamus directing the Town and

    Town Officials to place and keep LifeChurchs site plan application on the Planning

    Boards agenda and to vote on LifeChurchs site plan applicati on.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 28 of 30

  • 8/10/2019 Life Covenant Church Complaint

    29/30

    PLAINTIFFS ORIGINAL COMPLAINT Page 29

    5. Awarding compensatory damages in favor of LifeChurch and against the Town

    and Town Officials in such amount as the Court deems just and proper to compensate

    LifeChurch for the deprivation of its constitutional and statutory rights, and to compensate

    LifeChurch for its expenditures and fees caused by the Town s and Town Officials intentional

    and wrongful course of conduct which has delayed, obstructed and unreasonably denied

    LifeChurch the ability to develop its Property in an efficient and expeditious manner.

    6. Awarding LifeChurch the recovery its rea sonable and necessary attorneys fees,

    expert fees, costs, and expenses from the Town and Town Officials pursuant to 42 U.S.C.

    1988.7. Awarding LifeChurch the recovery of pre-judgment and post-judgment interest at

    the maximum applicable legal rates from the Town and Town Officials.

    8. Awarding LifeChurch the recovery of such other and further relief, both at law

    and in equity, to which it may show itself to be justly entitled.

    VII.

    DEMAND FOR JURY

    Pursuant to Rule 38(b) of the Federal Rules of Civil Procedure, LifeChurch hereby

    demands a trial by jury of this action of all issues that may be tried by a jury.

    LifeChurch respectfully submitted this 17th day of December, 2014.

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 29 of 30

  • 8/10/2019 Life Covenant Church Complaint

    30/30

    Respectfully submitted,

    /s/ Chr istoph er A. Pr iore ____________________CHRISTOPHER A. PRIOREState Bar No. 5054960

    DONALD ZEE, P.C.1 Winners Cir Ste 140Albany, NY 12205Phone: (518) 489-9423Fax: (518) 489-9428Email: [email protected]

    MICHAEL L. KNAPEK (pending pr o hac vice)Texas State Bar No. [email protected] W. DIMITT (pending pr o hac vice)

    Texas State Bar No. [email protected] WALKER L.L.P.901 Main Street, Suite 6000Dallas, Texas 75202(214) 953-6000 (telephone)(214) 661-6882 (facsimile)

    ATTORNEYS FOR PLAINTIFF LIFECOVENANT CHURCH, INC.

    11847771v.1 141947/00002

    Case 1:14-cv-01530-LEK-RFT Document 1 Filed 12/17/14 Page 30 of 30