1 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)1
Joel DarringtonContracting CounselDPR [email protected]
Brian PerlbergExecutive Director [email protected]
Tom RichertPrincipal Lean Project Consulting, [email protected]
Lean Contracting Practices without an IPD Contract and the New ConsensusDocs 305 Lean Construction Addendum
![Page 2: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/2.jpg)
2 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)2
ConsensusDocs 12+ Years
$1,000,000+ In donated free educational licenses.
12Years publishes best practice contracts
100+ Standard contract documents.
40Leading construction associations participating in the Coalition.
3,000+Subscribers.
1 GoalImprove the design and construction industry with Best Practice Contracts
$40+ Billion in Construction Contracts
ZERO Reported Cases
![Page 3: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/3.jpg)
What is the ConsensusDocs 305?
Owner/Design
ProfessionalContract
CD 305 Lean
ConstructionAddendum
Owner/Constructor
Contract
3 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)3
![Page 4: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/4.jpg)
Ways to Contract for Lean Design + Construction
• Integrated Project Delivery (IPD) Agreement (a/k/a IFOA)• e.g., CD 300 (2016 edition)
• Custom-created IPD-ish design & construction agreements• Vague references to Lean added to an owner’s standard
contract• Now with CD305, an industry standard form outside of IPD
that addresses a wide spectrum of Lean practices
4 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)4
![Page 5: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/5.jpg)
Addendum to What?
ConsensusDocs 305 can be used with:• ConsensusDocs 500 Agreement between Owner & CM• Other forms of CM at Risk contracts• Construction contracts under Design-Bid-Build• Owner contracts with Design Professional
• Not intended for Design-Build Prime Contracts, but … • ConsensusDocs 341 will be published this summer.
5 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)5
![Page 6: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/6.jpg)
How is this Different than IPD?
Owner
CM/GC
Key Trades
Key Design Consultants
IPD
Owner
CM/GC
Design Prof.
Sub-contractors
CD 305
Specialty Designers
CD305
6 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)6
DesignProf.
![Page 7: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/7.jpg)
Addendum vs. Silence
• Increase alignment among parties• First collaborative act• Parameters for Lean behavior and activities• Some Lean methods will conflict with standard contract
language, so Addendum overrides • Allows enforcement of Lean requirements, but take care
7 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)7
![Page 8: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/8.jpg)
Using the CD 305
• When? • O/A/C are committed to Lean, but one or more are not
ready or able to enter an IPD Agreement• As early in the Project as the Owner will allow
• How?• Jointly negotiated, separately attached• Check-the-box
8 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)8
![Page 9: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/9.jpg)
Typical Chronology of IPD Project
Allowable Cost
Preconstruction Phase Construction Phase
Expected Cost & Target Cost
Contract PriceActual Cost
Validation Phase
9 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)9
![Page 10: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/10.jpg)
CD305 Check-the-Box Example 1
Preconstruction Phase
Construction Phase
Validation Phase
Joint Worksite Investigation (6.1)
Evaluate Owner’s Program (6.2)
Validation Study (6.3)
Continuous Cost Modeling (6.4)
Integrated Design/Target Value Design (6.5)
Risk Identification/Management (6.6)
(Always included; no check boxes)
10 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)10
![Page 11: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/11.jpg)
CD305 Check-the-Box Example 2
Preconstruction Phase
Construction Phase
Validation Phase
Joint Worksite Investigation (6.1)
Evaluate Owner’s Program (6.2)
Validation Study (6.3)
Continuous Cost Modeling (6.4)
Integrated Design/Target Value Design (6.5)
Risk Identification/Management (6.6)
(Always included; no check boxes)
11 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)11
![Page 12: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/12.jpg)
CD305 Check-the-Box Example 3
Preconstruction Phase
Construction Phase
Validation Phase
Joint Worksite Investigation (6.1)
Evaluate Owner’s Program (6.2)
Validation Study (6.3)
Continuous Cost Modeling (6.4)
Integrated Design/Target Value Design (6.5)
Risk Identification/Management (6.6)
(Always included; no check boxes)
12 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)12
![Page 13: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/13.jpg)
What about Incentives?
• CD305 does not itself provide for incentive compensation
• Too much variability to standardize incentives
• CD305 does provide for Performance Improvement Program, which individual projects could use as a platform for incentive compensation
• Provide for incentives through amendment to Owner contracts
13 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)13
![Page 14: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/14.jpg)
Reliable Promises 3.3
• Conditions of satisfaction must be clear
• Competent to perform
• Time estimated and reserved
• Performer sincere
• Performer accepts consequences
14 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)14
![Page 15: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/15.jpg)
• Owner, Design Professional, and Constructor Reps, plus others invited
• Resolves problems through consensus decisions and best interests of the project
• Selects team• Provides daily leadership for the project• Manages budget and design process• Implements production control• Oversees personnel and team members.
15 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)15
Core Group Owner, Design Professional, Constructor
![Page 16: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/16.jpg)
• Candor and thick skin
• Enthusiasm for change and improvement
• Commitment to goals and principles
• Ability to decide and commit
• No hierarchy
• Shared accountability and responsibility.
16 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)16
Core Group - Key Attributes
![Page 17: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/17.jpg)
• 15 performance metrics
• Periodic evaluations
• A focus on team members’ behaviors
• Clear standards for evaluating performance
• Feedback mechanism on improvements.
17 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)17
Performance Improvement Program
![Page 18: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/18.jpg)
• Aligning Personal, Team and Project Goals
• Focus on Clarity of Requests and Commitments
• Coaching
• Equip the Team for Rapid Learning
18 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)18
Implementing Team Leadership & Culture
![Page 19: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/19.jpg)
Aligning Personal, Team and Project Goals
19 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)19
![Page 20: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/20.jpg)
20 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)20
Focus on Clarity of Requests and Commitments
![Page 22: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/22.jpg)
Where you are.
Where you want to be.
22 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)22
Equip the Team for Rapid Learning
![Page 23: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/23.jpg)
• Section 5.1• What is a Project Planning System• Weekly Planning Cycle• Daily Adjustments• Implied Practices
23 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)23
Project Planning System
![Page 24: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/24.jpg)
Source: Ballard, Tommelein. 2016 Benchmark for the Last Planner System®
24 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)24
What is a Project Planning System
®
![Page 28: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/28.jpg)
Allowable Cost
Expected Cost & Target Cost
Validation PhaseJoint Worksite Investigation (6.1)
Evaluate Owner’s Program (6.2)
Validation Study (6.3)
Program Services & Validation
28 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)28
![Page 29: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/29.jpg)
Preconstruction Phase
Expected Cost & Target Cost
Continuous Cost Modeling (6.4)
Integrated Design/Target Value Design (6.5)
Risk Identification/Management (6.6)
29 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)29
Integrated Design & TVD
![Page 30: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/30.jpg)
Preconstruction Phase: Constructor to:• Provide continuous cost modeling and analysis• Generate periodic cost model reports
Construction Phase: Constructor + Subcontractors to:• Provide cost information and estimates requested by Core Group
Core Group to:• Establish milestones for updating Project cost model• Direct actions if cost model exceeds Allowable Cost
Compare to lower design-assist option in CD 541.
30 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)30
Continuous Cost Modeling
![Page 31: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/31.jpg)
• Collaborative – DP still in charge and responsible, but must coord. + integrate with Team
• Value, Cost and Schedule and constructability are basic components of design (6.5.1)
• Written Protocols for Target costs [6.5.7.3 (a-h)]
• Add value w/ VAPs, TVD Clusters, A-3s (6.5.8)
• Design phases – planning/programming, design, detailing,
and production planning
• Uses pull based design process to drive innovation
31 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)31
Target Value Design
![Page 32: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/32.jpg)
Document Review
• Examine Design Documents with reasonable care
• Advise Core Group of issues prompting additional contingency
• Suggest options for additional investigation
Target Value Pricing 6.5.7
• Establish Expected Cost and Target Cost early
• Target Cost only exceeded by express approval of Core Group.
32 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)32
Target Value Design Processes
![Page 33: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/33.jpg)
Continuing refinement of cost models
Cost analysis not to be deferred• Byproduct of continuing TVD process• Core Group jointly manages
Escalation addressed in:• Estimates• Expected Cost• Target CostExpected Cost and Target Cost adjusted• At Final Completion• Reflecting difference between escalation allowance and actual escalation
33 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)33
Target Value Pricing
![Page 34: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/34.jpg)
• BIM (verb) as a process not a software application
• Interconnected models and databases
• The power of BIM makes the payoff of lean greater –Provide continuous, immediate, and
reliable informationRegarding design, scope, schedule,
and cost.
34 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)34
Building Information Modeling (B.I.M.)
![Page 35: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/35.jpg)
Design Model As-Built
Design Model Vs As-Built
www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)
![Page 36: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/36.jpg)
Design As-Built
Des
www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)
![Page 37: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/37.jpg)
• Identify material risks in early workshops
• Create risk identification report• Rank and focus on higher priority risksLikelihood of occurrenceTime and cost impacts
• Develop Risk Management Plan withContingency plansAssignment of primary responsibilityAddress roles of others in managing risk
37 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)37
Risk Assessment and Management 6.6
![Page 38: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/38.jpg)
Article 7
• 5S Plan• Quality, Standardized Work, PDCA• Material Flow• Information Flow
38 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)38
Construction Phase Lean Features
![Page 39: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/39.jpg)
5S Plan
39www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)39 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)39
Sort Set in Order Shine/Sweep
Standardize Sustain
![Page 40: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/40.jpg)
40 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)40
Quality, Standardized Work, PDCA
![Page 41: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/41.jpg)
41 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)41
Material Flow
![Page 43: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/43.jpg)
ConsensusDocs 541 Design Assist Addendum• Addendum to prime agreements, consultant and subs• Optional tools from CD 305:
• BIM• Owner’s program evaluation• Value Analysis• Cost modeling• Optional risk analysis• Optional production planning
• Constructability (in 541 only) • Manpower analysis, design-build packages early
procurement packages, etc. (in 541 only) • Design Coordination (in 541 only).
43 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)43
![Page 44: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/44.jpg)
How do you Structure the ConsensusDocs 305 & 541?
Owner
Constructor
Key Trades
Key Design Consultants
DesignProf.
IPDCD 300
Owner
CM/GCDesign
Prof
Sub-contractors
CD 305CD 541
Specialty Designers
CD305
44 www.consensusdocs.org| [email protected] | 866.925.DOCS (3627)44
CD 541or both
![Page 45: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/45.jpg)
TheCollabometer
DesignAssist
“Collabometer” Courtesy of Jack Mumma Michigan State University
45
![Page 46: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/46.jpg)
Design-Assist can help Prevent Against
www.consensusdocs.org| [email protected] | 866.925.DOCS (3627)
![Page 47: Lean Contracting Practices without an IPD Contract and the ... · Escalation addressed in: ... • Optional tools from CD 305: • BIM • Owner’s program evaluation • Value Analysis](https://reader035.vdocuments.us/reader035/viewer/2022071022/5fd704afaff616705e7f7cd1/html5/thumbnails/47.jpg)
47 www.consensusdocs.org | [email protected] | 866.925.DOCS (3627)47
Joel DarringtonContracting CounselDPR [email protected]
Brian PerlbergExecutive Director [email protected]
Tom RichertPrincipal Lean [email protected]
Lean Contracting w/o IPD & the New ConsensusDocs 305Download a sample by registering at www.consensusdocs.org.