john hart generating station replacement project june 2016 ... · june 2016 community construction...
TRANSCRIPT
John Hart Generating Station
Replacement Project
June 2016
Community Construction Update
Report #36
Prepared by: Stephen Watson, BC Hydro
(O) 250-755-4795 or (C) 250-616-9888
Twitter: @Puntledge Email: [email protected]
Three Years!
• Intake maintenance gate excavation (upstream of
existing dam) is now complete. Form and concrete
work to begin;
• The 60 metre intake shaft (downstream of dam) is
nearly complete, reaching the elbow point at the
bottom where it will connect to the power tunnel;
• Power tunnel is progressing toward the dam and
has reached the location of the surge shaft. Once
some preparation is completed, progress will
continue simultaneously on both the surge shaft
and power tunnel;
• Pilot hole for the 110 metre surge shaft completed;
• Concrete placement work well underway in the
powerhouse cavern; and
• Main access tunnel progressing well.
Project Status
Powerhouse cavern.
• June-February 2017:
Concrete work for
generator units in the
powerhouse;
• July: Main access
tunnel meets Adit D;
• July: Boring to begin
on surge shaft, working
from the bottom, up;
• November: Installation
of piping, pumps at
tailrace outlet
complete; and
• December: Excavation
under the John Hart
dam. Expected to be
complete in January
2017.
Project Schedule
Power tunnel excavation has now
progressed past the surge shaft.
Construction Pictures – Powerhouse Cavern
8
We have a new time lapse camera on the site, and this will take constant pics of the powerhouse cavern to show the advancements over time.
June 3
Construction Pictures – Powerhouse Cavern
11
Placement of form work, rebar and concrete for the sump areas that go underneath each of the three
turbines. Carpenters are working two shifts per day, 10 hours per shift, to build the wooden forms for the
concrete. There are now about 360 people working on the project in Campbell River. Much of this
increase is in carpenters for the concrete form work, iron workers and a few millwrights/labourers.
Construction Pictures – Powerhouse Cavern
12
A temporary crane was installed this month to help move in equipment and place
concrete.
Construction Pictures – Tailrace
15 Did you know: Will Campbell River water flows change as a result of the John
Hart project? Shaw TV: https://www.youtube.com/watch?v=ONidwO1pPxs&index=13&list=PL20EhecUEwZtYOsO1f35vttwd
D0hR0Ci3
John Hart
Project
Community Site
Event – July 17
16
People attending will get one of
these…a coveted fridge magnet.
Environment Update
17
While many are focused on the daily work required to make the John Hart project a success, the
environment team is thinking in terms of years – looking ahead to 2018/2019 when a
comprehensive replanting process will begin:
• Restoration plans will combine both density planting and natural means: in areas next to
broom stands, high-density planting will be required;
• Allowing restoration by natural means still requires work from the project team as they
manage invasive species and create ‘rough and loose’ terrain to encourage the spread of
natural species;
• Because new plantings are required to be ‘2-year stock’ – plans for the earliest stages of
restoration beginning 2018 are required now to ensure the plants meet that age requirement;
and
• Focus at this time is on project impact areas – areas where construction is underway now.
The restoration plan for the penstock corridor will be developed at a later date.
Tadpoles in Wetland E off Surge Tower Road, a deer with two fawns that came onto the site, and another saved ‘critter.’
People Profile – Valerie Masterman
Background:
Valerie is a Registered Professional Biologist (RP Bio) with a Bachelor of
Science from the University of Toronto and Master’s Degree in
Environmental Management from the University of Nottingham (UK). She’s
worked with Hatfield Consultants for almost 10 years on a range of projects
from water resource planning in Southern Africa to Agent Orange
contaminant pathway Investigations in Viet Nam, to environmental auditing
of the South Fraser Perimeter Road Project in the Lower Mainland.
Home:
Valerie grew up on Quadra Island before setting sail at the age of 17 for a
2-year International Baccalaureate term in Singapore. Since then she’s lived
in Toronto, Nottingham (England), India and Vancouver before moving back
‘home’ in 2014 for the John Hart project. Here, Val and her family (husband,
Stu, daughter Zoe (2) and soon-to-arrive baby) can be near family.
Hobbies:
Being outside is what matters most for Valerie and family: from rock climbing to sailing, hiking to skiing, being active outdoors is their main hobby.
Project Responsibility:
As on-site environmental coordinator, Valerie is responsible for guiding the constructor (ASL-JV) in environmental matters, including mitigation and compliance. Her position is shared between SNC-Lavalin and ASL-JV.
“I wanted to come back and be close to home – this job was that opportunity, and then it became the best job ever.”
About Valerie
Construction – Point Of Interest
Each month, BC Hydro and InPower BC will provide a construction
fact, occurrence, or situation.
SNC-Lavalin GEMS environmental Audit.
The John Hart Generating Station Replacement Project is one
of the best in the world when it comes to environmental
performance according to SNC-Lavalin’s corporate
environmental audit system:
• GEMS (Global Environment Management System) is the
way that SNC-Lavalin monitors the quality of
environmental protection on its projects around the world;
• It includes an annual audit conducted by GEMS
representatives which assesses 16 topic areas including
sediment control, flora and fauna, and environmental
record management systems;
• Last year, the John Hart project received a 97 per cent on
its assessment, and in the 2016 audit (conducted in mid-
June), the project managed to improve that number to 99
per cent; and
• This puts this project at number one in environmental
performance for all of SNC-Lavalin’s projects around the
world.
Polyphemus Moth