introduction to leed building commissioning
DESCRIPTION
Introduction to LEED Building Commissioning. Presented by Bob Alpers, PE TESTMARCx Commissioning Solutions. Agenda. Benefits Introduction to LEED Commissioning Requirements and Deliverables Process Questions. Commissioning Purpose. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/1.jpg)
Introduction toLEED
Building Commissioning Presented by Bob Alpers, PE
TESTMARCx Commissioning Solutions
![Page 2: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/2.jpg)
Agenda
Benefits Introduction to LEED Commissioning Requirements and Deliverables Process Questions
![Page 3: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/3.jpg)
How does the building function relative to the Owners Project Requirements?
Commissioning Purpose
![Page 4: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/4.jpg)
Benefits & Cost Savings Cost to Change
Concept Design Construction Acceptance Occupancy
$
Time
When should we start Commissioning?
![Page 5: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/5.jpg)
What is systems are impacted most?
Control System Problems Comfort Problems Air Quality Problems Building Maintenance Costs Operations Staff
understanding
![Page 6: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/6.jpg)
LEED Objective – Get Certified
LEED Rating Points Required
Certified 26-32 points
Silver 33-38 points
Gold 39-51 points
Platinum 52-69 points
Buildings Certified Under USGBC Guidelines
![Page 7: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/7.jpg)
LEED- EA Prerequisite 1
Water
Efficiency
8%Energy &
Atmosphere
27%
Materials &
Resources
20%
Sustainable
Sites
22%
Indoor
Environmental
Quality
23%
Commissioning underEnergy and Atmosphere
![Page 8: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/8.jpg)
WHAT ARE THE LEED Commissioning ACTIVITIES?
Energy and Atmosphere Credit Category
EA Prerequisite 1 ( required, must be completed) Fundamental Commissioning
EA Credit 3 ( additional available point) Enhanced Commissioning
![Page 9: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/9.jpg)
Fundamental Commissioning
Pre-Requisite 1 Overview:
1. Designate a third party Cx
2. Review OPR and BOD Document
3. Specify Commissioning in CD
![Page 10: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/10.jpg)
Fundamental Commissioning
Prerequisite Overview (Cont’d)
4. Develop a Cx Plan.
5. Verify installation meets BOD
6. Verify performance of systems
7. Summary report
8. Certify Commissioned
![Page 11: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/11.jpg)
Fundamental CommissioningEA Prereq. 1
The Process Under LEED
![Page 12: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/12.jpg)
Project Milestones in Construction Schedule
Project Timeline
PLAN DESIGN CONSTRUCT ACCEPT OCCUPANCY
Review Owners Functional
Requirements
& Basis of Design
Functional Testing
Final CxReport
Commissioning Plan
ScopingMeetings
Verify InstallationPre-Functional
Checklist
Collect Start-upCheck sheets
Incorporate
Commissioning
Specification
![Page 13: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/13.jpg)
Owners Project Requirements Workshops
Small groups to work out concepts
![Page 14: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/14.jpg)
Commissioning Plan
The commissioning plan must contain: Overview & goals Project information Systems to be commissioned Team’s roles & protocol Describe Deliverables List Key Milestones and schedule.
![Page 15: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/15.jpg)
What Systems does LEED require Commission? Systems and Assemblies having to do with
operational efficiencies: HVAC Systems Building Automation Lighting Controls Domestic Heating Renewable Energy
![Page 16: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/16.jpg)
Contract Divisions 1, 15 and 16
Commissioning Specifications
![Page 17: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/17.jpg)
Installation Verification
Focus is O&M
![Page 18: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/18.jpg)
Master Deficiency List
Date
Item
#
EQUIP #
/Spec
Section
DATE
REVIEWEDFIV/ FPT/O&M DEFICIENCY RESP. ACTION TAKEN
DATE Cx
VERIFIED
1 Panel HCR2 8/9/2004 FIVThe electrical working clearance for Panel HCR2 is not per NEC 110. Panel LCR2 blocks the right portion of the panel width within the 42" reqmt.
CEC
2 Panel LCR2 8/9/2004 FIV
The electrical working clearance for Panel LCR2 is not per NEC 110. The conduits at the floor in front of the panel, penetrate the floor in front of the plane of the panel can.
CEC
3 Panel HN3 8/9/2004 FIV
The electrical working clearance for Panel HN3 may not be per NEC 110. The transformer and flexible conduits @ the floor must be 42" from the panel (exposed live parts).
CEC
4 Panel LCR5 8/9/2004 FIVThe electrical working clearance for Panel LCR5 is not per NEC 110. The adjacent panel can blocks the right portion of the panel width within the 36" reqmt.
CEC
5 AHU 1 8/9/2004 FIVThe chilled water coil pull is blocked by the header at the coil.
B&KFlanged connections have been provided in the piping above the coil for piping removal for coil pull.
JAH9/20/04
6 RF 5A 8/9/2004 FIVThe relief duct is tapped into the back of the 90 degree silencer.
B&KPCA
Relief duct tap into 90o silencer approved and designed by M&I Systems.
JAH9/20/04
7 RF 5A and B 8/9/2004 FIV
The FSDs at the floor entering the return (see sheet M406) are not accessible without dismantling a section of the fabricated return plenum. An access door is not shown to be installed.
B&KPCA
Removable access panels have been provided in the return plenum for access to FSDs.
JAH9/20/04
Master Deficiency List
February 3, 2005(latest deficiencies in bold text)
![Page 19: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/19.jpg)
Verify System Performance
Functional Testing of Systems: Observe Startup Activities Functionally Test Equipment and Systems
![Page 20: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/20.jpg)
Final Commissioning Report
Must be presented to the owner within reasonable time and must include: Executive summary Testing results Deficiency List and History Outstanding Issues BOD review.
![Page 21: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/21.jpg)
Enhanced CommissioningEA Credit 3
The Process Under LEED
![Page 22: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/22.jpg)
Enhanced Cx
EA Credit 3 ( additional credit 1 point) Design Review Contractor Submittals Review Verify Training 10th Month Warranty & Operations Review Systems manual
![Page 23: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/23.jpg)
Fundamental & Enhanced
Project Timeline
PLAN DESIGN CONSTRUCT ACCEPT OCCUPANCY
Owners Functional
Requirements
& Basis of Design
Functional Performance
Testing
CxReport and
Systems ManualSubmittal & O&M
Review
Commissioning Plan
ScopingMeetings
Design DocumentReviews &
Commissioning In Specification Verify
Training
Warranty Review
10th month
Operation
Verify Installation & Checklist
Start-up
Revised Plan
![Page 24: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/24.jpg)
Review Mechanical Systems Sequence of
Control for Clarity
Enhanced – The Design Review
![Page 25: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/25.jpg)
Review Mechanical Equipment Submittal
Documents for Completeness
Enhanced -Submittal Review
![Page 26: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/26.jpg)
Enhanced – Verify Training
![Page 27: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/27.jpg)
Organizes the O&M Manual by
Commissioned System
Enhanced –Systems Manual
All of Chilled Water Storage in one Section of Manual
![Page 28: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/28.jpg)
Enhanced -Verify Training
Training meets requirements: Review Spec & Verify meet Spec. Include General
Purpose of systems Must include use of O&M
Manuals Must include operation
all modes Must be Qualified
Trainers
![Page 29: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/29.jpg)
Enhanced-Warranty ReviewSeasonal Testing
Functional Tests for Summer vs. WinterCheck Warranty Status and advise
![Page 30: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/30.jpg)
Issues & Lessons Learned
General Commissioning is Part of the Design Team Contractors understand the commissioning TEAM’s
Role Energy Efficient Systems
Controls Become Complex and increase Risks Technology is beyond Contractor Experience Coordination of interposing systems is critical
Control Systems Integration is coordinated Schematic diagrams, Sequence of control and point
lists are necessary Details of BMS get input from owner
Owner Training Video tape or not? Meeting with Staff to discuss needs Detailed Description in Spec of O&M needs. Systems Manual training
![Page 31: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/31.jpg)
Case Study
Community College Bldg. Classroom Laboratories
MEP Commissioning Started Late in Construction
Phase Issues
Integrate Phoenix Fume with ALC controls
System Balance Unoccupied Mode
Operation Success
teamwork
![Page 32: Introduction to LEED Building Commissioning](https://reader033.vdocuments.us/reader033/viewer/2022061608/5681581b550346895dc58047/html5/thumbnails/32.jpg)
LEED Commissioning
Questions?