introduction to dispute boards - camaramedellin.com.co board… · * see conditions of contract for...

35
The Dispute Board Federation Introduction to Dispute Boards Excellence in Dispute Resolution since 2001

Upload: nguyendan

Post on 15-Feb-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Introduction to Dispute Boards

Excellence in Dispute Resolution since 2001

Page 2: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Types of Dispute Boards

1. Dispute Review Board (‘DRB’):

• A DRB issues ‘Recommendations’, which are non-binding opinions.

• If no party expresses dissatisfaction with a Recommendation within a

© 2013 The Dispute Board Federation 2

• If no party expresses dissatisfaction with a Recommendation within astated time period, compliance is required.

• If a party expresses dissatisfaction within a certain period of time, thatparty may resort to arbitration, if so provided, or the courts. Pending aruling by the arbitral tribunal or the court, the parties are not required tocomply with the Recommendation.

Page 3: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Types of Dispute Boards (cont’d)

2. Dispute Adjudication Board (‘DAB’):

• A DAB issues ‘Decisions’, which are binding.

• The parties must comply with a Decision as soon as they receive it.

© 2013 The Dispute Board Federation 3

• If a party expresses dissatisfaction with a Decision within a specific time period,it may submit the dispute to final resolution by arbitration, or the courts, but theparties meanwhile remain contractually bound to comply with the Decision.

3. Combined Dispute Board (‘CDB’):

• A CDB normally issues Recommendations but may issue a Decision if a partyso requests and no other party objects.

Page 4: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

History of Dispute Boards

The first DB was called a Dispute Review Board (“DRB”) and it made

recommendations rather than decisions. Major developments regarding DRBs

were as follows:

1975 First Domestic DRB in U.S. (Eisenhower Tunnel)

© 2013 The Dispute Board Federation 4

1975 First Domestic DRB in U.S. (Eisenhower Tunnel)

1981 First international DRB (EL Cajon Dam, Honduras)

1995 World Bank makes DRBs mandatory for all IBRD-financed projects over US$50m

1997 Asian Development Bank and EBRD adopt DRB approach

Page 5: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

History of Dispute Boards

Subsequently, the Dispute Adjudication Board (“DAB”), which made decisions rather

than recommendations, developed internationally, as follows:

1995 FIDIC introduces DAB in its Orange Book

1998 England introduces mandatory statutory adjudication; subsequently, parts

© 2013 The Dispute Board Federation 5

1998 England introduces mandatory statutory adjudication; subsequently, parts of Australia, New Zealand and Singapore do the same

1999 FIDIC adopts DAB in all contracts for major works

2000 World Bank adopts DB recommendations as binding and requires parties to give effect to them unless and until revised by an arbitral award

2001 The Dispute Board Federation formed

Page 6: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

The Internationally-Accepted Options for Dispute Boards

The Four Main Internationally-Accepted Options for Dispute

Boards

© 2013 The Dispute Board Federation 6

Boards

Page 7: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

The FIDIC Rules

I. FIDIC [Fédération Internationale des Ingénieurs–Conseils]

• FIDIC Clause 20 (“Claims, Disputes and Arbitration”) provides for a

© 2013 The Dispute Board Federation 7

• FIDIC Clause 20 (“Claims, Disputes and Arbitration”) provides for acombination of a “Dispute Adjudication Board” (20.4), amicablesettlement (20.5), and ICC arbitration (20.6), in that order.*

* See Conditions of Contract for Construction (1st ed. 1999) (“CONS”), Conditions of Contract for Plant andDesign-Build (1st ed. 1999) (“P&DB”), and Conditions of Contract for EPC/Turnkey Projects (1st ed. 1999)(“EPCT”).

Page 8: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

The FIDIC Rules (cont’d)

FIDIC Clause 20: Dispute Adjudication Board or “DAB”

1. Now used by World Bank and all international development banks.

2. Constitution: 1 or 3 members, usually engineers, independent of parties, but all accepted by parties and/orappointed by FIDIC.

3. Permanent (Red Book) or Ad Hoc (Silver and Yellow Books).*

© 2013 The Dispute Board Federation 8

Permanent DAB: maintains familiarity with project, visits site periodically, decides disputes that arise by(provisional) binding decisions.

Ad Hoc DAB: constituted for and decides an individual dispute by a (provisional) binding decision.

4. Experience to date: successfully used on all major projects in U.S. and internationally.

* Conditions of Contract for Construction Works (for Buildin g and Engineering Works Designed by theEmployer) (1999) (Red book); Conditions of Contract for Plant and Design–Build For Elect rical andMechanical Works and for Building and Engineering Works Des igned by the Contractor ) (1999) (YellowBook); Contract for EPC Turnkey Projects (1999) (Silver Book).

Page 9: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

FIDIC (cont’d)

8.1 Com-

mencement

Date of the Project

20.2 Parties

appoint

the DAB

20.4 A Party

refers a dispute

to the DAB

20.4 A Party may

issue a “notice of

dissatisfaction”

20.6 Parties

initiate

arbitration

Typical Sequence of Dispute Events Envisaged in Clause 20

© 2013 The Dispute Board Federation 9

Parties present

submissions to the DAB

DAB gives its decisionArbitrator(s) appointed

< 28d < 84d < 28d < 56d

Amicable Settlement

Page 10: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

FIDIC (cont’d)

FIDIC Clause 20: Arbitration

• The FIDIC Arbitration Clause provides for arbitration by 3 arbitratorsaccording to the ICC Rules and (normally) in the language of the Contract.

© 2013 The Dispute Board Federation 10

• Arbitrators may “open up, review and revise” any decisions of the DAB.

• Neither party is limited before the arbitrator(s) to the evidence or argumentspreviously put before the DAB. But DAB Decision is seen as effective asevidence.

Page 11: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

World Bank

II. World Bank

• For projects financed by the World Bank, the World Bank’s Standard BiddingDocuments for Procurement of Works (“SBDW”) are mandatory in major workscontracts (estimated to cost more than $10 million, including contingency

© 2013 The Dispute Board Federation 11

contracts (estimated to cost more than $10 million, including contingencyallowance) unless otherwise agreed.

• Clause 20 of the SBDW (May 2006) is based on a “special edition” version ofFIDIC Clause 20.

• SBDW Clause 20 provides for a combination of a “Dispute Board” (20(4)),amicable settlement (20(5)), and ICC arbitration (20(6)).

Page 12: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

DBF

IV. DBF

a) The DBF Dispute Board Documents, in force as from 1 January 2001, consist of:

• Standard DBF Dispute Board Clauses, which the parties can incorporate into their contracts and whichprovide for two types of Dispute Boards: a Dispute Review Board (“DRB”); and a Dispute AdjudicationBoard (“DAB”);

© 2013 The Dispute Board Federation 12

• DBF Dispute Board Rules, which govern the procedure before any Dispute Board (DRB, DAB); and

• DBF Model Dispute Board Member Agreement, which can be used as the model for the agreements to beentered into between each of the Dispute Board members and the parties.

b) DBF Dispute Boards can be established for any type of contract and are not limited to construction contracts.c) DBF can select the Chair who then selects the other Board Members.d) DBF Rules provide for automatically binding Decisions from DAB’s with and/or without appeal to arbitration

and a Fast-Track DAB with Decisions within 30 days.

Page 13: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

ICC

III. ICC

a) The ICC Dispute Board Documents, in force as from 1 September 2004, consist of:

• Standard ICC Dispute Board Clauses, which the parties can incorporate into their contractsand which provide for three types of Dispute Boards: a Dispute Review Board (“DRB”); aDispute Adjudication Board (“DAB”); and a Combined Dispute Board (“CDB”);

© 2013 The Dispute Board Federation 13

Dispute Adjudication Board (“DAB”); and a Combined Dispute Board (“CDB”);

• ICC Dispute Board Rules, which govern the procedure before any Dispute Board (DRB, DABor CDB); and

• ICC Model Dispute Board Member Agreement, which can be used as the model for theagreements to be entered into between each of the Dispute Board members and the parties.

b) ICC Dispute Boards can be established for any type of contract and are not limited toconstruction contracts.

Page 14: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

The DB Experience

The DBs experience to date:

1. Internationally, the immediately binding decision feature of the DAB

procedure seems to make it more effective than the DRB procedure.

2. But there is still a need for the DB procedures to gain the confidence of

© 2013 The Dispute Board Federation 14

2. But there is still a need for the DB procedures to gain the confidence of

parties around the world.

3. The experience and expertise of the members of the DB is critical to the

success experienced.

4. That is why the DBF trains, accredits and certifies DB Members.

Page 15: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Current Problems with the DB

Internationally, the only problems with DBs include:

1. Parties think there will be no disputes on “their” project and delay

putting DBs in place at the start of the contract and wait till

© 2013 The Dispute Board Federation 15

putting DBs in place at the start of the contract and wait till

problems arise.

2. Delay in payment on DB Decisions.

3. Changing the recommended language and/or rules.

Page 16: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Current Problems with the DB (cont’d)

… continued

4. Difficulty of finding qualified, experienced and independent members for DBs

5. Difficulty in removing an unsatisfactory member of a Permanent DB.

© 2013 The Dispute Board Federation 16

Page 17: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

The Dispute Board

How Dispute Boards Are Different From Arbitration

© 2013 The Dispute Board Federation 17

Page 18: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

How Dispute Boards Are Different from Arbitration

Referral to a Dispute Board is similar to arbitration, but can be distinguished fromarbitration in two principal ways:

• While an arbitrator is chosen to exercise a judicial function and to resolve a disputebased upon submissions by the parties, a Dispute Board is chosen for its expertisein a certain subject matter and often does its own investigation or appreciation of

© 2013 The Dispute Board Federation 18

in a certain subject matter and often does its own investigation or appreciation ofthe issue, with or without submissions by the parties.

• While arbitral awards can be judicially enforced, a Dispute Board determination,unless re-qualified as an arbitration, is in some jurisdictions not enforceable incourt. The enforceability issue is governed by local law, and is unresolved in manyjurisdictions.

Page 19: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

ERTAN HYDRO Dispute Board

Project description: Concrete Dam /and Hydro plant

Approx value: US$5,000m

Location: China

Employer: Chinese State Organisation

© 2013 The Dispute Board Federation 19

Employer: Chinese State Organisation

Contract: FIDIC 4th with 2 main contracts with DRBs

Construction period: 1991 – 2000

Contractors: International Joint Ventures with local partners

Number on DRB: 3 – each side chose one and they chose Chair

Frequency of visits: 3 times each year

Total site visits: About 20

Page 20: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

ERTAN HYDRO Dispute Board

DRB determinations: Recommendations, not automatically final and not automatically binding

© 2013 The Dispute Board Federation 20

Disputes referred to DRB: 40

Disputes that went to arbitration: 0

Page 21: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

ERTAN HYDRO Dispute Board

Special factors:

�First DRB in China

© 2013 The Dispute Board Federation 21

�For most, first exposure to DB

�Chinese initially wary but later supportive as DB helped clear difficult disputes

�DB increasingly proactive, assisting both formally and informally

�DB instrumental in securing parties’ consent to final accounts settlement

Page 22: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

KATSE DAM Dispute Board

Project description: High Concrete Arch Dam

Approx value: US$2,500m

Location: Lesotho (Southern Africa)

© 2013 The Dispute Board Federation 22

Location: Lesotho (Southern Africa)

Employer: Lesotho Development Authority

Contract: FIDIC 4th with 1 main contract subject to DRB

Construction period: 1993 – 1998

Contractors: International Joint Ventures with local partners

Page 23: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

KATSE DAM Dispute Board

Number on DB: 3

How chosen: Jointly selected by parties

Frequency of visits: 2½ times each year

© 2013 The Dispute Board Federation 23

Frequency of visits: 2½ times each year

Total site visits: About 16

DRB determinations: Recommendations, not automatically final and not automatically binding

Disputes referred to DB: 12

Disputes that went to arbitration: 1 and importantly the DB was upheld

Page 24: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

KATSE DAM Dispute Board

Special factors:

�First DB in Africa

© 2013 The Dispute Board Federation 24

�First DB in Africa

�Party representatives all new to the process

�Some initial resistance to DB from employer

�Referrals to DB had to follow formal notice of arbitration

Page 25: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

HONG KONG AIRPORT Dispute Board

Project description: International Airport

Approx value: US$15,000 Billion

© 2013 The Dispute Board Federation 25

Location: Hong Kong SAR China

Employer: Airport Authority

Contract: Bespoke, similar to HK Government formwith 22 main contracts subject to DAB

Contractors: International, some Joint Ventures with local partners,many specialists (e.g. Air Traffic Control systems)

Page 26: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

HONG KONG AIRPORT Dispute Board

Number on DB: Convenor (non sitting) plus 6 others of various disciplines

© 2013 The Dispute Board Federation 26

How chosen: Agreement between Authority and Contractor’s Association, members selected prior to contract awards

Frequency of visits: Every 3 months

Total site visits: About 16

Page 27: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

HONG KONG AIRPORT Dispute Board

DB determinations: Decisions, not automatically final but binding in the interim

© 2013 The Dispute Board Federation 27

Disputes referred to DB: 6

Disputes that went to arbitration: 1 and the DRB decision was upheld

Page 28: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

HONG KONG AIRPORT Dispute Board

Special factors:

�DRB covered all main airport contracts

© 2013 The Dispute Board Federation 28

�Quarterly reviews / visits with all main contractors

�Each DRB member selected for specialist knowledge and experience

�Formal hearings with parties’ positions well presented by engineers, not lawyers

�Draft Decisions for party comments before finalisation

Page 29: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

DOCKLANDS RAILWAY Dispute Board

Project description: Urban Light Railway

Approx value: US$500m

Location: London, UK

© 2013 The Dispute Board Federation 29

Location: London, UK

Employer: Docklands Railway Authority

Construction period: 1996 – 1999

Contractors: UK domestic

Number on DRB: 5 - two sets of 3 with common chair

How chosen: Agreement of the parties

Frequency of visits: Quarterly

Total site visits: 10

Page 30: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

DOCKLANDS RAILWAY Dispute Board

Nature of DB’s determinations: Decisions final

Number of disputes referred to DB: 0

© 2013 The Dispute Board Federation 30

Number of disputes referred to DB: 0

Number of disputes that went to arbitration: 0

Special factors:

�Concession contract with separate works contractors

�Technical and financial boards under same Chair

�28-day determinations

Page 31: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

Sung Ha Dam Expansion Dispute Board

Project description: Hydro Plant

Approx value: US$5,500m

Location: China

© 2013 The Dispute Board Federation 31

Location: China

Employer: Local Electric Authority

Construction period: 2003 – 2006

Contractors: International JV

Number on DAB: 3 – Parties chose Chair who chose rest

How chosen: DBF Appointment

Frequency of visits: Quarterly

Total site visits: 14

Page 32: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Sample Dispute Board Projects

Río Paraná Dam Expansion Dispute Board

DAB determinations: Decisions, automatically final and binding unless taken to arbitration/court

Disputes referred to DB: 8

© 2013 The Dispute Board Federation 32

Disputes referred to DB: 8

Disputes that went to arbitration: 0

Special factors:

�Parties had minimal choice of DAB members

�Formal hearings well presented by engineers, not lawyers

�DB was asked to advise on several disputes without any Hearing

Page 33: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Dispute Board Benefits

The benefits for owners, contractors, funders, and industry are:

�Like the “Engineer” of old, the Dispute Board is part of the project

�Routine visits provide focus for parties to discuss disputes and potential

© 2013 The Dispute Board Federation 33

�Routine visits provide focus for parties to discuss disputes and potential disputes – tremendous opportunity for dispute avoidance

�The Dispute Board is “up to speed” at all times by routine visits (usually 3 times per year) and through review of regular reports

�The Dispute Board understands the project, the parties, individuals involved, physical difficulties, economic background

Page 34: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Dispute Board Benefits

Benefits continued:

�Speed of dispute resolution

�Economy (less than 0.02% of project cost)

© 2013 The Dispute Board Federation 34

�Economy (less than 0.02% of project cost)

�99% of the time the dispute is ended by the Dispute Board as parties reluctant to go on to arbitration/courts especially if the Dispute Board output is admissible

�Fear of unknown dispute resolution tribunal avoided

Page 35: Introduction to Dispute Boards - camaramedellin.com.co Board… · * See Conditions of Contract for Construction ... maintains familiarity with project, ... • ICC Model Dispute

The Dispute Board Federation

Contact Details

The Dispute Board Federation Singapore

1 Fullerton RoadOne Fullerton #02-01

Singapore 049213

The Dispute Board FederationGeneva

14, rue du Rhone1204 GenevaSwitzerland

© 2013 The Dispute Board Federation 35

Tel: (+65) 6832 5508Fax: (+65) 6408 3801

Tel: +41 22 819 19 68Fax: +41 44 732 69 95

www.dbfederation.org [email protected]