MGT 550: Introduction to Project Management March 31, 2002 1 For academic use only. MGT 550 Introduction to Project Management Chapter 7: Budgeting and Cost Estimation Wesley J. Howe School of Technology Management Course Development Team Members: Michael Poli Celia Desmond, PMP David Keeney, PMP, CQM, CPDT

Upload: sasaborz

Post on 04-Jun-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 1/41

MGT 550: Introduction to Project Management

March 31, 2002 1For academic use only.

MGT 550

Introduction to

Project Management

Chapter 7:

Budgeting and

Cost Estimation

Wesley J. Howe School of Technology Management

Course Development Team Members:Michael Poli

Celia Desmond, PMPDavid Keeney, PMP, CQM, CPDT

Page 2: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 2/41

MGT 550: Introduction to Project Management

March 31, 2002 2For academic use only.

Copyright Information

The slides in this file are provided to faculty instructing MGT 500 on behalf of the

Stevens Institute of Technology. Use is restricted to academic endeavorsassociated with the delivery of MGT 550 to students properly enrolled at theStevens Institute of Technology. All other rights are reserved by the original ownersof materials contained in this program.

The slides contain copyrighted material that has been reproduced and/or adapted tothe course syllabus under the doctrine of “fair use for academic purposes”. Allslides in this course are copyrighted by the original source. Requests to reproducematerials for other purposes should be directed to the copyright owner identified inthe bibliography that will be made available to faculty.

Page 3: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 3/41

MGT 550: Introduction to Project Management

March 31, 2002 3For academic use only.

Budgeting and Cost Estimation

M&M Text, Chpt. 7

Page 4: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 4/41

MGT 550: Introduction to Project Management

March 31, 2002 4For academic use only.

Module 7:

Cost Estimating and Budgeting

Purpose: prepare students to understandthe elements of a project budget and thetechniques commonly used to estimate

costs in a project plan.

Page 5: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 5/41

MGT 550: Introduction to Project Management

March 31, 2002 5For academic use only.

Module 7 Objectives

• Review Financial Statements

 – Describe the balance sheet, income statement, andcashflow statement

 – Explain the basic relationships between each financial

statement – Link the financial statements to measures of project

profitability discussed during project selection

 – Explain the differences between the capital budget, theoperating budget, and imputed costs

Page 6: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 6/41

MGT 550: Introduction to Project Management

March 31, 2002 6For academic use only.

WBS, OBS, RBS, and CBS

DirectCosts IndirectCosts

CBS

•Direct

Labor 

• DirectMaterial

•Period

Expenses

•Overhead•Burden

1.0

1.1 1.2 1.31.2.1 1.2.2

   A   5

   D   1

   D   3

   D   7

   S   3

   S   4

   O

   B   S

   W   B   S

Income

Statement

Cashflow

Statement

BalanceSheet

Imputed Costs

Keeney, 2000

Page 7: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 7/41

MGT 550: Introduction to Project Management

March 31, 2002 7For academic use only.

Key Cost Concepts• Cost is a resource foregone, in cash or in

kind, to obtain a set of benefits – Type of costs

• Capital

• Expense

• Sunk cost

• Imputed cost

• Opportunity cost

 – Economic analysis

 – Budgeting

 – Earned value – Contingency

Page 8: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 8/41

MGT 550: Introduction to Project Management

March 31, 2002 8For academic use only.

Capital Costs

• Must be depreciated or amortized over life of

capital asset (defined by taxing authorities)• Result in owned assets on the balance sheet

 – Historical cost (usually at acquisition)

 – Accumulated depreciation/amortization

 – Historical cost less accumulated depreciation

 – May have a salvage value• Cost of capital should be considered

 – Net cost for debt and equity sources of assets

 – Hurdle rate may be based on cost of capital

Page 9: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 9/41

Page 10: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 10/41

MGT 550: Introduction to Project Management

March 31, 2002 10For academic use only.

Sunk Costs

• Cost already expended• Should not be used in making

decisions about future.

• Should base decisions on futurecosts and impacts.

Page 11: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 11/41

MGT 550: Introduction to Project Management

March 31, 2002 11For academic use only.

Imputed Costs

• A cost that does not get reported on financialstatements

• Opportunity costs are an example of imputed

costs

Page 12: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 12/41

MGT 550: Introduction to Project Management

March 31, 2002 12For academic use only.

Opportunity Cost

• Benefits foregone as a result of choosingone of more than one alternatives

• Usually used as a comparative measure

• Useful in making decisions• Can use to compare project benefits to

opportunities from other projects.

Page 13: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 13/41

MGT 550: Introduction to Project Management

March 31, 2002 13For academic use only.

Opportunity Cost Example

We could upgrade our current billing system, at a cost of $800K or

purchase a new standalone system for the l.d. service we aredesigning for $500K, in 3 months time.Purchasing the new system would require process changes of anadditional $800K to integrate the output with the currently issued

bills. However once the systems and integrated processes are inplace, we expect to save $500K on each of four upcoming plannedservices.

Therefore the opportunity cost of upgrading is

(4x$500K) - ($500K+$800K) = 700Kbecause we are foregoing $700K savings to upgrade now.

This can be compared to the increase in profit expected over thenext 3 months to decide whether to go ahead.

Page 14: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 14/41

MGT 550: Introduction to Project Management

March 31, 2002 14For academic use only.

Funding Non profitable Projects

• There are several reasons that firms wouldchoose to fund project that is notprofitable:

 – To develop knowledge of technology – To get organization’s “foot in door”

 – To obtain parts or service portion of work

 – To be in good position for follow-on contract – To improve competitive position

 – To broaden product line or line of business

M&M Text, Chpt. 7

Page 15: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 15/41

MGT 550: Introduction to Project Management

March 31, 2002 15For academic use only.

Profitability Measurement

• Payback period

• Return On Investment (ROI)

• Discounted cash flow methods

 – NPV, net present value – IRR, internal rate of return

 – Benefit-cost ratio

All of these measurements require use of

a time-phased budget to assess profitability.

Page 16: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 16/41

MGT 550: Introduction to Project Management

March 31, 2002 16For academic use only.

Payback Period• Forecasts how long it will take for the net cash inflow to pay

back the investment outflow

 – ignores time value of money – ignores cash flow after payback

9001,5001,200500-2,100Cashflow

1501501501500Debt Service1251251251250Interest

252525250Amortization

4004004004000Depreciation

50011008001000NPAT

 Year 4 Year 3 Year 2 Year 1 Year 0

Payback Period = 2.4 years

Page 17: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 17/41

MGT 550: Introduction to Project Management

March 31, 2002 17For academic use only.

Return On Investment (ROI)

Many formulas exist for computing ROI.

• Return on Average Investment

• Return on Original Investment

(Average Yearly Profit)

(Original Investment) + (Working Capital)ROI =

(Working Capital) = (Current Assets) – (Current Liabilities)

Page 18: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 18/41

MGT 550: Introduction to Project Management

March 31, 2002 18For academic use only.

The future value F of a current sum at its present value PV, depends

upon the interest/investment rate i and the number of years involved, n.

FV = PV(1+ i  )n

Net present value NPV of a series of sums is

when II is the initial investment.

 An annuity, is the amount of money to be invested (A) each year over myears at a rate of investment (i) to provide the required amount i.e.enough to buy a customer care company.

PV = A (1+i)n -1 / i (1+i)n

 NPV = - II    MFVi

(1 + k)i

i=1

n

Present Value Concepts

Page 19: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 19/41

MGT 550: Introduction to Project Management

March 31, 2002 19For academic use only.

The Reciprocal Relationship of

PV and FV

0.0

1.0

2.0

3.0

4.05.0

6.0

7.0

8.0

  -   2   0   -  1   7

  -  1  4

  -  1  1   -   8   -   5   -   2   1 4 7

  1   0   1   3   1   6   1   9

Time Period

   V  a   l  u  e  o   f

   $   1

CompoundedValue

Discounted Value

N

OW

10%

5%

Page 20: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 20/41

MGT 550: Introduction to Project Management

March 31, 2002 20For academic use only.

Net Present ValueDiscount rate 10%

NPV = 1093

6151127996455-2,100PV

0.68300.75130.8640.90911.00PVIF

9001,5001,200500-2,100Cashflow

1501501501500Debt Service

1251251251250Interest

252525250Amortization

4004004004000Depreciation

50011008001000NPAT

 Year 4 Year 3 Year 2 Year 1 Year 0

MGT 0 I d i P j M

Page 21: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 21/41

MGT 550: Introduction to Project Management

March 31, 2002 21For academic use only.

Benefit/Cost Ratio

  Of Discounted Cash Inflows

  Of Discounted Cash OutflowsProfitability Index =

From the NPV Problem:• Discounted Cash Inflows = $3,193• Discounted Cash Outflows = $2,100

PI =

$3,193

$2,100= 1.52 If PI > 1.0,project is favorable.

MGT 550 I t d ti t P j t M t

Page 22: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 22/41

MGT 550: Introduction to Project Management

March 31, 2002 22For academic use only.

Internal rate of Return (IRR)

The discount rate that makes the present value ofall cash flows (in and out) equal to zero.

The IRR is found by iteration

- II = 0    MFVi

(1 + IRR)i

i=1

n

MGT 550 I t d ti t P j t M t

Page 23: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 23/41

MGT 550: Introduction to Project Management

March 31, 2002 23For academic use only.

NVP or IRR?

• For project decisions, NPV isrecommended over IRR as decision tool.

• NPV is more conservative and also more

consistent than IRR• Since IRR is calculated by a polynomial of

dimension n, it has n roots, not just one.

MGT 550: Introduction to Project Management

Page 24: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 24/41

MGT 550: Introduction to Project Management

March 31, 2002 24For academic use only.

Module 7 Objectives

• Cost Estimation Techniques

 – Describe analogous estimating and parametricmodeling

 – Explain bottom-up estimating and its relationship to the

WBS

MGT 550: Introduction to Project Management

Page 25: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 25/41

MGT 550: Introduction to Project Management

March 31, 2002 25For academic use only.

Cost Estimating Techniques

• Analogous

 – “top-down”

 – adjustments to actual cost of past projects

• Parametric – uses some measurable characteristic e.g.

• cost per line of code or per screen

• cost per square foot of living space

• Bottom-up

 – detailed

MGT 550: Introduction to Project Management

Page 26: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 26/41

MGT 550: Introduction to Project Management

March 31, 2002 26For academic use only.

Top-Down Budgeting

• Advantages: – Aggregate budgets can often be developed quite

accurately

 – Budgets are stable as a percent of total allocation

 – The statistical distribution is also stable, makingfor high predictability

 – Small yet costly tasks do not need to be

individually identified – The experience and judgment of the executive

accounts for small but important tasks to befactored into the overall estimate

M&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 27: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 27/41

MGT 550: Introduction to Project Management

March 31, 2002 27For academic use only.

Bottom-Up Budgeting

• Advantages:

 – Individuals closer to the work are apt to have amore accurate idea of resource requirements

 – The direct involvement of low-level managersin budget preparation increases the likelihoodthat they will accept the result with a minimumof aversion

 – Involvement is a good managerial trainingtechnique, giving junior managers valuableexperience

M&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 28: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 28/41

MGT 550: Introduction to Project Management

March 31, 2002 28For academic use only.

Budgeting

• Top-down budgeting is very common

• True bottom-up budgets are rare

 – Senior managers see the bottom-up process

as risky – They tend not to be particularly trusting of

ambitious subordinates who they fear may

overstate resource requirements – They are reluctant to hand over control to

subordinates whose experience and motives

are questionableM&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 29: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 29/41

MGT 550: Introduction to Project Management

March 31, 2002 29For academic use only.

Work Element Costing

• Each work element in the action plan or

WBS is evaluated for its resourcerequirements, and then the cost

• Direct costs for resources and machinery

are charged directly to the project. Labor isusually subject to overhead charges.Material resources and machinery may or

may not be subject to overhead.• There is also the General and Administrative

(G&A) charge

M&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 30: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 30/41

MGT 550: Introduction to Project Management

March 31, 2002 30For academic use only.

Category/Activity Budgeting vs.Program Budgeting

• The traditional organization budget is eithercategory oriented or activity oriented

• Often based upon historical data

accumulated through an accounting system• With the advent of project organizations, it

became necessary to organize the budget in

ways that conformed more closely to theactual pattern of fiscal responsibility

M&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 31: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 31/41

MGT 550: Introduction to Project Management

March 31, 2002 31For academic use only.

Category/Activity Budgeting vs.Program Budgeting

• Under traditional budgeting methods, thebudget could be split up among manydifferent organizational units

• This diffused control so widely that it wasalmost nonexistent

• This problem gave rise to program

budgeting, which alters the budgetingprocess so that budgets can beassociated with the projects that use them

M&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 32: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 32/41

j g

March 31, 2002 32For academic use only.

Program Budgeting

• Program budgeting aggregates income andexpenditures across programs (projects)

• Aggregation by program is in addition to,

not instead of, aggregation byorganizational unit

• These budgets usually take the form of a

spreadsheet with standard categoriesdisaggregated into “regular operations” andcharges to the various projects

M&M Text, Chpt 7

MGT 550: Introduction to Project Management

Page 33: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 33/41

j g

March 31, 2002 33For academic use only.

Module 7 Objectives

• Time-phased Budgets

 – Explain that the purpose of a budget is to assignresponsibility for costs to a cost center 

 – Explain the chart of accounts and its relationship to

work packages – Explain how the time-phased budget can be used to

evaluate profitability and cashflow on a project

MGT 550: Introduction to Project Management

Page 34: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 34/41

j g

March 31, 2002 34For academic use only.

From Schedule to BudgetID WBS Task Name Dur  

14 3 Technical Team Startup 28 days

15 3.1 Identify Team Members 1 day

16 3.2 Verify Team Members Acceptance 6 days

17 3.3 Schedule Kickoff Meeting 1 day

18 3.4 Hold Kickoff Meeting 1 day

19 3.5 Identify Technical Tracks 6 days

20 3.6 Assign Team Members To Technical

Tracks

1 day

21 3.7 Set Up Technical Team Web Site 5 days

22

23 4 Call For Papers 25 days

24 4.1 Write Technical Track Descriptions 15 days

25 4.2 Write Call f or Papers 5 days

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

16, '00 Jul 23, '00 Jul 30, '00 Aug 06, '00 Aug 13, '0

Project Budget

  0

  5

  10

  15

W1 W2 W3 W4 W5 W6 W7

Resources by Week

($000)

A B C DResource A = Contingency Allowance

Keeney, 2001

MGT 550: Introduction to Project Management

Page 35: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 35/41

March 31, 2002 35For academic use only.

Estimate Accuracy

• Project costs will generally be determinedfrom cost and time estimates made byteam members and project stakeholders.

• When expressing or accepting anyestimate, ensure that the accuracy of theestimate is specified

 – Most likely value (a mode) – Upper limit (worst case and probability)

 – Lower limit (best case and probability)

MGT 550: Introduction to Project Management

Page 36: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 36/41

March 31, 2002 36For academic use only.

Monthly Household BudgetMortgage

Utilities

Food

Miscellaneous

Total

$900

$1,000

$1,150

$100$200

$350

$700

$800

$900

$200

$400

$600

$1,900$2,400

$3,000

All Good Long RunAverage

All Bad

.00000001 Not Very Likely(.01)

4

(.01)

4

Keeney, 2001

MGT 550: Introduction to Project Management

Page 37: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 37/41

March 31, 2002 37For academic use only.

Contingency Allowances

Where to put them?

• single line item• standard % overall• weighted percentage

• by system or phase• by milestone• by summary task

Problems with this?• Specify potential problems for each method of

showing contingency

MGT 550: Introduction to Project Management

Page 38: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 38/41

March 31, 2002 38For academic use only.

Contingency Allowances

• Should be based on realistic expectations

• ARE EXPECTED TO BE SPENT

• Should not be hidden

• Are not for scope changes• Are not for inflation

• ARE USED FOR KNOWN UNKNOWNS

MGT 550: Introduction to Project Management

Page 39: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 39/41

March 31, 2002 39For academic use only.

Managerial Reserve Account

• Is for unknown unknowns

• Must be requested by PM

• IS NOT A SLUSH FUND to cover poor

planning

MGT 550: Introduction to Project Management

Page 40: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 40/41

March 31, 2002 40For academic use only.

Budgeting: Cashflow ForecastCumulative Cost

TimeTime Now

ACTUAL

BAC

EAC

PLAN

MGT 550: Introduction to Project Management

Page 41: Intro to Project Management - 07 - Budgeting and Cost Estimation

8/13/2019 Intro to Project Management - 07 - Budgeting and Cost Estimation

http://slidepdf.com/reader/full/intro-to-project-management-07-budgeting-and-cost-estimation 41/41

March 31, 2002 41For academic use only.

Reading Assignments

• From Chapter 7

 – Text• Pp 261 – 292

• Pp 295 – 301