budgeting n cost estimation

Upload: sanchit-batra

Post on 05-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Budgeting n Cost Estimation

    1/31

    Project ManagementA Managerial Approach

    Budgeting and Cost Estimation

  • 7/31/2019 Budgeting n Cost Estimation

    2/31

    What is a budget?

    A Plan for allocating resources.

    The act of budgeting is the process ofallocating the scarce resources to the

    various endeavors of an organization.

  • 7/31/2019 Budgeting n Cost Estimation

    3/31

    Budgeting and Cost Estimation

    The budget serves as a standard forcomparison

    It is a baseline from which to measure the

    difference between the actual and planned useof resources

    Budgeting procedures must associateresource use with the achievement of

    organizational goals or the planning/controlprocess becomes useless

    The budget is simply the project plan in anotherform

  • 7/31/2019 Budgeting n Cost Estimation

    4/31

    The degree to which the differentactivities of a project are supported byan allocation of resources is onemeasure of the importance placed on

    the outcome of the activity.

  • 7/31/2019 Budgeting n Cost Estimation

    5/31

    A budget serves as a controlmechanism.

    Exception reports can be generated ifresource expenditures are not consistentwith accomplishments.

    The pattern of deviations can beexamined to forecast significantdepartures from budget.

  • 7/31/2019 Budgeting n Cost Estimation

    6/31

    Estimating Project Budgets

    In order to develop a budget, we must: Forecast what resources the project will require

    Determine the required quantity of each

    Decide when they will be needed

    Understand how much they will cost - including the effectsof potential price inflation

    Approximation of projects costLast years figures+x

    Estimated wt of product*specific factor

  • 7/31/2019 Budgeting n Cost Estimation

    7/31

    All projects are uniqueAll project budgets are based on forecasts

    of resource usage and associated costs

    Estimating the cost for any project involvesriskProblems in multiyear usage (cost of

    materials)Degree of executive oversight and review.

  • 7/31/2019 Budgeting n Cost Estimation

    8/31

    Actual use of resources

    Suppose you have estimated that $5000 of agiven resource will be used in accomplishing atask over 5 weeks.

    The actual use of the resource may be none inWeek1, $3000 in Week2, none in Week3,$1500 in Week4, $500 in Week5

    Unless time pattern of resource usage is

    explained in the plan, the accounting deptt.Which takes a linear view will spread thisequally over the 5 week period.

  • 7/31/2019 Budgeting n Cost Estimation

    9/31

    There are two fundamentally differentstrategies for data gathering:Top-down

    Bottom-up

  • 7/31/2019 Budgeting n Cost Estimation

    10/31

    Top-Down Budgeting

    This strategy is based on collecting thejudgment and experiences of top and middlemanagers.

    These cost estimates are then given to lowerlevel managers, who are expected tocontinue the breakdown into budgetestimates.

    This process continues to the lowest level.

  • 7/31/2019 Budgeting n Cost Estimation

    11/31

    Top-Down Budgeting

    Advantages:Aggregate budgets can often be developed quite

    accurately

    Budgets are stable as a percent of total allocation

    The statistical distribution is also stable, making for high

    predictability

    Small yet costly tasks do not need to be individually

    identified The experience and judgment of the executive accounts

    for small but important tasks to be factored into the

    overall estimate

  • 7/31/2019 Budgeting n Cost Estimation

    12/31

    Bottom-Up Budgeting

    In this method, elemental tasks, their schedules, and theirindividual budgets are constructed following the WBS orproject action plan

    The people doing the work are consulted regarding times

    and budgets for the tasks to ensure the best level ofaccuracy Initially, estimates are made in terms of resources, such as

    labor hours and materials Bottom-up budgets should be and usually are, more

    accurate in the detailed tasks, but it is critical that allelements be included. Usual elements are labour, materials, consumables,

    capital expenditure, travel etc..

  • 7/31/2019 Budgeting n Cost Estimation

    13/31

    Bottom-Up Budgeting

    Advantages: Individuals closer to the work are apt to have a

    more accurate idea of resource requirements

    The direct involvement of low-level managers inbudget preparation increases the likelihood thatthey will accept the result with a minimum ofaversion

    Involvement is a good managerial trainingtechnique, giving junior managers valuableexperience

  • 7/31/2019 Budgeting n Cost Estimation

    14/31

    Budgeting

    Top-down budgeting is very common

    True bottom-up budgets are rareSenior managers see the bottom-up process as

    risky

    They tend not to be particularly trusting ofambitious subordinates who they fear may

    overstate resource requirementsThey are reluctant to hand over control to

    subordinates whose experience and motives arequestionable

  • 7/31/2019 Budgeting n Cost Estimation

    15/31

    Work Element Costing

    The actual process of building a budget -either top-down or bottom-up - tends to be a

    straightforward but tedious processEach work element in the action plan or WBS

    is evaluated for its resource requirements,

    and then the cost

  • 7/31/2019 Budgeting n Cost Estimation

    16/31

    Suppose a work element requires 25 hrs of labour by atechnician. The technician assigned to the job is paid$17.5 per hr. Overhead charges to this project are 84%of direct labour charges. Cost appears to be

    25 hr*$17.5*1.84=$805 Personal time of worker=12% of total work time. If Personal time was not included, in the 25 hr estimate

    made above, the cost calculation is

    1.12*25 hr*$17.5*1.84=$901.6Not including personal time would have resulted in

    underestimation.

  • 7/31/2019 Budgeting n Cost Estimation

    17/31

    Direct costs for resources and machineryare charged directly to the project. Laboris usually subject to overhead charges.

    Material resources and machinery mayor may not be subject to overhead.

    There is also the General and

    Administrative (G&A) charge

  • 7/31/2019 Budgeting n Cost Estimation

    18/31

    The Iterative budgeting process

    An individual concocting the action plan at thehighest level would estimate resourcerequirements and durations at the highest levelaction plan.

    Ri=Resource requirement for ith task.

    Ti=Time requirement for ith taskA subordinate estimates ri and ti

    Ideally Ri=ri. However,Ri

  • 7/31/2019 Budgeting n Cost Estimation

    19/31

    An Iterative Budgeting Process

    Resource estimates and actual requirements arerarely the same for several reasons: The farther one moves up the organizational chart, the

    easier, faster and cheaper the job looksWishful thinking leads the superior to underestimate cost

    (and time) because the superior has a stake in representing

    the project as a profitable venture

    The subordinates are led to build-in some level of protection

    against failure by adding an allowance for Murphys Law

    (contingency allowance)

  • 7/31/2019 Budgeting n Cost Estimation

    20/31

    An Iterative Budgeting Process

    Usually the initial step toward reducing the difference betweenthe superiors and the subordinates estimates is made by thesuperior

    The superior agrees to be educated by the subordinate in therealities of the job(Ri rises)

    The subordinate is encouraged by the superiors positiveresponse and then surrenders some of the protection of the

    budgetary slop(ri decreases) This is a time consuming process, especially when the project

    manager is negotiating with several subordinates

  • 7/31/2019 Budgeting n Cost Estimation

    21/31

    Category/Activity Budgeting vs.Program Budgeting

    The traditional organization budget is either

    category oriented or activity oriented

    Often based upon historical data accumulatedthrough an accounting system

    With the advent of project organizations, it became

    necessary to organize the budget in ways that

    conformed more closely to the actual pattern of

    fiscal responsibility

  • 7/31/2019 Budgeting n Cost Estimation

    22/31

    Category/Activity Budgeting vs.Program Budgeting

    Under traditional budgeting methods, the budget

    could be split up among many different

    organizational unitsThis diffused control so widely that it was almost

    nonexistent

    This problem gave rise toprogram budgetingwhichalters the budgeting process so that budget can be

    associated with the projects that use them

  • 7/31/2019 Budgeting n Cost Estimation

    23/31

  • 7/31/2019 Budgeting n Cost Estimation

    24/31

  • 7/31/2019 Budgeting n Cost Estimation

    25/31

    Program Budgeting

    Project Budget by Task and Month

    A 1 2 7000 5600 1400

    B 2 3 9000 3857 5143

    C 2 4 10000 3750 5000 1250

    D 2 5 6000 3600 2400

    E 3 7 12000 4800 4800 2400

    F 4 7 3000 3000

    G 5 6 9000 2571 5143 1286

    H 6 7 5000 3750 1250

    I 7 8 8000 2667 5333

    J 8 9 6000

    6000

    75000 5600 12607 15114 14192 9836 6317 5333 6000

    I i h P f C

  • 7/31/2019 Budgeting n Cost Estimation

    26/31

    Improving the Process of CostEstimation

    There are two fundamentally different waysto manage the risks associated with thechance events that occur on every project:The most common is to make an allowance for

    contingencies - usually 5 or 10 percent

    Another is when the forecaster selects most

    likely, optimistic, and pessimistic estimates

  • 7/31/2019 Budgeting n Cost Estimation

    27/31

    Funding Non profitable Projects

    There are several reasons that firms wouldchoose to fund a project that is not profitable:

    To develop knowledge of a technologyTo get the organizations foot in the door

    To obtain the parts or service portion of the work

    To be in a good position for a follow-on contract

    To improve a competitive position

    To broaden a product line or a line of business

  • 7/31/2019 Budgeting n Cost Estimation

    28/31

    Learning Curves

    Studies have shown that human performance usuallyimproves when a task is repeated

    In general, performance improves by a fixed percent each

    time production doubles

    More specifically, each time the output doubles, the worker

    hours per unit decrease to a fixed percentage of their previous

    value

    That percentage is called the learning rate

    The project manager should take the learning curve intoaccount for any task where labor is significant

  • 7/31/2019 Budgeting n Cost Estimation

    29/31

    Budgeting and Cost Estimation

  • 7/31/2019 Budgeting n Cost Estimation

    30/31

    Other Factors

    Anywhere from about three-fifths to five-sixths ofprojects fail to meet their time, cost, and/orspecification objectives

    There are several common causes:Arbitrary and impossible goalsScope creepWildly optimistic estimates in order to influence the

    project selection processChanges in resource pricesFailure to include an allowance for waste and spoilageBad luck

  • 7/31/2019 Budgeting n Cost Estimation

    31/31

    Types of Estimation Error

    There are two generic types of estimationerror:

    Random error- where overestimates andunderestimates are likely to be equal

    Bias - a systematic error where the chance of

    overestimating and underestimating are not likely

    to be equal