bab vii cost estimation & budgeting process
TRANSCRIPT
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
1/18
Chapter 7
Cost Estimation &
Budgeting Process
Erny Apriany SylwanaWidya Adi Nugraha
Fauzan Baskoro
Very Budiman
Harris
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
2/18
What is needed to develop a
budget?Forecast of:
What resources the project will require
Quantity of each
When they will be needed
How much they will cost (including the effect of potential
price inflation)
Uncertainty
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
3/18
ESTIMATING PROJECT
BUDGET1. TOP-DOWN BUDGETING
2. BOTTOM-UP BUDGETING
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
4/18
TOP-DOWN BUDGETING
A
B B
C C
D D D D
B
Estimators
Top-down budgeting is based on: Judgements and experiences of
top and middle managers
Available past data concerning
similar activities
Advantages:
Aggregate budgets can be often
developed quite accurately
Avoid overbudget
Weakness:
Potential debate with the lower
level managers
Small but important aspects
sometimes overlooked
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
5/18
BOTTOM-UP BUDGETING
A
B B
C C
D D D D
B
Estimators
Bottom-up budgeting is based on:
Budgeting from detailed tasks in
terms of resources then
constructed following the EBS
Advantages: More accurate resources
management
Giving junior manager experiences
in budgeting process
Weakness:
Complex process
Potential overbudget because
preparation of cutted budget
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
6/18
WORK ELEMENT COSTING
Each work element in the action plan or WBS is evaluated
for its resource requirements and, and the cost of each
resource is estimated
This cost consist of:
1. Direct cost
2. Overhead
3. General & Administrative (G&A) charges
PM usually prepare 2 budgets:1. With overhead and G&A charges (to estimate profit)
2. Without overhead and G&A charges
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
7/18
ITERATIVE BUDGETING
PROCESS In combination of top-down and bottom-up budgeting
approach, Superiors (PMs) review the plan, perhaps
suggesting amandments (negotiation in action)
Resource requirements (ri
) and duration of each step (ti
)
from Superiors, in fact, different with budgeting from lower
level (ri & ti)
Iterative is time-consuming process, because it involve
superior & subordinate at all levels. But it allows a free flow
of ideas up and down the system. This iterative process willreduce uncertainty in budget estimations
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
8/18
Category/Activity Budgeting vs.
Program Budgeting The traditional organization budget is either category oriented
or activity oriented
Often based upon historical data accumulated through an
accounting system
With the advent of project organizations, it became necessary
to organize the budget in ways that conformed more closely to
the actual pattern of fiscal responsibility
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
9/18
Category/Activity Budgeting vs.
Program Budgeting Under traditional budgeting methods, the budget could be
split up among many different organizational units
This diffused control so widely that it was almost nonexistent
This problem gave rise toprogram budgetingwhich alters the
budgeting process so that budget can be associated with the
projects that use them
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
10/18
Program Budgeting
Program budgeting aggregates income and expenditures
across programs (projects)
Aggregation by program is in addition to, not instead of,
aggregation by organizational unit
These budgets usually take the form of a spreadsheet with
standard categories disaggregated into regular operations
and charges to the various projects
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
11/18
Improving the Process of Cost
Estimation There are two fundamentally different ways to manage the
risks associated with the chance events that occur on every
project:
The most common is to make an allowance for contingencies -
usually 5 or 10 percent Another is when the forecaster selects most likely, optimistic,
and pessimistic estimates
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
12/18
Funding Non profitable
Projects There are several reasons that firms would choose to fund a
project that is not profitable:
To develop knowledge of a technology
To get the organizations foot in the door
To obtain the parts or service portion of the work
To be in a good position for a follow-on contract
To improve a competitive position
To broaden a product line or a line of business
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
13/18
Learning Curves
In a cigarette manufactory, A product made in 70 man hour.
labor paid = $12/hour
estimated of 25 unit?
$25 unit * $12/hr * 70 hr/unit = $21000
Nope, its below $21000
Because Human LearnIts that true?
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
14/18
Learning Curves
Experiences is a plus
More experiences = easy cost estimation, its fairly routine
Each time the output doubles, the worker hour per unit
decrease to a fix percentage of their previous value
The fix percentage called learning rate
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
15/18
Learning Curves
If individual need 10 minutes to accomplish certain task
at first time, and only 8 minute in second time, it said
learning rate=80%
Time required to produce a unit of output
Tn The time required for the nthunit of output
T1 The time reguired for the initial output
N The number of units to be produced, and
RLog decimal learning rate/log 2
Total time required:
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
16/18
Learning Curves
time
Number of
unit
Without allowance for learnig
Additional time used for
leaning
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
17/18
Learning Curves
Special case of LearningTechnological stock
If the parent organization is not experienced, performance measuressuch as time to installation, time to achive 80 percent etc are quiteuncertain
When we alter a system, we disturb it and it reacts in unpredictableways.
Other Factors
Project involve a tangible medium that tends not be under control
exp: a program with 1000 line code and 99,99% reliable just onlyworking about 36%
Mythical man-month
worker and time are interchangable
Adding manpower to a late software project makes it later
-
8/13/2019 Bab VII Cost Estimation & Budgeting Process
18/18
Types of Estimation Error
There are two generic types of estimation error:
Random error - where overestimates and
underestimates are likely to be equal
Bias - a systematic error where the chance of
overestimating and underestimating are not
likely to be equal