intro to construction 2
TRANSCRIPT
-
7/31/2019 Intro to Construction 2
1/52
Construction Methods & ManagementCIEG 486-010
-
7/31/2019 Intro to Construction 2
2/52
Construction Methods & Management
CIEG 486-010
Construction Management
Contractual arrangement: at-risk or
management services for fee only
or
Act of managing the construction process
-
7/31/2019 Intro to Construction 2
3/52
Construction Methods & Management
CIEG 486-010
Construction Management
Contractual arrangement
Construction management personnel can
represent owner or contractor
CM manages the basic resources of
construction
-
7/31/2019 Intro to Construction 2
4/52
Basic Resources
workforce
subcontractors
equipment
constructionplant
material
information
time
money
-
7/31/2019 Intro to Construction 2
5/52
Construction Methods & Management
CIEG 486-010
Project Management
Optimize the three attributes of: quality, cost,and time
Principle objective of a construction manager
is to complete each project on time and withinbudget, while maintaining acceptable levels of
safety and risk
-
7/31/2019 Intro to Construction 2
6/52
Construction Methods & Management
CIEG 486-010
Method or System of Project Delivery
Traditional design-bid-build
Phased or Fast-track
Design-build
-
7/31/2019 Intro to Construction 2
7/52
Traditional Design-Bid-Build
Phased or Fast-Track Construction
-
7/31/2019 Intro to Construction 2
8/52
WestApproach
Lighting
EastPiers
WestPier
s
BridgeDe
ck
EastAppr
oach
Towers
MainCables
Suspende
dSteel
Trusses/Framing
TestPiles
Anchorages
-
7/31/2019 Intro to Construction 2
9/52
Construction Methods & Management
CIEG 486-010
Contract Types
Traditional vs. alternative Classification by method of awardandmethod of pricing
Model contracts have been developedby AIA, AGC, CEC, DBIA, CMAA, andEngineers Joint Contract DocumentsCommittee (EJCDC)
-
7/31/2019 Intro to Construction 2
10/52
Construction Methods & Management
CIEG 486-010
Contract Types
Method of Award
1. Competitive bidding formally advertised public work
selective invitation for private work
awarding of contracts by: Lowest responsible bid or
Best value i.e.: technical score price orprice + time(ft), and other variations
-
7/31/2019 Intro to Construction 2
11/52
Construction Methods & Management
CIEG 486-010
Contract Types
Method of Award
2. Negotiated contracts Generally private work
Benefits include flexibility of pricing arrangement
Often used on projects of large size and great
complexity Owner may value expertise and integrity of a particular
contractor and can award contract without competitionthat may otherwise exclude that contractor from thework
-
7/31/2019 Intro to Construction 2
12/52
Construction Methods & Management
CIEG 486-010
Method of Pricing
Fixed-price
1. Lump sum Traditional, single fixed price
Predetermined price that includes profit,
overhead, and all other costs
Greatest risk to contractor resulting in ahigher markup (the greater the risk, the
higher required rate of return )
Most common contract form
-
7/31/2019 Intro to Construction 2
13/52
Construction Methods & Management
CIEG 486-010
Method of Pricing
Fixed-price
2. Unit-price contract Prices of specified units of work are fixed or
predetermined
Actual cost to the owner will vary with actualquantities placed
Best used when details and general characterof the work are known, but quantities aresubject to variation
Risk of unbalanced bids
-
7/31/2019 Intro to Construction 2
14/52
Construction Methods & Management
CIEG 486-010
Method of Pricing
Cost-plus
Contractor agrees to perform the work for a fixedor variable fee covering profit and home office
costs (general overhead)
Field costs are reimbursable at actual cost
Used when: nature of the work or physical conditions are
unpredictable
scope is unknown or difficult to define
-
7/31/2019 Intro to Construction 2
15/52
Construction Methods & Management
CIEG 486-010
Method of Pricing
Cost-plus All cost-plus contracts depend on cooperationamong A/E, owner, and contractor
Record keeping and timely evaluation are
extremely critical Detail record of labor hours and salaries, material
and equipment must be maintained
Good application for professional CM services
-
7/31/2019 Intro to Construction 2
16/52
Construction Methods & Management
CIEG 486-010
Types of Cost-plus Contracts
3. Cost plus fixed %
Fixed % based on portion or all ofreimbursable costs
Used in construction involving new
technology or extremely pressing needs
Owner assumes risk
Contractor cooperation very high
Little or no incentive for cost savings
-
7/31/2019 Intro to Construction 2
17/52
Construction Methods & Management
CIEG 486-010
Types of Cost-plus Contracts
4. Cost plus fixed fee More incentive for cost savings
Incentive for timely completion
Risk shared by owner and contractor
5. Cost plus variable %
Also called sliding scale % Keeps fee in line with type & volume of work
Fee becomes progressively smaller on work that isrepetitive, requires little or no re-engineering, re-planning, or additional layout
-
7/31/2019 Intro to Construction 2
18/52
Construction Methods & Management
CIEG 486-010
Types of Cost-plus Contracts6. Target estimate
May be based on dollar amounts, man-hours, schedule,or combination
Cost savings or overrun shared by owner and contractorat predetermined split
Cost underrun increases contractor profit, overrundecreases profit
7. Guaranteed maximum price Used with well defined scope of work
Particularly suitable for turnkey operation
Contractor or design-builder assumes all risk
Provisions to share savings can be applied
-
7/31/2019 Intro to Construction 2
19/52
Construction Methods & Management
CIEG 486-010
Construction Contracts
Prequalification of bidders Evidence of satisfactory previous experience Financial stability
Advanced or specialized prequalification may be
required as dictated by the magnitude and nature ofthe work
Bid bonds are often required
-
7/31/2019 Intro to Construction 2
20/52
Construction Methods & Management
CIEG 486-010
Elements of a legal contract
offer
acceptance
consideration
legal in every respect requires a meeting of the minds
offer + acceptance = binding obligation
-
7/31/2019 Intro to Construction 2
21/52
Construction Contract Documents
Advertisement for bids
Information for bidders Bid form
General notices
Notice of award
Notice to proceed
Bid bond
Performance bond
Payment bond
Contract form oragreement
General conditions orprovisions
Supplemental and/orspecial conditions
Plans
Specifications
-
7/31/2019 Intro to Construction 2
22/52
Construction Contract Documents
Characteristics of a good contract document:
1. Carefully considered
2. Expressed clearly3. Time-tested
4. Comprehensive
5. Fair
6. Balanced
7. Applicable to the elements of a construction projects
-
7/31/2019 Intro to Construction 2
23/52
Construction Methods & Management
CIEG 486-010
Construction Contracts
bidders are required to:
examine all portions of the contract documents
examine the physical conditions of the site
determine legal requirements affecting the work
complete these investigations prior to bidding
-
7/31/2019 Intro to Construction 2
24/52
Construction Methods & Management
CIEG 486-010
Construction Contracts
contract documents should: Include a hierarchy to determine which
documents govern in case of conflict, i.e.:
DelDOTs hierarchy
Not contain ambiguous language
Not contain exculpatory clauses
-
7/31/2019 Intro to Construction 2
25/52
Construction Contracts -- General Conditions
Contractors warranties Defective drawings
Approval of contractorsplans and equipment
Approval of shop drawingsother submittals
Guarantee by the Contractor
Conduct of the work
Defective work Relations with other
contractors andsubcontractors
Inspection of materials Inspection of field work
Authority of the Engr.
Duties of the inspector
Permits and licenses Labor considerations
Work done by the owner
Lines and grades
Order and discipline Performance
Final inspection &acceptance
-
7/31/2019 Intro to Construction 2
26/52
Construction Contracts -- General Conditions
Federal, state, and localgovernment regulations
Employment (EOE rules)
Emergencies
Minimum wage rate Domestic vs.foreign materials
and labor
Construction reports
Payrolls and bills of material Cooperation among
contractors
Patents
Retainage Bonding and insurance
Guarantee of equipment
Borings
Spare parts
-
7/31/2019 Intro to Construction 2
27/52
Risk Allocations -- General Conditions
Force majeure
Indemnification
Liens
Labor laws
Differing site conditions
Delays and extension of time
Liquidated damages
Consequential damage
Occupational safety, andhealth of workers
Permits, licenses, andregulations
Termination for default bycontractor
Suspension of work Warranties and guarantees
-
7/31/2019 Intro to Construction 2
28/52
Construction Methods & Management
CIEG 486-010
Specifications
Standard, supplemental, and special
provisions two types of specifications:
method specification dictates equipment
and proceduresperformance specspecifies only the
desired end result or product
should include hierarchy
-
7/31/2019 Intro to Construction 2
29/52
Construction Methods & Management
CIEG 486-010
Hierarchy
Governing ranking of contract components in
case of a discrepancy (DelDOT) General Notices Special Provisions
Plans
Supplemental Specifications
Standard Construction Details
Standard Specifications
-
7/31/2019 Intro to Construction 2
30/52
Construction Methods & Management
CIEG 486-010
Classification Coding System
Architectural building and site developmentindustry employees the CSI Format that
includes 16 divisions of work.
Public owners generally use a system ofsections or divisions developed and
employed for several decades
-
7/31/2019 Intro to Construction 2
31/52
Construction Methods & Management
CIEG 486-010
Codes, Standards, and Regulations
Model Codes Basic/National Building Code (BOCA Code)
Uniform Building Code
Standard Building Code
National Electric Code (NEC) and Life Safety Code by
the NFPA under ANSI
The International Building Code 2000 (IBC) replaces
the first three codes. Several subcodes of the IBC
include Fire, Residential, Plumbing, Energy
Conservation, Mechanical, & Private Sewage
-
7/31/2019 Intro to Construction 2
32/52
Construction Methods & Management
CIEG 486-010
Codes, Standards, and Regulations
Model Codes Model codes are adopted in whole or in part by the
local municipality, and become enforceable under thelaw
Zoning Regulations
imposed by local zoning commissionsEnvironmental Regulations
imposed by the EPA, State DEP (DNREC), or local
agency
-
7/31/2019 Intro to Construction 2
33/52
Construction Methods & Management
CIEG 486-010
Codes, Standards, and Regulations
StandardsASTM
Underwriters Laboratories, Inc. (UL)AASHTO
ACI
AISC many, many others
no enforcement by these agencies
specifications generally refer back to these
standards
-
7/31/2019 Intro to Construction 2
34/52
Construction Methods & Management
CIEG 486-010
Submittals required in the contract copies of subcontracts
shop drawings and support calculations
catalog cuts material or equipment samples
schedule(s)
certified payrolls certificates of insurance
environmental test reports
material test reports & certifications
-
7/31/2019 Intro to Construction 2
35/52
Construction Methods & Management
CIEG 486-010
Shop Drawings
structural steel details & erection plan
erection procedures (safety)
PS/PC concrete items
shoring & underpinning details
jacking plans and calculations
scaffolding and falsework
concrete formwork design and details
construction sequencing diagrams
-
7/31/2019 Intro to Construction 2
36/52
Construction Methods & Management
CIEG 486-010
Shop Drawings
cofferdam design & details
dewatering procedure stream diversions
pipe and ductwork fabrication details
reinforcing steel bending diagrams and bar lists
structural timber elements
ornamental iron or steel
maintenance of traffic plans (alternates)
-
7/31/2019 Intro to Construction 2
37/52
Construction Methods & Management
CIEG 486-010
Payments and related issues mobilization and initial costs
retainage progress payments and partial payments
material payments
change orders
substantial completion
punchlist
final acceptance and payment
-
7/31/2019 Intro to Construction 2
38/52
Construction Methods & Management
CIEG 486-010
Changes in plans and specs
clarification, correction, modifications prior to bidare referred to as addenda
owner must maintain a system of distributing and
acknowledging receipt of addendum
plan and spec changes after award are referredto as revisions, and generally require issuance
of a change order(s)
-
7/31/2019 Intro to Construction 2
39/52
Construction Methods & Management
CIEG 486-010
Change Orders a written order issued by the owner to the
contractor for a change to the contract within thescope of work
change orders are written for: extra work
increasing or decreasing the contract quantities alterations
change orders state the basis and amount ofpayment and time extensions
-
7/31/2019 Intro to Construction 2
40/52
Construction Methods & Management
CIEG 486-010
Contracts
Liquidated damages
Incentive/Disincentive (bonus/penalty)
Acceleration
Increase crew levels, crew size
Add shifts and/or extend work hours
CPM schedule is an extremelyvaluable tool inanalyzing delay claims
-
7/31/2019 Intro to Construction 2
41/52
Construction Methods & Management
CIEG 486-010
Claims and Disputes
a claim is a request by a contractor for additional
compensation or time extension for occurrences
beyond the contractors control including:
differing or unexpected site conditions
change in scope
delays caused by the owner
owner has duty to provide adequate, accurate data
to the bidders
-
7/31/2019 Intro to Construction 2
42/52
Construction Methods & Management
CIEG 486-010
Claims and Disputes Owner is liable to contractor when:
inaccurate data are given
extras develop because of improper design
design is significantly changed after the contractis signed (constructive change)
Contractor must prove entitlement and theassociated damages
Contractor must provide timely notice of claimupon discovering impact
-
7/31/2019 Intro to Construction 2
43/52
Construction Methods & Management
CIEG 486-010
Types of Claims
delay or disruption claim
extra work claim
acceleration
impossibility-of-performance claim
defective design claim (error or omission)
interference claim
superior knowledge claim
-
7/31/2019 Intro to Construction 2
44/52
Construction Methods & Management
CIEG 486-010
Dispute Resolution Early settlement between parties
Alternative depute resolution (ADR)
negotiation arbitration (1 or 3 members)
mediation neutral advisors
Dispute Review Board (DRB)
3 or more odd number of board members selectedevenly by both sides
Litigation sometimes unavoidable; usually undesirable; but
sometimes best method
-
7/31/2019 Intro to Construction 2
45/52
Construction Methods & Management
CIEG 486-010
Credits
Credits reimbursement from contractor toowner for work eliminated (lump sum
contract or item)
Credit may also be given when specifiedperformance criteria is not met
-
7/31/2019 Intro to Construction 2
46/52
Construction Methods & Management
CIEG 486-010
Claims Avoidance
producing comprehensive, accurate, contract
documents
constructibility review
clear understanding of contract requirements prior to
bidding
having good administrative procedures in place
open and honest communication
timely troubleshooting
-
7/31/2019 Intro to Construction 2
47/52
Construction Methods & Management
CIEG 486-010
Claims Avoidance
Claims avoidance begins in the pre-construction phase
Contract documents need to be clear,
accurate, comprehensive, and fairly
distribute risk
C i M h d & M
-
7/31/2019 Intro to Construction 2
48/52
Construction Methods & Management
CIEG 486-010
Ability to influence cost over time Greatest potential to influence cost is during the
pre-construction design phase
Claims avoidance begins during pre-construction Design phase
Intensive preparation and review of contract
documents Careful consideration of methods and
equipment = consider overall constructibility
-
7/31/2019 Intro to Construction 2
49/52
100%
0%
Ability to Influence Construction Costs over Time
Levelof
Influence
on
Cost
Oper.Concept &
Feasibility
Design and
EngineeringProcurement and Construction Startup
-
7/31/2019 Intro to Construction 2
50/52
Construction Methods & Management
CIEG 486-010
Design Professionals should:
Specify locally available material
Allow substitution of equal quality material
Avoid one-ofa-kind or non-standard items
where possibly
Design structures with as many redundant
elements as possible Design should allow construction using the
prevailing methods and equipment
-
7/31/2019 Intro to Construction 2
51/52
Construction Methods & Management
CIEG 486-010
Design Professionals should:
Design to minimize required labor
Specify a quality of workmanship consistent withthe quality of the project
Do not require the contractor to assume
responsibility for information that should be
furnished by the design engineer/architect Produce simple, straight-forward specs = clearly
state what is expected
-
7/31/2019 Intro to Construction 2
52/52
Construction Methods & ManagementCIEG 486-010