Importance of Utilities Data in

NCDOT Project Delivery

November 6, 2019

Page 2: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

2

1 2 3 4 5 6 7

When project is

scoped

PLANNING PRIORITIZATION

&

PROGRAMMING

PROJECT

DEVELOPMENT

DESIGN PROPERTY

ACQUISITION

CONSTRUCTION MAINTENANCE

When alignment is being refined

When Utilities

ACTUALLY commit

Improving Project Delivery = Knowing More Earlier = Better Scope, Schedule, Budget

NCDOT Project Delivery

When Utilities are

located

Page 3: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

• Over 400 unique utility providers in state

• Diverse services & providers

3

Water

Wastewater

Fiber

Comms

Electric

Gas

Utilities: A Complicated Task

Page 4: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

• 105 different power providers in the state

– Power Companies

• Duke

• Dominion

• Others

– Electric Membership Corporations (EMC)

– Municipalities

– Schools/Universities

4

Example: Power Providers

Page 5: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

5

Example: Power Providers

Dominion

Duke

Layer Features No Duke/No Dominion % Remaining

STIP Points 796 pts 399 pts 50.1

STIP Lines 22959560 lf 11685082 lf 50.8

Page 6: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

6

NCDOT Project U-3467

TYPE UTILITY

Electric Transmission DUKE Energy

Electric Distribution DUKE Energy

Electric Distribution Union Power Cooperative

CATV Spectrum (Charter/TWC)

TOLL/DATA Conterra (Broadplex)

TOLL/DATA CenturyLink {Level3}

TOLL/DATA MCI-Metro

LOCAL Telephone Windstream (Verizon/GTE)

Water Union County Water & Sewer

Sewer Union County Water & Sewer

Natural Gas Distribution Piedmont Natural Gas

Natural Gas TRANSMISSION Piedmont Natural Gas

Page 7: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

7

NCDOT Project U-3467

Page 8: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

8

NCDOT Project U-3467

TV

Electric Distribution

TV

TYPE UTILITY

Electric Transmission DUKE Energy

Electric Distribution DUKE Energy

Electric Distribution Union Power Cooperative

CATV Spectrum (Charter/TWC)

TOLL/DATA Conterra (Broadplex)

TOLL/DATA CenturyLink {Level3}

TOLL/DATA MCI-Metro

LOCAL Telephone Windstream (Verizon/GTE)

Water Union County Water & Sewer

Sewer Union County Water & Sewer

Natural Gas Distribution Piedmont Natural Gas

Natural Gas TRANSMISSION Piedmont Natural Gas

Page 9: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

9

NCDOT Project U-3467

Page 10: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

10

NCDOT Project U-3467

TYPE UTILITY

Electric Transmission DUKE Energy

Electric Distribution DUKE Energy

Electric Distribution Union Power Cooperative

CATV Spectrum (Charter/TWC)

TOLL/DATA Conterra (Broadplex)

TOLL/DATA CenturyLink {Level3}

TOLL/DATA MCI-Metro

LOCAL Telephone Windstream (Verizon/GTE)

Water Union County Water & Sewer

Sewer Union County Water & Sewer

Natural Gas Distribution Piedmont Natural Gas

Natural Gas TRANSMISSION Piedmont Natural Gas

Page 11: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

11

Costs

• Current costs of not knowing enough early– Altered preliminary design decisions

– Recurring design revisions (As late as 25% plans)

– Difficult utility coordination

– Schedule delays

• Utility needs to schedule move

• DOT must wait until complete

– Budget increases

• DOT (No MOA outside ROW)

• Utility (MOA inside ROW)

– Loss of trust

• Utility/DOT

• DOT/Public

• All of these translate directly to $$$

Page 12: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

12

We are trying…

• Contacted 811 directly via Project ATLAS

– No Success

• Contacted 811 directly via DOT Encroachments

– No Success

• Investigating, via the internet, for open source data

– Limited success

• Engaging consultants to contact individual utilities

– Maser Engineering via ATLAS

• Engaging consultants to assess the issue from the

executive level

– KPMG via DOT Mgmt

Page 13: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

Potential Use in ATLAS

GIS

WE

TL

AN

DS

& S

TR

EA

MS

PR

OT

EC

TE

D

SP

EC

IES

HIS

TO

RIC

RE

SO

UR

CE

S

TR

AF

FIC

CO

MM

UN

ITY

ST

UD

IES

BIK

ES

&

PE

DE

ST

RIA

NS

UT

ILIT

IESAdvancing

Transportation through

Linkages

Automation and

Screening

A

T

L

A

SATLAS Screening Tool

Page 14: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

14

Thoughts moving forward…

• Security is essential

– Location information can remain abstracted

– State requirements

• NCID

• Active Directory (EADS, NCDOT etc.)

• ArcGIS Portal

– Private Security Postures and Preferences

• Unknowns

• Embracing Web Services

– Architecture/Cloud

– Culture changes

Page 15: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP

15

What can NCGICC do?

• Advocacy

• Communication with Utility Owners

• Crafting Tactical Relationships

• Gather Feedback on the issue

– Construct Use Cases

• Form a Committee

– Similar to Parcel Map Initiative

• Blanket MOA or MOU similar to 811

Page 16: Importance of Utilities Data in NCDOT Project Delivery · 11/6/2019  · When project is scoped PLANNING PRIORITIZATION & PROGRAMMING PROJECT DEVELOPMENT DESIGN PROPERTY ... STIP