Page 1: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

IEC 61850TOP-DOWN DESIGN

Developing accurate and comprehensive IEC 61850 system specifications

that support the fluid interchange of multi-vendor devices

Page 2: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

Page 3: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSThis Presentation is about ….

How Utilities can

efficiently build and

maintain IEC 61850

Power Automation-

Systems !!!

Page 4: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSWe are going to cover the following topics

• SCL files SCD-ICD-SSD

IEC 61850 Tools and Process

• Why has it nearly not been used?

• Why should it be used?

• How can it be used to improve overall efficiency

System Specification with SSD Files

• Impose IEC 61850 IED data model to supplier.

• Impose formalized, detailed design to supplier.

Different approaches on system specification

• Additional Requirements on IEC61850 Standardization

• Additional Requirements on Tools and Key Players

Lookout

Page 5: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSDifferent Roles

IED

Configuration

Tool

System

IntegrationTool

System

Specification

Tool

SCL

Page 6: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSIEC 61850 Top Down Process

6

System

Specification

Tool

System

Configuration

Tool

IED

Configuration

Tool

CIDSSD SCD

Do

cICD

DocIID

Specification DesignSystem

Engineering

System

Specification

Description

Page 7: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSThe useless SSD ….

▪ Why did Utilities not use SSD files for system

specification and tendering?

▪ Why did System Integrators not use SSD files for

designing the system?

Page 8: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSContent of SCL Files

Data

Types Network

Power

System

IED(s)

Substation

Voltage Level

Bay

Circuit Breaker

LNode

IED

Logical Device

LN

Logical Node Type

Data Object Type

Data Attribute Type

SubNet

IED IED

IP Address Params

GOOSE Address Params

Com.

Conf.

(GOOS

ESV,R

EP.)

DOI,

DAI

Page 9: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS▪ The content of the Process Section is

by far not sufficient to specify a

Power Automation System.

▪ Organization did not fit.

▪ Challenging task of defining IEC

61850 mapping … for different IED

types

▪ Utility name spaces even more

challenging.

▪ Potential benefit for maintenance and

quality not recognized.

Why Utilities did not use SSD Files

Data

Types

Power

System

(Process

Section)

Substation

Voltage Level

Bay

Circuit Breaker

LNode

Logical Node Type

Data Object Type

Data Attribute Type

Page 10: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSMissing Content

▪ Custom Signal designations

▪ HMI texts ( Alarms/Events)

▪ Processing and routing information

▪ Applications & Logic

▪ Physical IO

▪ Protocolmappings e.g. IEC 60570-104 or DNP 3 Addresses

▪ Test information

Page 11: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS▪ The content of the Process Section does

not really help to build a Power

Automation System.

▪ Why draw again a Single Line if it already

exists?

▪ Where is the productivity gain in mapping

hundreds of logical nodes in SCL.

▪ Customers did not require an SCD with

Substation section.

Why System Integrators did not use SSD Files

Data

Types

Power

System

(Process

Section)

Substation

Voltage Level

Bay

Circuit Breaker

LNode

Logical Node Type

Data Object Type

Data Attribute Type

Page 12: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

Excel

&

VBA

Resulting Engineering Process

12

Informal Specification

Informal DesignBottom Up

Engineering

Excel,

Visio

&

MS Word

Design

Standards

IED

Configuration

Tool

IED

Configuration

Tool

IED

Configuration

Tool

IED

Configuration

Tool

IED

Configuration

Tool

CID

CID

CID

CID

CID

CID

Page 13: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSDrawback

System Integrators delivered very different solutions for similar systems.

No transparency of the design

Device interchangeability was hard to achieve.

Utilities lost grip on the installation

Maintenance became difficult and expensive

Page 14: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSUtilities took action ….

• Representatives joined TC57 WG10 and initiated User Feedback task-force

• Osmose project

ENTSO-E

• Utilities participated more intensively in IEC 61850 working group.

• Utilities left the “Asset Manager” comfort zone.

• Utilities defined IEC 61850 design standards and processes.

• Utilities invested in IEC 61850 training.

Investments in IEC 61850 design standards

Page 15: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS…and define solutions with different technical approaches:….

Impose Standard IED design to

suppliers (virtual IED)

Develop Utility Standards and

define mapping to different IED data

models

Page 16: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS…. and different pros and cons:

• Representatives joined TC57 WG10 and initiated User Feedback task-force

• Osmose project

ENTSO-E

• Utilities participated more intensively in IEC 61850 working group.

• Utilities left the “Asset Manager” comfort zone.

• Utilities defined IEC 61850 design standards and processes.

• Utilities invested in IEC 61850 training.

Investments in IEC 61850 design standards

Page 17: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS…. with different technical approaches:

Impose Standard IED design to suppliers (virtual IED)

+ Simpler to handle for Utilities

- Only large Utilities can “force” design upon manufacturers

- Standards are inflexible and hard to maintain

Develop Utility Standards and define mapping to different IED

data models

- Higher complexity because different IED Data Models need to be mapped.

+ More flexible and works also for smaller Utilities

+ Covers more IEDs on the market.

+ Standards are IED independent. Only the IED mapping needs maintance.

Page 18: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSVery sad ……

• Proprietary solutions

• Not represented in SCL

• No processing by IEC 61850 Engineering tools

In both approaches the

SSD file as a formal

specification is not really a key element!!!

Page 19: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSHow to enable Utilities to build more efficiently their systems

• SSD files need to contain enough information to specify most aspects of a power automation system independently of the IED architecture.

• IEC 61850 Standard needs to show the way from IED independent system specification to implementation.

IEC 61850 Standard

• Engineering tools must extend IEC 61850 communication engineering to general signal and application engineering.

• Engineering tools must support company design standards and SCL representation.

• Engineering tools must bridge the gap between customer data model and vendor specific implementations.

Engineering Tools

Page 20: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

Application Scheme

SCL : Quo Vadis TF 6-100 & Osmose

Substation(s)IED(s)

Substation

Voltage Level

Bay

Circuit Breaker

LNode

IED

Logical Device

LN,LN0

Com.

Conf.

(GOOSE

SV,REP.)

DOI,

DAI

Virtual

LNode

GUIDs for File Identification

Data

Exchange

DO

SDA

S

Function

SubFunction

Category

Page 21: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

Asset Management and Enterprise Data

Engineering Standards

Define the process IO &

wiring

Define control & protection functions

Engineer IEDs

Engineer horizontal

communication

Engineer vertical communication

Define HMI and NCC Data

Engineer Gateway

Engineer SCADA

IEC 61850 and

SCL based

Tools

AA

A

A

A A

Page 22: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

Template based Specification and

Design

Engineering Efficiency

22

Specification DesignSystem

Engineering

SCDSystem

Configuration

Tool

IED

Configuration

Tool

CID

ICD

Doc

IID

ICD

CID

System

Specification

Tool

Fully automated

communication

configuration

Specification

Libraries

Engineering

Libraries

Page 23: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

System Specification

Template Definition

System Integration

Standardisation

IED

Configuration

Tool

System

Specification

Tool

IED

Configuration

Tool

Engineering

Template

System

Integration

Tool

System

SpecificationSystem

Specification

Tool

System

Integration

Tool System

Configuration

Developing

Standards & Frame

Agreements

Executing Projects

Page 24: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

Page 25: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKS

System

IntegrationTool

Instantiate IEDS

Configure Network

Configure Communication

Create SCD File

System Integration Process

Page 26: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSCreate SCD File

SSD

Substatio

n

IID

LD/LNs

Data

Types

Network

SCD

IED

IED

IED

Substatio

n

Data

Types

Network

•Specified Logical Nodes are implementedLink IEDs to

Substation

•Description of the single CID /IID Files is mergedMerge IEDs

together

•Logica Node Types, Data Object Types and Data Attribute Types are merged

Merge Data Types

•Set IP Adresses and Network Access Points

Connect all IEDs to one

Network

•Put Data into Datasets and assign Control Blocks

Configure GOOSE

and Reports

IID

LD/LNs

Data

Types

Network

IID

LD/LNs

Data

Types

Network

IID

LD/LNs

Data

Types

Network

Page 27: IEC 61850 TOP-DOWN DESIGN · •IEC 61850 Standard needs to show the way from IED independent system specification to implementation. IEC 61850 Standard •Engineering tools must

IEC 61850 Global2019

HELINKSWhat can SSD be used for

Graphical representation of electrical scheme (Single Line) and the automation functions for

documentation

Base for colouring of HMI (monitoring and control systems)

Automated generation of standardized functional specification

Generation of structured function oriented signal lists with hierarchical naming.

Allocation of control and protection functions of the secondary equipment (IED‘s)