ice presentation final
TRANSCRIPT
-
8/14/2019 ICE Presentation Final
1/46
Wind Farm Development
Thursday 16th November 2006
-
8/14/2019 ICE Presentation Final
2/46
Introduction to Mott MacDonald Technical consultancy active in power, water,
transport, buildings, communication, education,health etc
Leading capability in power covering renewables,thermal and nuclear
Approximately 800 staff active in
powerequivalent of 90 in renewables
Mott MacDonalds renewable energy capabilityfocussed in Glasgow with wind, biomass and
marine technology skills
Currently involved in 30+ wind projects across UK,Europe and Asia
-
8/14/2019 ICE Presentation Final
3/46
Introduction to SgurrEnergy
Leading independent multi-disciplinary consultancyspecialising in renewables
Based in Glasgow and Beijing
Further international expansion planned
Over 40 experienced professionals
Accumulation of decades of experience
Experience in over 20 countries
-
8/14/2019 ICE Presentation Final
4/46
Drivers and Regulatory Structures
-
8/14/2019 ICE Presentation Final
5/46
Decommissioning
START OF COMMERCIALOPERATIONS
S
cheme
Dev
elopment
Procurement
O&M
Handover
Con
struction
Construction
Pre-Construction
PlanningOnshore No.
& MW
OffshoreNo. & MW
England 43 822 6 2718N. Ireland 29 599 0 0
Scotland 74 5399 0 0Wales 14 183 0 0
Total 160 7006 6 2718 150272227Total
601463Wales
0052314Scotland
00412N. Ireland
9011118England
OffshoreNo. & MW
OnshoreNo. & MW
Underconstruction
21341124114Total
60125423Wales
0056831Scotland
008911N. Ireland
153321049England
OffshoreNo. & MW
OnshoreNo. & MWOperational
UK Wind Project Development - Status
-
8/14/2019 ICE Presentation Final
6/46
Revenues available to a UK wind
generator
0
1020
30
40
50
60
70
8090
100
LEC
ROC
Energy
A UK wind generator will beable to earn revenue fromthree sources; sales ofenergy and ROCs and LECs
ROCs and LECs are tradablegreen certificates issued forrenewable generation ROCsderive from the RenewableObligation and LECs derivefrom the Climate ChangeLevy
-
8/14/2019 ICE Presentation Final
7/46
ROCs Renewable Obligation Certificates
Derive from the Renewable Energy Obligationintroduced in April 2002
Obligation on retailers to buy a certain percentageof their energy from accredited renewablesgeneration set at 3.2% in 2003, now 6.7%.
If a retailer does not comply it pays a fine buyout
penalty - now ~33/MWh - on top of its energy cost
Accredited renewables generators are issued ROCsfor energy produced - 1 ROC per 1 MWh
Retailers buy ROCs to demonstrate compliance withRO
-
8/14/2019 ICE Presentation Final
8/46
ROC recycle Buy-out payments are collected and are recycled to
holders of ROCs in proportion to their ROC holdings
This means that a ROC has a value greater than thebuy-out price as holders of ROCs receive a share ofbuyout monies
The recycle bonus rises as the level of shortfallincreases
If the RO target were met the ROC price would dropto zero!
-
8/14/2019 ICE Presentation Final
9/46
0
10
20
30
40
50
60
70
0 10 20 30 40 50
% shortfall on RO Target
ROCv
alue:/MWh
ROC values versus RO shortfall in
2006
-
8/14/2019 ICE Presentation Final
10/46
Drivers of ROC prices Supply and demand
Supply will depend on amount of renewable capacity built andits utilisation rule changes
Demand is set by the RO targets
Currently set to rise linearly to 10.4% in 2010
View is that target will be raised after 2010 possibly to the20% target aspired to.
Buy-out prices indexed to inflation
Banking of ROCs by suppliers/ traders may affect prices
Dominant suppliers (which are also the main owners of RE
plant) will ensure that RO target is not met to stop ROC valuesfalling to zero
Scheme is now being reviewed
-
8/14/2019 ICE Presentation Final
11/46
RO Review - Issues There are a number of concerns regarding the
RO
Rewards to lower cost renewable generators are toogenerous
There is considerable uncertainty regarding ROC prices,
especially after 2015
There is a cliff edge for ROC prices if full compliance ofthe RO is achieved
Rewards for high cost more innovative renewablegeneration are too small to support deployment
-
8/14/2019 ICE Presentation Final
12/46
RO Review Outcomes Future ROC allocation may be banded. Mature
technologies likely to issued less ROCs per MWh than
selected promising but high cost technologies (likePV).
Scheme likely to be rolled out to 2020
The recycle arrangements will be changed in order toeliminate the possibility of ROC prices collapsing tozero
EU Commission still favours that all Europe moved to
feed-in tariffs
-
8/14/2019 ICE Presentation Final
13/46
Climate Change Levy (CCL)
Introduced in 2002, CCL is a tax on energy consumption bylarge industrial and commercial users not paid by generators
Electricity is taxed at 4.3/MWh
Energy from certain renewable sources and from qualifyingcogeneration is exempted and is issued a Levy ExemptionCertificate (LEC).
Different set of renewables to RO LECs include mini hydro
and municipal waste, while ROC dont. ROCs include biomassco-firing, LECs dont
LECs are sold with energy to suppliers/customers who can thenoffset their CCL obligation (4.3/MWh) Can be separated foroutput sold off-site
Stand alone renewable generators can normally capture 85% ofLEC value
Unclear how long tax will continue
-
8/14/2019 ICE Presentation Final
14/46
Energy Review and Renewable Grid Issues One of the key issues that has delayed the
introduction of renewables and limits theachievement of the 2010 target.
ER06 states there is the need to resolve anumber of issues:
Final Sums Liability (paying up front forconnection)
Connection queues as a result ofincreased interest in renewables[Clustering, i.e. group connectionssimilar to NI, provide better networkplanning but can disadvantage somegenerators]
Renewables lower transmission use ofsystem charges?
Need to change from invest then
connect to connect and manage Regulatory framework for offshore wind
All above issues were identified aroundtime of ER03
Distribution-level issues
Distribution andTransmission-
level issues
Transmission-level issues
-
8/14/2019 ICE Presentation Final
15/46
Stern Review of Economics of Climate
Change Sir Nicholas Sterns review of the economics of
climate change has two key messages forrenewables
Renewables are central part of the carbon
mitigation strategy There should be a huge scale up in funding of R&D
and deployment of low carbon technologies,
including renewables
-
8/14/2019 ICE Presentation Final
16/46
Planning and Permitting Issues
-
8/14/2019 ICE Presentation Final
17/46
Overview of Legislation
Windfarm consent needs are driven by legislation
Planning permission/consent to build granted under
Section 36 of Electricity Act for over 50MW
Town and Country Planning Act for under 50MW
Environmental Impact Assessment (EIA) needed for planningapplications
The Electricity Works (Environmental Impact Assessment) Regulations 2000 Town and Country Planning (Environmental Impact Assessment)
Regulations 1999
If require consent for grid connection
Either Section 37 of Electricity Act or Town and Country Planning Act
Also need an EIA for grid connection consent
-
8/14/2019 ICE Presentation Final
18/46
Planning Process Initial Stage
Early consultation with key stakeholders
Initial approach to local authority
Seek initial views of key stakeholders
Scoping of EIA
Focus on key issues through consultation and discussion with keystakeholders
Time spent at scoping stage could save time later in process
Identification of likely need for baseline studies
Identify available data / data gaps early
Develop public consultation strategy
Landowner consultation
no surprises later
-
8/14/2019 ICE Presentation Final
19/46
Interfaces
ClientPublic
Consultees
Statutory Consultees(SEPA or EA, LPA, DTI or Scottish
Exec, English Nature orSNH, MOD, CAA etc)
Environmental Technical
Civil
Engineering
Geology
EIApreparation
Transport/Routes
LayoutOptimisation
Landscape and visualEcology
Ornithology
Hydrology & hydrogeologyNoise
CommunicationsArchaeology
Traffic & transport
Planning
-
8/14/2019 ICE Presentation Final
20/46
Planning Process EIA Stage
Ensure project assessed covers all potential technical options
EIA scope focussed on key issues in a robust manner e.g.
landscape and visual impact including cumulative impact
ornithology; presence of SPAs and SSSIs close to site ecology
radar interference
Input from experts capable of taking to Public Inquiry
Supporting studies commissioned in timely manner and scopeagreed with key consultees
Meeting project programme through management of largeenvironmental resource and sub-consultants
Integration with the design process
Ensure mitigation measures consistent with project design
-
8/14/2019 ICE Presentation Final
21/46
Planning Process Application Stage
Maintain close interface with local planningauthority (LA) / Scottish Ministers (SM) after
application Respond to queries/requests for more information
in timely manner
Close integration with project design team to tryand mitigate issues to avoid Public Inquiry
Agree planning conditions with LA and SM Translate planning conditions into contractor
requirements
-
8/14/2019 ICE Presentation Final
22/46
Public Consultation
On going throughout the planning stage
Manage flow of information / publicity to localpeople and organisations information voids canfill with bad news !
Understand the local and regional politicians background to phase 1 essential
Review comments from third parties of previous
EIAs and identify potential supporters and risks
-
8/14/2019 ICE Presentation Final
23/46
Project Evaluation
-
8/14/2019 ICE Presentation Final
24/46
Site Identification & Provisional Layout
Wind resource and regime
NOABL
Reanalysis
Grid connection
Access and buildability
Constraints
-
8/14/2019 ICE Presentation Final
25/46
Underground
Cables /
Pipelines
Technical & Environmental Constraints
Roads
Houses(noise,
Shadow-flicker)
Areas with
Historical
Importance
Wildlife Areas
OverheadLines LandownerBoundary
-
8/14/2019 ICE Presentation Final
26/46
Wind Regime Assessment
Undertake wind regime assessment campaign using:
Wind Monitoring Masts
SODAR
LIDAR
Monitor for 12 months or more
Monitor at multiple locations
-
8/14/2019 ICE Presentation Final
27/46
Measured Turbulence Intensity & Wind Shear
Ambient turbulenceintensity and
Measured and Modeled Turbulence with
Height
0
10
20
30
40
50
60
0% 10% 20% 30% 40%
Tubulence (%)
Height(m)
ModeledFit
Measured
Data
Measured and Modeled Wind Shear in Forestry
0
10
20
30
40
50
60
70
80
0 1 2 3 4 5 6 7 8
Ave rage Wind Speed (m/s)
HeightAboveGroundLevel(m)
Open MoorlandWind Shear Zo =0.4
Forested AreaWind Shear
TheoreticalForest WindShear based onZo = 0.8
wind shear must be
accounted for infatigue life calculations
-
8/14/2019 ICE Presentation Final
28/46
Added Turbulence
Wake induced turbulence must alsobe investigated.
Modified Sten Frandsen modelcombined with far wake modelling
Plotting predicted CTI against IEC threshold
10%
15%
20%
25%
30%
35%
0 5 10 15 20 25
Wind Speed (m/s)
CharacteristicTurbulenceIntens
ity
CTI (V90
2MW)IEC 61400
threshold
Plotting predicted CTI against IEC threshold
10%
15%
20%
25%
30%
35%
0 5 10 15 20 25
Wind Speed (m/s)
CharacteristicTurb
ulenceIntensity
CTI (Bonus
2.3)
IEC 61400
threshold
-
8/14/2019 ICE Presentation Final
29/46
Impact of Complex Roughness
Complex roughness, such as buildings and forestry hassignificant impact on wind turbine operation.
These features produce higher than specified turbulenceintensity & wind shear.
Effects on:
Power Curve
Operational Loads
Fatigue Life
The effects of trees are further
complicated by growth and felling
-
8/14/2019 ICE Presentation Final
30/46
Extreme Wind Speed
Analysis typicallyperformed only at sitemast
Two methodologies for
Extreme Wind
WAsP Engineering tomodel gust values
across the site
-
8/14/2019 ICE Presentation Final
31/46
Components of a Wind Turbine(Model shown is Vestas V80)
Rotor
blades
High voltage
transformer
Gearbox
Tower
Yaw gears
Electricalgenerator
Hub
controller
Ultrasonic
sensors
Hydraulic
system
Main shaft
Oil coolerNacelle
-
8/14/2019 ICE Presentation Final
32/46
Technology Selection
IEC Classification
Mean & Extreme Wind Speed
Turbulence Intensity Wind Shear
Compliance
Noise Emission Grid Code Compliance
Environmental Conditions
Economic Viability Production
Cost
-
8/14/2019 ICE Presentation Final
33/46
Energy Yield Modelling Final layout iteration
Compromise betweenmaximum production andconstraints
Predict energy yield
Rigorous quality checks
Multiple MCP techniques
Model validation and tuning
Complex forestry modelling
Quantification of
uncertainty
-
8/14/2019 ICE Presentation Final
34/46
Performance Testing
Power performance testing
Noise compliance Planning & environmental compliance
Grid code compliance
-
8/14/2019 ICE Presentation Final
35/46
Project Procurement and Financing
f
-
8/14/2019 ICE Presentation Final
36/46
Overview of Contracting Strategies
- Who and Why EPC Contracts
Majority of risks on Contractor
One contract to deal with
Sometimes developers with little experience or as a pre-requisite to Project Financing
Multi-Contract Lower overall costs
Increased competition; more choice of contractors
Usually developers with sufficient in house experience orgood OE support, using own funds
Prevalent for UK onshore projects
-
8/14/2019 ICE Presentation Final
37/46
EPC Contracts
Single Contractor
Takes most of the risks, handles the interface workload andrisks, provides price certainty
More expensive than multi-contract; risk premium added in
Not always the WTG supplier who leads
Can be for multiple sites
Owner still needs to do front-end development andgain permits
Owner may also need technical support
M l i C
-
8/14/2019 ICE Presentation Final
38/46
Multi-Contract
Multiple Contractors covering several scopes
Electrical, civil, WTG supply, grid connection
Lower overall cost
Owner takes interface risk and has much higher workload
Owner still needs to do front-end development andgain permits
Several contracts to negotiate instead of one
Owner likely to need more technical or projectmanagement support
S f F di
-
8/14/2019 ICE Presentation Final
39/46
Sources of Funding
Equity Debt
Shares
Investors
i.e. VC
Standby
Equity
Project
FinanceBonds
Mezzanine
Finance
Subordinated
Debt
Return on Investment
Payback period Initial commitment
Guarantees/Support
Definite Term
Financial Market Rates Fees
Cover Ratios
Wh P j t Fi D d h
-
8/14/2019 ICE Presentation Final
40/46
Why Project FinanceDepends on who
you are?PF for Sponsors
Insulation from Project Debt and
Risks!
Spread of risks for large projects
Off balance sheetCorporate borrowing restrictions
Tax advantages
Risk sharing
PF for Utilities/Govt
Access to foreign investment
Foreign skills and know how
Outside Public Sector Borrowing
Accelerates non-priority projects
P j t Fi h t!
-
8/14/2019 ICE Presentation Final
41/46
Project Financewhy not!
Time..
Project scale..
P j t St t
-
8/14/2019 ICE Presentation Final
42/46
Project Structure
Sponsors
Banks
LocalLegislation
Government
Project Company
Suppliers
Offtakers
Operator
Contractor
SupplyAgreements
OfftakeAgreements
Consents/Permits
Concession
Agreement
CreditAgreements
ShareholderAgreements
O&MAgreement
Financial Risks Market Risks
Construction & Operation Risks
Legal & Regulatory Risks
ConstructionAgreement
Implications of Gearing and Non/Limited
-
8/14/2019 ICE Presentation Final
43/46
Implications of Gearing and Non/Limited
Recourse NatureTurbine Technology - turbine reliability issues ranging
from minor to very major
EPC risk Wrapped EPC no longer essential for banks
but is risk pricing sufficiently clear?
Operations - Availability of third-party maintenance
providers post warranty period
Offtake Risk Firm Power Purchase Agreement (PPA)
and confidence regarding Green Certificates
Wind Risk Confidence needed in P50 or P90 value in
FM
Summary
-
8/14/2019 ICE Presentation Final
44/46
Summary
DriversMarket drivers in the UK are sufficiently strong to ensure
continued growth of RE projects. ROC improvements will
reinforce this
Barriers
Availability of grid connection and planning consent are the
major obstacles to the rate of deployment
Development Focus
An awareness of project financing and project risks is a
requirement from the outset all technical and environmentalissues must ultimately relate to these
Summary
-
8/14/2019 ICE Presentation Final
45/46
Summary
Contract Strategy
Need to adopt contract strategy based on resources and
attitude to risk
Financing
Financing options must be considered from the outset to
ensure the project is developed appropriately
Need to understand how to match project structure and risk
profile to financing options
-
8/14/2019 ICE Presentation Final
46/46
www.mottmac.com