ice presentation final

Upload: sebascian

Post on 30-May-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 ICE Presentation Final

    1/46

    Wind Farm Development

    Thursday 16th November 2006

  • 8/14/2019 ICE Presentation Final

    2/46

    Introduction to Mott MacDonald Technical consultancy active in power, water,

    transport, buildings, communication, education,health etc

    Leading capability in power covering renewables,thermal and nuclear

    Approximately 800 staff active in

    powerequivalent of 90 in renewables

    Mott MacDonalds renewable energy capabilityfocussed in Glasgow with wind, biomass and

    marine technology skills

    Currently involved in 30+ wind projects across UK,Europe and Asia

  • 8/14/2019 ICE Presentation Final

    3/46

    Introduction to SgurrEnergy

    Leading independent multi-disciplinary consultancyspecialising in renewables

    Based in Glasgow and Beijing

    Further international expansion planned

    Over 40 experienced professionals

    Accumulation of decades of experience

    Experience in over 20 countries

  • 8/14/2019 ICE Presentation Final

    4/46

    Drivers and Regulatory Structures

  • 8/14/2019 ICE Presentation Final

    5/46

    Decommissioning

    START OF COMMERCIALOPERATIONS

    S

    cheme

    Dev

    elopment

    Procurement

    O&M

    Handover

    Con

    struction

    Construction

    Pre-Construction

    PlanningOnshore No.

    & MW

    OffshoreNo. & MW

    England 43 822 6 2718N. Ireland 29 599 0 0

    Scotland 74 5399 0 0Wales 14 183 0 0

    Total 160 7006 6 2718 150272227Total

    601463Wales

    0052314Scotland

    00412N. Ireland

    9011118England

    OffshoreNo. & MW

    OnshoreNo. & MW

    Underconstruction

    21341124114Total

    60125423Wales

    0056831Scotland

    008911N. Ireland

    153321049England

    OffshoreNo. & MW

    OnshoreNo. & MWOperational

    UK Wind Project Development - Status

  • 8/14/2019 ICE Presentation Final

    6/46

    Revenues available to a UK wind

    generator

    0

    1020

    30

    40

    50

    60

    70

    8090

    100

    LEC

    ROC

    Energy

    A UK wind generator will beable to earn revenue fromthree sources; sales ofenergy and ROCs and LECs

    ROCs and LECs are tradablegreen certificates issued forrenewable generation ROCsderive from the RenewableObligation and LECs derivefrom the Climate ChangeLevy

  • 8/14/2019 ICE Presentation Final

    7/46

    ROCs Renewable Obligation Certificates

    Derive from the Renewable Energy Obligationintroduced in April 2002

    Obligation on retailers to buy a certain percentageof their energy from accredited renewablesgeneration set at 3.2% in 2003, now 6.7%.

    If a retailer does not comply it pays a fine buyout

    penalty - now ~33/MWh - on top of its energy cost

    Accredited renewables generators are issued ROCsfor energy produced - 1 ROC per 1 MWh

    Retailers buy ROCs to demonstrate compliance withRO

  • 8/14/2019 ICE Presentation Final

    8/46

    ROC recycle Buy-out payments are collected and are recycled to

    holders of ROCs in proportion to their ROC holdings

    This means that a ROC has a value greater than thebuy-out price as holders of ROCs receive a share ofbuyout monies

    The recycle bonus rises as the level of shortfallincreases

    If the RO target were met the ROC price would dropto zero!

  • 8/14/2019 ICE Presentation Final

    9/46

    0

    10

    20

    30

    40

    50

    60

    70

    0 10 20 30 40 50

    % shortfall on RO Target

    ROCv

    alue:/MWh

    ROC values versus RO shortfall in

    2006

  • 8/14/2019 ICE Presentation Final

    10/46

    Drivers of ROC prices Supply and demand

    Supply will depend on amount of renewable capacity built andits utilisation rule changes

    Demand is set by the RO targets

    Currently set to rise linearly to 10.4% in 2010

    View is that target will be raised after 2010 possibly to the20% target aspired to.

    Buy-out prices indexed to inflation

    Banking of ROCs by suppliers/ traders may affect prices

    Dominant suppliers (which are also the main owners of RE

    plant) will ensure that RO target is not met to stop ROC valuesfalling to zero

    Scheme is now being reviewed

  • 8/14/2019 ICE Presentation Final

    11/46

    RO Review - Issues There are a number of concerns regarding the

    RO

    Rewards to lower cost renewable generators are toogenerous

    There is considerable uncertainty regarding ROC prices,

    especially after 2015

    There is a cliff edge for ROC prices if full compliance ofthe RO is achieved

    Rewards for high cost more innovative renewablegeneration are too small to support deployment

  • 8/14/2019 ICE Presentation Final

    12/46

    RO Review Outcomes Future ROC allocation may be banded. Mature

    technologies likely to issued less ROCs per MWh than

    selected promising but high cost technologies (likePV).

    Scheme likely to be rolled out to 2020

    The recycle arrangements will be changed in order toeliminate the possibility of ROC prices collapsing tozero

    EU Commission still favours that all Europe moved to

    feed-in tariffs

  • 8/14/2019 ICE Presentation Final

    13/46

    Climate Change Levy (CCL)

    Introduced in 2002, CCL is a tax on energy consumption bylarge industrial and commercial users not paid by generators

    Electricity is taxed at 4.3/MWh

    Energy from certain renewable sources and from qualifyingcogeneration is exempted and is issued a Levy ExemptionCertificate (LEC).

    Different set of renewables to RO LECs include mini hydro

    and municipal waste, while ROC dont. ROCs include biomassco-firing, LECs dont

    LECs are sold with energy to suppliers/customers who can thenoffset their CCL obligation (4.3/MWh) Can be separated foroutput sold off-site

    Stand alone renewable generators can normally capture 85% ofLEC value

    Unclear how long tax will continue

  • 8/14/2019 ICE Presentation Final

    14/46

    Energy Review and Renewable Grid Issues One of the key issues that has delayed the

    introduction of renewables and limits theachievement of the 2010 target.

    ER06 states there is the need to resolve anumber of issues:

    Final Sums Liability (paying up front forconnection)

    Connection queues as a result ofincreased interest in renewables[Clustering, i.e. group connectionssimilar to NI, provide better networkplanning but can disadvantage somegenerators]

    Renewables lower transmission use ofsystem charges?

    Need to change from invest then

    connect to connect and manage Regulatory framework for offshore wind

    All above issues were identified aroundtime of ER03

    Distribution-level issues

    Distribution andTransmission-

    level issues

    Transmission-level issues

  • 8/14/2019 ICE Presentation Final

    15/46

    Stern Review of Economics of Climate

    Change Sir Nicholas Sterns review of the economics of

    climate change has two key messages forrenewables

    Renewables are central part of the carbon

    mitigation strategy There should be a huge scale up in funding of R&D

    and deployment of low carbon technologies,

    including renewables

  • 8/14/2019 ICE Presentation Final

    16/46

    Planning and Permitting Issues

  • 8/14/2019 ICE Presentation Final

    17/46

    Overview of Legislation

    Windfarm consent needs are driven by legislation

    Planning permission/consent to build granted under

    Section 36 of Electricity Act for over 50MW

    Town and Country Planning Act for under 50MW

    Environmental Impact Assessment (EIA) needed for planningapplications

    The Electricity Works (Environmental Impact Assessment) Regulations 2000 Town and Country Planning (Environmental Impact Assessment)

    Regulations 1999

    If require consent for grid connection

    Either Section 37 of Electricity Act or Town and Country Planning Act

    Also need an EIA for grid connection consent

  • 8/14/2019 ICE Presentation Final

    18/46

    Planning Process Initial Stage

    Early consultation with key stakeholders

    Initial approach to local authority

    Seek initial views of key stakeholders

    Scoping of EIA

    Focus on key issues through consultation and discussion with keystakeholders

    Time spent at scoping stage could save time later in process

    Identification of likely need for baseline studies

    Identify available data / data gaps early

    Develop public consultation strategy

    Landowner consultation

    no surprises later

  • 8/14/2019 ICE Presentation Final

    19/46

    Interfaces

    ClientPublic

    Consultees

    Statutory Consultees(SEPA or EA, LPA, DTI or Scottish

    Exec, English Nature orSNH, MOD, CAA etc)

    Environmental Technical

    Civil

    Engineering

    Geology

    EIApreparation

    Transport/Routes

    LayoutOptimisation

    Landscape and visualEcology

    Ornithology

    Hydrology & hydrogeologyNoise

    CommunicationsArchaeology

    Traffic & transport

    Planning

  • 8/14/2019 ICE Presentation Final

    20/46

    Planning Process EIA Stage

    Ensure project assessed covers all potential technical options

    EIA scope focussed on key issues in a robust manner e.g.

    landscape and visual impact including cumulative impact

    ornithology; presence of SPAs and SSSIs close to site ecology

    radar interference

    Input from experts capable of taking to Public Inquiry

    Supporting studies commissioned in timely manner and scopeagreed with key consultees

    Meeting project programme through management of largeenvironmental resource and sub-consultants

    Integration with the design process

    Ensure mitigation measures consistent with project design

  • 8/14/2019 ICE Presentation Final

    21/46

    Planning Process Application Stage

    Maintain close interface with local planningauthority (LA) / Scottish Ministers (SM) after

    application Respond to queries/requests for more information

    in timely manner

    Close integration with project design team to tryand mitigate issues to avoid Public Inquiry

    Agree planning conditions with LA and SM Translate planning conditions into contractor

    requirements

  • 8/14/2019 ICE Presentation Final

    22/46

    Public Consultation

    On going throughout the planning stage

    Manage flow of information / publicity to localpeople and organisations information voids canfill with bad news !

    Understand the local and regional politicians background to phase 1 essential

    Review comments from third parties of previous

    EIAs and identify potential supporters and risks

  • 8/14/2019 ICE Presentation Final

    23/46

    Project Evaluation

  • 8/14/2019 ICE Presentation Final

    24/46

    Site Identification & Provisional Layout

    Wind resource and regime

    NOABL

    Reanalysis

    Grid connection

    Access and buildability

    Constraints

  • 8/14/2019 ICE Presentation Final

    25/46

    Underground

    Cables /

    Pipelines

    Technical & Environmental Constraints

    Roads

    Houses(noise,

    Shadow-flicker)

    Areas with

    Historical

    Importance

    Wildlife Areas

    OverheadLines LandownerBoundary

  • 8/14/2019 ICE Presentation Final

    26/46

    Wind Regime Assessment

    Undertake wind regime assessment campaign using:

    Wind Monitoring Masts

    SODAR

    LIDAR

    Monitor for 12 months or more

    Monitor at multiple locations

  • 8/14/2019 ICE Presentation Final

    27/46

    Measured Turbulence Intensity & Wind Shear

    Ambient turbulenceintensity and

    Measured and Modeled Turbulence with

    Height

    0

    10

    20

    30

    40

    50

    60

    0% 10% 20% 30% 40%

    Tubulence (%)

    Height(m)

    ModeledFit

    Measured

    Data

    Measured and Modeled Wind Shear in Forestry

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 1 2 3 4 5 6 7 8

    Ave rage Wind Speed (m/s)

    HeightAboveGroundLevel(m)

    Open MoorlandWind Shear Zo =0.4

    Forested AreaWind Shear

    TheoreticalForest WindShear based onZo = 0.8

    wind shear must be

    accounted for infatigue life calculations

  • 8/14/2019 ICE Presentation Final

    28/46

    Added Turbulence

    Wake induced turbulence must alsobe investigated.

    Modified Sten Frandsen modelcombined with far wake modelling

    Plotting predicted CTI against IEC threshold

    10%

    15%

    20%

    25%

    30%

    35%

    0 5 10 15 20 25

    Wind Speed (m/s)

    CharacteristicTurbulenceIntens

    ity

    CTI (V90

    2MW)IEC 61400

    threshold

    Plotting predicted CTI against IEC threshold

    10%

    15%

    20%

    25%

    30%

    35%

    0 5 10 15 20 25

    Wind Speed (m/s)

    CharacteristicTurb

    ulenceIntensity

    CTI (Bonus

    2.3)

    IEC 61400

    threshold

  • 8/14/2019 ICE Presentation Final

    29/46

    Impact of Complex Roughness

    Complex roughness, such as buildings and forestry hassignificant impact on wind turbine operation.

    These features produce higher than specified turbulenceintensity & wind shear.

    Effects on:

    Power Curve

    Operational Loads

    Fatigue Life

    The effects of trees are further

    complicated by growth and felling

  • 8/14/2019 ICE Presentation Final

    30/46

    Extreme Wind Speed

    Analysis typicallyperformed only at sitemast

    Two methodologies for

    Extreme Wind

    WAsP Engineering tomodel gust values

    across the site

  • 8/14/2019 ICE Presentation Final

    31/46

    Components of a Wind Turbine(Model shown is Vestas V80)

    Rotor

    blades

    High voltage

    transformer

    Gearbox

    Tower

    Yaw gears

    Electricalgenerator

    Hub

    controller

    Ultrasonic

    sensors

    Hydraulic

    system

    Main shaft

    Oil coolerNacelle

  • 8/14/2019 ICE Presentation Final

    32/46

    Technology Selection

    IEC Classification

    Mean & Extreme Wind Speed

    Turbulence Intensity Wind Shear

    Compliance

    Noise Emission Grid Code Compliance

    Environmental Conditions

    Economic Viability Production

    Cost

  • 8/14/2019 ICE Presentation Final

    33/46

    Energy Yield Modelling Final layout iteration

    Compromise betweenmaximum production andconstraints

    Predict energy yield

    Rigorous quality checks

    Multiple MCP techniques

    Model validation and tuning

    Complex forestry modelling

    Quantification of

    uncertainty

  • 8/14/2019 ICE Presentation Final

    34/46

    Performance Testing

    Power performance testing

    Noise compliance Planning & environmental compliance

    Grid code compliance

  • 8/14/2019 ICE Presentation Final

    35/46

    Project Procurement and Financing

    f

  • 8/14/2019 ICE Presentation Final

    36/46

    Overview of Contracting Strategies

    - Who and Why EPC Contracts

    Majority of risks on Contractor

    One contract to deal with

    Sometimes developers with little experience or as a pre-requisite to Project Financing

    Multi-Contract Lower overall costs

    Increased competition; more choice of contractors

    Usually developers with sufficient in house experience orgood OE support, using own funds

    Prevalent for UK onshore projects

  • 8/14/2019 ICE Presentation Final

    37/46

    EPC Contracts

    Single Contractor

    Takes most of the risks, handles the interface workload andrisks, provides price certainty

    More expensive than multi-contract; risk premium added in

    Not always the WTG supplier who leads

    Can be for multiple sites

    Owner still needs to do front-end development andgain permits

    Owner may also need technical support

    M l i C

  • 8/14/2019 ICE Presentation Final

    38/46

    Multi-Contract

    Multiple Contractors covering several scopes

    Electrical, civil, WTG supply, grid connection

    Lower overall cost

    Owner takes interface risk and has much higher workload

    Owner still needs to do front-end development andgain permits

    Several contracts to negotiate instead of one

    Owner likely to need more technical or projectmanagement support

    S f F di

  • 8/14/2019 ICE Presentation Final

    39/46

    Sources of Funding

    Equity Debt

    Shares

    Investors

    i.e. VC

    Standby

    Equity

    Project

    FinanceBonds

    Mezzanine

    Finance

    Subordinated

    Debt

    Return on Investment

    Payback period Initial commitment

    Guarantees/Support

    Definite Term

    Financial Market Rates Fees

    Cover Ratios

    Wh P j t Fi D d h

  • 8/14/2019 ICE Presentation Final

    40/46

    Why Project FinanceDepends on who

    you are?PF for Sponsors

    Insulation from Project Debt and

    Risks!

    Spread of risks for large projects

    Off balance sheetCorporate borrowing restrictions

    Tax advantages

    Risk sharing

    PF for Utilities/Govt

    Access to foreign investment

    Foreign skills and know how

    Outside Public Sector Borrowing

    Accelerates non-priority projects

    P j t Fi h t!

  • 8/14/2019 ICE Presentation Final

    41/46

    Project Financewhy not!

    Time..

    Project scale..

    P j t St t

  • 8/14/2019 ICE Presentation Final

    42/46

    Project Structure

    Sponsors

    Banks

    LocalLegislation

    Government

    Project Company

    Suppliers

    Offtakers

    Operator

    Contractor

    SupplyAgreements

    OfftakeAgreements

    Consents/Permits

    Concession

    Agreement

    CreditAgreements

    ShareholderAgreements

    O&MAgreement

    Financial Risks Market Risks

    Construction & Operation Risks

    Legal & Regulatory Risks

    ConstructionAgreement

    Implications of Gearing and Non/Limited

  • 8/14/2019 ICE Presentation Final

    43/46

    Implications of Gearing and Non/Limited

    Recourse NatureTurbine Technology - turbine reliability issues ranging

    from minor to very major

    EPC risk Wrapped EPC no longer essential for banks

    but is risk pricing sufficiently clear?

    Operations - Availability of third-party maintenance

    providers post warranty period

    Offtake Risk Firm Power Purchase Agreement (PPA)

    and confidence regarding Green Certificates

    Wind Risk Confidence needed in P50 or P90 value in

    FM

    Summary

  • 8/14/2019 ICE Presentation Final

    44/46

    Summary

    DriversMarket drivers in the UK are sufficiently strong to ensure

    continued growth of RE projects. ROC improvements will

    reinforce this

    Barriers

    Availability of grid connection and planning consent are the

    major obstacles to the rate of deployment

    Development Focus

    An awareness of project financing and project risks is a

    requirement from the outset all technical and environmentalissues must ultimately relate to these

    Summary

  • 8/14/2019 ICE Presentation Final

    45/46

    Summary

    Contract Strategy

    Need to adopt contract strategy based on resources and

    attitude to risk

    Financing

    Financing options must be considered from the outset to

    ensure the project is developed appropriately

    Need to understand how to match project structure and risk

    profile to financing options

  • 8/14/2019 ICE Presentation Final

    46/46

    www.mottmac.com