group 1 gspl
DESCRIPTION
GSPL Pipeline optimisationTRANSCRIPT
Natural Gas Pipeline Optimisation
About GSPL
• 2nd Largest pure Natural Gas Transmission network in India• 2192 km• Volume Capacity – 18MMSCMD• Current Capacity-22MMSCMD• Equipped with the latest bi-directional gas transmission technology to
enable two-way gas flow.
Pipeline Optimization
• Scope for Pipeline Layout optimization Includes • Determining Optimal Layout• Determining Optimal Diameter of various pipes• Determining the locations and number of valves, regulators, and compressors
• Initial Laying cost (c) has 3 major components: • Steel quantity• Overcoating of pipes • Cost of Laying pipes underground
• Most of these costs are fixed w.r.t Pipe diameter
• Initial Pressure (Baroda)• Required Pressure (Baroda)• Initial Pressure (salaya)• Required Pressure (salaya)• Power requirement (MW/day)• NG requirement (in SCMD)• Total Cost/year (in Cr)• Total Cost over lifespan of compressors (in Cr)
Case 1 2 3
Assumed Demand(in MMSCMD) 11 14 15
Initial Pressure (Baroda) 78.63 78.63 -
Required Pressure (Baroda) 94.6 92.42 -
Initial Pressure (salaya) 64.35 41.1 -
Required Pressure (salaya) 69 84.8 -
Power requirement (MW/day) 4.81 20.788 35.27
NG requirement (in SCMD) 28904.46 124728 211620
Total Cost/year (in Cr) 14.87 60.31 94.23
Total Cost over lifespan of compressors (in Cr) 223.05 904.65 1413.45
Conclusion
• The cost decrease if we use compressor for demand up to 13-14
MMSCMD.
• The increase in 1 MMSCMD increases the cost by 30 cr.
• Hence the loop lines are best option for demand more than
13-14 MMSCMD
Key points
• As a Industry is dynamic in nature it is very difficult to ascertain future
supply and demand.
• As the pipeline has life of 40 years it must be designed considering
future demand and operations.
• Usage of Multistage instead of single stage
• The Compressor locations should be planned as per future Demand.