bar & bench () in the high court of ...images.assettype.com/.../single-judge-order-gspl.pdf ·...
TRANSCRIPT
C/SCA/21738/2017 CAV JUDGMENT
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SPECIAL CIVIL APPLICATION NO. 21738 of 2017
FOR APPROVAL AND SIGNATURE:
HONOURABLE MS.JUSTICE BELA M. TRIVEDI Sd/-
==========================================================
1 Whether Reporters of Local Papers may be allowed to see the judgment ? YES
2 To be referred to the Reporter or not ?YES
3 Whether their Lordships wish to see the fair copy of the judgment ? YES
4 Whether this case involves a substantial question of law as to the interpretation of the Constitution of India or any order made thereunder ?
YES
==========================================================
GUJARAT STATE PETRONET LIMITED....Petitioner(s)
Versus
M/s.GAIL INDIA LIMITED & 3....Respondent(s)==========================================================
Appearance:
MR MIHIR THAKORE, SR. ADVOCATE WITH MR ASPI M KAPADIA,
ADVOCATE for the Petitioner(s) No. 1
MR KAMAL TRIVEDI, SR. ADVOCATE WITH ,MR MIHIR JOSHI, SR.
ADVOCATE WITH MR VISHWAS K SHAH, CAVEATOR for the Respondent(s)
No. 1
MR S.I. NANAVATI, SR. ADVOCATE WITH MRS SUMAN KHARE,
ADVOCATE for the Respondent(s) No. 2
MR RITURAJ M MEENA, ADVOCATE for the Respondent(s) No. 3
MR DEVANG VYAS, ADVOCATE for the Respondent(s) No. 4==========================================================
CORAM: HONOURABLE MS.JUSTICE BELA M. TRIVEDI
Page 1 of 80
Page 1 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Date : 26/12/2017
CAV JUDGMENT
1. The petitioner Gujarat State Petronet Limited
(hereinafter referred to as "GSPL”) has filed the
present petition, seeking following reliefs as
contained in paragraph 19 thereof:-
“19. a. To quash and set aside the
permission accorded by the respondent No.4
i.e. the Approval Committee in its 76th
meeting held on 11.10.2007 at Item No.76.4.1
as well as any subsequent communication to
respondent No.1 and/or respondent No.2 in
respect thereto;
b. To restrain the respondent Nos.1 and 2
from carrying out any pipeline laying
activity in the Dahej SEZ area for
transportation of Natural Gas;
c. Pending the hearing and final disposal
of this petition, to stay the operation,
execution and implementation of the
permission accorded by the respondent No.4
Page 2 of 80
Page 2 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
i.e. the Approval Committee in its 76th
meeting held on 11.10.2007 at Item
No.76.4.1;
d. Pending the hearing and final disposal
of this petition restrain the respondent
Nos.1 and 2 from carrying out any pipeline
laying activity in the Dahej SEZ area for
transportation of Natural Gas;
e. To grant such other and further reliefs
as this Hon’ble Court deems fit and proper
in the facts and circumstances of the case;
f. To award costs of this petition.”
2. It may be noted that the petition filed on
30.11.2017 was sought to be circulated on the
same day at 2.30 p.m., and the said permission
was granted by the Court, considering the urgency
in the matter. The Court after hearing the
learned Sr. Advocate Mr.Mihir Thakore for the
petitioner and the learned Sr. Advocate Mr.Kamal
Trivedi appearing on caveat for the respondent
No.1 M/s.GAIL India Limited (hereinafter referred
to as "M/s.GAIL”), had issued the notices to the
Page 3 of 80
Page 3 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
respondents making them returnable on 1.12.2017
and granted an ad-interim relief restraining the
respondent No.1 M/s.GAIL from laying and
connecting the 8” Natural Gas Pipeline by tap off
from its existing Dahej-Uran Pipeline (DUPL) for
supplying gas to the respondent No.2 ONGC Petrol
Additions Limited (hereinafter referred to as
"M/s.OPAL”) situated in Special Economic Zone,
Dahej (hereinafter referred to as "SEZ, Dahej”)
till the next date. The said order is continued
till this date. The respondent No.2 M/s.OPAL on
filing the Civil Application No.15785 of 2017,
seeking vacation of the said ad-interim relief,
and the parties having completed the pleadings,
the Court heard the Special Civil Application for
admission at length along with the said Civil
Application.
FACTUAL MATRIX:
3. The case of the petitioner as stated in the
petition is that the petitioner GSPL is a listed
public limited company, and is subsidiary of
Gujarat State Petroleum Corporation Limited
(hereinafter referred to as "GSPC”). The main
Page 4 of 80
Page 4 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
activity of the petitioner is laying of gas
pipelines for developing gas grid in the State of
Gujarat for transportation of natural gas. On
the Special Economic Zones Act, 2005 (hereinafter
referred to as "the SEZ Act”) having come into
force, the petitioner Company had entered into a
Co-Developer Agreement dated 27.7.2009 (Annexure-
A) with the respondent No.3 M/s.DSL, the
Developer under the said Act. According to the
petitioner, the necessary permission being
No.F2/9/2003/EPZ dated 12.11.2009 (Annexure-B)
was accorded by the Government of India, Ministry
of Commerce and Industry, Department of Commerce
(SEZ Section), which was a permission by Board of
Approval under Section 3(12) of the SEZ Act.
Initially, the said approval was given for a
period of three years, which was subsequently
extended as per the letter dated 14.5.2012
(Annexure-C), and the validity of the said
permission and the Co-Developer Agreement was
made coterminous with that of the Developer. It
is further case of the petitioner that the
petitioner has set up gas infrastructure
facility, which includes gas pipeline made for
Page 5 of 80
Page 5 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
transmission of natural gas to the units set up
in the Dahej SEZ area and accordingly the
petitioner is also transmitting gas to the
respondent No.2 M/s.OPAL. However, the
respondent No.1 M/s.GAIL in violation and in
contravention of the provisions contained in the
SEZ Act sought permission from the respondent
No.4 Approval Committee to lay 8” dia pipeline
from its existing Dahej Ural Pipeline to the
plant of the respondent No.2 M/s.OPAL for
providing facility for transportation of natural
gas. The respondent No.4 Approval Committee,
Dahej SEZ Limited (hereinafter referred to as
"the Approval Committee”), in its meeting held on
11.10.2017 at Item No.76.4.1, decided to approve
the said request of the respondent No.1
(Annexure-D). According to the petitioner, such
permission could have been granted by the Board
of Approval constituted under Section 8 of the
SEZ Act and not by the Approval Committee
constituted under Section 13 of the said Act.
The petitioner being a Co-Developer had
exclusivity to develop infrastructure for
transportation of gas and distribution of gas
Page 6 of 80
Page 6 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
within SEZ area in view of the agreement dated
27.7.2009 entered into with the respondent No.3,
DSL. The petitioner, therefore, wrote a letter
on 8.11.2017 (Annexure-E) to the respondent No.3
i.e. the CEO, M/s.DSL, requesting him to
reconsider the decision of granting approval to
the respondent No.1. The CEO of the respondent
No.3, therefore, wrote a letter dated 24.11.2017
(Annexure-F) to the respondent No.2 M/s.OPAL with
a copy marked to the respondent No.1 GAIL stating
that the Gujarat State Petroleum Corporation
Limited (GSPC), being a Co-Developer, it should
obtain No Objection Certificate (hereinafter
referred to as "NOC”) from the GSPC. Thereafter,
the petitioner wrote a letter dated 29.11.2017 to
the respondent No.1 (Annexure-G), requesting it
not to undertake any gas pipeline laying activity
without seeking due permission from the Developer
M/s.DSL and the Co-Developer GSPL. A similar
letter was also written to the respondent no.2 on
29.11.2017 (Annexure-H). The petitioner
apprehending that the respondent No.1 M/s.GAIL
would make the Tap off and lay the pipeline for
transportation of gas to the respondent No.2,
Page 7 of 80
Page 7 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
filed the present petition on 30.11.2017 seeking
afore-stated reliefs.
4. The respondent No.1 GAIL and the respondent No.2
OPAL filed elaborate affidavits-in-reply raising
various contentions, including the preliminary
objections as regards the maintainability of the
petition and alleging that the petition was filed
on 30.11.2017 with oblique motive and ulterior
purpose suppressing material facts to stall the
work of the respondent No.1, which was going on
in full swing at the site. The alternative
remedy of filing suit under Section 23 and of
filing arbitration proceedings under Section 42
of the SEZ Act was available to the petitioner.
The petition also suffered from the vice of delay
and laches, as after issuing letter on 8.11.2017,
the petition was filed on 30.11.2017 with oblique
motive.
5. It has been contended by the respondent No.1
inter alia that M/s.DSL is a company floated by
GIDC and ONGC duly notified by the Ministry of
Commerce and Industry, Government of India, as a
Developer of Multi Product SEZ at Dahej. On
Page 8 of 80
Page 8 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
26.5.2004, GIDC had approved the proposal of the
respondent No.1 for laying 30” dia pipeline
Dahej-Hazira Gas Pipeline through GIDC corridor.
The Dahej SEZ was notified by the Ministry of
Commerce and Industry, Government of India, as a
Multi Product SEZ. On 27.7.2009 an agreement was
executed between the DSL and the petitioner, by
virtue of which the petitioner became Co-
Developer, and was conferred exclusive right with
respect to development, operation and maintenance
of Gas transmission pipeline and distribution of
Gas in SEZ. The respondent No.1 was granted
permission on 10.5.2010 by the Petroleum and
Natural Gas Regulatory Board under Regulation
17(1) of the Petroleum and Natural Gas Regulatory
Board (Authorizing Entities to lay, build,
operate or expand Natural Gas pipelines)
Regulations, 2008 (hereinafter referred to as
"the PNGRB Regulations 2008”) (Annexure-R/1). On
27.12.2011 a lease deed was executed between the
respondent No.2 M/s.OPAL and respondent No.3
M/s.DSL, and clause 4.6 thereof permitted the
M/s.OPAL to obtain any service, amenities or
facilities, which are not provided by the M/s.DSL
Page 9 of 80
Page 9 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
and the Co-Developer the petitioner (Annexure-
R/2). On 12.10.2016 the petitioner by E-mail
refused to book additional supply of gas and
communicated to M/s.OPAL to look for an alternate
arrangement for additional capacity (Annexure-
R/3), by which the petitioner had waived its
right under the agreement with DSL.
6. The respondent No.1 has further contended that on
31.8.2017, the respondent M/s.GAIL had sought
permission from the respondent No.3 M/s.DSL for
laying 8” dia pipeline by Tap off from the
existing respondent’s DUPL 30” dia natural gas
pipeline to M/s.OPAL across GIDC/SEZ area in
existing Right of Use (ROU) of the respondent
(Annexure-R/6). Accordingly, on 29.9.2017 the
respondent No.3 had granted, in principle,
approval to the respondent No.1 (Annexure-R/7).
Thereafter, on 11.10.2017 the respondent No.4 -
Approval Committee in its meeting decided to
approve the said request of the respondent No.1
vide Item No.76.4.1. On 27.10.2017, the
Development Commissioner of M/s.DSL wrote a
letter to the respondent No.1 and the respondent
Page 10 of 80
Page 10 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
No.2, stating that the Approval Committee in its
meeting held on 11.10.2017 had decided to approve
the said request. Despite the said permission
and approval granted by the respondent Nos.3 and
4, the respondent No.3 M/s.DSL wrote a letter
dated 24.11.2017 asking the respondent No.1 to
seek NOC from the GSPC, who had no locus in the
entire matter. The said letter was dispatched on
27.11.2017 and delivered at 1.30 p.m., on
29.11.2017. The petitioner, on 29.11.2017 wrote
a letter to the respondent No.1 requesting it to
refrain from undertaking any gas pipeline
activity without seeking permission from the
petitioner and the respondent No.3, though the
respondent No.3 had already granted permission as
per the letter dated 29.9.2017. It is also
contended that the respondent No.1 already had
its natural gas pipeline laid near the respondent
No.2 M/s.OPAL’s location. Since the respondent
No.2 M/s.OPAL required such quantity of natural
gas, which the petitioner was not in a position
to fulfill, the respondent No.1 GAIL, who was
inclined to provide sufficient quantity of gas to
OPAL, came into picture. There was no provision
Page 11 of 80
Page 11 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
under the SEZ Act giving exclusivity or monopoly
to the petitioner to provide natural gas to the
units set up in SEZ. The petitioner and the
respondent No.3 had also waived their rights
conferred under the agreement in view of the
various correspondences and the E-mails that had
ensued between the parties. There was a separate
and independent natural gas pipeline
infrastructure (9 km) existing for the supply of
natural gas to one of the units i.e. M/s.Torrent
Power Limited, apart from the natural gas
pipeline infrastructure of the petitioner and the
said unit is not functioning on the basis of
natural gas supply and transportation received
from the petitioner GSPL. It is also contended
that the respondent No.1 is supplying natural gas
in liquid form through a pipeline laid and
operated by ONGC to ONGC’s C-2, C-3 Dahej Plant
located in the Dahej SEZ since 2003 and the said
pipeline was not installed by the petitioner.
There are other various independent pipelines
existing, whereby various units are receiving
natural gas from different and distinct
alternatives other than the petitioner, and
Page 12 of 80
Page 12 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
therefore, the petitioner could not claim
exclusivity as claimed in the petition. Further,
as per the PNGRB Regulation 2008 an obligation is
cast on the respondent No.1 to provide
connectivity to the consumers within the tariff
zone corridor up to 50 kms from either side of
the natural gas pipeline and that the premises of
M/s.OPAL is located approximately 25 kms from the
existing pipeline of the respondent No.1. The
respondent No.1, therefore, had accepted the
request of the respondent No.2 M/s.OPAL for
transportation of natural gas, for which the
commercial arrangements were also entered into.
According to this respondent, supply of gas by
creating Tap off would not fall within the
definition of “infrastructure facilities”
contained in Section 2(p) of the SEZ Act. The
facility sought to be provided by the respondent
No.1 is relatable to Section 14(1) of the said
Act as the respondent No.1 would be supplying gas
only to the respondent No.2 M/s.OPAL and not to
the entire SEZ, and therefore, there was no
necessity to obtain approval from the Board.
Lastly, it is contended that the action of the
Page 13 of 80
Page 13 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
petitioner tantamounted to monopolistic and
restrictive trade practice, defeating the purpose
of SEZ Act and PNGRB Act.
7. The respondent No.2 M/s.OPAL has also filed
detailed affidavit-in-reply raising number of
issues and placing on record voluminous
correspondences that had ensued between the
parties through E-mails and letters, to show as
to how the petitioner had suppressed material
facts from the Court. Mainly it has been
contended that the respondent No.2 is a joint
venture company promoted by M/s.Oil and Natural
Gas Corporation and co-Promoted by M/s.GAIL i.e.
the respondent No.1, and Gujarat State Petroleum
Corporation Ltd. (GSPC). The respondent No.2
OPAL has set up their grass root mega
petrochemical project of national importance for
manufacturing petrochemical products and other
allied products at Dahej SEZ, Gujarat in
PCPIR/SEZ with an investment of USD 4.5 billion
and in a way, M/s.OPAL Plant is Asia’s largest
single point Petrochemical complex, and has
impacted entire polymer industries of the country
Page 14 of 80
Page 14 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
by providing world class polymer product. The
respondent No.2 M/s.OPAL had entered into a lease
agreement with the respondent No.3 on
27.12.2011 (Annexure-R/1). As per Clause 4.5 of
the said lease deed the supply of piped gas was
to be made by the petitioner GSPL. As per Clause
4.6 of the said lease deed the respondent No.2
M/s.OPAL was free to obtain any service,
amenities or facilities, which were not provided
by the M/s.DSL or Co-Developer/Service Provider,
directly from the concerned third party agencies.
Pursuant to the Clause 4.5 of the lease
agreement, a Gas Transmission Agreement
(hereinafter referred to as "GTA”) dated
12.8.2014 came to be executed between the
respondent No.2 M/s.OPAL and the petitioner GSPL.
According to the said agreement, GSPL was a
transporter of Gas through its pipeline network
to be supplied in the units of SEZ. Thus, the
respondent No.2 M/s.OPAL had an option to secure
its supply from any third party and could
transport to its plant through Pipeline Net Work
of GSPL laid in the SEZ. M/s.OPAL could also
increase or decrease the quantity of demand for
Page 15 of 80
Page 15 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
the gas as per Clause 5.2 of the GTA. According
to the respondent No.2 M/s.OPAL, it had initially
demanded CT of 0.5 MMSCMD during the construction
and commissioning phase of the plant, however, on
the completion of the commissioning of the plant,
it had anticipated increase of gas requirement
for 100% production of its plant. M/s.OPAL,
therefore, in terms of Clause 5.2 of GTA had made
a request for the additional booking of
transmission capacity to the petitioner through
various E-mails, requesting an additional CT of
0.80 MMSCMD for the period from 10.10.2016 to
16.10.2016 and additional CT of 0.5 MMSCMD for
the period from 17.10.2016 to 23.10.2016 at PLL-
GSPL connectivity. In response to the said
request, the petitioner GSPL refused to confirm
additional capacity in their pipeline and advised
M/s.OPAL to make alternate arrangement by E-mail
dated 12.10.2016. M/s.OPAL had again made a
request for additional capacity through
subsequent E-mails, however, GSPL had refused to
provide the same citing reasons of being over-
booked, as per the E-mail dated 13.10.2016.
According to the respondent No.2, it had made
Page 16 of 80
Page 16 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
several requests time and again for additional
capacity, however, the petitioner had refused to
provide the same. Lastly, it was refused by the
petitioner as per the E-mail dated 24.4.2017.
All the communications through E-mails have been
produced on record by the respondent No.2 as
Annexure-R/II (colly).
8. Thus, according to the respondent No.2 M/s.OPAL,
the petitioner GSPL had failed to provide the
transmission capacity as demanded by M/s.OPAL in
terms of Clause 5.2 of GTA and thereby had
created a situation for the M/s.OPAL either to
close down the unit or to explore other source
for booking capacity as advised by GSPL to meet
with its energy requirement of gas supply.
M/s.OPAL, therefore, had identified already
existing 30” dia DUPL natural gas pipeline of the
respondent No.1 M/s.GAIL, passing from the
M/s.OPAL Plant and had decided to procure its
additional requirement of gas by booking gas
transmission capacity from the said existing DUPL
pipeline by laying 8” dia pipeline for 0.25
meters to its plant. According to the respondent
Page 17 of 80
Page 17 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
No.2, the respondent No.1 M/s.GAIL for laying 8”
dia pipeline had sought permission from the
Development Commissioner of M/s.DSL, vide the
letter dated 31.8.2017 and the respondent No.2
M/s.OPAL had also sought consent from the
respondent No.3 DSL, vide its letter dated
15.9.2017 for laying of 8” dia pipeline. The
respondent No.3 DSL vide letter dated 29.9.2017
also granted, in principle, approval to M/s.GAIL
for laying 8” dia pipeline, subject to the
conditions mentioned therein. The Development
Commissioner also vide the letter dated
27.10.2017 had intimated the M/s.GAIL about the
approval given by the Approval Committee, in its
76th Approval Committee meeting held on 11.10.2017
for laying the said pipeline.
9. It is further contended by the respondent No.2
M/s.OPAL that the petitioner GSPL after denying
the requisite gas to M/s.OPAL, addressed a letter
dated 8.11.2017 to the respondent No.3 DSL to
reconsider its decision granting approval for
laying 8” dia pipeline without marking any copy
thereof to M/s.OPAL. According to the respondent
Page 18 of 80
Page 18 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
No.2, respondent No.3 DSL all of a sudden issued
a letter dated 24.11.2017 to the M/s.OPAL
informing that for laying 8” dia pipeline, it was
required to get NOC from GSPC. According to the
respondent No.2 though the said letter was dated
24.11.2017 it was posted on 27.11.2017 and was
received by M/s.OPAL only on 29.11.2017, when the
work of laying pipeline was almost completed.
The respondent No.2 has further alleged that the
petitioner GSPL, with mala fide intention had
tried to obstruct M/s.OPAL from sourcing its
transmission capacity requirement from other
alternatives, and after managing with the DSL to
issue back-dated letter 24.11.2017, GSPL through
its letter dated 29.11.2017 intimated to M/s.GAIL
and M/s.OPAL about their not granting NOC for
laying of 8” dia pipeline. The said letter dated
29.11.2017 was received on 1.12.2017 after the
interim relief was granted by the Court in the
present petition. The said letter was replied by
M/s.OPAL vide its letter dated 1.12.2017
(Annexure-R/VI).
10.The respondent No.2 has further contended that by
Page 19 of 80
Page 19 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
the GTA Amendment Agreement dated 22.11.2017
(Annexure-R/VII) executed between the GSPL and
M/s.OPAL, the GSPL had committed the capacity of
only 0.75 MMSCMD CT to M/s.OPAL for the period
from 1.1.2018 to 31.12.2019. Thus, according to
the respondent No.2 all these material facts were
concealed by the petitioner in the petition and
had created a mirage urgency for filing the
petition at the eleventh hour when almost entire
work of laying pipeline was already completed by
M/s.GAIL, which had started in the month of
October, 2017. The respondent No.2 has also
alleged other various suppression of material
facts as stated in the reply. According to the
respondent No.2, the provisions of SEZ Act were
misinterpreted by the petitioner and the Approval
Committee having validly approved the request of
M/s.OPAL and M/s.GAIL, there was no need to
obtain any approval from the Board of Approval,
the laying of pipeline being not to create
infrastructure facility in the SEZ as
contemplated in Section 2(p) of the SEZ Act.
There was also an arbitration Clause contained in
the GTA/Co-Developer Agreement executed between
Page 20 of 80
Page 20 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
the parties, and therefore, alternative remedy
being available to the petitioner, the petition
deserved to be dismissed.
11. The respondent No.3 has filed affidavit-in-
reply in cursory manner without dealing with any
of the issues raised in the petition or the
affidavit-in-rejoinder filed by the other
respondents. The petitioner GSPL has filed the
affidavit-in-rejoinder to the reply filed by the
respondent No.1, supplementary affidavit-in-
rejoinder to the reply filed by the respondent
No.1 and affidavit-in-rejoinder to the additional
affidavit-in-reply filed by the respondent No.2
denying the allegations made by the respondent
Nos.1 and 2, and further contending inter alia
that the petitioner and the respondent No.2
M/s.OPAL had entered into the GTA on 12.8.2014,
valid for a period of five years, under which the
petitioner had undertaken to transport the gas
through its pipeline. After the execution of the
GTA, the parties thereof have to enter into
Capacity Tranche (CT) by way of Amendment
Agreements from time to time, whereby the
Page 21 of 80
Page 21 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
specific period, specific quantity, specific
entry point and the tariff applicable as per
specific zone under the PNGRB Act 2006 is agreed
by the parties. The CTs are executed at the
request of the shipper i.e. M/s.OPAL in the
instant case. If the CTs are on firm basis, it
would contain the provision for “ship or pay”
obligation upon the shipper as well as payment of
liquidated damages obligation upon the
transporter. Accordingly, in the year 2014
M/s.OPAL had entered into a CT-1 with the
petitioner for a period of 2½ years and
thereafter further CTs were executed based on the
request and requirement of M/s.OPAL. The
petitioner had always transported the booked
capacity under the said CTs to the M/s.OPAL. It
is further contended that the M/s.OPAL was in the
process of commissioning its plant till January
2017 and the volume of its requirements were
fluctuating, and therefore, M/s.OPAL opted for
entering into various short-term CTs for specific
volume for additional requirements above the 0.5
MMSEMD booked under CT-1.
Page 22 of 80
Page 22 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
12. As regards E-mail dated 12.10.2016 of the
petitioner, wherein it was stated to make
alternative arrangements, it has been contended
by the petitioner that the said statement was
made indicating that M/s.OPAL instead of
insisting for capacity from PLL-GSPL, Dahej
direct entry point, M/s.OPAL may make alternative
arrangement to source and deliver gas at some
other entry point including the one at GSPL-
M/s.GAIL Dahej inter-connect entry point. It may
be noted that the Schematic Diagram of
arrangement of pipeline connectivity with the
PLL, Dahej terminal and M/s.OPAL unit has been
annexed as Annexure-D to the said affidavit-in-
rejoinder, and the same is made part of this
order to understand the issue in better manner.
Page 23 of 80
Page 23 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Page 24 of 80
Page 24 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
13. According to the petitioner, to overcome the
issue of lower pressure at the delivery point,
the petitioner GSPL had requested Petronet LNG
Ltd (PLL) to provide separate header to GSPL at
the PLL, Dahej terminal and accordingly separate
header has been provided in September 2017, and
therefore, the supply pressure issues are not
likely to arise now. It is also stated that the
spur-line laid by the petitioner for the supply
of gas to M/s.OPAL is capable of transporting 3.4
MMSCMD gas volumes and now the petitioner GSPL is
in a position to supply and meet with all the gas
volume requirements of M/s.OPAL. While denying
the claim of M/s.OPAL that the GSPL had not met
with the M/s.OPAL’s requirement of gas
transportation, it has been stated that during
the period from 1.2.2017 to 30.11.2017 on a
average 1.43 MMSCMD was transported to M/s.OPAL.
To meet with the balance requirement, M/s.OPAL
used to invite tenders for short term gas supply
on delivered basis, and used to enter into
Delivered Contracts with the supplier of Gas.
Relying upon Clause 4.5 of the land lease
Page 25 of 80
Page 25 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
agreement dated 27.12.2011 entered into between
M/s.OPAL and M/s.DSL, it has been stated that the
said clause recognized that M/s.OPAL Unit was
required to transport gas through pipeline
network of GSPL, the Co-Developer of SEZ. Since
there was no failure on the part of the
petitioner, and M/s.OPAL can not avail services
of a third party for gas transportation.
14. During the course of the arguments it was
alleged by the learned Sr. Advocate Mr.Nanavati
for the respondent No.2 M/s.OPAL that some
mischief was played by the officers of the
petitioner and the respondent No.3 in issuing the
letter dated 24.11.2017 addressed to the
respondent No.1 M/s.GAIL and the respondent No.2
M/s.OPAL, which was received by the said
respondents only on 29.11.2017, whereas it was
received by the petitioner on 27.11.2017, the
Court had directed the Company Secretary of the
petitioner and the CEO of the respondent No.3 to
file their respective affidavits as per the order
dated 12.12.2017. Accordingly, the said
affidavits were filed and the CEO of the
Page 26 of 80
Page 26 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
respondent No.3 had also remained personally
present on 13.12.2017. Pertinently, the CEO of
the respondent No.3 was not in a position to
answer the query of the Court put to him, as to
what was the need to issue the letter dated
24.11.2017 when the DSL had already granted, in
principle, approval on 29.9.2017 and the approval
Committee had also granted approval in its
meeting held on 11.10.2017. The said conduct of
the CEO has been recorded by the Court in the
order dated 13.12.2017.
LEGAL SUBMISSIONS:
During the course of lengthy arguments, series of
diverse and multifarious submissions were made by
the learned Advocates appearing for the parties.
The pith and substance of their submissions may
be stated as under:-
15. Submissions of learned Sr. Advocate Mr.Mihir
Thakore for the petitioner GSPL:
15.1 As regards the preliminary objection
raised by the respondents in respect of
alternative remedy being available, it has been
Page 27 of 80
Page 27 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
submitted that the Courts have not been
designated so far, as contemplated under Section
23 of the SEZ Act. Section 42 of the said Act
for deciding disputes by Arbitrator does not
apply to the parties as the dispute could not be
said to be between two or more entrepreneurs or
two or more developers or between an
entrepreneurs and a developer. The provisions
contained in Section 24 of the PMGRB Act also did
not apply as under the said provision, the
Petroleum Board has jurisdiction to decide the
dispute relating to the matters enlisted in Sub-
section (2) thereof and the present dispute can
not fall within any of the matters contained
therein. Even otherwise, existence of
alternative remedy could not be said to be an
absolute bar against preferring writ petition
under Article 226 of the Constitution of India,
as held by the Supreme Court in case of Calcutta
Discount Co. Ltd. Vs. Income Tax Officer,
Companies District and Anr., reported in AIR
1961 SC 372 and in case of Whirlpool Corporation
Vs. Registrar o Trade Marks, Mumbai, reported
in (1998) 8 SCC 1.
Page 28 of 80
Page 28 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
15.2 As regards suppression of material facts
it has been submitted that all the relevant facts
for challenging the decision of the approval
committee were disclosed in the petition. The
GTA entered into between the respondent No.2 and
the petitioner was produced by the petitioner
upon the observation made by the Court that the
GTA should have been filed by the petitioner.
Though GTA would throw light on the contractual
relationship between the petitioner and the
respondent No.2, it was not necessary for
deciding the core issue raised by the petitioner
in the petition. The communications referred by
the respondent Nos.1 and 2 in their respective
affidavits-in-reply were not germane or relevant
for deciding the issue whether the approval
committee’s decision was without jurisdiction or
ultra vires the provisions of SEZ Act. In this
regard, reliance is placed upon the decision of
the Supreme Court in case of S.J.S. Business
Enterprises (P) Ltd. Vs. State of Bihar and
Ors., reported in (2004) 7 SCC 166.
15.3 As regards the challenge to the impugned
Page 29 of 80
Page 29 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
decision of the Approval Committee, it has been
submitted that laying of pipeline for
transportation of natural gas by the respondent
No.1 in Dahej SEZ area is an “infrastructure
facility” within the meaning of Section 2(p) of
the SEZ Act read with the definition of
“infrastructure” under Rule 2(1)(s) of the
Special Economic Zones Rules 2006 (hereinafter
referred to as "the said Rules”). As per Section
9(2)(d) of the SEZ Act only the Board has the
power and jurisdiction to grant approval for
providing infrastructure facility within SEZ
area. The approval committee did not have any
power under Section 14 of SEZ Act to grant such
approval. As per Section 3(11), the person
intending to provide infrastructure facility has
to submit the proposal to the Board of approval
after entering into the agreement with the
developer and as per Section 3(12), the person
having approval of Board of approval and the
Central Government for providing infrastructure
facilities would be a Co-Developer.
15.4 There is no restriction under the SEZ
Page 30 of 80
Page 30 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Act in respect of granting exclusivity, and
therefore, the exclusive right was granted to the
petitioner by the respondent No.3 developer under
the Co-Developer agreement, which is supported by
the provisions of PNGRB Act. The respondent No.1
did not have unfettered right to lay any pipeline
anywhere in India under PNGRB Act, as such right
would be subject to the provisions of the SEZ
Act, which has overriding effect in the event of
any inconsistency between the two Acts. The
expression “for the time being in force” would
not only include the present legislations, but
would also include future legislations, as
interpreted by the Supreme Court in case of Yakub
Abdul Razak Memon Vs. State of Maharashtra,
reported in (2013) 13 SCC 1 (p. 653).
15.5 The respondent No.1 being Central
Government authorized entity under Regulation
No.17 of the PNGRB Regulations 2008 (hereinafter
referred to as "the Regulations 2008), the
schedule-J thereof does not apply to the
respondent No.1.
15.6 Under the GTA, the petitioner has
Page 31 of 80
Page 31 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
executed various capacity tranches from time to
time, according to which the respondent No.2 has
the obligation to supply gas at entry point at
PLL-Dahej terminal at a particular pressure
range, which the respondent No.2 had failed to
provide at the said pressure. The meaning of
alternative arrangement referred to in the E-mail
dated 12.10.2016 was to off take gas at different
entry points and the same was understood to be so
by the respondent No.2. The additional capacity
could also have been booked from Hazira L & T
terminal but the same was never sought from that
source by the respondent No.2.
15.7 Denying the allegations of monopolistic
and restrictive trade practice, it has been
submitted that the petitioner is booking capacity
in its pipeline on non-discriminatory basis as
per the provision of PNGRB Regulations. However,
there were pressure issues due to which the
petitioner could not book additional capacity for
the respondent No.2. The entities, who had
already booked capacities in the petitioner’s
pipeline were in a position to transport gas
Page 32 of 80
Page 32 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
through their booked capacity and accordingly
GSPC, the holding Company of the petitioner was
able to supply gas from the petitioner’s pipeline
to M/s.OPAL. Despite the pressure issues, the
petitioner has always supported the respondent
No.2 in meeting with its gas requirements.
15.8 As regards the letter of M/s.DSL in
respect of NOC requirements, it has been
submitted that the respondent No.3 M/s.DSL vide
its letter dated 29.9.2017 had granted, in
principle, approval only for the Right Of Use in
Dahej SEZ area, and the respondent No.1 was
required to obtain permission from the
Development Commissioner/Board of Approval. As
the Development Commissioner was not authorized
to grant permission, it was only the Board of
Approval, which was the competent authority for
granting permission for laying of pipeline by the
respondent No.1. Against the said approval
Committee’s decision the petitioner had written
letter dated8.11.2017 to the respondent No.3, and
realizing their mistake, the respondent No.3 had
vide its letter dated 24.11.2017 asked the
Page 33 of 80
Page 33 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
respondent No.2 with a copy marked to the
respondent No.1 to get the NOC from the
petitioner. The judgement of Appellate Tribunal
for Electricity in Appeal No.3/2011 relied upon
by the respondents was not applicable to the
facts of the present case, as the said judgement
did not deal with the specific issue of
requirement of the Board of Approval for setting
up infrastructure in Dahej SEZ.
16. Following submissions were made by the
learned Sr. Advocate Mr.Kamal Trivedi and learned
Sr. Advocate Mr.Mihir Joshi with learned Advocate
Mr.Vishwas Shah for the respondent No.1
M/s.GAIL:-
16.1 Raising the preliminary objection
against the maintainability of the petition, it
has been submitted that the petitioner has
efficacious alternative remedy since the disputes
between the petitioner, M/s.OPAL and M/s.GAIL
could be resolved in a civil suit to be filed in
the Designated Court, or through arbitration
under Section 42 of the SEZ Act or by PNGR Board
under Section 24 of the PNGRB Act 2006. The writ
Page 34 of 80
Page 34 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Court may not interfere with the contractual
matters involving technical aspects. The
petitioner has approached this Court with gross
delay and laches. The petitioner had sent
objections on 8.11.2017 with regard to the
approval granted by the Approval Committee, and
the work of laying pipeline had already been
undertaken in October-November, 2017, however,
the petitioner approached the Court after a long
time and that too, seeking hearing on urgent
basis at the eleventh hour on 13.11.2017.
16.2 The petitioner had not approached the
Court with clean hands and had suppressed gas
transmission agreement between itself and
M/s.OPAL, NOC dated 12.10.2016, the in-principle
approval granted by the respondent No.3 on
29.9.2017 and other correspondences. The conduct
of the petitioner in trying to promote its
holding company GSPC for supply of gas and
seeking monopoly for transmission and supply of
gas itself dis-entitles the petitioner from
claiming any relief. The letter dated 24.11.2017
issued by the CEO of DSL was received by M/s.GAIL
Page 35 of 80
Page 35 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
on 29.11.2017 and on the same day, the petitioner
wrote a letter dated 29.11.2017 refusing NOC to
M/s.GAIL, though the letter dated 24.11.2017 was
not addressed to the petitioner and though no
such NOC was sought by M/s.GAIL or M/s.OPAL from
the petitioner, which smacked of mala fide
intention of the petitioner.
16.3 The petitioner had waived its rights in
the light of the fact that in May 2016 and
February 2017 using GSPC pipeline infrastructure,
M/s.GAIL had supplied natural gas to M/s.OPAL.
There is an independent and separate natural gas
pipeline infrastructure (9 km) existing for
supply of natural gas to the Torrent Power
Limited, apart from the natural gas pipeline
infrastructure of the Co-Developer i.e. the
petitioner. The respondent GAIL since 2013 is
supplying natural gas in liquid form through the
pipeline laid and operated by ONGC to ONGC’s C-2
C-3 Dahej plant located in the DSL. The
respondent No.2 M/s.OPAL is also sourcing natural
gas in liquid form (C-2 C-3) through the pipeline
laid by M/s.OPAL within Dahej SEZ. The E-mail
Page 36 of 80
Page 36 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
dated 12.10.2016 of the petitioner to M/s.OPAL to
make alternative arrangement also established
that the petitioner had waived its right of
exclusivity.
16.4 There is no inconsistency between the
provisions contained in SEZ Act and PNGRB Act and
therefore, Section 51 of SEZ Act was not
applicable. In this regard reliance is placed on
the judgement dated 23.3.2012 of Appellate
Tribunal for Electricity in case of Torrent
Energy Ltd. Vs. Dakshin Gujarat Vj Co. Ltd. and
Ors., reported in (2014) 8 SCC 444.
16.5 Pressing into service the PNGRB
Regulations 2008 and Clause 1(g) of Schedule-J to
the said Regulation, it has been submitted that
the respondent No.1 M/s.GAIL has to provide
connectivity to the consumers within a tariff
zone in a natural gas pipeline and grant of any
restrain order against the M/s.GAIL would compel
it to violate and contravene the statutory
obligation as mandated in the said Regulations.
The M/s.GAIL pipeline has pre-existed the DSL
and hence, also M/s.GAIL has right to supply gas
Page 37 of 80
Page 37 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
under the PNGRB Act and its Regulations. Supply
of gas by M/s.GAIL through its 25 mtr., long
pipeline to itself i.e. M/s.OPAL being one of the
units in SEZ, and in which M/s.GAIL is one of the
major shareholders, cannot be considered to be
“development, operation and maintenance of gas
transmission pipeline infrastructure facility
for the entire Dahej SEZ, under Section 2(p) of
the said Act or under Rule 2(1)(s) of the said
Rules. The said supply of gas is nothing but
sale of goods.
16.6 The definition of “infrastructure
facilities” given in Section 2(p) read with Rule
2(1)(s) is exhaustive in nature, inasmuch as Rule
2(1)(s) uses the words “means” followed by
“includes” with the enumeration of specific/named
facilities. “Transmission of Gas pipeline” is
not mentioned therein. Letter dated 12.11.2009
(Annexure-B) granting approval to the agreement
dated 27.7.2009 conferring exclusivity in favour
of the petitioner in the matter of providing gas
transmission pipeline infrastructure would not
make the said agreement statutory one.
Page 38 of 80
Page 38 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
16.7 The power to grant approval dated
1.10.2017 by the Approval Committee to M/s.GAIL
and communicated by the Development Commissioner
vide the communication dated 27.10.2017 could be
traced to Section 14(1)(c) of the SEZ Act, or at
the best an administrative decision of the
approval committee. Such decision could not be
said to be without jurisdiction.
16.8 Alternatively, it has been submitted
that the requirement of obtaining NOC from
petitioner was beyond the purview of the said Act
and once DSL having given the permission, the
CEO, DSL had no power to issue letter dated
24.11.2017. Invoking the principles of interim
relief, it has been submitted that the respondent
M/s.GAIL has spent huge amount of Rs.20 crore for
various works for laying down 25 mtr long
pipeline for the purpose of supplying/selling gas
to M/s.OPAL and therefore, apart from prima facie
case being in favour of M/s.GAIL, balance of
convenience is also in favour of M/s.GAIL.
Reliance is placed on the decision of the Supreme
Court in case of Prabhjot Singh Mand and Ors.
Page 39 of 80
Page 39 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Vs. Bhagwant Singh and Ors., reported in (2009)
9 SCC 435 and in case of Reliance Natural
Resources Ltd. Vs. Reliance Industries Ltd.,
reported in (2010) 7 SCC 1.
17. The learned Sr. Advocate Mr.S. I. Nanavati
for the respondent no.2 M/s.OPAL has made
following submissions:-
17.1 The petition was filed by the petitioner
concealing material facts and misinterpreting the
provisions of the Act and creating imaginary
urgency, when almost entire work of laying
pipeline was completed by M/s.GAIL which had
started in October-November, 2017. The material
facts not stated in the petition have been
highlighted during the course of the submissions
and relying upon the various decisions of the
Supreme Court the prayer has been made to dismiss
the petition on the ground of suppression of
material facts alone. To buttress his
submission, Mr.Nanavati has placed reliance on
the decision of Supreme Court in case of
Prestige Lights Ltd. Vs. State Bank of India,
reported in (2007) 8 SCC 449, in case of Dalip
Page 40 of 80
Page 40 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Singh Vs. State of Uttar Pradesh and Ors.,
reported in (2010) 2 SCC 114 and in case of
Bhaskar Laxman Jadhav and Ors. Vs. Karamver
Kakasaheb Wagh Education Society and Ors.,
reported in (2013) 11 SCC 531.
17.2 In addition to the submissions made on
behalf of the respondent No.1, it has been
submitted that M/s.OPAL is a joint venture
company promoted by ONGC with 49.36% share and
co-promoted by M/s.GAIL with 49.21% share and
GSPC with 1.43% share, which is parent company of
the petitioner GSPL. In response to the request
made by M/s.OPAL for transportation of additional
supply of gas on firm basis by various E-mails
and for a period from 1.2.2017 to 31.1.2022, the
petitioner GSPL had refused to supply additional
quantity of gas by E-mail dated 12.10.2016 and
other E-mails and advised M/s.OPAL to make
alternative arrangement of gas supply, citing
reasons of capacity being overbooked. The
petitioner had created a situation where either
M/s.OPAL had to close down its unit or to explore
other source of its energy requirement of gas
Page 41 of 80
Page 41 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
supply. According to Mr.Nanavati, the petitioner
GSPL with GSPC tried to see that M/s.OPAL had to
pay higher transmission cost for M/s.GAIL-GSPL
connectivity and for PLL-GSPL connectivity.
Submissions were also made to show as to how the
petitioner had tried to use monopolistic
structure against M/s.OPAL by not confirming the
transmission through its network on firm basis.
17.3 Relying upon the decision of the Supreme
Court in case of Hardeep Singh Vs. State of
Punjab and Ors., reported in (2014) 3 SCC 92, it
was sought to be submitted that the words “means”
and “includes” used in definition clause gives
“hard and fast definition” and no other meaning
can be assigned. Hence, the definition of
infrastructure facilities as contained in Section
2(p) read with Rule 2(1)(s) is required to be
construed strictly. In the instant case, the
pipeline is laid by M/s.GAIL to provide gas only
to M/s.OPAL and to no other units, and therefore,
could not be said to have created infrastructure
facility for SEZ.
17.4 As gas is raw-material required for the
Page 42 of 80
Page 42 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
M/s.OPAL’s plant, the power to grant approval for
import and to monitor the utilization of gas and
services or warehousing or trading in SEZ, would
be with the Approval Committee under Section
14(a) and (c) of the SEZ Act. Hence, approval
granted by the Approval Committee in its meeting
held on 11.10.2017 was within its powers and
agenda.
17.5 All manufacturing units arrange a
redundant back up system for their raw material
supply so that in case of any eventuality, the
running plants are not stopped, because any
stoppage of gas supply for even five minutes will
result into approximately Rs.15 crore loss to
M/s.OPAL. The balance of convenience tilts
towards the respondent No.2 as it is only
M/s.OPAL which is incurring huge financial loss
every day. If at all GSPL has any exclusive
rights then it is an inter se dispute between
GSPL and DSL, to which a non-party to the
agreement should not be made to suffer.
18. The learned Advocate Mr.Meena for the
respondent No.3 has submitted that the respondent
Page 43 of 80
Page 43 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
No.3 had granted, in-principle approval to the
respondent No.1 as per its request as per the
letter dated 29.9.2017, however, realizing that
such approval was likely to result into breach of
contract dated 1.7.2009 entered into by the
respondent No.3 with the petitioner, the CEO of
the respondent No.3 had written the letter dated
24.11.2017 to the respondent GAIL and OPAL for
obtaining NOC from the petitioner company before
the execution of the work at the site. According
to him, the petitioner company was given office
copy of the said letter dated 24.11.2017 on
27.11.2017, and the letter was dispatched to the
respondent Nos.1 and 2 on 27.11.2017 as 24th and
26th were public holidays.
PROVISIONS OF SEZ ACT:
19. Before adverting to the submissions made by
the learned Advocates for the parties with regard
to the provisions contained in SEZ Act and the
PNGRB Act, it would be beneficial to reproduce
the relevant provisions. Some of the relevant
Clauses contained in Section 2 are as under:-
Page 44 of 80
Page 44 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
“2. Definition. In this Act, unless the context
otherwise requires,
(a) xxx
(b) “Approval Committee” means an Approval Committee constituted under subsection (1) of section 13;
(c) & (d) xxx
(e) "Board” means the Board of Approval constituted under subsection (1) of section 8;
(f) "CoDeveloper" means a person who, or a State Government which, has been granted by the Central Government a letter of approval under subsection (12) of section 3;
(g) “Developer” means a person who, or a State Government which, has been granted by the Central Government a letter of approval under subsection (10) of section 3 and includes an Authority and a CoDeveloper;
(h) to (o) xxx
(p) "infrastructure facilities" means industrial, commercial or social infrastructure or other facilities necessary for the development of a Special Economic Zone or such other facilities which may be prescribed;”
Section 3 pertains to the procedure for making proposal to establish Special Economic Zone. Subsections (11) and (12) thereof read as under:
(11) Any person who, or a State Government which, intends to provide any infrastructure facilities in the identified area referred
Page 45 of 80
Page 45 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
to in subsection (2) to (4), or undertake any authorised operation may, after entering into an agreement with the Developer referred to in subsection (10), make a proposal for the same to the Board for its approval and the provisions of subsection (5) and subsections (7) to (10) shall, as far as may be, apply to the said proposal made by such person or State Government.
(12) Every person or a State Government referred to in subsection (11), whose proposal has been approved by the Board and who, or which, has been granted letter of approval by the Central Government, shall be considered as a CoDeveloper of the Special Economic Zone.
Section 8 pertains to constitution of Board of approval and Section 9 pertains to the duties, powers and functions of Board, the relevant part thereof is reproduced as under:
9. Duties, powers and functions of Board.(1) Subject to the provisions of this Act, the Board shall have the duty to promote and ensure orderly development of the Special Economic Zones.
(2) Without prejudice to the generality of the provisions contained in subsection (1), the powers and functions of the Board shall include –
(a) to (c) xxx
(d) granting of approval or rejecting of proposal for providing infrastructure facilities in a Special Economic Zone or modifying such proposals;
(e) to (i) xxx
The functions of Development Commissioner are enumerated in Section 12. Section 13 pertains to constitution of Approval Committee and Section 14
Page 46 of 80
Page 46 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
pertains to powers and functions of the Approval Committee, the relevant part thereof is reproduced as under:
14. Powers and functions of Approval Committee. (1) Every Approval Committee may discharge the functions and exercise the powers in respect of the following matters, namely:
(a) & (b) xxx
(c) monitor the utilisation of goods or services or warehousing or trading in the Special Economic Zone;
Section 51 giving overriding effect to the Act reads as under:
51. The provisions of this Act shall have effect notwithstanding anything inconsistent therewith contained in any other law for the time being in force or in any instrument having effect by virtue of any law other than this Act.
The Central Government has framed the Rules namely the Special Economic Zones Rules, 2006 in exercise of the powers conferred by Section 55 of the SEZ Act. The relevant definition “Infrastructure” as contained in Rule 2(1)(s) reads as under:
“2(s) infrastructure’ means facilities needed for development, operation and maintenance of a Special Economic Zone and includes industrial, business and social amenities like development of land, roads, building, sewerage and effluent treatment facilities, solid waste management facilities, port, including jetties, single point moorings, storage tanks and interconnecting pipelines for liquids and gases, Inland Container Depot or Container Freight Station, warehouses, airports, railways, transport system, generation and distribution of power, gas and other forms
Page 47 of 80
Page 47 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
of energy, telecommunication, data transmission network, information technology network, hospitals, hotels, educational institutions, leisure, recreational and entertainment facilities, residential and business complex, water supply, including desalination plant, sanitation facility;”
20. It is beyond any cavil that the provisions
of the statute must receive strict interpretation
and that scrupulous compliance thereof is
imperative. However, before appreciating the
submissions made by the learned Advocates for the
parties in the light of the provisions of the SEZ
Act and PNGRB Act, the conduct of the petitioner
GSPL before and after approaching this Court
needs to be highlighted. It can not be gainsaid
that the writ jurisdiction is an extraordinary
equitable jurisdiction. It is a rule of equity
as well as of law that a suppresio veri is
equivalent to a suggestio falsi. Suppression of
truth is the suggestion of what is false. The
first and foremost preliminary objection raised
by the learned Advocates for the respondents is
that the petition was filed with oblique motive
and ulterior purpose suppressing material facts
from the Court. According to them, the
petitioner had not disclosed all the correct,
Page 48 of 80
Page 48 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
material and relevant facts in the petition and
the same were sought to be brought on record by
way of affidavits-in-rejoinder, in reply to the
affidavits-in-reply filed by the respondent Nos.1
and 2. In this regard, it may be stated that as
held by the Division Bench of this Court in case
of Hiralaxmi and Ors. Vs. Municipal Corporation
of the City of Ahmedabad and Anr., reported in
AIR 1967 Gujarat 198, by and large the writ
jurisdiction proceedings, which are prerogative
proceedings have to be decided on the contents of
the petitions and the affidavits filed in reply.
Contentions not found amongst the grounds on
which relief is sought in the petition, if are
raised for the first time in rejoinder affidavit,
it would not be proper even to accept such
contentions, except in exceptional cases. In
matters of the nature of high prerogative writs
it is not only desirable, but necessary that the
petitioner should be precise in putting forward
his case, which the opposite party is called upon
to meet. It is also but proper that the
petitioner should state grounds with sufficient
particularity and disclose in the petition all
Page 49 of 80
Page 49 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
the material and the grounds on which they move
the Court for the relief asked. It would
otherwise lead to most undesirable and
unsatisfactory results if petitioners are allowed
to raise new pleas or grounds by way of
supplementary pleas or trot out a plea not at all
made out in the petition.
21. In the instant case, as stated herein above
an urgent hearing of the petition was sought by
the learned Advocate for the petitioner on
30.11.2017 and the matter was permitted to be
circulated and heard at 2.30 p.m. on the same
day. The Court after considering the averments
made in the petition and the documents annexed
thereto, and after hearing the learned Sr.
Advocate Mr.Mihir Thakore appearing with learned
Advocate Mr.Aspi Kapadia for the petitioner and
learned Sr. Advocate Mr.Kamal Trivedi and
learned Sr. Advocate Mr.Mihir Joshi with learned
Advocate Mr.Vishwas Shah appearing on caveat for
the respondent GAIL, had granted an ad-interim
relief, restraining the respondent No.1 GAIL from
laying and connecting the 8” natural gas pipeline
Page 50 of 80
Page 50 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
by tap off from its existing Dahej-Uran pipeline
for supplying gas to the respondent M/s.OPAL
situated in SEZ, Dahej. The respondents after
service of the notices appeared and filed their
respective affidavits-in-reply in detail, raising
various contentions, including the contention
that the petition suffered from the vice of
suppression of material facts. The petitioner
thereafter filed three affidavits-in-rejoinder
one after the other, from which it has been found
by the Court that the petitioner had not made
true and correct disclosure of material facts and
suppressed very relevant and important documents
and the correspondences that had ensued between
the parties, more particularly with the
respondent No.2 M/s.OPAL with regard to the
subject matter of the petition.
22. It is pertinent to note that though the
petitioner had entered into Gas transmission
agreement with the respondent No.2 M/s.OPAL on
12.8.2014 agreeing to make necessary arrangements
for transportation of gas for the respondent No.2
M/s.OPAL from time to time, subject to the terms
Page 51 of 80
Page 51 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
and conditions mentioned therein, and had also
entered into various capacity tranches under the
said agreement from time to time, and had entered
into number of correspondences with the
respondent No.2 through E-mails and letters with
regard to the transportation of the additional
supply and also lastly entered into the GTA
Amendment agreement with M/s.OPAL on 22.11.2017,
there was not even a whisper made in the petition
about any of such agreements or the documents or
correspondences. It was only when the
respondents raised the contentions and the Court
also found that GTA and other documents should
have been produced on record, the same were
produced. The main contention raised by the
respondent No.2 in its affidavit-in-reply is that
because the petitioner refused additional booking
capacity for transmission of gas through its
pipeline, and suggested to look for an
alternative arrangement, the respondent No.2 had
sought for the alternative arrangement from the
respondent No.1 and accordingly the respondent
Nos.1 and 2 had sought the permissions from the
respondent No.3 DSL and the Approval Committee.
Page 52 of 80
Page 52 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
It is also pertinent to note that the petitioner
had already raised objections against the said
permissions before the respondent No.3 DSL vide
the letter dated 8.11.2017. Under the
circumstances and in the background of these
facts, it was incumbent on the part of the
petitioner to place on record the basic and
material facts and documents along with the
petition.
23. As rightly submitted by the learned Sr.
Advocate Mr.S. I. Nanavati it is for the Court
and not for the litigant to decide as to which
fact is or is not material. It is the obligation
of the litigant to state candidly all material
facts. It is also well settled legal position
that if there is any suppression of material
facts on the part of the petitioner or twisted
facts have been placed on record by the
petitioner, the petition should be dismissed
without entering into the merits of the matter.
In this regard a very pertinent observations made
by the Supreme Court in case of Prestige Lights
Ltd. Vs. State Bank of India, reported in (2007)
Page 53 of 80
Page 53 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
8 SCC 449 deserve to be reproduced as under:-
“33. It is thus clear that though the appellantCompany had approached the High Court under Article 226 of the Constitution, it had not candidly stated all the facts to the Court. The High Court is exercising discretionary and extraordinary jurisdiction under Article 226 of the Constitution. Over and above, a Court of Law is also a Court of Equity. It is, therefore, of utmost necessity that when a party approaches a High Court, he must place all the facts before the Court without any reservation. If there is suppression of material facts on the part of the applicant or twisted facts have been placed before the Court, the Writ Court may refuse to entertain the petition and dismiss it without entering into merits of the matter.
34. The object underlying the above principle has been succinctly stated by Scrutton, L.J., in R v. Kensington Income Tax Commissioners, [(1917) 1 KB 486 : 86 LJ KB 257 : 116 LT 136], in the following words:
"It has been for many years the rule of the Court, and one which it is of the greatest importance to maintain, that when an applicant comes to the Court to obtain relief on an ex parte statement he should made a full and fair disclosure of all the material facts facts, not law. He must not misstate the law if he can help it. The Court is supposed to know the law. But it knows nothing about the facts, and the applicant must state fully and fairly the facts, and the penalty by which the Court enforces that obligation is that if it finds out that the facts have not been fully and fairly stated to it, the Court will set aside, any action which it has taken on the faith of the
Page 54 of 80
Page 54 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
imperfect statement".
35. It is well settled that a prerogative remedy is not a matter of course. In exercising extraordinary power, therefore, a Writ Court will indeed bear in mind the conduct of the party who is invoking such jurisdiction. If the applicant does not disclose full facts or suppresses relevant materials or is otherwise guilty of misleading the Court, the Court may dismiss the action without adjudicating the matter. The rule has been evolved in larger public interest to deter unscrupulous litigants from abusing the process of Court by deceiving it. The very basis of the writ jurisdiction rests in disclosure of true, complete and correct facts. If the material facts are not candidly stated or are suppressed or are distorted, the very functioning of the writ courts would become impossible.”
24. In case of Bhaskar Laxman Jadhav and Ors.
Vs. Karamver Kakasaheb Wagh Education Society
and Ors., reported in (2013) 11 SCC 531, it has
been observed in paragraphs 44, 45, and 46 as
under:-
44. It is not for a litigant to decide what fact is material for adjudicating a case and what is not material. It is the obligation of a litigant to disclose all the facts of a case and leave the decision making to the Court. True, there is a mention of the order dated 2nd May 2003 in the order dated 24th July 2006 passed by the JCC, but that is not enough disclosure. The petitioners have not clearly disclosed the facts and circumstances in which the order dated 2nd
Page 55 of 80
Page 55 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
May 2003 was passed or that it has attained finality.
45.We may only refer to two cases on this subject. In Hari Narain v. Badri Das, AIR 1963 SC 1558 stress was laid on litigants eschewing inaccurate, untrue or misleading statements, otherwise leave granted to an appellant may be revoked. It was observed as follows:
“9. ...It is of utmost importance that in making material statements and setting forth grounds in applications for special leave, care must be taken not to make any statements which are inaccurate, untrue or misleading. In dealing with applications for special leave, the Court naturally takes statements of fact and grounds of fact contained in the petitions at their face value and it would be unfair to betray the confidence of the Court by making statements which are untrue and misleading. That is why we have come to the conclusion that in the present case, special leave granted to the appellant S.L.P. (C) No. 30469 of 2009 ought to be revoked. Accordingly, special leave is revoked and the appeal is dismissed. The appellant will pay the costs of the respondent.”
46. More recently, in Ramjas Foundation v. Union of India, (2010) 14 SCC 38 the case law on the subject was discussed. It was held that if a litigant does not come to the Court with clean hands, he is not entitled to be heard and indeed, such a person is not entitled to any relief from any judicial forum. It was said:
“21. The principle that a person who does not come to the court with clean hands is not entitled to be heard on the merits of his grievance and, in any
Page 56 of 80
Page 56 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
case, such person is not entitled to any relief is applicable not only to the petitions filed under Articles 32, 226 and 136 of the Constitution but also to the cases instituted in others courts and judicial forums. The object underlying the principle is that every court is not only entitled but is duty bound to protect itself from unscrupulous litigants who do not have any respect for truth and who try to pollute the stream of justice by resorting to falsehood or by making misstatement or by suppressing facts which have a bearing on adjudication of the issue(s) arising in the case.”
1. In view of the afore-stated legal and factual
position, the Court has no hesitation in holding
that the petitioner having suppressed material
facts from the Court and having made incorrect
and inaccurate statements in the petition, the
same deserves to be dismissed on the said ground
alone. Nonetheless, the petition having been
argued at length on various other issues, the
Court deems it proper to deal with those issues
also.
2. As regards alternative remedy, it was sought to
be submitted by the learned Sr. Advocate
Mr.Trivedi for the respondent No.1 GAIL that the
disputes between the parties could be resolved by
Page 57 of 80
Page 57 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
filing civil suit under Section 23 or through
arbitration under Section 42 of the SEZ Act or
under Section 24 of PNGRB Act. However, the said
submission can not be accepted. It is not
disputed that the Courts have not been designated
to try the suit of civil nature arising in the
SEZ, as contemplated under Section 23 of the SEZ
Act. Whether the dispute raised in the petition
could be referred to the arbitration under
Section 42 of the SEZ Act or under section 24 of
PNGRB Act or not would be a debatable issue,
which the Court is not called upon to decide in
this petition. Even if it is presumed that the
same could be referred to the arbitration,
whether the said remedy could be said to be
effective or efficacious remedy or not, would be
another issue. In any case, as held by Supreme
Court in Whilepool Corporation Vs. Registrar of
Trade Mark (supra), the existence of the
alternative remedy itself would not operate as
bar, where the writ petition is filed for the
enforcement of any fundamental rights, or where
there has been violation of the principles of
natural justice or where the order or proceedings
Page 58 of 80
Page 58 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
are alleged to be wholly without jurisdiction or
where the vires of the Act is challenged. In the
instant case, the statutory powers of the
Approval Committee and the Development
Commissioner have been challenged by the
petitioner, amongst others, and therefore, the
petition could not be rejected on the ground of
availability of an alternative remedy alone.
Having said that, let us examine the other issues
involved in the matter.
3. The bone of contention raised by the learned Sr.
Advocate Mr.Mihir Thakore for the petitioner is
that the action of laying of pipeline for
transportation of natural gas by the respondent
No.1 GAIL in Dahej SEZ area being an
“infrastructure facility” within the meaning of
Section 2(p) of SEZ Act, the necessary permission
was required to be obtained by the GAIL from the
Board of approval constituted under Section 8,
and that the approval granted by the Approval
Committee constituted under Section 13 was dehors
the provisions of the said Act. The said
submission made by Mr. Thkore though sounds very
Page 59 of 80
Page 59 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
attractive and impressive, on the close reading
of the provisions of the Act, the Court does not
find any substance in the same.
4. It is significant to note that Section 3 of the
said Act pertains to the procedure for making
proposal to establish Special Economic Zone.
Sub-section (11) thereof provides inter alia that
any person, who, or a State Government, which
intends to provide any infrastructure facility in
the identified area referred to in Sub-section
(2) to (4) or undertake any authorized operation
made, after entering into an agreement with the
developer referred to in Sub-section (10) make a
proposal for the same to the Board for its
approval. As per Sub-section (12) thereof, the
person whose proposal has been approved by the
Board and who has been granted letter of approval
by the Central Government would be considered as
Co-Developer of the SEZ. Now, so far as
“infrastructure facilities” are concerned, the
same has been defined in Section 2(p) of the Act,
to mean industrial, commercial, or social
infrastructure or other facilities necessary for
Page 60 of 80
Page 60 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
development of Special Economic Zone or other
facilities which may be prescribed. What is
significant in this definition is the word
“necessary”. The definition is in two parts. In
the first part, it is stated that the industrial,
commercial or social infrastructure or other
facilities necessary for the development of a
Special Economic Zone. It does not state about
the facilities necessary for the development of
the units set up in the SEZ. In the second part,
it is stated that “or other facilities which may
be prescribed”. In the opinion of the Court the
words “infrastructure facilities” themselves
imply that such facilities would be required at
the time of establishment and development of the
Special Economic Zone. Further, the other
infrastructure facilities have been prescribed in
the Rule 2(1)(s) of the said Rules. According to
Rule 2((1)(s), “infrastructure” means facilities
needed for the development, operation and
maintenance of a Special Economic Zone and
includes industrial, business and social
amenities as enumerated in the said Clause. Here
also, the emphasize is on the facilities “needed”
Page 61 of 80
Page 61 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
for development, operation and maintenance of the
Special Economic Zone and not on the facilities
“needed” for the development, operation or
maintenance of the units set up by an
entrepreneurs in the Special Economic Zone. By
necessary corollary, it would mean that the
facilities or amenities needed for the units
could not be said to be the infrastructure
facilities needed for the Special Economic Zone.
5. It is well settled principle of interpretation of
statutes that no word or provision should be
considered redundant or superfluous. The
legislature attributes a particular meaning to
each word in a statute, and that word of a
statute must prima facie be given its ordinary
meaning. In this regard, a pertinent
observations made by Supreme Court in case of
Sankar Ram & Co. Vs. Kasi Nasicker and Ors.,
reported in (2003) 11 SCC 699, be made.
“7. It is a cardinal rule of construction that normally no word or provision should be considered redundant or superfluous in interpreting the provisions of a statute. In the field of interpretation of statutes, the courts always presume that the legislature inserted every part thereof
Page 62 of 80
Page 62 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
with a purpose and the legislative intention is that every part of the statute should have effect. It may not be correct to say that a word or words used in a statute are either unnecessary or without any purpose to serve, unless there are compelling reasons to say so looking to the scheme of the statute and having regard to the object and purpose sought to be achieved by it. A Constitution Bench of this Court in Jaipur Zila Sahakari Bhoomi Bank Ltd. Vikas vs. Shri Ram Gopal Sharma and Ors. [JT 2002 (1) SC 182] while interpreting and considering the effect of proviso to Section 33(2)(b) of the Industrial Disputes Act, 1947 in para 13 observed:(SCC pp. 25253)
"13. The proviso to Section 33(2)(b) as can be seen from its very unambiguous and clear language, is mandatory........... Taking a contrary view that an order of discharge or dismissal passed by an employer in contravention of the mandatory conditions contained in the proviso does not render such an order inoperative or void, defeats the very purpose of the proviso and it becomes meaningless. It is wellsettled rule of interpretation that no part of statute shall be construed as unnecessary or superfluous. The proviso cannot be diluted or disobeyed by an employer......... The interpretation of statute must be such that it should advance the legislative intent and serve the purpose for which it is made rather than to frustrate it."
6. In case of Gurudevdatta VKSSS Maryadit and Ors.
Vs. State of Maharashtra and Ors., reported in
(2001) 4 SCC 534, it has been observed as under:-
Page 63 of 80
Page 63 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
“26. Further we wish to clarify that it is a cardinal principle of interpretation of statute that the words of a statute must be understood in their natural, ordinary or popular sense and construed according to their grammatical meaning, unless such construction leads to some absurdity or unless there is something in the context or in the object of the statute to suggest to the contrary. The golden rule is that the words of a statute must prima facie be given their ordinary meaning. It is yet another rule of construction that when the words of the statute are clear, plain and unambiguous, then the Courts are bound to give effect to that meaning, irrespective of the consequences. It is said that the words themselves best declare the intention of the law giver. The Courts have adhered to the principle that efforts should be made to give meaning to each and every word used by the legislature and it is not a sound principle of construction to brush aside words in a statute as being inapposite surpluses, if they can have a proper application in circumstances conceivable within the contemplation of the statute. Bearing in mind, the aforesaid principle of construction, if the expression any new member society occurring in the proviso to sub section (3) of Section 27 is construed, it conveys the only meaning that it refers to the societies to be formed hereafter and not of those societies which have already become member societies of the federal society. Therefore, the requirement of the completion of the period of three years from the date of its investing any part of its fund in the shares of such federal society would apply only to those societies which became member society of the federal society after 20th August, 2000. In this view of the matter, the impugned judgment of the High Court does not suffer from any infirmity. Even if there remained any doubt in the matter of interpreting the proviso, the
Page 64 of 80
Page 64 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Ordinance that has been promulgated on 27th
February, 2001, called the Maharashtra Ordinance No. X of 2001, after the first proviso to subsection (3), a second proviso had been inserted, has removed any doubt or controversy in as much as it has been indicated therein that the first proviso will not apply to the member society which has invested any part of its fund in the share of the federal society before the commencement of the Maharashtra Cooperative Societies (Amendment) Act, 2000 dated 20th
August, 2000. The aforesaid Ordinance also has been given a retrospective effect, to be effective from 23rd August, 2000. The Ordinance having been held to be valid by us as stated above, the socalled prohibition contained in the first proviso to subsection (3) of Section 27 will not apply to all those societies which have already become members of the federal society prior to 2382000.”
7. In the light of afore-stated proposition of
law, the words “necessary for the development of
a Special Economic Zone” contained in Section
2(p), and the words “needed for development,
operation and maintenance of a Special Economic
Zone” contained in Rule 2(1)(s) have to be given
their ordinary meanings, which would advance the
legislative intent and serve the purpose of the
Act.
8. Further, the facilities and amenities enumerated
in Rule 2(1)(s) do not cover the amenity of
Page 65 of 80
Page 65 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
laying of natural gas pipeline for the supply of
gas to a particular unit. Though Mr.Thakore had
sought to submit that such amenity would be
included in the amenity of “generation and
distribution of power, gas or other form of
energy”, it is difficult to accept the said
submission. As held by Supreme Court in case of
Hardeep Singh Vs. State of Punjab (supra),
wherever the words “means and include” are used,
it is an indication of the fact that the
definition “is a hard and fast definition”, and
no other meaning can be assigned to the
expression that is put down in the definition.
It indicates an exhaustive explanation of the
meaning which for the purpose of the Act, must
invariably be attached to the words and
expression.
9. In the instant case, it is not disputed that the
respondent No.2 M/s.OPAL needed an additional
supply of gas, which the petitioner had refused
to book for transmission through its pipeline
laid in the respondent No.3 SEZ, and therefore,
the respondent No.1 had agreed to supply the
Page 66 of 80
Page 66 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
additional quantity of gas to the respondent No.2
by laying 8” dia pipeline by Tap off from the
existing M/s.GAIL DUPL. Such necessity of
facilities or services of the respondent No.1
M/s.OPAL, which is one of the units set up in the
DAL could not be said to be an infrastructure
facility necessary or needed for the development
of the respondent No.3 DSL, as contemplated in
Section 2(p) read with Rule 2(1)(s) of the said
Rules. In that view of the matter, the Court is
of the opinion that under the circumstances, the
respondent No.1 and respondent No.2 were not
required to take any approval from the Board of
Approval under Section 9(d) of the said Act. It
is also pertinent to note that neither the
Approval Committee, nor the Development
Commissioner, at any point of time asked the
respondent Nos.1 and 2 to obtain the approval
from the Board of Approval, probably because they
also did not consider such necessity of procuring
additional supply of gas by M/s.OPAL from
M/s.GAIL to be an infrastructure facility. The
approval granted by the Approval Committee in its
meeting held on 11.10.2017, and conveyed by the
Page 67 of 80
Page 67 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
Development Commissioner vide letter dated
27.10.2017 is required to be construed as the
approval granted in respect of the matter
contained in Section 14(1)(c) read with Section
12(2) of the Act. The respondent No.3 DSL had
also granted in-principle approval to the
respondent No.1 as per the letter dated
29.9.2017. The petitioner itself while raising
objection against such approval in its letter
dated 8.11.2017 had not contended that such
facility being infrastructure facility, the
respondent No.1 GAIL would be required to obtain
approval from the Board of Approval, or that the
Approval Committee had no such powers to grant
approval. Such contention has been raised for
the first time in the petition, which is
thoroughly misconceived.
10. Placing heavy reliance on the Dahej, Co-
Developer agreement dated 27.7.2009 (Annexure-A)
entered into by and in between Ms.DSL and GSPL,
the learned Sr. Advocate Mr.Thakore would submit
that the petitioner had sole and exclusive right
with respect to the development, operation and
Page 68 of 80
Page 68 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
maintenance of gas transmission pipeline
infrastructure and distribution of gas in the
SEZ. In this regard, it is pertinent to note
that the said agreement was entered into between
the petitioner GSPL and the respondent No.3 DSL.
The same could not be made binding to the
respondent No.1 or respondent No.2, who were not
the parties to the said agreement. None of the
provisions contained in the said Act contemplates
exclusivity to the Co-Developer for providing
infrastructure facilities.
11. Mr.S.I. Nanavati, learned Sr. Advocate for
the respondent No.2 in this regard has rightly
relied upon the various clauses of the Sub-lease
deed dated 27.12.2011(Annexure-R/1) entered into
between the respondent No.3 M/s.DSL and the
respondent No.2 M/s.OPAL to submit that the
respondent No.2 was free to obtain any service,
amenities or facilities not provided by the
DSL/Co-Developer/service provider in Dahej SEZ
directly from the concerned agency. Further,
though the petitioner GSPL was the Co-
Developer/service provider for the supply of
Page 69 of 80
Page 69 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
piped gas to the units of Dahej SEZ, the
respondent No.2 had an option to apply to GSPL
for gas supply on such terms and conditions as
may be mutually agreed between the sub-lessee
M/s.OPAL and the Co-Developer GSPL, as
contemplated in Clause 4.5 of the said sub-lease
agreement. Under the circumstances, in absence
of any provision under the Act and in absence of
any clause contained in the agreement between the
petitioner Co-Developer and the respondent No.2
as the sub-lessee, conferring exclusive right on
the petitioner for providing infrastructure
facilities, more particularly of laying the
pipeline for the transmission of gas supply to
the units set up in the special economic zone,
the claim of exclusivity made by the learned Sr.
Advocate Mr.Thakore for the petitioner is found
devoid of any merits.
12. The respondent No.3 M/s.DSL had already
granted, in-principle approval to the respondent
No.1 for offering land on Right of Use by letter
dated 29.9.2017, subject to the conditions
mentioned therein. One of the conditions was
Page 70 of 80
Page 70 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
that the respondent No.1 M/s.GAIL had to obtain
permission/approval from the development
Commissioner SEZ, Government of India/Board of
approval MOCI, Delhi for laying 8” dia pipeline
by Tap off from existing M/s.GAIL – DUPL 30” dia
natural gas pipeline to M/s.OPAL in Dahej SEZ
area. The proposal being not for providing
infrastructure facility for the development of
SEZ, the approval of Board was not required, and
hence the permission was rightly sought by the
GAIL from the Development Commissioner who, in
turn, had put up the proposal before the approval
committee, and the said committee in its 76th
meeting held on 11.10.2017 had decided to approve
the said proposal.
13. It further transpires that the petitioner
after having come to know about the said approval
granted by the approval Committee had raised
objection by writing letter dated 8.11.2017
(Annexure-E) to the CEO of the respondent No.3
DSL. The petitioner in the said letter had
referred to the Co-Developer agreement executed
with Dahej SEZ and stated that the GSPL was
Page 71 of 80
Page 71 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
entrusted with the sole responsibility to
develop, operate and maintain complete natural
gas infrastructure facilities in Dahej SEZ, and
therefore, the decision to approve the proposal
of M/s.GAIL and M/s.OPAL for development of
natural gas pipeline for M/s.OPAL was required to
be reconsidered. From the said letter, it
clearly emerges that the petitioner was aware at
least on 8.11.2017 about approval granted by the
Approval Committee and, about the in-principle
approval granted by the respondent No.3, and if
it was so aggrieved, could have approached the
Court, but it did not. It is further interesting
to note that the CEO of the respondent No.3
thereafter suddenly on 24.11.2017 addressed a
letter to the respondent No.2 M/s.OPAL with a
copy marked to the respondent No.1 M/s.GAIL
informing the respondent No.2 that M/s.Gujarat
State Petroleum Corporation (GSPC) being Co-
Developer for supply of natural gas in Dahej SEZ
area, the respondent No.2 was required to get no
objection certificate from M/s.Gujarat State
Petroleum Corporation (GSPC) before execution of
the work at the site. It is pertinent to note
Page 72 of 80
Page 72 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
that M/s. Gujarat State Petroleum Corporation is
the holding company of the petitioner GSPL, and
it was the petitioner GSPL who was the Co-
Developer and not the GSPC. Be that as it may,
it is further pertinent to note that though the
said letter was addressed to the respondent Nos.1
and 2, and not even marked to the petitioner, the
CEO had furnished the office copy of the said
letter to the petitioner before dispatching the
said letter to the respondent Nos.1 and 2. The
said letter was dispatched on 27.11.2017 and was
received by the respondent Nos.1 and 2 only on
29.11.2017. Interestingly, though no such NOC
was asked for either by the respondent No.1 or by
the respondent No.2, the petitioner on 29.11.2017
issued a letter to the respondent No.1 M/s.GAIL
(Annexure-G) and to the respondent No.2 M/s.OPAL
(Annexure-H), intimating that the petitioner was
not in a position to issue NOC either to the
M/s.GAIL or to the M/s.OPAL for developing
natural gas pipeline to connect M/s.OPAL, and
requested the GAIL to cease all activities
including pipeline laying activities immediately.
When the letter dated 24.11.2017 issued by the
Page 73 of 80
Page 73 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
CEO of the respondent No.3 was received by the
respondent Nos.1 and 2 only on 29.11.2017, there
was no question of seeking NOC from the
petitioner by the respondent Nos.1 and 2 before
29.11.2017 and therefore, there was no occasion
for the petitioner to write letters on 29.11.2017
refusing to grant NOC to them. The Court,
therefore, having found substance in the
submission made by Mr.S.I. Nanavati for the
respondent No.2 that the said letter dated
24.11.2017 was issued by the CEO of the
respondent No.3 in collusion with the petitioner,
with a view to create an imaginary urgency in the
matter for filing the petition on 30.11.2017,
though the petitioner was very much aware about
the approval granted by the Approval Committee
and the respondent Dahej SEZ as back as on
8.11.2017, the Court had directed the CEO of DSL
to remain personally present with his affidavit
explaining the situation. On his remaining
present before the Court, a specific query was
put by the Court as to what was the need for
issuing the letter dated 24.11.2017 when the
respondent No.3 DSL had already granted, the in-
Page 74 of 80
Page 74 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
principle approval on 29.9.2017, and the approval
committee had also granted approval on
11.10.2017, the CEO of the respondent No.3 was
not in a position to answer the said query. The
said conduct of the CEU has been recorded by the
Court in the order dated 13.12.2017.
14. From the afore-stated conduct of the
petitioner and the CEO of the respondent No.3 it
clearly transpires that the said letters dated
24.11.2017 issued by the CEO of the respondent
No.3 and the letters dated 29.11.2017 issued by
the petitioner refusing to grant NOC were
prepared in collusion with each other to create
an artificial urgency in the matter, to file
petition on 30.11.2017, though the petitioner was
aware about the granting of approval by the
respondent No.3 DSL and by the Approval Committee
as back as on 8.11.2017, and though the work of
laying 25 mtr., pipeline was already started by
the respondent No.1 in October 2017 as stated by
the respondent No.2 in its affidavit-in-reply,
which has remained un-controverted by the
petitioner. Under the circumstances, the Court
Page 75 of 80
Page 75 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
is constrained to hold that by seeking urgent
hearing of the petition, which contained
inaccurate and incorrect statements, and which
suffered from the vice of the suppression of
material facts, the petitioner had tried to
misuse the process of law. Such conduct on the
part of the petitioner has not only led to
miscarriage of justice, but huge financial loss
to the respondent No.2. The other technical
issues arising out of the contractual disputes
being highly disputed questions are not required
to be gone into, and therefore, not dealt with.
15. Much was argued on whether there is any
inconsistency between the SEZ Act and PNGRB Act,
and whether the SEZ Act has an overriding effect
over the PNGRB Act or not. It can not be
gainsaid that in view of Section 51 of the SEZ
Act, the provisions of the said Act would have
effect notwithstanding anything inconsistent
therewith contained in any other law for the time
being in force. The expression “for the time
being in force” would not only include the
existing legislations but would also include
Page 76 of 80
Page 76 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
future legislations, as observed by Supreme Court
in case of Yakub Abdul Razak Memon Vs. State of
Maharashtra (supra). Hence, though the PNGRB Act
has been enacted later in point of time, the
provisions of SEZ Act would override the
provisions of the PNGRB Act, if there is any
inconsistency between any of the provisions
contained in the two Acts. As transpiring from
the long title of the PNGRB Act, the Act has been
enacted to provide the establishment of Petroleum
and Natural Gas Regulatory Board to regulate
amongst others transportation, distribution,
marketing etc.,of petroleum products and natural
gas so as to protect the interests of consumers
and entities engaged in the specified activities
to ensure uninterrupted and adequate supply of
petroleum, petroleum products and natural gas in
all parts of the country and to promote
competitive markets. It is not disputed that the
provisions of PNGRB Act applies to both, the
petitioner GSPL and the respondent No.1 GAIL.
Both are authorized entities as per Section 2(d)
and common carriers as per Section 2(j) of the
PNGRB Act. The PNGRB Board, in exercise of the
Page 77 of 80
Page 77 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
powers conferred under Section 61 of the PNGRB
Act, has framed and amended the Regulations from
time to time, and has amended latest as per the
Amendment Regulations,2016. The learned Sr.
Advocate Mr.Thakore though relied upon the
provisions of both the Acts, had failed to point
out any inconsistent provision contained in the
PNGRB Act, which would get overridden by the SEZ
Act. According to him, the respondent No.1GAIL
could not be said to have an unfettered right to
lay pipelines for the supply of gas in any part
of the country,and that its rights and
obligations are subject to the SEZ Act, if the
area falls under the SEZ. There can not be any
disagreement to the said proposition, however, in
the facts and circumstances of the case, and in
view of the afore-discussed legal position, the
facilities or services sought to be provided by
the respondent No.1 to the respondent No.2 being
not the infrastructure facilities, the Court does
not find any inconsistency between the provisions
of the said two Acts. The issue whether Clause-
1(g) of Schedule J of the PNGRB Authorisation
Regulations, 2008, as amended in 2016, is
Page 78 of 80
Page 78 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
applicable to the respondent No.1 GAIL or not,
also pales into insignificance, in view of the
fact that requisite approvals have already been
obtained by the respondent Nos.1 and 2 under the
SEZ Act for the purpose of laying 8” dia pipeline
in question. There is no provision contained in
the SEZ Act, which grants exclusivity to any
person, which otherwise would encourage
monopolistic and restrictive trade practices, or
which would run counter to and frustrate the very
purpose and object of promoting competitive
markets in the matter of petroleum, petroleum
products and natural gas, as contained in the
PNGRB Act.
16. In the afore-stated premises, the petition
being devoid of any merits and having been filed
suppressing material facts and documents,
deserves to be dismissed and is dismissed. Ad-
interim relief stands vacated forthwith. Notices
stand discharged.
(BELA M. TRIVEDI, J.)
Page 79 of 80
Page 79 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)
C/SCA/21738/2017 CAV JUDGMENT
FURTHER ORDER:-
The request made by the learned Sr. Advocate
Mr.Mihir Thakore for the petitioner to extend the
ad-interim relief is rejected for the reasons
stated in the judgement.
(BELA M. TRIVEDI, J.) vinod
Page 80 of 80
Page 80 of HC-NIC Created On Tue Dec 26 19:30:23 IST 201780
Bar & Bench (www.barandbench.com)