October 4, 2019
GRINNELL COLLEGEHumanities & Social Studies Center
Owner and Design Team
➢ Grinnell College HSSC Project
Leadership Team:
➢ Anne Harris
➢ Jim Swartz
➢ Erik Simpson
➢ Keith Brouhle
➢ Rick Whitney
➢ Dave Robinson
➢ Larry Gleason
➢ Keith Archer
➢ Nancy Combs
➢ Christi Baker
➢ Jane Taylor
➢ EYP Architects
➢ Jennifer Amster
➢ Eric Kern
➢ Eric Petersen
➢ Alison Ledwith
➢ OPN Architects
➢ Bill Catrenich
➢ Pylar Eaton
McGough Project Team
➢ Dustin Schwake – Project Executive
➢Matt Schroeder – Senior Project Manager
➢ Josh Miltenberger – Senior Project Manager
➢ Jennifer Radniecki – Project Manager
➢ Alex Maass – Assistant Project Manager
➢ Amy Robinson – Project Coordinator
➢ Chuck Carpenter – Senior Superintendent
➢ Greg Evans – Superintendent
➢ Ed Polito – General Foreman
Subcontractors
➢ 1st Interiors
➢ Advance Equipment Co.
➢ All-American Scaffold
➢ American Fence Co.
➢ American Structural Metals
➢ Architectural Wall Systems
➢ Baker Electric
➢ Baker Group
➢ Bartley Sales
➢ Blue Sky Cleaning
➢ Bolander
➢ C&C Demolition
➢ CGA
➢ D&N Fence
➢ DA Bunch
➢ Danny’s Construction
➢ Des Moines Marble
➢ Energy Control of Iowa
➢ Floors by Beckers
➢ Forman Ford
➢ Heartland Finishes
➢ J&M Roofing
➢ Johnson Specialty Sales
➢ KONE Elevator
➢ Larry’s Window Services
➢ Midwest Caulking
➢ Navetta
➢ PAC-VAN
➢ Pella Tree Service
➢ Peterson Contractors, Inc.
➢ Premier Edge
➢ Pro-Bel
➢ S&F Underground
➢ Seedorff Masonry
➢ Skold Companies
➢ Soil-Tek
➢ Summit Fire Protection
➢ Superior Painting
➢ Swanson & Youngdale
➢ Waldinger Mechanical
➢ Walsh Door & Security
➢ Western Specialty
➢ Wilkie Sanderson
➢ Wynn O. Jones
Current Highlights
➢Carnegie:
➢Plaster restoration nearly complete
➢Ceramic tile has started in bathrooms
➢Finishes continue
➢ARH:
➢Steel erection is complete in the knuckle
➢Overhead MEP continues
➢ Interior wall framing / rough-in continues
HSSC Courtyard
ARH Level 1 – knuckle – electrical rough-in
ARH Level 1 – knuckle
ARH Level 2 – knuckle
ARH Level 3 – knuckle
ARH main corridor – Level 1 – Fire door framing
ARH – Overhead MEP
ARH – exterior wall framing – level 2
ARH level 3 – Overhead MEP
Carnegie basement – drywall finish
Carnegie – Level 1 - finishes
Carnegie – Level 1 - finishes
Carnegie – bathroom tile
Carnegie – plaster restoration progress
Upcoming Highlights
➢Carnegie:
➢Plaster restoration complete
➢Finishes continue
➢ARH:
➢ Interior rough-in continues
➢Slab on grade / slab on metal deck concrete pours