glyn rhonwy pumped storage development consent...
TRANSCRIPT
Glyn Rhonwy Pumped Storage Development Consent Order
Environmental Statement Volume 1: Non Technical Summary
PINS Reference EN010072
Document No. 6.01
Regulation 5(2)(a) and Infrastructure Planning (Environmental ImpactAssessment) Regulations 2009
Author AECOM
Revision Date Description
0 October 2015 Submission Version
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
RevisionNo.
Date ofIssue
Comments Author(s) Checker Approver
0October
2015Final Issued Various CA DR
August /
September
2015
Working Draft Various CA DR
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
ContentsEXECUTIVE SUMMARY
CHAPTER 1 INTRODUCTION
CHAPTER 2 APPROACH TO EIA & CONSULTATION
CHAPTER 3 DESIGN EVOLUTION AND ALTERNATIVES
CHAPTER 4 PROJECT DESCRIPTION
CHAPTER 5 SUMMARY OF ENVIRONMENTAL IMPACT ASSESSMENT
FiguresFIGURE 1.1 SITE LOCATION PLAN
FIGURE 1.2 ORDER LIMITS
FIGURE 3.1 ECOLOGICAL DESIGNATIONS
FIGURE 3.2 LANDSCAPE DESIGNATIONS
FIGURE 3.3 SNOWDONIA NATIONAL PARK AUTHORITY
FIGURE 3.4 SITE DESCRIPTION
FIGURE 3.5 DESIGN REVIEW 1
FIGURE 3.6 DESIGN REVIEW 2
FIGURE 3.7 DESIGN REVIEW 3
FIGURE 3.8 DESIGN REVIEW 4
FIGURE 3.9 DESIGN REVIEW 6
FIGURE 3.10 DESIGN REVIEW 7
FIGURE 3.11 DESIGN REVIEW 8
FIGURE 4.1 DEVELOPMENT OVERVIEW
FIGURE 4.2 INDICATIVE ROUTE OF ELECTRICAL CONNECTION
FIGURE 5.1 ZONE OF THEORETICAL VISIBILITY
FIGURE 5.2 CUMULATIVE DEVELOPMENTS
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
Abbreviations & Glossary2012 ES The previously submitted ES
AGL Above Ground Level
AOD Above Ordnance Datum
AQMP Air Quality Management Plan
BOCC Birds of Conservation Concern
BPM Best Practicable Means
BS4142 British Standard – Method for Rating Industrial Noise Affecting Mixed
Residential and Industrial Areas
BS7445 British Standard- Description and Measurement of Environmental Noise
CADW The Welsh Government's Historic Environment Service
CCW Countryside Council for Wales (now NRW)
CEMP Construction Environmental Management Plan
CoCP Code of Construction Practice
CTMP Construction Traffic Management Plan
DCO Development Consent Order
DECC Department of Energy & Climate Change
Development The proposed 99.9MW Glyn Rhonwy Pumped Storage Facility
DMP Dust Management Plan
DNO District Network Operator
EIA Environmental Impact Assessment
EN-1 Overarching National Policy Statement for Energy
EN-3 National Policy Statement for Renewable Energy Infrastructure
EN-5 National Policy Statement for Electricity Networks Infrastructure
EP Environmental Permit
EP Environmental Permit
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
ERFMP Emergency Response and Flood Risk Management Plan
ES Environmental Statement
ES The Environmental Statement for the Glyn Rhonwy Pumped Storage
DCO
FCA Flood Consequences Assessment
GAPS Gwynedd Archaeological Planning Service
GC Gwynedd Council
GI Ground Investigation
Ha / ha Hectare
HASP Halth and Safety Plan
HDPE High Density Poly-ethylene
Headpond Upper reservoir
HGV Heavy Goods Vehicle
HMP Habitat Management Plan
HRA Habitat Regulation Assessment
Hz Hertz
ICP Independent Connection Provider
kv Kilovolt – measure of electrical current
LCA Landscape Character Area
LHA Local Highway Authority
LSE Likely Significant Effect
LVIA Landscape & Visual Impact Assessment
LWS Local Wildlife Site
m Metres
m3 Cubic metres
MTAN Minerals Technical Advice Note
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
MW Mega Watts – measure of energy, one million watts
MWh Mega Watt Hours – measure of energy generated in hours
NMP Noise Management Plan
NPS National Policy Statement
NRW Natural Resources Wales (formally EAW and CCW)
NSIP Nationally Significant Infrastructure Project
NSR Noise Sensitive Receptor
NTS Non-Technical Summary
NVC National vegetation Classification
PC Principal Contractor
PEIR Preliminary Environmental Information Report
Penstock The pipe connecting the headpond to the power house
PINS Planning Inspectorate
Power House Containing the combined pump/turbines
PPP Pollution Prevention Plan
PPW Planning Policy Wales
PRoW Public Rights of Way
Q1 Quarry 1- Chwarel Fawr
Q2 Quarry 2- Chwarel Cefn Du
Q3 Quarry 3- Cook
Q4 Quarry 4- Ddol
Q5 Quarry 5- unnamed but known locally as Gideon Quarry (previously
known as Glynrhonwy)
Q6 Quarry 6- Glyn Rhonwy (also locally known as Mancer Quarry)
Q7 Quarry 7- Unnamed and is a smaller quarry excavated between and to
the south of Glyn Rhonwy (Q6) and the former munitions store (Q8). It
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
has been used to dispose of slate waste and has more established
vegetation colonising its base than other quarries at the site.
Q8 Quarry 8 former WWII munitions store (known locally as the bombstore)
QBC Quarry Battery Company Ltd
SAC Special Area of Conservation
SNP Snowdonia National Park
SNPA Snowdonia National Park Authority
SoCC Statement of Community Consultation
SoS Secretary of State
SP Scottish Power
SPH Snowdonia Pumped Hydro Ltd or “the Applicant”
Spillway Infrastructure A discharge point from the headpond and a joint
discharge/abstraction point from the tailpond
SSSI Site of Special Scientific Interest
SUDS Sustainable Urban Drainage Systems
T&CPA application The planning application submitted under the Town & Country
Planning Act for the 49.9MW scheme as approved by GC
T&CPA Town and Country Planning Act 1990
TA Traffic Assessment
Tailpond Lower reservoir
Tailrace The pipe connecting the power house to the tailpond
TAN Technical Advice Note
TBM Tunnel Boring Machine
The Act The Planning Act 2008
The Applicant Snowdonia Pumped Hydro (SPH) Ltd
The Approved Scheme The approved 49.9MW scheme Glyn Rhonwy Pumped
Storage facility
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
TPO Tree Protection Order
TWL Top Water Level
UDP Unitary Development Plan
UXO Unexploded Ordnance
V Volt
WFD Water Framework Directive
WG Welsh Government
WMP Waste Management Plan
WTMP Water Management Plan
ZTV Zone of Theoretical Visibility
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
Introduction
This Non-Technical Summary (NTS) accompanies a Development Consent
Order (DCO) application which has been submitted by Snowdonia Pumped
Hydro (SPH – hereafter referred to as “the Applicant”) for the construction
and operation of a pumped storage scheme with an output capacity of 99.9
megawatts (MW) at the Glyn Rhonwy and Chwarel Fawr quarries, near
Llanberis (hereafter referred to as ‘the Development”).
The Development exceeds 50MW installed output capacity, and is therefore
designated as a Nationally Significant Infrastructure Project (NSIP) under
the Planning Act 2008 (“the Act”). The application for the DCO is submitted
to the Planning Inspectorate and will be determined by the Secretary of
State for Energy & Climate Change (SoS).
Environmental Impact Assessment
EIA is the process of identifying, evaluating and, where possible, mitigating
the likely significant environmental effects of a proposed development. It
promotes the early identification and evaluation of the potentially significant
environmental effects of a proposed development and enables appropriate
mitigation (that is measures to avoid, reduce or offset significant adverse
effects) to be identified and incorporated into the design of a development,
or commitments to be made to environmentally sensitive construction
methods and practices.
The Infrastructure Planning (Environmental Impact Assessment)
Regulations 2009 (as amended) (the EIA Regulations) apply in the case of
applications under the Planning Act 2008. The EIA Regulations require an
Environmental Impact Assessment (EIA) to be carried out to determine the
likely significant effects of a proposed development on the environment.
EXECUTIVE SUMMARY
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
The results of the EIA also ensure that decision makers such as the SoS
and statutory consultees such as planning authorities, in this case Gwynedd
Council, as well as other interested parties, including local communities, are
aware of a development’s environmental effects so that these may be
considered before a decision is taken on whether or not the development
should be approved.
An Environmental Statement (ES) reports the findings of the EIA. The ES
which accompanies the application for the DCO has been prepared by
AECOM on behalf of the Applicant.
The methodology section within individual technical chapters of the ES sets
out the criteria used in judging the significance of effects and the process
that has been undertaken to gather baseline information and predict the
likely effects and their magnitude.
Mitigation measures are actions that are implemented to reduce the
significance of an environmental effect. Should a likely significant effect
remain after the implementation of mitigation measures, this is known as a
significant residual effect.
Pre-Application Consultation
Under the Planning Act 2008, the Applicant is required to undertake formal
consultation with the local community and stakeholders to allow them to find
out more about the Development, and give the Applicant their views on the
proposals in line with the requirements of the Act. Formal statutory
consultation was conducted during February and March 2015. Comments
and responses received from the consultation stage were reviewed and
considered in finalising the proposed scheme and the final ES to be
submitted with the DCO application.
Purpose of this NTS
This document provides a Non-Technical Summary (NTS) of the ES
including setting out the evolution of the Development as well as describing
the results of the EIA to allow readers to understand the likely significant
effects of the Development would be, both adverse and beneficial, and the
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
proposed mitigation measures to avoid or minimise adverse effects, where
appropriate.
The NTS summarises the ES and is structured as follows:
Chapter 1 – Introduction
Chapter 2 – Approach to EIA & Consultation;
Chapter 3 – Design Evolution & Alternatives
Chapter 4 - Project Description
Chapter 5 – Summary of Environmental Impact Assessment
Chapter 6 - Conclusions
Submission
The SoS will consider the ES and all other relevant technical information, as
part of their responsibilities for determining the application. They will also
take into account any representations made by interested parties during the
examination of the application.
Further Information and Consultation
Additional copies of this NTS can be requested free of charge, and are
available from the project website (www.snowdoniapumpedhydro.com). A
Welsh language version of this NTS is available on the project website and
hard copies are available upon request.
The ES is available on the project website
(www.snowdoniapumpedhydro.com) and can be inspected at several
locations as detailed in Table 1.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
October 2015
Table 1 Inspection Venue Details
Location & Address Copy available Opening TimesLlyfrgell LlanberisLibrary, Ffordd CapelCoch, Llanberis, LL554SH
One inspection hardcopy and electroniccopies available
Tuesday 1400-1800,Thursday 1000-1200 and1300-1700, Friday 1400-1800.
Gwynedd CouncilHeadquarters, CastleStreet, Caernarfon,LL55 1SE
One inspection hardcopy and electroniccopies available
Monday – Friday 0840-1700
Caernarfon Library,Pavilion Hill,Caernarfon, LL55 1AS
Electronic copiesavailable
Monday and Tuesday 0930– 1900, Wednesday 0930– 1300
Waunfawr Surgery,Liverpool House,Waunfawr, LL55 4AG
Electronic copiesavailable
Monday, Tuesday &Thursday 0800-1830
Deiniolen Library , TyElidir, High Street,Deiniolen, LL55 3HR
Electronic copiesavailable
Monday 1500-1800,Wednesday 1400-1700,Friday 1000-1200.
Copies of the ES and DCO submission are available on request and will be
charged at £250 for a printed hard copy (including appendices) and £5 for
an electronic copy on CD/DVD.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-1
October 2015
1.1 Introduction
1.1.1 This document is the non-technical summary (NTS) of the Environmental
Statement (ES) for the Glyn Rhonwy Pumped Storage Development
Consent Order (hereafter referred to as the “Development”). The ES has
been submitted in four volumes. This NTS is Volume 1 with the remaining
volumes as follows:
Volume 2 – Main Text (Document Ref: 6.02)
Volume 3 – Appendix (Document Ref: 6.03)
Volume 4 – Figures & Photomontages (Document Ref: 6.04)
1.1.2 The Final ES has been produced to accompany the Development Consent
Order (DCO) Application under the Planning Act 2008 (“the Act”). The
Development exceeds 50 megawatts (MW) capacity and is therefore
classed as a Nationally Significant Infrastructure Project (NSIP) which
requires the consent of the Secretary of State (SoS) through the approval of
a DCO under the Act. The decision of whether or not to grant the DCO will
be made by the Secretary of State for Energy and Climate Change (“SoS”).
If the DCO is granted, the decisions on the detailed approvals under the
conditions in the DCO (known as “Requirements”) will be made by
Gwynedd Council (GC).
1.1.3 The Development will require a number of other consents in addition to the
DCO (for example permission to abstract water from Llyn Padarn to fill the
reservoir) which are not dealt with in this document, but are explained in
Document 5.04 “Details of Other Consents and Licenses” and within the
technical chapters of the ES, as appropriate.
1.1.4 The location of the Development is shown on Figure 1.1.
1 INTRODUCTION
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-2
October 2015
1.1.5 This NTS gives an overview of the Development, including the need for the
project, the alternatives that have been considered and a description of the
Development itself. This NTS also provides an overview of the conclusions
reached in the ES. Feedback received during the pre-application
consultation process has helped to inform the detail of the Development
and to further refine the EIA. The full and detailed findings of the EIA have
been presented in the ES.
1.1.6 This document is a summary (in non-technical language) of the ES for the
Development. The ES and the accompanying NTS have both been
prepared in accordance with Regulations 2 and 10 of the Infrastructure
Planning (Environmental Impact Assessment) Regulations 2009 (as
amended) (the ‘EIA Regulations’).
1.2 The Applicant
1.2.1 Snowdonia Pumped Hydro Limited (“SPH”) is the applicant for this DCO.
The company is a subsidiary of the Quarry Battery Company Limited
(“QBC”) which seeks to develop disused quarry systems into pumped
storage facilities.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-3
October 2015
1.3 Planning History
1.3.1 The Development is located approximately 1.5km north west of Llanberis,
as shown on Figure 1.1.
1.3.2 QBC was granted planning permission (Ref: C12/1451/LL) by GC on the
19th February 2014 for the construction and operation of a 600MWh
(megawatt hours) pumped storage scheme, with an output capacity of
49.9MW, at the Glyn Rhonwy and Chwarel Fawr quarries, near Llanberis.
The permission was granted under the Town & Country Planning Act 1990
(T&CPA). An application (Ref: C15/0308/15/DA) for a non-material
amendment (NMA) (was submitted in March 2015 to correct an inaccuracy
in the plans listed under Condition 2 of the extant permission. The
application was approved on 6th May 2015 and Condition 1 of the NMA
approval lists the approved plans correctly.
1.3.3 An EIA was undertaken of the approved scheme and the T&CPA
application was accompanied by an Environmental Statement.
1.3.4 Subsequent to the grant of planning permission under the T&CPA, SPH has
been established as a subsidiary of QBC to take the Glyn Rhonwy scheme
forward.
1.3.5 Due to changes in the energy market, the decision was taken to increase
the capacity of the approved scheme to 99.9MW. As the capacity of the
scheme is above 50MW, it falls under the definition of a NSIP and therefore
requires a DCO under the Act, rather than Planning Permission under the
T&CPA. The 99.9MW proposal is referred to throughout this document as
‘the Development’.
Terminology
1.3.6 The following terminology is used throughout this NTS (and the ES):
The ‘approved scheme’ refers to the approved 49.9MW Glyn Rhonwy
Pumped Storage facility;
’T&CPA application’ refers to the planning application submitted under
the Town & Country Planning Act for the 49.9MW scheme as approved
by GC;
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-4
October 2015
The ‘2012 ES’ refers to the previously submitted ES;
‘The Development’ refers to the proposed 99.9MW Glyn Rhonwy
Pumped Storage facility;
‘The Development site’ refers to land within the red line site boundary or
the “Order Limits” shown in Figure 1.2 of the NTS below;
‘Order Limits’ refers to the red line site boundary; and
‘The Applicant’ refers to Snowdonia Pumped Hydro Limited (SPH).
1.3.7 Further details of the Development can be found in Section 4 of this NTS
and in Chapter 4 Project Description of the ES.
1.4 Concept of Pumped Storage
1.4.1 Pumped storage is a method of generating electricity at times of peak
demand at short notice. This is achieved by releasing water from an upper
reservoir, which passes through a turbine, into a lower reservoir. Water is
then pumped back up during periods of low demand. The water is then
stored in the upper reservoir ready for the next time of peak demand. More
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-5
October 2015
detail is provided in Chapter 4 Project Description of the ES and in section 4
of this NTS.
1.5 Background & Need for the Development
1.5.1 The electricity supply network in the UK relies on the generation of
electricity from several sources, more traditionally through baseload thermal
generation plants such as coal, gas and also nuclear. These generators all
provide power to keep the national grid at a steady 50 Hertz (Hz), essential
to the smooth operation of electrical equipment throughout the UK.
1.5.2 At times of peak demand, pumped storage has the ability to provide
electricity quickly. Pumped Storage systems are able to start extremely
rapidly from cold start and even quicker from standby mode, in some cases
achieving full power within 15 seconds.
1.5.3 Compared to thermal power stations, which can take several hours to reach
full generating capacity, pumped storage has the ability to store and
generate large quantities of energy, making such facilities the most flexible
of all grid-scale electrical generation technologies.
1.5.4 Pumped storage is not a form of renewable energy as it requires energy to
pump the water back up from the lower reservoir to the upper reservoir,
ready for the next supply of energy to the electricity network. This happens
at night when abundant cheaper electricity can be utilised.
1.6 Introduction to the Development
1.6.1 The quarry system has been numbered from Q1 in the west to Q8 in the
east, which can be seen in Figure 1.2:
Quarry 1 (Q1) – Chwarel Fawr;
Quarry 2 (Q2) – Chwarel Cefn Du;
Quarry 3 (Q3) – Cook;
Quarry 4 (Q4) – Ddol;
Quarry 5 (Q5) – unnamed (known locally as ”Film Set Quarry”);
Quarry 6 (Q6) – Glyn Rhonwy;
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-6
October 2015
Quarry 7 (Q7) – unnamed; and
Quarry 8 (Q8) – former WWII munitions store (known locally as “the
bombstore”).
1.6.2 The Development utilises Q1 and Q6.
The Development
1.6.3 Pumped storage projects comprise of seven main elements:
A headpond - upper reservoir;
A tailpond - lower reservoir;
A power house - containing the combined pump/turbines;
A penstock - the pipe connecting the headpond to the power house;
A tailrace - the pipe connecting the power house to the tailpond;
Pumping station; and
Spillway infrastructure – a discharge point from the headpond and a joint
discharge/abstraction point from the tailpond.
1.6.4 The Development at Glyn Rhonwy comprises of the following permanent
features:
one headpond (Q1), its dam, access shaft and spillway to the Nant Y
Betws;
one tailpond (Q6), its dam, access shaft and spillway to Llyn Padarn;
a pumping station at Llyn Padarn;
a power house at Glyn Rhonwy Industrial Estate Platform 5 (south of Q6)
with an underground turbine hall housing turbines with an electrical
output of up to 99.9MW;
a penstock (connecting Q1 to the power house); and
a tailrace (connecting the power house to Q6).
1.6.5 The Development also incorporates temporary features such as temporary
construction compounds and lay down areas at Q1 and Q6.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-7
October 2015
1.6.6 Further details are provided in ES Chapter 4 Project Description and
section 4 of this NTS.
1.7 The Planning Framework
1.7.1 The Department for Energy and Climate Change (DECC) has published a
number of National Policy Statements (NPSs) in relation to energy
infrastructure. These NPSs set out national policy against which proposals
for NSIPs are assessed and determined. The DCO application for the
Development will be determined in accordance with these policies.
1.7.2 The NPS of principal relevance to the proposed Development is the
overarching NPS for Energy (NPS EN-1). This was published in 2011 and
sets out national policy for energy infrastructure as defined by the Act. NPS
EN-1 provides the primary basis for decisions on energy projects by the
SoS. Consideration is also given to the NPS for Renewable Energy
Infrastructure (2011) (NPS EN-3), and the NPS for Electricity Networks
Infrastructure (2011) (NPS EN-5).
1.7.3 NPS EN-1 states that consideration may be given to planning policy outside
the NPSs where it is important and relevant to the SoS's decision. Other
national, regional and local planning policies have therefore been
considered in the preparation of the ES as these may be relevant to the
determination of the proposed DCO Application, including:
• Planning Policy Wales (PPW) (7th Edition, July 2014);
• Technical Advice Notes (TANs);
• Minerals Technical Advice Notes (MTANs) (2009)
• People, Places, Futures: The Wales Spatial Plan Update (July 2008);
• Mon a Menai Strategy Programme (2008)
• Gwynedd Unitary Development Plan (2009)
• Gwynedd Local Planning Authority Supplementary Planning Guidance:
Development Brief Caernarfon Dependency Catchment Area
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
1-8
October 2015
• Emerging Anglesey and Gwynedd Joint Local Development Plan
(Deposit Plan, 2014) and
• Glyn Rhonwy Development Plan and Implementation Strategy
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-1
October 2015
2.1 Introduction
2.1.1 Environmental Impact Assessment (EIA) is the process of compiling,
evaluating and presenting environmental information about the likely
significant environmental effects of a Development. The assessment is
designed to help produce an environmentally informed project. The early
recognition of likely significant adverse environmental effects enables
appropriate mitigation (e.g. measures to avoid, reduce or offset significant
adverse effects) to be identified and incorporated into the design of a
project; or what measures will be taken to protect the environment during
construction and operation.
2.1.2 The EIA provides the decision maker and interested parties with information
about the likely significant environmental effects of the project and
proposed mitigation to assist with the determination of relevant applications.
Scoping
2.1.3 Scoping is a process which seeks to identify a suitable approach to the EIA
based on the best information available at the time that a scoping opinion is
sought.
2.1.4 The scope of the ES submitted with the DCO application has fully
considered the conclusions of the 2012 ES, the conditions attached to the
planning permission for the approved scheme and also the ongoing
discussions with statutory consultees.
2.1.5 During early consultation with the statutory consultees and PINS, the
Applicant sought to agree a scope directly with the statutory consultees,
namely Gwynedd Council (GC), Natural Resources Wales (NRW), Welsh
Government (WG), CADW, Snowdonia National Park Authority (SNPA) and
Gwynedd Archaeological Planning Service (GAPS). Therefore, a letter
setting out the proposed scope of the EIA for the Development was
2 APPROACH TO EIA & CONSULTATION
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-2
October 2015
submitted to these parties on the 12th November 2015. In response to this
letter, initial comments were provided by SNPA, NRW and GC. Following
this initial dialogue, it was agreed with those parties that a formal request
for a scoping opinion would be made to the SoS.
2.1.6 A request for a Scoping Opinion was submitted to the SoS on 5th January
2015, accompanied by a Scoping Report. The Scoping Report outlined
which environmental topics were to be covered by the EIA and how the
assessments were to be undertaken. The Scoping Opinion from PINS on
the 13th February 2015 and is contained within ES Volume 3, Appendix 2.4.
Draft ES / Preliminary Environmental Information Report (PEIR)
2.1.7 As part of the statutory pre-application consultation for the Development
under s47 of the Act, a Draft ES (February 2015) was prepared as
Preliminary Environmental Information (PEI) and made available to
consultees and the public during formal statutory consultation which
commenced on 12th February 2015. The Draft ES presented the
information gathered to date and provided the draft results of technical
assessments as to the likely significant environmental and social effects,
both positive and negative, of the construction, operation and
decommissioning phases of the Development.
2.1.8 The Draft ES was sent either electronically or in hard copy to all identified
s42 consultees on the 12th February 2015. Consultees were then given a
minimum of 28 days to respond with any comments on the Development
(which finished on the 13 March 2015). It was also available for viewing at a
number of locations in the vicinity of the Development and at the public
exhibitions held on the 27th and 28th February 2015. Full details of the
consultation activities can be found in the Consultation Report (Document
5.01) and in the Summary of Consultation Report (Document 5.01.1).
2.1.9 The Preliminary Environmental Information Report (PEIR) is an
intermediate step in the EIA process as required under the Act, and
provides environmental information compiled by the Applicant at the time of
publication, to enable consultees to develop an informed view of the
Development. The PEIR assesses the likely environmental effects of the
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-3
October 2015
Development and identifies potential approaches to mitigation based on the
environmental and social data collated at the time of publication, and
outlines whether further assessment needs to be carried out.
2.1.10 Feedback received during the pre-application consultation process has
helped to inform the detail of the Development and to further refine the EIA.
The full results of the technical studies are provided in the Final ES, which
accompanies the DCO application.
EIA
2.1.11 In accordance with EIA regulations, the EIA process for the Development
incorporates the following main steps:
Production of a Scoping Report to identify the likely significant effects
(scoped in) and the proposed methodology for their assessment in line
with relevant legislation, guidance and methods, and justification for any
significant effects that are not likely (scoped out). The Scoping Report
sought agreement of study areas, data sources, survey methodologies
and terminology;
Baseline surveys are undertaken to identify and describe the
environmental character of the area that could potentially be affected by
the Development. Where baseline data indicates major constraints to the
Development, this information is to be provided to the design team
immediately;
Relevant natural and manmade processes that may change the
character of the site are identified;
Consideration is then given to the possible interactions between the
Development and both existing and future site conditions. These
interactions or impacts are assessed using set criteria based on
accepted guidance and good practice;
Using the initial designs of the Development, the likely significant
environmental effects, both direct and indirect, can be established;
Production of a Preliminary Environmental Information report for
consultation purposes:
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-4
October 2015
Recommendations are made to avoid, minimise or mitigate adverse
effects and enhance positive effects. Alterations to the design will then
be reassessed and the significance of likely residual environmental
impacts ascertained; and
Following statutory consultation, the results of the EIA in combination
with the responses to the Scoping Opinion will be set out in an ES that
will accompany the application for a DCO.
2.1.12 Feedback received during the previous consultation process in connection
with the approved scheme and the ongoing pre-application consultation
through the DCO process has helped to inform the design of the
Development and the findings of and commitments made in the EIA.
2.2 Consultation
2.2.1 Effective pre application consultation is an important requirement of the Act,
which requires applicants to consult with both technical (Section 42) and
community (Section 47) consultees.
2.2.2 The Applicant has engaged in pre-application consultation with a number of
statutory consultees, namely PINS, GC, GAPS, CADW and NRW, prior to
the submission of the DCO. Table 2.1 outlines the meetings which have
been held:
Table 2-1 Record of MeetingsDate Attended by Issues discussed15th October2014
Gwynedd Council Intention to apply for DCO
1st December2014
Gwynedd Council& Cadw
DCO workshop includingdiscussions about the changes inred line boundary
2nd December2014
Gwynedd Council,NRW, PINS
PINS site visit plus follow upmeeting with GC and NRWregarding introduction to theproject and DCO process.Minutes taken.
22nd January2015
NRW To discuss SI works and HRAScreening
9th March 2015 PINS To discuss progress on the DCO26th March 2015 Horizon Nuclear
PowerTo discuss cumulative effects
26th March to 16th NRW, GC & Informal meetings during
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-5
October 2015
Table 2-1 Record of MeetingsDate Attended by Issues discussedJuly Gwynedd
ArchaeologicalTrust
preliminary GI works.
30th March 2015 NRW & GwyneddCouncil
To discuss s42 responses fromGwynedd Council and NRW.NRW provided a formal responseon the agenda and both partiesalso provided comments on theUXO report. Minutes taken.
15th May 2015 PINS To discuss progress on theproject and draft DCOdocumentation
15th July 2015 NRW andGwynedd Council
To discuss results of the breedingbird and aquatic ecology surveys,UXO and amends to projectdescription. Minutes taken.
16th September2015
PINS To discuss progress on theproject and draft DCOdocumentation
Public Consultation
2.2.3 Consultation with local people, businesses and organisations is also an
essential part of the DCO process and has helped to influence the final
designs of the Development.
2.2.4 Full details of the consultation that has been undertaken by SPH in
connection with the Development are provided in the Consultation Report
(Document 5.01) which records the consultation undertaken and its
conclusions, in particular how it has influenced the Development and the
Application.
2.2.5 Over 200 people attended the public exhibitions held on the 27th February
2015 in Caeathro and 28th February 2015 in Llanberis. Over 640 individual
items of feedback from 639 unique correspondents were received as part of
the s47 consultation.
2.3 Approach to Assessing the Significance of Effects
2.3.1 The following approach provides an overview of the assessment
methodology. However, within individual technical chapters in the ES, the
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-6
October 2015
approach may differ due to topic-specific guidance, policies and legislation.
Where this occurs, the variation in methodology is explained clearly and
fully.
2.3.2 The determination of the significance of the likely environmental effects
arising from the Development is a key stage in the EIA process. In order to
assess the significance of an impact, it is necessary to establish the
sensitivity or value of the receiving environment or receptor and the
magnitude of the impact occurring, i.e. the scale, duration etc of the change
to the existing conditions as a result of the Development. Assessment of
significance for individual environmental topics will typically combine
professional judgment with consideration of a number of factors:
The sensitivity of the resource or environmental feature (known as 'a
receptor') under consideration;
The magnitude of the impact in relation to the degree of change which
occurs as a result and whether the effect is temporary, permanent,
and/or reversible.
2.3.3 Other factors include the type of effect, i.e. whether it is adverse, beneficial,
neutral or uncertain; and the probability of the effect occurring based on the
scale of certain, likely or unlikely.
2.3.4 The sensitivity of the baseline conditions is assessed according to the
relative importance of existing environmental features on or near to the site,
or by the sensitivity of receptors, which would potentially be affected by the
Development. Table 2-2 lists the criteria for the determination of the
sensitivity or value of receptors are established based on approved
guidance, legislation, statutory designation and/or professional judgment.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-7
October 2015
Table 2-2: Criteria for determining sensitivity of receptorsSensitivity DefinitionVery High The receptor has little or no ability to absorb change without
fundamentally altering its present character, is of very highenvironmental value, or of international importance.
High The receptor has low ability to absorb change withoutfundamentally altering its present character, is of highenvironmental value, or of national importance.
Medium The receptor has moderate capacity to absorb change withoutsignificantly altering its present character, has someenvironmental value or is of national importance.
Low The receptor is tolerant of change without detriment to itscharacter, is low environmental value, or local importance.
Negligible The receptor is resistant to change and is of little environmentalvalue.
2.3.5 The magnitude of potential effects on environmental baseline conditions is
identified through consideration of the Development taking into account the
scale or degree of change from the existing baseline as a result of the
effect. Consideration is given to the duration and reversibility of the effect as
well as consideration of relevant legislative or policy standards or
guidelines. Table 2-3 provides a general definition for determining the
magnitude of a particular effect.
Table 2-3: Criteria for determining the magnitude of a particular effectMagnitude DefinitionHigh Total loss or major alternation to key elements / features of
the baseline conditions such that post development character/ composition of baseline condition will be fundamentallychanged.
Medium Loss or alteration to one or more key elements / features ofthe baseline conditions such that post development character/ composition of the baseline condition will be materiallychanged.
Low Minor shift away from baseline conditions. Changes arisingfrom the alteration will be detectable but not material; theunderlying character / composition of the baseline conditionwill be similar to the pre-development situation.
Negligible Very little change from baseline conditions. Change is barelydistinguishable, approximating to a “no change” situation.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-8
October 2015
2.3.6 The general approach adopted in the assessment of significance, as it
relates to sensitivity and magnitude, is outlined in Table 2-4 below. A
combination of the magnitude of the impact under consideration and the
sensitivity of the receiving environment determines the significance of
effect. For some specialist topics, additional categories have been added
where a greater level of definition is required. It should be noted that this
general approach is a framework only, the significance of an effect is
assessed on a case-by-case basis.
Table 2-4 Approach to Assessment of Effects
Magnitude Sensitivity
Very High High Medium Low Negligible
High Major Major Moderate Moderate Minor
Medium Major Moderate Moderate Minor Negligible
Low Moderate Moderate Minor Negligible Negligible
Negligible Minor Minor Negligible Negligible Negligible
2.3.7 The significance of the effects arising from the Development have been
reported using a seven-point scale, as follows:
Major Adverse, Moderate Adverse, Minor Adverse;
Negligible; and
Major Beneficial, Moderate Beneficial, Minor Beneficial.
2.3.8 Effects predicted to be Minor are considered to be manageable and such
effects are considered to be ‘Not Significant’. Effects assessed as
Moderate or Major are considered to be 'Significant'. When the residual
significance of impacts is assessed this takes into account mitigation, i.e.
the assessment applies to the residual effects of the project, which can be
defined as any impact that would remain following the implementation of
proposed mitigation measures.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-9
October 2015
2.4 Structure of the ES
2.4.1 The ES reports the findings of the EIA and ensures that decision makers
such as the SoS and statutory consultees such as planning authorities, in
this case GC, as well as other interested parties, including local
communities, are aware of a development’s environmental effects so that
these may be considered before a decision is taken on whether or not the
development should be approved.
2.4.2 The ES also contains a series of technical assessments which have
assessed the potential for likely significant effects during the construction,
operation and decommissioning of the Development. The scope of these
technical assessments was presented within the Scoping Report submitted
to PINS on the 5th January 2015 and consultation with interested parties
and statutory consultees has shaped the scope of these assessments.
Further detail on consultation can be found in Chapter 2 Approach to EIA &
Consultation of the ES.
2.4.3 The structure of the ES is as follows:
Introductory chapters including the approach to the EIA and consultation,
the design evolution, the main alternatives considered, the project
description, and planning policy (Chapters 1-5);
Landscape Character and Visual Amenity(Chapter 6);
Ecology (Chapter 7);
Geology & Ground Conditions (Chapter 8);
Water Resources (Chapter 9);
Flood Risk (Chapter 10);
Archaeology & Cultural Heritage (Chapter 11);
Traffic & Transportation (Chapter 12);
Noise and Vibration (Chapter 13);
Air Quality (Chapter 14);
Socio-economics (Chapter 15);
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-10
October 2015
Environmental Management (Chapter 16);
Cumulative Effects (Chapter 17); and
Schedule of Mitigation (Chapter 18).
2.4.4 Additional documentation has been submitted with the ES as follows:
Statement in respect of statutory nuisance (Document 5.02);
European site appropriate assessment report, otherwise known as a
Habitat Regulation Assessment (HRA) (Document 5.03);
Details of other consents and licenses (Document 5.04); and
Code of Construction Practice (CoCP) and associated management
plans (Volume 3, Appendix 16.1).
2.4.5 The CoCP is the document that brings together all the construction phase
mitigation measures proposed for the Development. It covers the
management of a Principal Contractor’s (PCs) activities and those of any
Sub-Contractors, and defines the minimum requirements that have to be
met. It identifies the procedures required to minimise the impact of
construction activities for the Development. It includes details of measures
to be employed to ensure that no pollution incidents occur, that impacts on
protected species / designated sites are minimised as far as possible, that
archaeological features are identified and recorded, and that impacts on
nearby residents are kept to an absolute minimum.
2.5 Cumulative and In-Combination Effects
2.5.1 The effects of the Development have been assessed in combination with
two other developments in the vicinity of the Order Limits (i.e. ‘cumulative
effects’). Consideration has been given to the Wylfa C New Nuclear Power
Station and the Caernarfon to Bontnewydd bypass, but only in relation to
socio-economic and traffic and transportation effects due to the distance
between the Developments.
2.5.2 The effects of the Development on shared receptors have also been
assessed (i.e. ‘combined effects’).
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non-Technical SummaryVolume 1
2-11
October 2015
2.5.3 In-combination effects (where two effects which are not significant could
combine to result in a potential cumulative effect which is significant) have
also been considered as part of the EIA and are discussed within each
chapter of the ES (and summarised in Chapter 17 Cumulative Effects) and
in Section 5 of this NTS.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-1
October 2015
3.1 Surrounding Environment
3.1.1 The Development is located approximately 1.5km north west of Llanberis
and 11km south east of Caernarfon, as shown in Figure 1.1 of the NTS. It is
located on the slopes of Cefn Du, centred at National Grid reference SH
56268 60660.
3.1.2 The site is located within, and in close proximity to, environmentally
designated sites; Llyn Padarn to the east is a Site of Special Scientific
Interest (SSSI), as shown in Figure 3.1.
3.1.3 The Development site itself is within a Landscape Character Area (LCA)
(designated for its historical landscape) and also within Dinorwig Landscape
of Outstanding Historical Interest, as shown in Figure 3.2.
3 DESIGN EVOLUTION AND ALTERNATIVES
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-2
October 2015
3.1.4 The site is located approximately 1km outside of Snowdonia National Park
(SNP), this is shown in Figure 3.3.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-3
October 2015
3.1.5 The Development site encompasses a series of disused quarries, the Glyn
Rhonwy Industrial Estate platforms and an area adjacent to Llyn Padarn, all
within the boundary of GC. This is shown in Figure 3.4.
3.1.6 The Development covers an area of approximately 91.24ha.
3.1.7 The site’s physical characteristics include a number of quarry pits, slate
tips, a mature plantation woodland, rough grazing land and road network
leading to Glyn Rhonwy Industrial Estate platform in the south and off the
A4085 in the north. Ffordd Clegir separates two of the lower quarries and
also forms the western boundary of the Glyn Rhonwy Industrial Estate. This
is shown in Figure 3.4.
3.1.8 Water has collected in two of the quarries. Bathymetric surveys undertaken
in Q6 have recorded the depth at approximately 17m. Q1 is estimated to be
approximately 7m deep.
3.1.9 The slopes around the quarries are built up with slate waste and
interspersed with the remains of outhouses and quarry workings, scattered
over grazing land. The neighbouring land is mainly agricultural, although
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-4
October 2015
there is an industrial estate between Glyn Rhonwy and Llyn Padarn, an
area of commercial forestry to the south west, and a large industrial
complex to the south of the site towards Llanberis.
3.1.10 A former World War II munitions store (Q8) is not included within the Order
Limits but is within close proximity to the Development.
3.1.11 Several Public Rights of Way (PRoW) cross the Order Limits in addition to
Ffordd Clegir (translated as Clegir Road) which bisects the quarry system.
Several individual properties are located on Ffordd Clegir with the nearest
properties approximately 400m away in Clegyr and Pen-draw. Additional
dwellings and properties are located approximately 1-2 km to the north west
of the Order Limits in Gallt-y-Celyn, Pen-y-Bwlch and Bwlch. The settlement
of Waunfawr is located approximately 2 km to the west of Q1 and the main
centre of Llanberis located approximately 1.5km from Q6. Further detailed
information is provided in Chapter 4 Project Description of the ES.
3.1.12 Although development of the Glyn Rhonwy industrial site has provided
improved access – including public access – access to the site is restricted
by locked gates and the quarries themselves are fenced off. The site is
used for informal (unauthorised) leisure activities and there is evidence that
forced access has been gained. Some quarries and buildings including the
Industrial Estate itself have been known to suffer vandalism in the form of
tipping, graffiti and damage to the fencing, which has facilitated
(unauthorised) access.
3.2 Design Evolution
3.2.1 The Development has evolved in two principal stages. The first design
evolution related to the approved scheme, with the second evolution taking
place following the grant of permission for the approved scheme in advance
of the submission of the DCO. This was in response to the Electricity
Market Reform which meant that the approved scheme was unlikely to be
deliverable with an output capacity of 49.9MW and that an increased
capacity would be required.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-5
October 2015
Approved Scheme - Review 1: Initial Design prepared for report to
accompany formal Scoping Request to Gwynedd Council (November 2011)
3.2.2 The initial design was based upon technical requirements of the pumped
storage scheme together with development constraints including proximity
to residential dwellings and designated sites, and incorporated three dams
at Q1, Q2 and Q6 with heights of 12m, 26m and 17m above ground level
(AGL) respectively. An alternative option was considered which comprised
an increase in the height of the dam at Q1 to 15m AGL, thereby avoiding
the need for a dam at Q2, and a reduced dam height at Q6 of 8m AGL.
3.2.3 The overland penstock route was to be routed on the northern side of the
Cook (Q3) and Dhol (Q4) quarries to avoid protected birds. The penstock
would be up to 2000m long with two 2.5m diameter pipes.
3.2.4 The power house was to be located on the western side of Ffordd Clegir in
Q5. The location of site compounds and access tracks was undetermined.
3.2.5 The use of Llyn Padarn as a tailpond was considered but was discounted
on the basis that it is designated as a SSSI and is a popular recreational
destination. The scheme at Design Review 1 is shown in Figure 3.5 below
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-6
October 2015
Approved Scheme Review 2: Engineering review following survey works
(April 2012)
3.2.6 The principal change as part of Design Review 2 was the removal of the
dam at Q2. The engineering review identified the potential to provide
approximately 1,100,000m3 of storage in Q1 meaning that the three dams
initially proposed were not required. In addition, the engineering review also
identified that significant engineering and geotechnical stabilisation works
would be required at Q2 and Q5, in addition to the ecological constraints
identified in Q5. As a result, dams were only required at Q1 (headpond) and
Q6 (tailpond) which would be 25m above ordnance datum (AOD) and 15m
AOD high respectively.
3.2.7 The proposed location of the power house was moved (from the munitions
store) to Platform 5 of the Glyn Rhonwy Industrial Estate.
3.2.8 Two penstock / tailrace construction methods to transfer water from Q1 to
Q6 were still being considered at this stage – one above ground and one
below ground. Design Review 2 is shown in Figure 3.6 below.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-7
October 2015
Approved Scheme - Review 3: Review following stakeholder consultation
(July 2012)
3.2.9 It was determined that the penstock for the approved scheme should be
constructed by underground tunnel excavation. The route, established at
Design Review 2, would be used, albeit along a more direct underground
route between Q1 and Q6. The open cut construction option was
discounted following consultation with regulators.
3.2.10 The location of the spillway pipe from Q6 to Llyn Padarn was still subject to
landownership discussions, specifically related to the bombstore (Q8). A
location for the pumping station was identified at a small inlet adjacent to
the public car park.
3.2.11 It was agreed that the excess material excavated from Q1 and Q6 would
stay onsite and be landscaped into the existing spoil mounds at Q1, to
avoid any adverse effects from transportation offsite through Waunfawr.
3.2.12 The scheme at Design Review 3 is shown in Figure 3.7 below.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-8
October 2015
Approved Scheme - Review 4: Final design for planning approval (August
2012)
3.2.13 The construction method for the penstock was confirmed as underground
tunnel excavation, removing the need for any above ground excavation.
3.2.14 Two dams were proposed; one at Q1, approximately 25m above existing
ground levels and 510m long (at the longest point), and a second at Q6,
approximately 15m above existing ground levels and 215m long (at the
longest point). The power house for the approved scheme was located on
Platform 5 of the Glyn Rhonwy Industrial Estate.
3.2.15 The location of the pumping station was confirmed as being at National Grid
ref SH 57250 61192 on the banks of Llyn Padarn due to the deeper water
and minimal effect on the car parking areas in this location.
3.2.16 The location of the spillway was confirmed as being to the south and south
east of Q8, outside of the bombstore, and therefore reducing the impact on
the former munitions store. The scheme at Design Review 4 (the approved
scheme) is shown in Figure 3.8 below
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-9
October 2015
DCO Development - Review 5: Engineering Review to increase output
capacity to 99.9MW (December 2014)
3.2.17 It was confirmed that the output capacity of the Development could be
increased to 99.9MW without any substantial changes being made to the
principal elements of the approved scheme. The main changes included:
More powerful turbines with a combined output capacity of 99.9MW
located within the underground turbine hall. The turbine hall remained
the same size as the approved scheme;
If required, additional noise attenuation for the turbines was proposed to
comply with any limits set by a DCO Requirement (as per planning
conditions for the approved scheme); and
A minor increase in the number of construction based deliveries to bring
the larger turbines and associated infrastructure on to site. As the
additional deliveries would have been to Q6, it was predicted that the
A4086 road infrastructure would accommodate the slight increase in
construction delivery traffic (particularly as the planning conditions
relating to traffic mitigation and management for the approved scheme
were to be reflected in DCO Requirements).
3.2.18 The Order Limits proposed for the Development at this stage comprised an
area of 59.3ha which reflected the size of the redline boundary for the
approved scheme, as shown in Figure 3.8 in this NTS.
DCO Development: Review 6: Design Review for report to accompany
formal Scoping Request to SoS (January 2015)
3.2.19 The Order Limits around Q1 were increased to allow for construction
activities around the new excess slate mounds to the south and an area to
the north to accommodate potential quarry wall re-profiling.
3.2.20 The area around and including Q1 is registered as Common Land, so an
application will be made to deregister the parts which will be permanently
affected and fenced off. The land north and south of the penstock corridor
and west of the Q1 construction compounds was identified as replacement
land in terms of being a similar quality, size and access. The land was
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-10
October 2015
included in the Order Limits as land negotiations had not been concluded at
the time; this was to ensure that powers could be sought under the DCO to
compulsorily acquire rights over / ownership of this land if required. An
additional area was also included for a potential replacement road to the
power house.
3.2.21 The Order Limits around the penstock were widened to 114m to allow for
flexibility in the underground penstock route due to the potential for dolerite
intrusions which may be present.
3.2.22 The Order Limits were also extended to allow for flexibility in the location of
the pumping station and its working area. The pumping station was still
proposed to be constructed in the manner outlined in the 2012 ES (i.e.
sunken design with a control box / kiosk above ground). The depth of the
spillway infrastructure into Llyn Padarn remains 5m beneath the water level
– this depth was previously agreed with the Countryside Council for Wales
(CCW) (now NRW) as it would avoid any potential effects to Arctic Char by
being above the thermocline, and also to recreational users.
3.2.23 As a result of the design review, the Order Limits increased from 59.3ha to
91.73ha. This was included within the Draft ES and is shown in Figure 3.9.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-11
October 2015
DCO Development - Review 7: Engineering Review (February – March
2015)
3.2.24 Subsequent to the issue of the Draft ES (February 2015) as part of the
consultation period, the Applicant undertook a final review of the temporary
and permanent PRoW diversions required in connection with the DCO. This
identified a need to extend the Order Limits by approximately 6ha to a total
of 97.77ha, this is shown in Figure 3.10.
3.2.25 During the formal consultation period, the Applicant continued to carry out
survey work of the land within the Order Limits. This included a full
topographical survey of the access route to Q1 (Green Road) and the laser
mapping of the Q1 and Q6 voids to prepare a more extensive and accurate
picture of the site’s topography. Localised topographical surveys around the
quarries were also completed to supplement the digital terrain and LiDAR
mapping previously undertaken for the entire site.
3.2.26 In addition, the preliminary GI works were also being undertaken at this
time. However the results of these investigations did not affect the Order
Limits.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-12
October 2015
DCO Development - Review 8: Final Design for DCO Application (August
2015)
3.2.27 Since the issue of the Draft ES in February 2015, a final series of further
changes have been made to the Development design and the Order Limits.
These have been made in response to comments received through the
formal consultation process, and to also reflect a reduction in the extent of
land take required for the DCO. Changes to the Development design have
also occurred as a result of the extensive mapping and data collection
exercise. The overall land area within the Order Limits was reduced to
91.24ha. Further details of the amendments made at this design review
stage are provided below.
Increase in Storage Capacity
3.2.28 Since the submission of the Draft ES, the mapping of the quarry voids has
identified the potential to increase the storage capacity from 1,100,000m3 to
up to 1,300,000m3. This increase in potential storage capacity does not
materially change the Development as consulted on in February 2015. Both
GC and NRW were informed of this capacity change in a meeting held on
the 15th July 2015.
3.2.29 The increase in reservoir capacity will deliver an increase in energy
generating capacity from 600MWh to up to approximately 800MWh. The
overall output capacity of the Development remains at up to 99.9MW (as
the increased storage capacity will allow the facility to operate for a longer
time period).
3.2.30 It must be noted that the increased storage capacity has not been achieved
through any changes to the overall size of the dams or the above ground
buildings (such as the power house). It is purely a result of the greater
volume of the reservoirs being confirmed which increases the length of time
the scheme can operate at its maximum output of 99.9MW.
Changes to Material Volumes
3.2.31 The detailed topographic and digital mapping survey also identified that
whilst the void at Q1 is larger than previously estimated, Q6 is smaller than
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-13
October 2015
originally estimated. At Q6, this is due to the presence of a number of
geological intrusions below the surface of the water identified through the
bathymetric survey - these intrusions will need to be removed to create the
reservoir at Q6. In order to provide the equivalent storage capacity in Q6 as
Q1, up to approximately 650,000m3 of screened unsuitable material will
need to be moved from Q6; all suitable virgin material will be used for the
construction of the Q6 dam.
3.2.32 SPH therefore undertook a design review, under which alternative storage
areas for spoil material were considered. It was considered that any
potential storage would potentially have an adverse visual effect and be in
closer proximity to residential dwellings and private water supplies. In
addition, the lack of available space to store the excess material
permanently in the vicinity of Q6 rendered this option unviable.
3.2.33 In full recognition of the previous commitment not to transport excess
material through Waunfawr, it is therefore proposed that the excess
material not utilised in the construction of the Q6 dam will be transported
through the penstock with a conveyor. Excavation of the penstock utilises a
conveyor for removal of excavated material, and this conveyor will be
connected to run the full penstock length between Q6 and Q1 to carry
material. This material will then be deposited within the proposed slate
mounds at Q1.
3.2.34 The material excavated from Q6 will result in an increase in the volume of
the slate mounds at Q1 from up to approximately 690,000m3 to up to
approximately up to 935,000m3. However, the slate mounds still remain in
the same orientation as approved previously and as per the photomontage
of Viewpoint 2 Moel Eilio (see Volume 4 Figure 6.4b). The excess slate
mounds will occupy a slightly larger footprint than previously proposed, but
will remain 4m away from the nearest public right of way (and their
associated permanent diversions), 10m away from the Nant Y Betws and
2m away from the Order Limits boundary in any other non-constrained
areas. The use of detailed terrain data has confirmed that there is sufficient
space to accommodate this increase and the landscape and visual impact
assessment has confirmed that there are no additional effects.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-14
October 2015
Changes at Q6 and Pumping Station
3.2.35 To enable the construction of the potential bifurcation valve, a secondary
temporary access shaft and access tunnel will be sunk to enable
excavation. This will be in addition to the main turbine shaft and tailrace but
will not be used during operation and so will be removed after construction.
3.2.36 Whilst there was no change in the Order Limits, the location of the pumping
station was moved further back from Llyn Padarn to an area of vegetation
adjacent to the main car park. A secondary alternative location is also being
investigated and is subject to ongoing discussions with utility companies
regarding easements. This alternative location is immediately adjacent to
the toilet block in front of the access to the bombstore. The DCO Work
Plans have accounted for this flexibility should the secondary option be
feasible from an easement and engineering perspective.
3.2.37 The scheme at Design Review 8 (the Development subject to the DCO
application) is shown in Figure 3.11 below.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-15
October 2015
3.3 Rochdale Envelope
3.3.1 As the Development has evolved since the grant of planning permission for
the approved scheme, further investigation into the proposed engineering
design has been undertaken. In light of this, sufficient flexibility has been
built into the DCO to allow for the final design to reflect the most appropriate
construction techniques identified for the delivery of the Development. This
flexibility may be required to address unexpected constraints, such as
ground conditions and alternative construction methods.
3.3.2 As certain aspects of the Development still require design flexibility, the
DCO application, and therefore the EIA, is based on the application of
maximum and, where relevant, minimum parameters or limits of deviation.
These include the tunnelling method, the height of dams, the location of the
pumping station, the horizontal and vertical alignment of the penstock, and
the internal configuration of the power house. In light of this, it was
necessary for the technical assessments to assess an ‘envelope’ within
which the works will take place.
3.3.3 To remain in accordance with the EIA regulations it is essential that the
parameters are as ‘“limited” as possible to ensure that the ‘likely significant
effects’ are identified, rather than unrealistically amplified effects, which
could be deemed to be unlikely. It was proposed to use maximum and
minimum parameters for the Development in each relevant technical
assessment.
3.3.4 The final Rochdale envelope parameters are provided in Table 4-1:
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-1
October 2015
Table 4.1 – Rochdale Envelope Parameters
Area Description
Q1
Maximum elevation of dam of 395m AOD to crestPlan width 150m and length 371mMax volume of 1,300,000m3
Max water level 392m AOD
Excess SpoilsMounds Max combined volume of 935,000m3
Penstock
To be tunnelled within 114m buffer and between a maximumelevation of 330m AOD to a minimum depth of 55m AODUp to 1600m long within Order Limits (plan length) but potentiallyup to 1800m to allow for any underground deviations, and 4.5minternal diameter
Tailrace Up to 160m long Tailrace, 4.5m internal diameter
Q6
Maximum elevation of 156m AODPlan width 95m and length 210mMax volume of 1,300,000m3
Max water level 154m AOD
Power House 15m high to apex x 27m wide x 60m long
Turbine HallTwo underground turbines with maximum electrical output of up to99.9MWVolume of excavation approximately 100,000m3
Switchgear 10m high to apex x 18m wide x 30m long
Transformer 7m wide x 7m long x Assumed to be 10m high
GIS Substation12m high to apex x 12m wide x 30m longGas Insulated
PumpingStation 1.6m high x 2m long x up to 0.8m deep
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-2
October 2015
3.4 Alternatives
Engineering Alternatives
3.4.1 Throughout the design evolution, alternatives have been considered. These
are outlined in detail in Sections 3.6 – 3.7 of the Final ES and are
summarised below:
The use of Llyn Padarn as the tailpond – whilst the potential optimal
solution in terms of engineering, this was discounted early in the scheme
development due to its highly sensitive, environmental, ecological and
social importance;
An alternative to the movement of material offsite through Waunfawr
resulted in the creation of the excess slate mounds and internal
conveyor from Q6;
The underground excavation of the penstock was confirmed on the basis
of significantly adverse visual, environmental and archaeological effects
from an open cut alternative;
Routing of the underground penstock to avoid any potential geotechnical
instability issues from drilling under existing slate mounds and close to
quarries contained highly sensitive and protected ecological features;
and
Placement of the discharge outlet into Llyn Padarn above the
thermocline to avoid any potential effects on the Arctic Char.
Alternatives to the site at Glyn Rhonwy
3.4.2 As required by the Overarching National Policy Statement for Energy (EN-
1) and as advised by the SoS in Section 2.56 of his Scoping Opinion
(February 2015) consideration has been given to alternatives to the
Development as proposed in the DCO application. The following section
details why SPH selected the Glyn Rhonwy site for the Development over
other potential locations.
3.4.3 The technologies, plant and construction methodologies to be used, where
definable at this stage of the development process, are detailed within the
following section in this NTS and ES Chapter 4 Project Description.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-3
October 2015
Alternative construction methods and technologies to those assessed in the
ES were considered; however, they have not been carried forward or
selected for the final design for various reasons, typically due to their
engineering inefficiency and non-compliance with best practice guidelines.
3.4.4 Sites suitable for pumped storage are limited by the need for specific
physical characteristics. Importantly, pumped storage requires at least two
or more quarries or reservoirs where water can be released from a high to a
low elevation. An initial source of water is also required and sites need to be
reasonably close to existing electrical connections.
3.4.5 The feasibility study work undertaken by the Applicant for the development
of pumped storage included a detailed mapping exercise undertaken to
examine the feasibility of pumped storage throughout Great Britain, against
key indicators including:
the geology, ground conditions and terrain;
accessibility;
safety and feasibility of construction;
the physical shape and sizes of the reservoirs and requirements for
dams;
the distance between the reservoirs and the distance to the transmission
grid;
the environmental sensitivity of the site; and
whether any impacts of the development could feasibly be designed out
or mitigated.
3.4.6 This exercise identified a number of locations where pumped storage is
considered feasible, including Glyn Rhonwy. However, Glyn Rhonwy was
identified as a highly suitable location for pumped storage for several
reasons:
There are two quarries separated by a large height difference but
geographically close to each other;
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-4
October 2015
The local geology of the Llanberis Welsh Slates formation is a
reasonably impermeable seam, the use of which has already been
proven by the Dinorwig Pumped Storage facility; and
The site is only 7km from a connection point to the electricity network,
which, given the other critical criteria, is considered to be relatively close.
3.4.7 The Gwynedd Unitary Development Plan (UDP) (2001 - 2016) specifically
identifies pumped storage (Policy C27) as a suitable use on the previously
developed land at Glyn Rhonwy Redevelopment Site (Policy C6).
Do Nothing Scenario
3.4.8 Pumped storage provides fast response energy in times of peak demand.
Without this ability to rapidly respond to peak demand the UK would rely
increasingly on baseload thermal power stations and inflexible forms of
renewable energy, such as wind, to provide energy whether it is required or
not. This would lead to significant inefficiencies and unnecessary green
house gas emissions through unnecessary burning of fossil fuels.
3.4.9 NPS EN-1 supports the use of technologies such as pumped storage under
the classification of “electricity storage” to provide back up to an energy
market increasingly supplied by less predictable renewable energy sources.
Section 3.3.12 of NPS EN-1 states
‘There are a number of other technologies which can be used to
compensate for the intermittency of renewable generation, such as
electricity storage, interconnection and demand-side response, without
building additional generation capacity. Although Government believes
these technologies will play important roles in low carbon electricity system,
the development and deployment of these technologies at the necessary
scale has yet to be achieved. The Government does not therefore consider
it prudent to solely rely on these technologies to meet demand without the
additional back-up capacity. It is therefore more likely that increasing
reliance on renewable will mean that we need more total electricity capacity
than we have now, with a larger proportion being built only or mainly to
perform back-up functions.’
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-5
October 2015
3.4.10 There are limited sites across the UK which are deemed suitable for
pumped storage. Making use of the Glyn Rhonwy site to provide electricity
storage capacity will make an important contribution to the delivery of a low
carbon electricity system in the UK, as outlined in NPS EN-1. In a ‘Do
Nothing Scenario’, this contribution would not be made.
Project Optimisation
3.4.11 This EIA assesses the worst case scenario by making reasonable
assumptions based on current knowledge and engineering design. The
engineering design has been undertaken and refined where possible based
on the information gained to date and there will be elements which will be
subject to detailed design and further site investigation works.
3.4.12 However there is also the potential for opportunities within the design for
engineering improvements and optimisation. These are indentified as
follows:
Turbine Shaft - The turbine shaft as shown in ES Volume 4, Figure 4.11
is considered the maximum extent of excavation. However the turbine
shaft can be optimised by excavating two smaller individual shafts or a
thinner single shaft opening into a larger underground turbine hall.
Therefore the assessment has been made on the worst case
engineering option.
Material to be excavated - The volume of material to be excavated has
been derived using a bulking factor of 1.6. This is considered to be a
conservative assumption and any lesser value would be considered an
improvement.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-1
October 2015
4.1 Development Overview
4.1.1 The Development will cover an area of 91.24ha. The Development consists
of the following components:
one headpond (Q1), its dam, access shaft and spillway infrastructure to
the Nant Y Betws;
one tailpond (Q6), its dam, access shaft and spillway infrastructure to
Llyn Padarn;
a pumping station at Llyn Padarn;
a power house at Glyn Rhonwy Industrial Estate Platform 5 (south of
Q6);
a penstock (connecting Q1 to the power house); and
a tailrace (connecting the power house to Q6).
4.1.2 Q8 does not form part of the Development but will be in close proximity to
the Order Limits. This is shown in Figure 4.1 of this NTS.
4.1.3 Q7 is included within the Order Limits due to some localised reprofiling
which may be needed around Q7 for the construction of the Q6 dam and
continuation of the existing access road to the upper platforms. A retaining
wall will be built to maintain structural integrity for the road. It is proposed
not to infill or enter Q7 other than to seal connecting tunnels.
4.1.4 The following sections provide a description of the key components of the
Development, construction methods and programme. These sections also
highlight the status and progress of certain elements of the design including
those that are subject to detailed design or those that have a lesser degree
of flexibility. Working areas are allocated as per the submitted Works Plans
(Document 2.04).
4.1.5 The Development is illustrated in Figures 4.1 to 4.16 within Volume 4 of the
Final ES, and on the indicative plans, elevations and sections submitted as
4 PROJECT DESCRIPTION
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-2
October 2015
Documents 2.05 and 2.06. These drawings provide an indication of the
Development proposed based on the parameters assessed within this ES.
Headpond – Q1
4.1.6 The headpond will be formed at Q1 by the construction of a dam across the
south western side of the quarry. The headpond will have an approximate
volume of 1,300,000m3 of water. The dam will have a maximum elevation of
395m AOD. The normal maximum operational water level is 392m AOD.
The overflow level is 393m AOD which provides up to 1m of freeboard for
operating water level fluctuations before any overflow (spilling) would occur.
A further 2m of freeboard above the overflow is provided, primarily for wave
action.
4.1.7 Externally, the dam will be landscaped using slate and profiled so as to
appear similar to the slate mounds which surround the existing quarries. It
is likely to have a slope of between 1:1 and 1:2 although this is subject to
detailed design and agreement from the Construction Engineer appointed
under the Reservoirs Act.
4.1.8 To make the quarry safe and operable as a reservoir, stabilisation and
lining of the quarry may be required, once access has been made by
battening platforms into the quarry sides.
4.1.9 Stabilisation works will include the remodelling and reprofiling of the current
quarry edges to remove the fractured rock face and provide a smoother
operational surface. The use of rock anchors in appropriate locations to
stabilise the quarry sides will be undertaken as required. The quarry may
also need to be lined to reduce or prevent water loss through natural
seepage.
4.1.10 A freestanding combined overflow and relief valve outlet structure (or draw-
off tower) will be constructed adjacent to the Q1 dam and within the
reservoir. The overflow is provided in case of failure of the pump system or
cessation of generation which would result in natural filling of the reservoir.
The relief valve outlet (also commonly known as the 'scour' and shown on
drawings as such) provides a means of draining the reservoir to the level of
the base of the dam if required in an emergency situation.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-3
October 2015
4.1.11 The spillway infrastructure to the Nant Y Betws will consist of two pipes –
one 800mm diameter drainage pipe and a 400mm diameter scour pipe
which will be within an enclosed spillway infrastructure channel.
Tailpond – Q6
4.1.12 The tailpond at Q6 will be formed by the construction of a dam across the
north eastern end of the quarry following stabilisation and access works to
make the quarry operationally safe and functional. The dam will have a
maximum elevation of 156m AOD. Q6 would also hold a maximum volume
of up to 1,300,000m3 of water. The maximum normal operational water level
is 154m AOD. The overflow level is 154.5m which provides up to 0.5m of
freeboard for operating water level fluctuations before any overflow (spilling)
would occur. A further 1.5m of freeboard (above the overflow) is provided,
primarily for wave action.
4.1.13 In a similar construction method to Q1, the dam at Q6 may potentially be
lined and stabilised. The extent of the stabilisation works at Q6 may affect
the existing slate mound to the north of Q6, hence why this precautionary
approach to the extent of the Order Limits.
4.1.14 A freestanding combined overflow and relief valve outlet structure (or draw-
off tower) will be provided within the Q6 reservoir. This would generally
operate as per the overflow and relief valve (or ‘scour’) tower in Q1. The
relief valve outlet or scour pipe also acts as a rising main for water
abstraction from Llyn Padarn to Q6.
Removal of Water within the Quarries
4.1.15 Both Q1 and Q6 hold water within the existing quarry voids. Bathymetry
surveys estimate a depth of 7m in Q1 and 17m in Q6. Water sampling for
determining water quality has been undertaken within the quarries and
more details are provided in ES Chapter 9 Water Resources.
4.1.16 Water in Q1 will be pumped out and discharged to Nant Y Betws. If
required, the water will be passed through settlement lagoons and / or a
‘Siltbuster’ (or similar) to minimise the discharge of suspended solids. There
is up to approximately 100,000m3 of water within Q6 which will be pumped
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-4
October 2015
out to the adjacent Llyn Padarn via a temporary pumping main. The rate
and volume of any discharges will be undertaken in line with the required
Environmental Permit.
Excavation of the Quarries
4.1.17 Approximately 550,000m3 will be excavated from Q1, most of which is
expected to be utilised within the dam construction. Approximately
360,000m3 will be excavated from Q6, with approximately 90,000m3 to be
utilised in the dam construction.
Stabilisation Works
4.1.18 The sides of the existing quarries Q1 and Q6 are potentially unstable and
require stabilisation to allow the safe construction and operation of the
reservoirs. Where rock excavation is required then stable slopes will be
formed using controlled blasting, with localised remedial works as required.
In other areas, stabilisation works will include the remodelling and
reprofiling of the current quarry sides to form stable rock faces, excavation
will either be by machinery or by controlled blasting or by a combination of
these two methods.
4.1.19 Due to a combination of geological variations and previous quarry workings,
Q1 will be stabilised by reprofiling. The south eastern side is to be retained
as far as possible with any loose material removed.
4.1.20 Stabilisation works on the northern side of Q6 may have the potential to
infringe on the existing slate mound further to the north of Q6. Detailed site
investigation works will confirm if this existing mound is stable and also if
any stabilisation works have the potential to affect it. Should stabilisation be
required this would be achieved by removing the spoil mound area which
could be at risk and temporarily relocating this to another area within the
existing slate mound. Once stabilisation works are complete the area will be
regraded and landscaped.
4.1.21 Other methods of stabilisation potentially include the following:
Removal – removal or scaling of individual features;
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-5
October 2015
Containment – localised containment using rock netting or rock traps
(these can be permanent or temporary fences, ditches or stand-offs);
Strengthening – localised reinforcement using rock anchors, bolts or
dowels; and
Support or protection – localised support using retaining walls,
buttresses, sprayed concrete or anchored beams.
Unexploded Ordnance (UXO) & Sediment Remedial Works
4.1.22 There is documented evidence of the lower quarries being used historically
for military bomb storage and disposal. The bombstore (Q8) was
abandoned after the roof collapsed during World War II, but has been
subsequently remediated by the former Welsh Development Agency. There
are records of ordnance being disposed of in Q6 and also of a later
remediation operation in the 1970s by the Ministry of Defence. However,
there is the potential for unexploded ordnance (and also spent ordnance
scrap) to be present in and around Q6. As part of the development, a
recorded Ordnance Management Strategy will be undertaken in full
consultation with the appropriate authorities in relation to any potential
unexploded ordnance (UXO).
4.1.23 A UXO report is contained within ES Volume 3, Appendices 8.5 and 8.6
which provides further details, with an assessment contained within ES
Chapter 8 Geology & Ground Conditions.
4.1.24 Sediment collection from Q1 and Q6 was attempted in May 2015, however,
no discernible samples were collected due to the absence of any significant
depths of sediment. Once drained, should there be any sediment at the
base of the quarries, this will be tested and investigated for UXO and
contamination. Depending on the level of potential contamination present or
ordnance found, this will be remediated as, and if, required. It is not
proposed to remove any contaminated sediments from the Development.
Quarry Lining Works
4.1.25 For the base of the quarries, one of the following two methods is intended
to be employed (to be confirmed at detailed design):
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-6
October 2015
1. An impermeable High Density Poly-ethylene (HDPE) liner will be
constructed in the base of the quarry. A sub-lining drainage system
would be required to collect and discharge any leakage and
groundwater. This will comprise of the following elements:
Landforming of the base;
A sub-lining drainage system;
Underlying and overlying regulating layers;
Impermeable liner;
Overlying protection geotextile fleece; and
Cover or protection layers.
This would prevent uplift pressures occurring during drawdown of the
pond in generation and would allow the detection of leakage through
the base; or
2. Pressure grouting of the base will be undertaken through boreholes in
the base of the quarry. The grout would fill in any fractures within the
rock mass and therefore reduce permeability.
4.1.26 It is likely that pressure grouting using cementitous grout will be the most
appropriate method for the quarry side slopes. The requirement for side
slope grouting will be confirmed by permeability testing following detailed
site investigation works as part of the enabling stage.
Dam Footprints
4.1.27 The dams will be founded on sound bedrock. This requires any superficial
deposits and existing quarry spoil to be removed prior to dam construction.
The elevation of the bedrock profile is likely to be variable and will only be
confirmed following stripping of the existing quarry spoil. Because of the
difference between existing ground level and bedrock level, the roots of the
dam will extend underground until they meet bedrock. Ground levels will be
restored to at or about the existing ground levels (or as otherwise agreed)
around the edges of the dams.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-7
October 2015
Wave Action and Protection
4.1.28 The dams will have a concrete wave wall running along the crest that the
upstream impermeable membrane will be tied into. Depending on the type
of impermeable membrane used (i.e. if an HDPE geo-membrane is used),
surface protection to the upstream face of the dam may be required through
the placement of a layer of selected rock, able to resist wave action. This
will be underlain by protective and regulating layers between the membrane
and a gradation of materials comprising sand through to crushed rock.
Penstock & Tailrace
4.1.29 The penstock is a pipe which will convey the flow of water between the
headpond and power house (and vice versa). The tailrace (or 'draft tube') is
a pipe which will convey water from the power house to Q6 (and vice
versa). The penstock will include a bifurcation in the approach to the power
house, this is shown in Figure 4.1 of the NTS. These will both be tunnelled.
4.1.30 The penstock will be approximately 1600m long, stretching from Q1 to Q6
(as shown on Figure 4.1) and have an approximate internal diameter of
4.5m. The length may deviate to a total length of 1800m dependent on
ground conditions.
4.1.31 The proposed excavation method is to use either a Tunnel Boring Machine
(TBM) or drill and blast. However due to the presence of potentially doleritic
intrusions within the bedrock, drill and blast may be used, or a combination
of the two approaches. This will be confirmed upon instruction of a Principal
Contractor (PC).
4.1.32 The outlet from Q1 is at an elevation of approximately 335m AOD
(approximately 50m below current ground levels). Where the penstock
enters the shaft for the turbine hall at the power house it is at an elevation
of approximately 60m AOD (approximately 90m below current ground level)
It should be noted that the elevation of the penstock may change
underground during detailed design of the scheme dependent on the
ground conditions and particular technical requirements, including the
pump-turbines selected. Construction of the penstock is likely to take up to
12 months.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-8
October 2015
Power House
4.1.33 The power house is an above ground building with offices, plant hall,
crane(s), workshop, welfare facilities and a control room. This building is
approximately 15m high to its apex, 60m long and 27m wide. The power
house straddles the shaft that contains the turbine hall which houses the
turbine-pumps and generators.
4.1.34 It is likely to be faced and roofed in slate but the final external design and
appearance will be subject to a DCO Requirement. It is expected that the
power house will be manned by up to approximately 35 people during
normal operation. The turbine hall will house turbines with a combined net
output capacity of 99.9MW. Due to the depth of the turbine hall, specialist
heavy equipment will be needed to lift the turbine and associated
infrastructure into position at depth.
4.1.35 The power house is also likely to contain the switchgear equipment which is
required to connect the Development to the electricity network.
Pumping Station
4.1.36 The pumping station is required so that water may be abstracted from Llyn
Padarn into Q6 in order to fill up the Development as part of the
commissioning process and also to 'top up' levels, or discharge any excess
water, during operation. The pumping station will only be operational when
water is required to be pumped from Llyn Padarn into the Development and
will not be operational when water is discharged to Llyn Padarn.
4.1.37 In response to consultation responses, the location of the pumping station
has been located away from the edge of Llyn Padarn, within an area of
vegetation adjacent to the car park. A secondary location is being
investigated further back towards the existing toilet block and is subject to
ongoing discussions with utility providers.
4.1.38 The pumping station will comprise of a below ground wet well, valve
chamber and cable pit, and above ground control box / kiosk. The majority
of the structure is below ground and can be located so as to avoid any
areas normally used by users of the car park and lagoon area.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-9
October 2015
4.1.39 The pumping station size will depend on the final location but will be
completely underground and located at depth. A small above ground
control box would be present and this is likely to be approximately 2m long
by 1.6m high by up to 0.8m deep and would resemble a communications
control box, most likely covered in British Standard 14-C-39 Green (subject
to DCO Requirement). A manhole cover and grid plate is also required to
gain access to the pumping station for maintenance purposes.
4.1.40 There would be no operational requirement for fencing around the control
box and no operational lighting. The underground pumping station will be
equipped with sufficient acoustic attenuation to minimise any disturbance
above ground.
Spillway Infrastructure
4.1.41 The spillway infrastructure contains an overflow from Q6 which will be
connected to Llyn Padarn directly with an approximately 800mm diameter
pipe. The spillway infrastructure also contains a combined scour and rising
main as a separate pipe approximately 450mm in diameter.
4.1.42 The spillway infrastructure will be culverted under the Q6 dam and will be
buried in an opencut trench for the full route to the pumping station and
then to Llyn Padarn. The indicative route around the south side of the
bombstore, and across the A4086, to the pumping station (which is
bypassed by the overflow and relief or scour outlet) and then to Llyn Padarn
is shown in Figure 4.1 of the NTS.
4.1.43 Valving will allow the relief or scour to discharge direct to Llyn Padarn
(bypassing the pumping station). The purpose of the overflow is to
discharge excess water collected within the reservoir(s) during operation.
The purpose of the scour is to allow drawing-down of the water level in the
reservoir to the base of the dam, including in an emergency situation. Any
relief or overflow discharges will be gravity fed.
4.1.44 As part of the 2012 ES, it was agreed that spillway infrastructure would be
screened to avoid any impacts to fish, be located above the thermocline,
approximately 5m below the minimum recorded water survey level to avoid
impacts to protected fish species, Arctic Charr, and impacts to recreational
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-10
October 2015
users. Surface buoys would mark the location of the pipe terminals. There
will be a fine mesh screen on the pipes to prevent any wildlife, detritus or
material from entering the pipe.
4.1.45 As it will be at depth, the working environment will be sheet piled to ensure
a safe, water tight environment for the installation of the spillway
infrastructure. This will be approximately 5m x 20m.
4.1.46 Where the spillway infrastructure enters Llyn Padarn through the tree line,
the working width will be minimised as much as possible to minimise any
impacts to tree root systems. A tree survey will be undertaken prior to
construction commencing to microsite the pipe through this area. Any trees
that are removed will be subject to mitigation measures outlined in the
Habitat Management Plan (HMP).
4.1.47 Where construction enters Llyn Padarn, access around this immediate area
will be temporarily restricted to maintain a safe environment to the users of
Llyn Padarn. This is expected to last up to 12 weeks.
4.1.48 There are potentially two options for the construction of the spillway
infrastructure into Llyn Padarn, as follows:
Option 1
4.1.49 Using the coffer dam area, as outlined above, the pipes will be “strung out”
and sunk in place with pre-cast concrete weights.
4.1.50 Once the pipe is laid and the dry area reflooded, reinstated and coffer dam
removed, access will be allowed. It is expected that this element of the
construction of the pumping station and spillway infrastructure will be short
and temporary in nature. It is paramount that the health of safety of the
construction is managed correctly due to the nature of the works.
Option 2
4.1.51 A smaller coffer dam would be used but a small boat or barge would then
be used to string out the pipes and then connect to the onshore pipework
once the pipe is sunk using pre-cast concrete weights. Access to this area
would again be temporarily restricted whilst these works are ongoing to
maintain the health and safety of users and construction workers.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-11
October 2015
4.1.52 Detailed information on the construction method is contained with section
4.6 of Chapter 4 Project Description of the ES.
Commissioning
4.1.53 Once the pumping station and spillway infrastructure is in place, pressure
testing will be undertaken. This will be a temporary occurrence and last a
few weeks. Once the Q6 reservoir is ready to receive water, the abstraction
from Llyn Padarn will commence.
4.1.54 On the basis of 1,300,000m3 required, this will take 394 days on the basis
of 3300m3 per day. An abstraction license has been granted on the basis of
1,100,000m3 and a variation to this license will be submitted to NRW prior
to the start of the Examination in relation to the1,300,000m3 volume.
Programme
4.1.55 It is proposed not to work within the summer school holidays to minimise
any significant adverse effects to users of Llyn Padarn and the lagoons.
Outside summer school holidays, it is proposed to construct the overflow
and pumping station sequentially to minimise any disturbance to users of
Llyn Padarn and the lagoons. A small construction compound may be
required but access for cycle and vehicle users on the shore will not be
impeded, where necessary diversions will be implemented. It is not
proposed to block off or sever any existing routes for Llyn Padarn users but
some traffic management will be in place during critical activities.
4.1.56 There is no requirement for night time lighting during construction outside
working hours other than for security purposes.
Electrical Connection
4.1.57 The Development will be connected to the electricity distribution system
network via a new electrical connection. This will be exported from an
onsite substation to an offsite connection terminating at Pentir. This is
shown on Figure 4.2 of the NTS
4.1.58 This is likely to be a 132kV connection, which as associated development in
Wales, will not be consented under the Act. It may be possible to complete
the works under SP Manweb’s permitted development rights, or through the
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-12
October 2015
formal grant of planning permission under the Town and Country Planning
Act 1990. Any application for the appropriate consents will be made by
SPH, an Independent Connection Provider (ICP) or SP Manweb as
appropriate. A high level cumulative assessment has been undertaken on
the indicative route and this is assessed in ES Chapter 17 Cumulative
Effects. This assessment is based on the current grid connection
agreement which was applicable at the time of submission.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-13
October 2015
4.1.59 SPH has committed to this connection being provided underground and the
current grid connection offer being discussed with SP Manweb seeks an
underground connection.
4.1.60 The switchgear building is adjacent to the power house and is also likely to
be faced and roofed in slate. The final building materials and finishes will be
subject to a DCO Requirement. The substation will contain 11kV and 400V
electrical distribution equipment and will measure approximately 10m high,
18m wide and 30m long.
4.1.61 The external transformer compound will have provision for a single
11kV/400V transformer and two 11kV/132kV transformers for the 132kV
electrical connection. Only the building required to house the substation
equipment will be included within and authorised by the DCO.
Permanent Excess Slate Mounds
4.1.62 Up to two excess slate mounds will be created south of Q1 with a volume of
up to 935,000m3. This will consist of a new slate tip to the south of the
existing mound, and an extension to the existing mound.
4.1.63 Material will be generated from the excavation of the Q1 and Q6 quarries to
form the headpond and tailpond reservoirs. This material will be crushed
and graded with only suitable material utilised in the construction of the
dam(s), with less suitable material used for landscaping purposes or
incorporated into the new excess slate mounds south west of Q1.
4.1.64 Excess material generated at Q6 will be transported by a conveyor within
the completed penstock for placement within the excess slate mounds.
Access
4.1.65 Access to Q1 will be via the existing unclassified road (known as the Green
Road) from the A4086 and through Waunfawr. Upgrades will be made from
the A4086 to the Q1 site compound with temporary access tracks from the
compound to the quarry. These upgrades are classed as associated
development and so will be subject to a planning application to Gwynedd
Council. Based on dialogue with the Council to date, the road will retain its
single track status with several passing places being constructed for vehicle
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
3-14
October 2015
movements. The improvements to Green Road will be undertaken before
construction and then fully reinstated to adoptable road standards once
construction is complete. Further detail can be found in ES Chapter 12
Traffic and Transportation.
4.1.66 Access to Q6 will be through the existing road network off the A4085 to
within the existing Glyn Rhonwy Industrial Estate. Minor amendments may
be made to the A4085 and Industrial Estate junction for delivery of plant
and materials during construction although these will be reinstated post-
construction, unless their retention is agreed with the Highways Authority.
4.1.67 Ffordd Clegir, which runs between Q5 and Q6, will not be used for any
construction or operational traffic, although it may be subject to a temporary
closure for health and safety reasons on critical activities. Advance notice
will be given to the local residents, appropriate signage provided on the
road, and approval of GC as Highways Authority will be gained prior to any
works commencing.
4.2 Construction Phase
4.2.1 The construction phase is expected to last approximately 4 years from
commencement of works. Table 4-1 outlines an indicative simplified
programme of the Development. Please note that several activities have
been incorporated together which in reality will be distinctly separate in the
programme. A PC has not yet been appointed, and so it is envisaged that
the following indicative construction sequence will be followed.
Glyn Rhonwy Pumped Storage Development ConsentOrder
6.01 Non Technical SummaryVolume 1
4-15
October 2015
Table 4-1 Indicative Construction ProgrammePhase Location Activity Year 1 Year 2 Year 3 Year 4
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4Enabling Works Q1 & Q6 Offsite access road improvements, creation of replacement temporary car park
Establish construction compounds including fencing and security.Onsite general Mobilisation (and potential GI works) and site clearance
Dewatering Q1 & Q6 Dewatering of quarriesReservoir Works Q1 Access made to quarry floor and reprofiling including blasting, drilling, lining,
excavation and rock bolting and grout curtain constructionPartial removal of existing spoil mounds and crushing of excavated materialsConstruction of damConstruction of scour tower, overflow / relief valves and spill, inlet / outlet worksand chambersPlacement of excess material in new slate moundsConstruction of spillway infrastructure to Nant Y Betws
Q6 Access made to quarry floor and reprofiling including blasting, drilling, lining,excavation and rock bolting and grout curtain constructionPartial removal of existing spoil mounds and crushing of excavated materialsUXO Remedial worksConstruction of dam and placement of excess materialConstruction of scour tower, overflow / relief valves and associated pipework, inlet/ outlet works and chambersFill reservoir from abstraction and rainfall
Pumping Station Llyn Padarn Construction of spillway infrastructure to Llyn Padarn and pumping stationPenstockConstruction
Penstock Sink launch shaft from platform 5Excavation of penstock, bifurcation value and chambersLine tunnel
Conveyor Setup and movement of material from Q6 to Q1Power House Platform 5/6
Glyn RhonwyIndustrialEstate
Sink turbine shaft and construction of tailraceLining works and fit out shaft infrastructureConstruct power house superstructure, including crane and fit out power houseInstall turbines and electrical infrastructure below ground and above ground.Test and commission
De-mobilisation Q1 & Q6 Removal of site compounds and equipment from site. Reinstatement of accessroad improvement works.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
4-16
October 2015
4.2.2 Site preparation and enabling works will be required prior to
commencement of the main construction phase. These include:
Highway improvements to be completed;
PRoW diversions to be implemented;
Potential secondary ground investigation (GI) works; and
Mobilisation to site and establishment of temporary compounds.
4.2.3 Temporary construction buildings and laydown areas will be required.
These will be located within the Order Limits and consist of offices, meeting
rooms, a car park, storage and laydown areas for construction equipment
and vehicles, and welfare facilities for workers. The indicative location of
these temporary features is shown in Figure 4.1 of the NTS.
4.2.4 A variety of standard construction plant and equipment will be required as
part of the construction activities and these include (but are not limited to):
Low loaders – for delivery of plant and equipment;
Moxy – dumper trucks for transportation of materials internally in
quarries and externally to storage areas;
Wheeled and tracked 360 Excavators - for excavations works;
Mobile crushing and screening plant;
Bulldozers;
Graders;
Compaction plant; and
Cranes.
4.2.5 Other machinery and equipment may include, but not be limited to::
Concrete batching plant;
Welfare units and portacabins;
Pipework (in sections);
Temporary fencing;
Generators (at Q1 for electrical supply unless locally available); and
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
4-17
October 2015
Bowsers.
4.2.6 Should TBM be used as the penstock excavation method, this will be
brought to site in a modular fashion on the back of a low loader.
4.2.7 The 2012 ES proposed a Construction Environmental Management Plan
(CEMP) which the PC will be required to operate under. This has evolved
into a CoCP submitted in support of the DCO Application. It will implement
the mitigation measures identified within the 2012 ES, the planning
conditions attached to the T&CPA permission for the approved scheme,
and any additional measures identified in the ES. Further details are found
in Chapter 16 Environmental Management of the ES.
4.2.8 Construction working hours will be 07:00 – 19:00 Monday to Friday and
07:00 – 13:00 Saturday. Where construction activities are required outside
these hours, then this will be undertaken only with the prior approval of GC.
4.2.9 The number of construction staff on site will vary according to the
construction phase and activities being undertaken, and will be confirmed
by the PC upon instruction. However it is expected that up to 250 people
will be employed during the construction phase at its peak, after which it will
then generally decrease as construction is progressed through to the
commissioning phase. However, this will be subject to the requirements of
the PC and therefore could change.
4.2.10 Security lighting will be required within the Development during
construction, especially on the temporary compounds and storage areas.
This lighting will have due regard to nearby residential properties and
sensitive habitats and species. Workplace lighting at the onsite temporary
compounds will have due regard to UK guidelines on construction lighting,
namely Health and Safety Executive guidance HSG38 Lighting at Work and
also Bat Conservation Trust Statement on the Impact and Design of
Artificial Light on Bats (May 2011).
4.2.11 Access around the two working areas and the existing and diverted PRoWs
will be maintained during construction wherever possible to recreational and
common land users. The car park at Q1 will be temporarily relocated near
the temporary PRoW diversion so that these links can still be used.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
4-18
October 2015
4.2.12 Temporary closures of the PRoWs may occur and access to land may be
controlled during certain times in the construction phase for critical path
activities such as blasting or drilling. This is due to health and safety for
users, residents and the onsite workers. Appropriate signage will be
deployed on all PRoW diversions and the appropriate notice provided for
any closures.
4.2.13 In addition, the two working areas around Q1 and Q6 will have 24 hour
security to prevent public access with appropriate fencing, signage, lighting
and CCTV installed. There will no workers villages or overnight
accommodation at either temporary compound during construction. The
only 24 hour attendance will be security.
4.3 Operational Phase
4.3.1 The indicative operational lifespan of the Development is 125 years. The
Development will have continuous operation throughout its lifecycle except
for planned maintenance.
4.3.2 SPH estimate that approximately up to 35 people will be employed during
the operational lifetime of the Development to perform operational and
maintenance tasks. Therefore, operational traffic is limited to staff travel and
delivery of ancillary materials and plant during the Development lifespan.
4.3.3 As per the construction phase, the operational lighting strategy will have
due regard for residents, ecology and health and safety. It is proposed that
this is agreed as part of a DCO Requirement.
4.3.4 Once the Development is fully commissioned with 1,300,000m3 of water,
this will pass between Q1 and Q6 in order to provide the battery storage
and generate electricity at peak times.
4.3.5 Operational discharges will be intermittent and dependant on rainfall and
operational requirements. An essential component of any raised reservoir is
the ability to lower the water level behind the dam (draw-down); emptying
the reservoir to the point where there is no hydraulic load on the structure.
For the purpose of reservoir safety this facility must be available at all times.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
4-19
October 2015
4.3.6 At times of normal operation, the main and primary mechanism for draw
down for the Q1 reservoir is through the penstock to Q6. The penstock pipe
has the capacity to provide draw-down of the reservoir in approximately 7
hours at a rate in the order of 46 m3/s. This is more than adequate to serve
the draw-down need for the Q1 reservoir.
4.3.7 At times of normal operation, the main and primary mechanism for draw
down for the Q6 reservoir is through the penstock to Q1, using the turbines
in the turbine house in pumping mode. However, because of the variables
in operation and maintenance of the scheme, and the need to have a draw-
down capacity at all times; it is considered prudent to include a facility to
lower the reservoir independent of the penstock and powerhouse.
4.3.8 Therefore both dams provide a secondary method for draw down, with
water being discharged to the Nant y Betws at Q1 and to Llyn Padarn at
Q6. This will only occur if the penstock is unavailable. The relief valves are
sized to allow the reservoir(s) to be drawn down to 50% of the volume
impounded by the dam(s) within 7 days. These discharges would be
controlled through the required discharge consent.
4.3.9 The relief valves are manually activated i.e. they will only be opened when
the operator intervenes. Such intervention will only take place in one of two
scenarios as follows:
a) when the there is a need to lower the water level behind the dam and
the water cannot, for whatever reason, be drawn down through the
penstock i.e. it would only be in an unusual situation when drawdown of
the reservoir is required and this cannot be achieved through the
penstock.
b) for maintenance; to ensure the valves are operational as part of the dam
safety regime, it will be necessary from time to time to briefly operate the
valves.
4.3.10 In short, emergency valve operation is considered an extremely unlikely
situation and, other than infrequent small amounts for valve testing, are not
part of the normal operation of the scheme and would be very unlikely,
possibly never, in an unplanned situation.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
4-20
October 2015
4.3.11 In the maintenance scenario (b above) the discharge would be managed as
per the requirements of the discharge consent. In this scenario, the valve
can be used in a controlled manner, when the flows in Nant-y-Betws and
the Afon Gwyrfai are low enough to accept the flows from the reservoir
without causing an increased risk of flooding from the watercourses.
4.3.12 No water is directly discharged into Llyn Padarn from the turbines.
4.4 Decommissioning
4.4.1 For the purposes of the EIA, it is assumed that decommissioning may occur
after an indicative 125 year operational lifespan. The implications of
decommissioning will be reviewed once it is evident the plant is
approaching the end of its working life.
4.4.2 At the end of the 125 year operational life, the Development will be
decommissioned:
Assessment of any buildings that are to be removed, including ecology;
Removal of all above ground structures, notably the power house;
Water will be drained from Q1 to Q6 and released at an agreed rate and
timescale through the appropriate licensing regime into Llyn Padarn;
Pumping station will be removed, although the overflow pipework at Q6
will remain in situ after being sealed;
Dams and access tracks to remain in situ;
Security fences will remain although access through the dam structures
will be secured;
Penstock pipework between Q1 and Q6 will remain in situ and sealed;
and
Overflow pipework at Q1
4.4.3 It is proposed that due to the anticipated lifespan of the Development, a
Decommissioning Plan will be required by the relevant authorities at the
point of decommissioning this Development. This will therefore be a
Requirement of the DCO.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-1
October 2015
5.1 Introduction
5.1.1 The ES identifies the key environmental topics that have been assessed as
part of the formal EIA process. These are as detailed in Section 2.3 of this
NTS.
5.1.2 For each assessment topic, the ES describes the proposed approach to
assessment, provides existing information on the local environment (the
environmental ‘baseline’ of the surrounding area), and describes the
potential effects on that environment during construction, operation and
decommissioning.
5.1.3 The environmental topic areas reported on in the ES are summarised
below.
5.2 Landscape Character and Visual Amenity
5.2.1 Chapter 6 of the ES contains an assessment of the landscape and visual
effects of the Development. The LVIA has been informed by the production
of a Zone Theoretical Visibility (ZTV) map for the quarry dams and slate
tips, which was undertaken for the 2012 ES.
5.2.2 Based on the ZTV, 12 representative viewpoints were agreed with
Gwynedd Council (GC), Environment Agency Wales (now NRW) and
Snowdonia National Park Authority (SNPA) as part of the 2012 ES. These
12 viewpoints have been used in the ES for the DCO, in order to present
views of the Development in the landscape. The ‘worse case scenario’ is
defined as the views from the most sensitive landscape and visual
receptors with the highest visibility of the Development. The ZTV and
locations of the 12 viewpoints can be seen in Figure 5.1 of the NTS. A
number of photomontages were produced for these viewpoints, showing the
Development as it will look when operational. These are shown in Volume
4, Figures 6.4a to 6.4l of Volume 4 of the ES.
5 SUMMARY OF ENVIRONMENTAL IMPACT
ASSESSMENT
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-2
October 2015
5.2.3 The landscape and visual effects have been assessed during the
construction, operation and decommissioning stages with respect to:
Landscape elements within the Development;
Landscape designations and the Snowdonia National Park;
LANDMAP aspects areas (geological, habitats, visual and sensory,
historic and cultural);
Views (visual amenity).
Effects during Construction
5.2.4 Construction elements and activities will have an adverse effect on the
landscape around Llanberis and the Snowdonia National Park. This effect is
however limited by the screening of the surrounding hills. Construction will
affect views from Moel Eilio, the Llanberis Lake Railway, Cefn Du and
Dinorwig. Screening by vegetation and the limited disruption on the
underlying character or focus of the view mean these effects of the
Development are limited.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-3
October 2015
Effects during Operation
5.2.5 The visual amenity of walkers using Cefn Du will be moderately adversely
affected by the permanent dam at Q1.
5.2.6 Mitigation measures have been integrated into the design as far as
reasonably possible through excavation of the penstock rather than open
trench pipe route; layouts to minimise the effects on vegetation; the
reinstatement of landforms and vegetation and the use of natural screening
to avoid direct views from sensitive viewpoints onto material storage and
the power house. Permanent features and structures such as the power
house will be clad with local materials, and dams and excess spoil mounds
will use slate waste excavated on site to soften their features. Stone walls
will be reinstated wherever necessary and fencing at Q1 and Q6 will be
chosen to reflect existing fencing types.
Effects during Decommissioning
5.2.7 Decommissioning effects will be temporary and of a short duration. The
elements of the Development to be removed at the decommissioning stage
are described within ES Chapter 4 Project Description. The lifespan of the
development is such that the landscape will have evolved during the 125
years and an appropriate restoration strategy will need to be developed
reflecting the future character and visual amenity of the landscape. It is not
considered that the landscape and visual effects during decommissioning
would be greater than the residual effects assessed (in the LVIA) during
summer year 15.
Conclusions
5.2.8 There will be No Permanent Significant effects on the LANDMAP
Aspects, LCAs or landscape designations within the study area.
5.2.9 There will be a permanent Significant adverse residual effect on receptors
at Viewpoint 7 (Cefn Du) due to the close proximity of the viewpoint to the
dam and reservoir at Q1.
5.2.10 No Significant residual visual effects have been identified for the remaining
viewpoints. This is due in part to the limited visibility of the components of
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-4
October 2015
the Development in the wider study area, with much screening provided by
the topography of the study area and wooded nature of the area
immediately surrounding the site. The mitigation measures proposed as an
inherent part of the Development, notably the use of existing slate, will
successfully integrate the development into the landscape context, further
reducing its potential visual prominence.
5.3 Ecology
5.3.1 Chapter 7 of the ES contains an assessment of the effects of the
construction, operation and decommissioning of the Development on
sensitive ecological receptors.
5.3.2 To assess the current ecological conditions at the Development site, the
following surveys and assessments have been undertaken:
Consultation with the County Ecologist and NRW;
Desk based study to identify sites of nature conservation and protected
and priority species in the surrounding area;
Extended Phase I Habitat Survey (which is a habitat classification study)
for the majority of the Order Limits;
Assessment of Bat Potential;
Winter/Hibernation and Summer Bat surveys;
Reptile Surveys;
Amphibian survey;
Great Crested Newts Habitat Suitability Assessment;
Breeding Bird Habitat Suitability Assessment;
Breeding bid surveys;
Winter bird surveys;
Badger surveys;
Otter surveys;
Invertebrate Habitat Suitability Assessment;
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-5
October 2015
Habitat Regulations Assessment – Stage One: Screening;
Freshwater surveys in Q1 and Q6 for diatoms, phytoplankton,
invertebrates, fish and aquatic plants;
Aquatic plant surveys for floating water plantain, spring quillwort and
Canadian/Nuttall’s pondweed;
National Vegetation Classification (NVC) Survey;
Fungi and lichen surveys; and
Arboricultural Assessment.
5.3.3 Further details are provided in the ES Chapter 7 Ecology and its
accompanying appendices in Volume 3 of the ES.
Effects during Construction
5.3.4 The Development will have a permanent residual minor adverse effect on
Llyn Padarn SSSI through the potential very small loss of lake bed habitat
due to the pipe line connection to the lake bed. The effect on Llyn Padarn
SSSI is deemed to be Not Significant.
5.3.5 The Development will have a permanent residual minor adverse effect on
Bwlch-y-Groed Quarry Local Wildlife Site (LWS) through the loss of 9.0ha
(21.9%) low value habitat due to the construction of the spoil heaps and Q1
dam. The effect on Bwlch-y-Groed Quarry LWS is deemed to be NotSignificant.
5.3.6 The Development will have a permanent residual minor adverse effect on
Coed Donen Las LWS and Llwyn Coed Heath LWS through the loss of
10.7ha (16.1%) and <0.001ha (0.001%) respectively of low value habitat
due to the construction of the Q6 dam. The effect on both the LWS’s is
deemed to be Not Significant.
5.3.7 The Development will have a permanent residual minor adverse effect on
Pen Gilfach LWS through the loss of low value habitat to facilitate access
for the construction of the pumping house and outlet pipes. The effect on
Pen Gilfach LWS is deemed to be Not Significant.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-6
October 2015
5.3.8 The Development will have a permanent residual minor adverse effect on
Cefn Du LWS through the loss of 1.0ha (0.3%) low value habitat to facilitate
the construction of a section of the Q1 dam. The effect on Cefn Du LWS is
deemed to be Not Significant.
5.3.9 The Development will have a permanent residual minor adverse effect on
broadleaved semi-natural woodland through the loss of 0.5 ha (10.7%) of
habitat due to the enabling works for the provision of access to facilitate the
construction of the pumping house and lake bed outfall, the construction of
the pumping house, and a section of the Q1 dam. Due to the small loss of
overall habitat and implementation of a CoCP, the effect on broadleaved
semi-natural woodland is deemed to be Not Significant.
5.3.10 The Development will have a permanent residual minor adverse effect on
coniferous woodland through loss of 8.0ha (72.7%) of negligible value
habitat due to the creation of the permanent slate mounds. However, this
area is managed plantation and has been subject to recent felling. The
effect is therefore considered to be Not Significant.
5.3.11 The Development will have a permanent residual minor adverse effect on
semi natural mixed woodland through the loss of habitat due to the enabling
works for the provision of access to facilitate the construction of the
pumping house and lake bed outfall. The effect on semi-natural mixed
woodland is deemed to be Not Significant.
5.3.12 The Development will have a permanent residual minor adverse effect on
dry heath / acid grassland through the loss of low value habitat due to the
construction of the Q1 dam. The effect on dry heath / acid grassland is
deemed to be Not Significant.
5.3.13 The Development will have a permanent residual minor adverse effect on
standing water (oligotrophic water) through the loss of habitat due to the
infilling with water of Q1 and Q6. The effect on standing water (oligotrophic
water) is deemed to be Not Significant.
5.3.14 The Development will have a permanent residual minor adverse effect on
the quarry habitat through the loss of habitat due to the infilling with water of
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-7
October 2015
Q1 and Q6. The effect on the quarry habitat is deemed to be NotSignificant.
5.3.15 The Development will have a permanent residual minor adverse effect on
the spoil habitat through the loss of negligible value habitat due to the
creation of the two dams. The effect on the spoil habitat is deemed to be
Not Significant.
5.3.16 The Development will have a permanent residual minor beneficial effect on
the spoil habitat through the creation of approximately 8.85ha of spoil
habitat. The effect on the spoil habitat is deemed to be Not Significant.
5.3.17 The Development will have a permanent residual minor adverse effect on
the stone wall habitat through the loss of habitat. The effect on the spoil
habitat is deemed to be Not Significant.
5.3.18 The Development will have a permanent residual minor adverse effect on
the Tree Protection Order (TPO) designated area A5 through the loss of
habitat. The effect on the TPO area A5 is deemed to be Not Significant.
5.3.19 The Development will have a permanent residual minor adverse effect on
Arctic Charr through vibration. The effect on the Arctic Charr is deemed to
be Not Significant.
5.3.20 The Development will have a permanent residual minor adverse effect on
reptiles through the loss of habitat (removal of quarries, spoil, grassland,
scrub and woodland). The effect on the reptiles is deemed to be NotSignificant.
5.3.21 The Development will have a permanent residual minor adverse effect on
the Schedule 1 of the Wildlife and Countryside Act bird species, and Birds
of Conservation Concern (BOCC) Red and Amber List bird species through
the loss of habitat (removal of potential nesting habitat through removal of
quarries and woody habitats). Due to the availability of alternative habitat,
and the timing and proximity of the construction activities of the
Development. The effect on the Schedule 1 bird species, and BOCC Red
and Amber List bird species is deemed to be Not Significant.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-8
October 2015
5.3.22 Development will have a permanent residual minor adverse effect on bats
from construction vibration, roost modification, loss of roosts in tunnels,
isolation and fragmentation and operational lighting. The effect on the bats
is deemed to be Not Significant. Development will have a permanent
residual moderate adverse effect on bats from loss of tree roosts. The effect
on the bats is deemed to be Significant.
5.3.23 Ecological mitigation measures are to include:
enhancement of the existing tunnels and bat habitat to mitigate those
lost as part of the Development,
pre-construction surveys,
the employment of an Environmental Clerk of Works,
implementation of a Habitat Management Plan, and
engineering solutions (such as the placement of the outlet into Llyn
Padarn above the thermocline (which is a transition temperature layer
between the mixed layer at the surface and a deep water layer within
a water body) to avoid any adverse effects to fish, namely Arctic Charr
proposed mitigation for bats is outlined the Bat Licence Application
Method Statement.
Effects during Operation
5.3.24 Once operational, there will be a permanent loss of the quarry habitats in
Q1 and Q6 but no other effects from day to day operation.
5.3.25 The Development will have a residual minor adverse effect on Afon Gwyrfai
a Llyn Cwellyn Special Area of Conservation (SAC) through the alteration of
the flow regime, alteration of temperature during the routine discharges,
nutrient enrichment, and introduction of invasive species. The effect on
Afon Gwyrfai a Llyn Cwellyn SAC is deemed to be Not Significant.
5.3.26 The Development will have a residual minor adverse effect on Llyn Padarn
SSSI through the alteration of the hydrological regime, alteration of
temperature during the routine discharges, nutrient enrichment, light spill,
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-9
October 2015
and pollution during routine maintenance. The effect on Llyn Padarn SSSI
is deemed to be Not Significant.
5.3.27 Precautionary measures will ensure that no invasive species are transferred
from Q6 into Llyn Padarn. In addition, should the water within Q6 be found
to be contaminated, prior to discharge to Llyn Padarn, an Environmental
Permit (EP) will be applied for and the appropriate treatment measures
undertaken.
5.3.28 The Development is not expected to influence algal bloom in Llyn Padarn.
Scour and wave action will be minimised by the design and siting of the
outlet pipes
Effects during Decommissioning
5.3.29 The residual effects during decommissioning are likely to be similar to those
identified during construction. However, due to the lifespan of the project
(125 years) it is not currently possible to predict potential and residual
effects on designated sites, habitats and species, as the baseline is likely to
change over this period.
Conclusions
5.3.30 Implementation of the mitigation measures outlined will avoid or minimise
the potential effects on the majority of the ecological receptors. The overall
residual effect is assessed as minor adverse (excluding effects on bat tree
roosts). Therefore the effects are considered to be Not Significant. The
overall residual effect assessment on bat tree roosts only is assessed as
moderate adverse. Therefore the effects are considered to be Significant
in EIA terms. Mitigation measures have been incorporated in the design to
minimise impacts on bats; these are outlined in the bat licence application.
Other European Protected Species Licences will be applied for if required.
5.3.31 A No Significant Effects study (HRA screening assessment) was
undertaken to identify what effects the Development could have on Natura
2000 sites in the surrounding area. This HRA Screening concluded that with
the implementation of mitigation measures the Development will not haveany Likely Significant Effects (LSE’s) on the integrity of Natura 2000
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-10
October 2015
Sites. Therefore, an Appropriate Assessment – Stage Two of the HRA
process – was not required.
5.4 Geology
5.4.1 Chapter 8 of the ES contains an assessment on the geo-environmental
characteristics within the Order Limits. It provides an assessment of the
impacts of the Development on these characteristics during the
construction, operational and decommissioning phases.
5.4.2 The study area has been set to incorporate all potential receptors that could
be impacted (i.e. sensitive environments) and historical land uses that may
have an impact on the Development (i.e. historical development in
surrounding area, potentially contaminative permitted activities, etc).
Effects during Construction
5.4.3 The Development is not expected to adversely affect local geology or soils.
5.4.4 Slate waste, which is excavated, will be recycled into the dams at Q1 and
Q6, however there will be an excess of slate waste from the Development
of up to approximately 810,000m3. Approximately 650,000m3 will be derived
from works at Q6 and will be incorporated into permanent slate mounds at
Q1. Quarry reprofiling and general landscaping will disturb ground and
there is the potential for the discovery of unidentified contaminated land or
unexploded ordnance (UXO) (from previous use of part of the site as a
munitions store).
5.4.5 If any residual ground contamination is discovered, this will be managed
through appropriate remedial strategies developed with NRW and GC
secured through a DCO Requirement.
5.4.6 An Ordnance Management Strategy will outline what happens if any
unexpected ordnance or munitions are found.
Effects during Operation
5.4.7 The Development is unlikely to adversely affect local geology or soils during
operation.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-11
October 2015
Effects during Decommissioning
5.4.8 The Development is not expected to adversely affect local geology or soils
during decommissioning as the dams will remain in situ.
Conclusions
5.4.9 The Development comprises the utilisation of former slate quarries
excavated mainly into the Llanberis Slates Formation. Slate waste created
from the works will be re-used on site as aggregate for the dams at Q1 and
Q6 and in the stabilisation of slate mounds to the south of Q1.
5.4.10 The only nationally important geological feature in the area is part of the
Afon Gwyfrai a Llyn Cwellyn SSSI, located to the west of the Order Limits.
This includes a small exposure of a fluorite mineral working. As the location
of the SSSI is upstream of the Development, this would not be affected by
the Development.
5.4.11 Overall, it is concluded that effects of the Development on soils and geology
will be Not Significant.
5.5 Water Resources
5.5.1 Chapter 9 of the ES contains an assessment of the potential effects of the
Development on the surface water environment and water resources in the
vicinity of the Development.
Effects during Construction
5.5.2 Private water supplies were identified and consulted upon as part of the
2012 ES. Due to the increase in the Order Limits, this consultation was
repeated to identify any further private water supplies. The Development,
however, is not expected to affect any private water supplies or water
quality of the designated water bodies connected to the Development.
5.5.3 The construction phase of the Development presents a potential risk to
water resources largely through the generation of runoff with high sediment
loads. Pollution prevention measures would be implemented around all
construction areas to prevent the direct discharge of silt laden runoff to
surface watercourses. All site runoff would be directed through appropriate
treatment systems before being discharged, potentially under consent from
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-12
October 2015
NRW. With mitigation measures being implemented impacts are predicted
to be minor adverse with regards to Llyn Padarn and negligible for all other
water bodies. Therefore this is considered to be Not Significant.
5.5.4 Good construction site management would be implemented through the
CoCP to control potentially contaminative activities associated with the
construction site operations. There is the potential for the accidental
spillage or release of construction materials (such as cement, concrete,
diesel or hydraulic fluid) directly into surface water drains and into the
quarries in the vicinity of construction activities. Such materials may also
become mobilised by surface runoff and eventually enter watercourses,
drainage systems or groundwater and may result in a deterioration in water
quality and pose a temporary minor adverse effect with regards to
groundwater and all surface waters except Llyn Padarn, where a temporary
localised moderate adverse effect is predicted due to its position
downstream of the works and the need for works directly in the lake.
5.5.5 Water would be discharged to Llyn Padarn during the construction phase in
Q6. Although there is no evidence that this water poses a risk to the lake, a
programme of water quality monitoring would be implemented to determine
any variations in the quality of the water discharged, and if necessary,
treatment would be undertaken under an Environmental Permit and the
discharge made under consent from NRW.
5.5.6 Following the completion of the works on Q6, water would be abstracted
from Llyn Padarn to assist in the initial filling of the reservoir. The reservoir
also would be filled through the storage of rainfall incident to the quarry and
the surrounding area. A daily abstraction of 3300 m3 equates to
approximately 0.00022% of the total lake volume per day or approximately
a 3.4mm drawdown per day across the entire lake surface. It is considered
that there would be no significant adverse effect of the abstraction on lake
levels in Llyn Padarn. This is due to the hands off flow condition on the
abstraction license, linked to levels in the downstream Afon Seiont.
Consequently, it is considered that there would be no effect on aquatic
receptors in the lake (including at its margins). Overall, the abstraction
regime is not considered to have any significant impact on lake water levels
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-13
October 2015
(and therefore littoral habitat quality and extents) and/or water quality (as it
is affected by changing water levels). Therefore, a negligible impact is
predicted on Llyn Padarn from the short term abstraction of commissioning
water and any future ‘top-up’ abstractions.
5.5.7 Precautionary monitoring at Llyn Padarn and post-construction consents
and licenses regarding Llyn Padarn will be agreed in consultation with
NRW. A Water Management Plan has been included within the CoCP
which is found in Appendix 16.1 in Volume 3 of the ES.
5.5.8 It is concluded that with the implementation of the mitigation measures, the
residual effects of the Development on water resources during the
construction phase would be minor to negligible adverse and thus NotSignificant.
Effects during Operation
5.5.9 During the operation of the Development, potential impacts on water
resources would largely be restricted to the management of excess water
from within the Development.
5.5.10 The spillway from Q6 initially would form the spillway infrastructure from
Llyn Padarn to assist in the filling of Q6. The outfall will be fitted with a
diffuser head to help disperse flows and avoid scour of the lake bed
immediately in front of the outfall. The intake and outfall will be positioned at
least 5 m below the average minimum annual water level so as to avoid
impacts on lake users, and above the thermocline. Although the loss of lake
bed to new structures has been minimised, in accordance with the
assessment criteria a permanent moderate adverse effect is predicted.
There would also be a residual effect of moderate adverse effect on the
Nant-y-Betws stream due to the potential culverting of two short sections of
this watercourse to provide access for the PRoW diversions.
5.5.11 The spillway infrastructure will be constructed from both Q1 and Q6 to
provide a controlled discharge from the two quarries to manage excess
water. It is proposed that under normal operation excess water would
discharge from Q6 to Llyn Padarn, rather than from Q1 to the Afon Gwyrfai
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-14
October 2015
via the Nant-y-Betws, although the facility at Q1 would be utilised should it
not be possible to use the Q6 spillway or transfer water from Q1 to Q6.
5.5.12 It is considered that a negligible effect would occur from discharges to Llyn
Padarn (including bathing waters) and the Afon Gwyrfai. However, due to
the smaller size of the Nant-y-Betws stream and its lower dilution potential,
a minor adverse effect is predicted, despite the extremely low frequency of
discharges to this watercourse - although this is unlikely due to the
preference during operation to discharge from Q6 to Llyn Padarn. However,
a review of available water quality data and the proposed operation of the
Development does not give rise to any concerns and No Significantadverse impacts are predicted.
5.5.13 Sealing of Q6 potentially may block existing drainage pathways between
the quarries. This could cause flooding in Q5, which could have adverse
ecological impacts. Subject to further detailed investigations, it may be
necessary to provide a water management scheme in Q5, potentially
involving dewatering, to maintain an acceptable water level in Q5.
Maintenance of an appropriate water level in Q5 will minimise ecological
impacts and have an adverse minor residual impact on surface water flow.
Effects during Decommissioning
5.5.14 The Development is not expected to affect private water supplies or water
quality of the designated water bodies connected to the Development
during decommissioning. The draining of Q6 will be undertaken via the
Decommissioning Plan agreed with the appropriate regulators at that time
and water will be gradually released into Llyn Padarn so as not to cause
any adverse effects.
Conclusions
5.5.15 As a result of the geological conditions of the area, it is considered that
groundwater does not form an important contribution to regional or local
water resources.
5.5.16 There are a number of private water supplies in the vicinity of the
Development. As the Development will have no impact on groundwater
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-15
October 2015
flow, and the fact that Q2 and the adjacent area of the slate spoil heap will
not be disturbed by the Development, it is concluded that the existing
private supplies will not be affected.
5.5.17 The construction phase of the Development presents a potential risk to
water resources largely through the generation of runoff with high sediment
loading (potentially containing elevated levels of aluminium), the risk from
chemical spillages, and in the short term from the discharge of dewaters
from Q1 and Q6. Mitigation measures would be implemented around all
construction areas to prevent the direct discharge of contaminated runoff to
surface watercourses.
5.5.18 It is concluded that with the implementation of the mitigation measures, the
impacts of the Development on water resources during the construction
phase would be minor to negligible adverse and are therefore NotSignificant.
5.5.19 Following the completion of construction, impacts on water resources would
be limited to those associated with the effective management of excess
water in the system. Excess water would be discharged from Q6 to Llyn
Padarn replicating the current flows. No Significant adverse impacts are
predicted.
5.5.20 New crossings for the PRoW diversions over the Nant-y-Betws and two of
its tributaries, together with the diversion of one tributary would result in a
permanent effect of moderate adverse significance, which is considered
Significant. However these are short crossings and any effects will be
temporary in nature during the short construction of the culverts.
5.5.21 The results of an assessment under the WFD have shown that the
Development is compliant with the objectives of the WFD and associated
proposed mitigation measures for Llyn Padarn, Afon Seiont and the Afon
Gwyrfai.
5.5.22 Other than the possible need to include a water management system in Q5
and the short crossings on the Nant-y-Betws, it is concluded that the
operation of the Development would have negligible impacts to water
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-16
October 2015
resources receptors other than a minor effect on the Afon Gwyrfai via the
Nant-y-Betws. No Significant effects on water resources are predicted.
5.6 Flood Risk
5.6.1 Chapter 10 of the ES contains an assessment of the flood risk presented by
the Development.
Effects during Construction
5.6.2 The Development will not increase the risk of local flooding resulting from
construction activities. Activities and events that have been assessed as
part of the Flood Consequences Assessment (FCA) include working within
the floodplain, restriction of flow by mud or debris, a temporary increase in
impermeable areas, fluvial flooding and flooding from overland flow and
groundwater. Implementation of an Emergency Response and Flood
Management Plan, incorporated into the CoCP, and the installation of
temporary Sustainable Drainage Systems (SuDS) will result in negligible
effects on receptors from these construction activities and events. Upon the
implementation of mitigation measures, the risk of flooding is reduced to a
negligible effect, and therefore Not Significant.
Effects during Operation
5.6.3 The Development will not increase the chance of local flooding. Reservoir
safety design and construction standards, in line with the Reservoirs Act
1975, will ensure that dam breach risks are minimised to acceptable levels.
5.6.4 In addition to compliance with legislation relevant for the construction
maintenance and monitoring of dams and reservoirs, in the unlikely event of
a breach, the topography and large areas of land surrounding the site will
limit flow reducing negative effects. The Emergency Response and Flood
Risk Management Plan, which will be developed in conjunction with NRW
and GC, will ensure that an effective and coordinated response to any
emergency can be implemented to further mitigate the potential
consequences of such an event.
5.6.5 Overall, it is considered that the residual effects during operation of the
Development, assuming appropriate design and management, including
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-17
October 2015
implementation of the mitigation measures, will result in No Significanteffects.
Effects during Decommissioning
5.6.6 During decommissioning the dams will be slowly drained into Llyn Padarn in
agreement with NRW. The emptying of the dams will be managed by
agreement with NRW through discharge consent.
5.6.7 Once the dams have been emptied, there will be no risk of a breach of the
dams or a flooding event.
Conclusions
5.6.8 There are potential risks during construction and operation from
groundwater flooding, pluvial flooding and flooding from existing drainage
which require consideration within the detailed design of the site, the
buildings, the surface water drainage systems and the reservoirs.
5.6.9 The assessment demonstrates that it is possible to mitigate the identified
risks through the application of appropriate site management at the
construction stage, appropriate design principles at the detailed design
stage, and appropriate system management principles in operation. The
mitigation measures outlined in the CoCP are designed to protect the users
of the development, the development itself, and off-site properties from the
effects of flooding.
5.6.10 The FCA has set out the guiding principles by which the design will be
undertaken to ensure that there is no unacceptable increase in flood risk
from the Development. It is therefore considered that effects during
construction, operation and decommissioning will be Not Significant.
5.7 Cultural Heritage and Archaeology
5.7.1 Chapter 11 of the ES contains an assessment which identifies the potential
effects that the Development may have on archaeological and cultural
heritage resources.
5.7.2 The assessment has collated data from online sources and databases,
historic mapping and other documentary sources. A site visit was also
undertaken in October 2014, as well as extensive consultation under with
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-18
October 2015
GAPS and CADW. The assessment of the archaeological and cultural
heritage sites within a 1km study area identified a total of 329 recorded
assets.
Effects during Construction
5.7.3 It is anticipated that all effects on heritage assets will be restricted to the
construction phase with 24 assets or groups of assets likely to be wholly or
partially affected by the Development. The majority of these assets are
associated with the slate extraction industry in the area, and the
construction of the reservoirs and associated dams will result in the total
loss of a number of assets. The re-modelling of spoil heaps and
construction of new spoil heaps will also result in the loss or partial loss of
further assets, as will the construction of access tracks, work compounds,
and associated infrastructure.
5.7.4 There is potential for previously unrecorded archaeological features to be
present within the Order Limits, although this is considered to be limited to
areas currently occupied by spoil heaps. Following consultation with the
Senior Planning Archaeologist at GAPS and archaeological advisor for GC,
further archaeological investigation will be required within the Order Limits.
This will inform the requirement for additional archaeological mitigation.
5.7.5 Mitigation is likely to comprise building recording, landscape survey,
archaeological excavation and recording, and archaeological monitoring.
This work will be agreed with the Senior Planning Archaeologist at GAPS
and will provide a record of the affected assets. The Development will have
a permanent residual moderate adverse effect and will therefore have a
Significant effect on archaeology and cultural heritage.
Effects during Operation and Decommissioning
5.7.6 There are not expected to be any adverse effects on remaining
archaeological features and cultural heritage assets during operation or
decommissioning. Should any additional heritage assets be identified as
part of any new amended Development, proposed extensions or
remodelling after the proposed site becomes operational, they would be
subject to an additional planning application.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-19
October 2015
Conclusions
5.7.7 Effects on heritage assets are expected to be restricted to the construction
phase of the Development, however they will have a Significant adverse
effect on heritage assets. Mitigation works will be agreed with GC to provide
a record of the affected assets.
5.8 Traffic and Transportation
5.8.1 Chapter 12 of the ES considers the traffic impact of the Development during
the construction, operation and decommissioning phases. The scope of
assessment was discussed and agreed with GC (as Local Highway
Authority (LHA)) as part of the 2012 ES. Further discussions have taken
place with the LHA during the preparation of the DCO application in relation
to the upgrade to the Green Road to Q1.
5.8.2 A baseline of existing conditions has been established which analyses
traffic flow data and accessibility for all modes of transport in order to
accurately assess the effects of the Development on the local transport
network.
Effects during Construction
5.8.3 During the construction phase, access will be required to both sides of the
quarry system, Q1 on the Waunfawr side (west) and Q6 on the Llanberis
side (east) of the site.
5.8.4 Traffic movements during construction include additional vehicle
movements from workforce, deliveries and abnormal loads. Traffic
requirements during operation of the facility will be restricted to staff
commuting and site maintenance, and therefore will be concentrated at the
Glyn Rhonwy (Q6) end of the Development.
5.8.5 A Construction Traffic Management Plan (CTMP) will schedule heavy
goods vehicle (HGV) movements and abnormal loads to minimise delays
for other road users; detailing how traffic will be managed and how
pedestrian and cyclist movements will be safely managed in the event of
closures and/or diversions to routes during construction. The CTMP will be
part of the CoCP.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-20
October 2015
5.8.6 The number of HGVs associated with construction traffic is likely to have an
adverse, but temporary, effect on the local highway network, and therefore
the programming of such movements will be subject to restricted periods of
the day and working week.
5.8.7 A community liaison group will be formed to facilitate communication
between the PC and local residents.
5.8.8 The CTMP will also promote sustainable travel to the site and detail
measures to control traffic to site and minimise effects to the surrounding
communities.
5.8.9 The CoCP also contains both an Air Quality Management Plan and a Dust
Management Plan which will be implemented to reduce dust emissions
from construction traffic locally.
5.8.10 Slate waste will be re-used on site wherever possible minimising movement
of material off site and reducing the need to import materials for dam and
track construction.
5.8.11 The Development is predicted to have No Significant adverse effectsduring construction.
5.8.12 Minor highway improvements will be carried out on Green Road from
Waunfawr to Q1. As associated development, these improvements do not
form part of the DCO application but will be subject to a planning application
under the T&CPA.
Effects during Operation
5.8.13 During operation, it is not expected that there will be significant vehicle trips
required to and from the Development on a daily basis. Only those needing
to operate the facility or perform routine maintenance are expected to
require travel to the site. Therefore there are no adverse effects predicted,
which is considered to be Not Significant.
Effects during Decommissioning
5.8.14 During decommissioning it is not expected that there will be significant
vehicle trips required to and from the Development on a daily basis and
therefore there are no adverse effects expected.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-21
October 2015
Conclusions
5.8.15 The findings of the traffic assessment demonstrate that all traffic can be
accommodated on the local road network without compromising existing
traffic levels.
5.8.16 The Traffic and Transport chapter within the ES outlines that the
Development will result in a temporary increase in traffic volume on the
surrounding network. However mitigation measures have been identified to
reduce the potential traffic effect – this includes improvement to the road
network to Q1 and implementation of a CTMP.
5.8.17 The Development therefore accords with the relevant local, regional and
national planning policy guidance in that it is accessible by a range of
modes other than the private car. The CTMP will also assist in complying
with the relevant guidance by encouraging use of alternative modes to
minimise single occupancy car trips to the site.
5.8.18 The internal site layout provides for pedestrian movement both within the
Development and through the site to the surrounding area, where
achievable.
5.8.19 It is concluded that traffic effects from the construction, operation and
decommissioning of the Development are Not Significant.
5.9 Noise
5.9.1 Chapter 13 of the ES contains an assessment of the noise and vibration
impacts of the Development. The assessment provides an update to that
carried out on the approved scheme in the 2012 ES.
5.9.2 The study area for noise and vibration has been defined as the distance
around the site where potential effects of noise from construction and
operation phases may be expected. In consultation with GC, agreement
was made on six residential receptor locations for the monitoring of existing
ambient and background noise levels. Noise monitoring has been repeated
at the six monitoring locations from the 2012 survey and at two additional
locations, a caravan park which is currently under construction and Surf
Lines (commercial/leisure premises). For the April 2015 surveys, 24-hour
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-22
October 2015
unattended noise surveys were carried out at locations surrounding the
Development site. Supplementary attended noise monitoring was
conducted during daytime, evening and night-time periods. Survey locations
are presented in Figure 13.1 in Volume 4 of the ES.
5.9.3 Baseline noise monitoring was conducted at these locations to establish the
existing noise environment and determine representative background noise
levels at the surrounding Noise Sensitive Receptors (NSRs) near to the
Development site.
5.9.4 Measurements have been conducted in accordance with the principles of
BS 7445-1:2003 'Description and Measurement of Environmental Noise
Part 1: Guide to Quantities and Procedures' and BS 4142:2014.
Effects during Construction
5.9.5 Noise and vibration limits are predicted to be temporarily exceeded during
construction in some locations because of activities including surface plant,
tunnel drilling and blasting, and traffic, giving rise to potential temporary
significant effects to localised properties. However, levels of vibration
generated are unlikely to cause cosmetic damage to structures. Based
upon a preliminary assessment of potential noise from surface plant during
the construction phase, it is considered that effects of up to major adverse
could arise without mitigation. Such effects should be minimised where
possible by adopting Best Practicable Means, a CoCP and a Noise
Management Plan (NMP), and the setup of a local liaison group, to
specifically identify potential effects and appropriate mitigation based upon
site specific information as the project progresses. Once specific and exact
construction methods are known by a contractor, an assessment should be
undertaken to determine a more accurate noise assessment.
5.9.6 Significance of construction traffic noise and vibration effects has been
considered for representative NSRs. Construction traffic effects can be
mitigated through management methods, road maintenance and ongoing
monitoring and would be anticipated to result in short term effects (less than
5 years). This would result in effects that are no greater than minor adverse
at the worst affected NSRs and therefore are considered Not Significant
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-23
October 2015
Effects during Operation
5.9.7 During operation, noise and vibration effects potentially result from turbines
and generators; transformers and switchgear; the workshop and pumping
station. However due to the underground or enclosed nature of these
components combined with appropriate building design and materials, the
Development is predicted to result in negligible effects on NSRs, and
therefore is considered Not Significant. Noise control and mitigation
measures will be finalised during detailed design in order to ensure that
airborne noise emissions from operational plant will achieve suitable
operational limits following guidance from BS 4142.
Effects during Decommissioning
5.9.8 As the quarries and dams will remain in situ, no blasting or crushing will be
required and it is considered that the effects will be negligible and therefore
Not Significant.
Conclusions
5.9.9 Based upon a preliminary assessment of potential noise from surface plant
during the construction phase, it is considered that effects of up to major
adverse could arise without mitigation. Such effects should be minimised
where possible by adopting Best Practicable Means (BPM), a CoCP and a
NMP, and the setup of a local liaison group, to specifically identify potential
effects and appropriate mitigation based upon site specific information as
the project progresses. Once specific and exact construction methods are
known by a contractor, an assessment should be undertaken to determine
a more accurate noise assessment.
5.9.10 Construction traffic effects can be mitigated through management methods
and therefore are considered Not Significant.
5.9.11 Effects during operation and decommissioning will be Not Significant.
5.10 Air Quality
5.10.1 A qualitative assessment was conducted to determine the potential dust
effects during the construction phase of the Development, with reference to
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-24
October 2015
proposed activities, duration of works, baseline conditions and proximity of
potential sensitive locations.
Effects during Construction
5.10.2 Dust emissions are likely to be caused by construction activities including
drilling, blasting, rock bolting, bulk excavation, crushing of excavated
material and partial removal of existing spoil heaps.
5.10.3 The effect of construction dust will be mitigated through the methods
outlined in both the Air Quality Management Plan (AQMP) and Dust
Management Plan (DMP) within the CoCP, which are based on best
practice guidelines. Before starting work, potential dust generating activities
will be identified and good site planning and management will prevent
unnecessary dust generation, for example through the use of wheel wash
facilities, road sweepers and speed restrictions.
5.10.4 Where appropriate, dust generating activities will be undertaken off-site,
however, where this is not possible these activities will be located away
from residential properties.
5.10.5 The Llyn Padarn SSSI is located adjacent to where the outlet and pumping
station will be constructed, but is over 100m from other construction
activities. However, this is a wet environment, and so the risk of effects due
to dust were considered to be negligible and not significant (no other
designated ecological sites are located with 100m of the Development site).
5.10.6 Based on the proximity of the nearest sensitive receptor and potential dust
emission class, the risk of effects during the earthworks, construction works
and track-out was considered to be a likely, major, adverse effect, if no
mitigation measures are adopted.
5.10.7 General mitigation measures are recommended to be used in conjunction
with more detailed, activity specific measures. Mitigation measures include
the preparation and implementation of a Dust Management Plan which will
be used in conjunction with more detailed, activity specific measures such
as onsite monitoring. The overall significance of the residual effects are
determined to be a likely, minor, adverse effect for both human and
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-25
October 2015
ecological exposure. Overall the Development effects will be NotSignificant, with regard to air quality.
5.10.8 The potential effects due to road vehicle emissions during the construction
phase were also assessed and deemed to be Not Significant.
Environmental Effects during Operation
5.10.9 The Development will produce negligible emissions to air during operation
and will therefore be Not Significant.
Environmental Effects during Decommissioning
5.10.10 The Development will produce negligible emissions to air during
decommissioning and will therefore be Not Significant.
Conclusions
5.10.11 Overall the Development effects will be Not Significant, with regard to air
quality.
5.11 Socio-Economics
5.11.1 Chapter 15 of the ES contains an assessment of the potential socio-
economic, access, and amenity effects of the Development on:
Socio-economics: the local communities and associated economies in
the vicinity of the Development; and
Tourism and Recreation: Tourist/visitor attractions as well as recreational
land uses such as visitor centres and walking or cycling routes.
5.11.2 The study area defined takes into account potential receptors of effects
such as local communities that could be affected by the scheme, local
tourism operators and recreational users (such as users of Public Rights of
Way (PRoW), cycleways and areas of high public amenity value).
Effects during Construction
5.11.3 At the peak of construction there will be approximately 250 construction
staff onsite, although on average there will be about up to 100 construction
staff at any one time and dependant on the build programme.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-26
October 2015
5.11.4 There will be direct and indirect positive effects to the local economy during
the construction phase from increased employment activities and indirect
benefits through increased use of facilities in the area, such as
accommodation and restaurants. There will be direct inward investment due
to use of local services and employment. SPH, or the PC as appropriate,
will hold "meet the buyer" events to encourage local businesses to engage
with the construction tender process. It is considered that employment
opportunities will have a temporary regional minor beneficial impact. The
Development is likely to have a temporary local, minor, beneficial impact on
the local economy.
5.11.5 During the construction phase, tourism facilities located alongside the
A4086, A4085 and the minor road leading to Q1 are likely to be temporarily
affected by construction traffic during the construction period. Recreational
activities involving public access in the immediate vicinity of the site will
experience a temporary, local, minor adverse impact during this phase of
development.
5.11.6 Any decrease in tourist visitor numbers due to the construction activities will
only be temporary in nature.
5.11.7 A CTMP will be produced to ensure there is minimal disruption to
community and tourist traffic during the construction phase. SPH will work
with the local communities and businesses within villages such as
Waunfawr, Croesywaun and Groeslon to ensure the phasing of the
construction works minimises any negative effects on the local
communities.
5.11.8 Mitigation measures will include temporary closures and diversions of
PRoWs, permissive routes and open access land within the Order Limits to
ensure safety to recreational users during the construction period. These
temporary and permanent diversions will be secured through the DCO
process. There is likely to be a temporary, local minor adverse impact
during construction on the Green Road affecting villages such as
Waunfawr, Croesywaun and Groeslon due to upgrading the access road.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-27
October 2015
Effects during Operation
5.11.9 During the operational phase, 20-35 jobs will be created and the
Development will have a number of net benefits on the local and regional
economy.
5.11.10 There will be negligible effects to socio-economic receptors during
Operation, effects are therefore Not Significant.
Environmental Effects during Decommissioning
5.11.11 There will be negligible effects to socio-economic receptors during
decommissioning, effects are therefore Not Significant.
Conclusions
5.11.12 There are no Significant adverse effects on socio-economic receptors
expected throughout the life cycle of the Development. There will be some
likely localised temporary minor beneficial effects on receptors due to
increased expenditure in the region during construction and potential
localised temporary minor adverse effects on tourism routes and points of
interest.
5.12 Environmental Management
5.12.1 Chapter 16 of the ES describes the Applicant's proposals for the
environmental and waste management strategy. This strategy has been
developed into an outline CoCP which will be developed further at the
detailed design stage, subject to written approval from GC and NRW. The
CoCP provides a framework to ensure that the appropriate environmental
management practices are adopted during construction of the
Development. This will ensure that environmental effects are minimised and
mitigation measures, as described in the ES, are implemented.
Construction
5.12.2 The aim of the CoCP is to provide a framework of minimum standards to
ensure:
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-28
October 2015
Mitigation measures identified in the ES are implemented and that there
is an agreed approach to identifying mitigation for any unexpected
environmental effects that occur during construction;
The adoption of good construction practices;
That the PC and other subcontractors are complying with environmental
legislation and statutory consents; and
That the PC and other subcontractors comply with auditing,
environmental monitoring, environmental inspections and reporting
requirements.
5.12.3 The CoCP sets out a variety of control measures for managing the potential
environmental effects of construction works including control and
management of noise, dust, surface water runoff, waste and pollution
control.
5.12.4 The CoCP includes the following topic specific environmental management
plans:
Water Management Plan (WTMP) – provided as outline in the CoCP;
Pollution Prevention Plan (PPP) – provided as outline in the CoCP; and
Construction Traffic Management Plan (CTMP) - provided as outline in
the CoCP.
5.12.5 These plans will be finalised and agreed with GC and NRW through the
submission of the finalised CoCP which will be submitted and agreed prior
to construction commencing in accordance with a DCO Requirement.
5.12.6 Further plans which will be written under the CoCP in conjunction with the
PC in line with DCO Requirement 6 include:
Dust Management Plan (DMP)
Waste Management Plan (WMP)
Reinstatement/Landscape Plan;
Noise Management Plan (NMP);
Waste Management Plan (WMP);
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-29
October 2015
Emergency Response and Flood Risk Management Plan (ERFRMP);
Habitat Management Plan (HMP);
Breeding Bird Method Statement; and
Silt Management Plan;
5.12.7 Other plans required as per Requirement 7 are as follows:
Air Quality Baseline Monitoring Plan;
Materials Management Plan;
Ordnance Management Strategy;
Archaeological Compensation and Enhancement Strategy;
Land Discovery Strategy;
Health & Safety Plan (HASP); and
Bio Security Plan.
5.12.8 Some construction activities may be noisy, such as blasting and ground
preparation works. Due consideration will be given to the timings of such
works and also the methods to mitigate any potential noise impacts.
Operation
5.12.9 The site will be subject to the operators’ Environmental Policy and subject
to regular monitoring and auditing. The Development will also have a
health, safety and environmental integrated management system assured
under relevant standards. The management system will incorporate
environmental control procedures, which will be regularly independently
audited and certified.
5.12.10 Waste generation during the operational phase will be minimal, resulting
mainly from maintenance activities and will either be recycled using the
onsite recycling facilities or, where this is not possible, be disposed offsite.
Decommissioning
5.12.11 At the time of decommissioning, a Decommissioning Plan will be developed
in consultation with the necessary bodies to ensure that works are
undertaken in compliance with all relevant legislation and regulations.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-30
October 2015
Conclusions
5.12.12 All mitigation measures outlined in the ES will be developed into a full
CoCP, which will be subject to detailed design and then agreed and
finalised with GC, NRW, CADW and GAPS. These will include several other
management plans to cover water, waste, transport, noise, dust, flood risk
and waste which will be finalised with the PC is instructed and prior to
construction works starting.
5.13 Cumulative Effects
5.13.1 Chapter 17 of the ES identifies and outlines the cumulative effects
associated with the Development, both for intra-project (in-combination) and
inter-project effects.
5.13.2 Cumulative effects can be defined as the effects on the environment that
result from incremental changes caused by the combination of the
Development together with other reasonably foreseeable future actions.
Intra-project (In-combination) effects
5.13.3 For the purpose of this assessment, consideration has been given to “in-
combination effects” between environmental topics and also the potential
for ‘shared receptors’ that may be affected by the different components of
the Development, such as a local resident that could be affected by dust,
noise and traffic disruption during the construction of a scheme, with the
result being a greater nuisance than each individual effect alone.
5.13.4 In-combination effects were considered in relation to how effects may
interact and whether combining individual effects may enhance the overall
effect on a receptor.
5.13.5 There are unlikely to be any intra-project effects from the operation and
decommissioning phases of the Development and so these are not
considered further.
5.13.6 For the construction period, shared receptors identified included local
communities, ecological features and water bodies. The cumulative effects
of traffic and construction works on noise levels and air quality were
considered. Through the application of mitigation measures, which will be
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-31
October 2015
secured in the CoCP and its various management plans, it is considered
that the intra-project combined effects are negligible and minor.
5.13.7 These are therefore unlikely to add to the overall significance of proposed
effects of the Development and therefore are considered to be NotSignificant.
Inter-project effects
5.13.8 A review of the planning applications and proposed developments within
the area around the Development was undertaken to scope in the
developments that were considered to constitute ‘major development’
schemes. Cumulative developments are shown in Figure 5.2 of the NTS.
5.13.9 The sources of potential cumulative effects in the vicinity of Glyn Rhonwy
have been identified as:
The electrical connection and the switchgear station to connect the
Development to the electricity distribution system (to be developed and
owned by SP Manweb);
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-32
October 2015
The construction of Wylfa Newydd Nuclear Power Station and its
associated infrastructure and developments; and
The construction of the Caernarfon to Bontnewydd bypass.
5.13.10 The main source of potential cumulative effects in the vicinity of the site was
identified as Wylfa C New Nuclear Power Station. Traffic and Transport,
and socio-economic effects were considered.
5.13.11 However, due to the distance between the two developments, the
staggered timing of enabling and peak construction periods of both
developments, plus the potential alternative means for Wlyfa Newydd to
reduce traffic volumes if required, there are also no cumulative effects
anticipated on local road networks including the A5.
5.13.12 Cumulative effects may arise through the upskilling of businesses in the
region to work in the construction of low carbon energy developments such
as Wylfa Nuclear Power Station. Therefore this is anticipated to be a minor
beneficial cumulative effect.
5.13.13 Due to the substantial distance between Wylfa Newydd Nuclear Power
Station and the Development, there are no cumulative effects anticipated
on tourism or recreational receptors.
5.13.14 Presuming appropriate mitigation is adopted during the construction of the
Caernarfon to Bontnewydd Bypass, such as diversions and warnings to
road users, and the scale of construction activities, these potential effects
will be minimised. As the works will also be temporary, in-combination
effects on the local highway network are likely to be minor adverse.
However, the local investments resulting from these developments are
likely to have minor beneficial effects.
5.13.15 The electrical connection was also considered. Through early pre-
application discussion and at the request of GC and NRW, a high level
assessment on the current known details and route of the electrical
connection has been undertaken.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-33
October 2015
Electrical Connection
5.13.16 As the electrical connection will be underground, it is unlikely that there will
be any significant adverse effects on the surrounding landscape. In
addition, due to the size, location, scale and nature of the Development and
the electrical connection, it is likely that these will be viewed as a single
construction project.
5.13.17 It is considered that due to these elements, the construction of the electrical
connection would not be seen from the wider landscape, nearby
settlements or indeed by the majority of the visual receptors. In addition, the
excavation for the electrical connection would only require a shallow trench
and therefore it is unlikely that there would be any need for any tree
removal. Therefore in combination with the power house, this is considered
a negligible effect.
5.13.18 The narrow trench and confined working area will minimise the production
of dust during the installation. Dust is therefore considered to have no
potential for cumulative effects.
5.13.19 However, it is recognised that there may be some adverse effects to the
local communities on the A4244 whilst the connection is being installed into
the highway verge from disruption and disturbance from the works. It is
recognised that there may be a perception that these construction works
will be of the same magnitude of the repair works to the 400kv connection
to the Pentir substation for the Dinorwig scheme. It is not possible to
provide details at this stage about the duration of construction works or the
method of installation. An initial grid connection offer statement prepared by
SP Manweb considers disruption to have a temporary minor adverse effect.
This is considered Not Significant.
5.13.20 It is considered that No Significant effects resulting from the Development
and the electrical connection for the Development, the Wylfa Newydd
Nuclear Power Station or the Caernarfon to Bontnewydd Bypass will occur.
Glyn Rhonwy Pumped StorageDevelopment Consent Order
6.01 Non Technical SummaryVolume 1
5-34
October 2015
5.14 Summary
5.14.1 This NTS outlines the findings and conclusions of the EIA for the
Development which were reported in the ES which accompanied the DCO
application. Sensitive receptors have been identified and potential
environmental effects of the Development assessed by competent
professionals in line with best practice for their specific technical topic.
5.14.2 Where necessary and reasonably practical, mitigation measures (detailed in
full in ES Chapter 18, Schedule of Mitigation) have been committed to
reduce the significance of the effects of the Development.
5.14.3 Following the implementation of the identified mitigation measures during
the construction, operation and decommissioning of the Development,
residual effects have been assessed and are summarised in Table 5-1
below.
5.14.4 In addition to stand-alone technical assessments, inter and intra project
cumulative effects of the Development have been assessed, however none
were found to be significant.
Glyn Rhonwy Pumped Storage Development ConsentOrder
6.01 Non Technical SummaryVolume 1
October 2015
Table 5-1. Summary of ES Significance of Effects
Topic Significance of Effects within the ES for the Development
LandscapeCharacter andVisual Amenity
There are no fundamental changes to the above ground structures or features of the Development incomparison to the approved scheme and therefore the number of receptors has not changed. There will beNo Permanent Significance effects on the LANDMAP Aspects, LCAs or landscape designation in the studyarea. There will be a Significant adverse residual effect on the receptors at Viewpoint 7.These findings are consistent with the effects identified in the 2012 ES.
Ecology The overall residual effect ecological impact assessment is assessed as minor adverse (excluding effects onbat tree roosts). Therefore the effects are considered to be Not Significant in EIA terms.
The overall residual effect assessment on bat tree roosts only is assessed as moderate adverse. Thereforethe effects are considered to be Significant in EIA terms. Mitigation measures have been incorporated inthe design to minimise impacts on bats; these are outlined in the bat licence application.Although the Final ES conclusions have been supplemented with additional survey data, these findings areconsistent with the effects identified in the 2012 ES.A No Significant Effects Report has been prepared (Document 5.04) and this has concluded that there areNo Significant Effects to any Natura 2000 sites
Geology andGround Conditions
It is considered unlikely that any major sources of ground contamination would be identified. Overall it isconcluded that the Development would have No Significant impacts on soil and geology duringconstruction, operation or decommissioning. The management of any UXO will be dealt with as per DCORequirement 7 for the Ordnance Management Strategy.This is consistent with the findings of the 2012 ES
Water Resources Appropriate mitigation measures will be implemented through the abstraction license and the updated WFDassessment and water balance model has concluded that the impacts of the Development on waterresources during the construction phase would be negligible, and therefore Not Significant.Sealing of Q6 may potentially block existing drainage pathways which may result in flooding in Q5.
Glyn Rhonwy Pumped Storage Development ConsentOrder
6.01 Non Technical SummaryVolume 1
October 2015
Table 5-1. Summary of ES Significance of Effects
Topic Significance of Effects within the ES for the Development
Therefore, subject to further detailed investigations a water management system may need to be included.Other than this it is concluded that the operation of the Development would have negligible effects (NotSignificant) on water resources receptors
With the exception of the Q5 drainage, this is consistent with the findings of the 2012 ES
Flood Risk There are potential flooding risks during construction and operation from groundwater flooding, pluvialflooding and flooding from existing drainage. Overall it is considered that, if appropriate mitigation measuresare implemented, the residual impacts will be of negligible effect and Not Significant.The reservoirs will be designed in line with the requirements of the Reservoir Act and therefore the potentialfor breach will be minimised. Therefore there is no change to the operational effects and these are stillconsidered to be Not Significant.This is consistent with the conclusions of the 2012 ES.
Archaeology andCultural Heritage
This assessment has been updated to incorporate changes including amendments in the Order Limits. Whilethe impacts on the archaeology and cultural heritage of the site are of the same nature, the wider area of theOrder Limits has resulted in a larger number of sites that potentially could be impacted by the Development.As a result the Development will have a significance of effect of moderate adverse on archaeology andcultural heritage and will therefore be Significant.DCO Requirement 7 outlines the requirement to implement an archaeological enhancement andcompensation scheme. However the overall conclusion is still consistent with the 2012 ES.
Traffic &Transportation
The Development will result in an increase in traffic volume on the surrounding network and the mainconstruction access points have not changed since the approved scheme. However mitigation measures,such as the CTMP, have been identified to reduce the potential traffic effect. Therefore it is concluded thattraffic effects from the construction and operation of the Development are Not Significant.This is consistent with the conclusions of the 212 ES.
Glyn Rhonwy Pumped Storage Development ConsentOrder
6.01 Non Technical SummaryVolume 1
October 2015
Table 5-1. Summary of ES Significance of Effects
Topic Significance of Effects within the ES for the Development
Noise Residual effects during construction are still expected to range from negligible (Not Significant) to moderateadverse (Significant) during construction and it has been concluded that once specific and exactconstruction methods are known by a contractor, an assessment should be undertaken to determine a moreaccurate noise assessment. A NMP will be implemented during construction.It is still expected that potential effects during operation will be negligible and therefore Not Significant.This is consistent with the conclusions of the 2012 ES.
Air Quality Due to changes in assessment procedures, significance criteria and mitigation controls have been updated.However the overall Development effects are still considered to be Not Significant with regards to airquality.It is still expected that potential effects during operation will be negligible and therefore Not Significant.This is consistent with the conclusions of the 2012 ES.
Socio-Economics There will be direct and indirect beneficial effects to the local economy during the construction phase fromincreased employment activities and indirect benefits through increased use of facilities in the area.The construction phase is likely to cause an increase in traffic along the A4086 and A4085. A CTMP willmitigate as far as is reasonably practicable any disruption caused by traffic generated during theconstruction phase and therefore the impact will be Not Significant.Other management plans will be implemented such as the NMP and DMP. In addition the EnvironmentalClerk of Works will maintain a communication programme to inform local residents of the main constructionactivities such as blasting and abnormal loads.Works at Llyn Padarn will be timed to avoid summer school holidays to minimise any disruption to users.Health and Safety will be paramount during the main spillway infrastructure and pumping station works.Minor diversions may be in place but access will not be impeded. The car park area will still be in use byusers.
Glyn Rhonwy Pumped Storage Development ConsentOrder
6.01 Non Technical SummaryVolume 1
October 2015
Table 5-1. Summary of ES Significance of Effects
Topic Significance of Effects within the ES for the Development
The pumping station will not have any operational lighting or fencing, and only an above ground kiosk /control box will be visible. Through the consultation period. The location of the pumping station has beenrelocated further back from Llyn Padarn. Therefore it is considered that effects during operation areconsidered to be Not SignificantThis is consistent with the conclusions of the 2012 ES.
Cumulative and In-combination Effects
The Development has been cumulatively assessed against Wylfa C New Nuclear Power Station for trafficand socio-economic effects. There are expected to be No Significant cumulative effects should theconstruction of both projects coincide. The inter-project effects were also considered for the construction ofthe electrical connection and the Caernarfon to Bontnewydd Bypass. No Significant effects were noted.There are expected to be No Significant in-combination effects for the Development.