estimate
DESCRIPTION
COLLEGE CAMPUS INDICATNG PROPOSED CONSTRUCTION IN RED. ESTIMATED COST OF CONSTRUCTION Rs . 13,34,96,171/-. Estimate. 4. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Estimate](https://reader036.vdocuments.us/reader036/viewer/2022080916/56812d64550346895d927285/html5/thumbnails/1.jpg)
COLLEGE CAMPUS INDICATNG PROPOSED CONSTRUCTION IN RED. ESTIMATED COST OF
CONSTRUCTION Rs. 13,34,96,171/-
![Page 2: Estimate](https://reader036.vdocuments.us/reader036/viewer/2022080916/56812d64550346895d927285/html5/thumbnails/2.jpg)
![Page 3: Estimate](https://reader036.vdocuments.us/reader036/viewer/2022080916/56812d64550346895d927285/html5/thumbnails/3.jpg)
![Page 4: Estimate](https://reader036.vdocuments.us/reader036/viewer/2022080916/56812d64550346895d927285/html5/thumbnails/4.jpg)
4
Estimate
S.No. LIST OF WORKS RATE
1. CIVIL WORK Rs. 9,44,28,766 /-
2. ELECTRICAL WORK Rs. 1,30,21,519/-
3. PLUMBING WORK Rs. 1,11,12,576/-
4. FIRE FIGHTING WORK Rs. 1,03,17,505 /-
5. AIR CONDITIONING WORK Rs. 46,15,805/-
TOTAL Rs. 13,34,96,171/-