design of substation

Upload: sameera-joshi

Post on 06-Apr-2018

282 views

Category:

Documents


8 download

TRANSCRIPT

  • 8/2/2019 Design of Substation

    1/62

    Design of 400/220kV

    Sub-station

    S.M. MUJUMDAR

    General Manager

    (sub-station Engineering)

    27th April 2005 Jyoti Structures Ltd.,

    Mumbai

  • 8/2/2019 Design of Substation

    2/62

    Agenda

    Overview of 400kV sub-station

    Design Process

    Design considerations

    Question / Answer

  • 8/2/2019 Design of Substation

    3/62

    Imp. considerations in substation design

    Safety of personnel and equipment

    Reliability and Security

    Adherence to

    Statutory obligations

    I.E. rules, Environmental aspects

    Electrical design considerations

    Structural design considerations

    Ease of maintenance Possibility to Expand

  • 8/2/2019 Design of Substation

    4/62

    System parameters

    1000 mV

    (156kV)

    1000 mV

    (320kV)

    Radio interference voltage at 1MHZ

    (for phase to earth voltage)

    10.

    40kA40kARated short ckt. Current for 1 sec.8.

    25mm/kV25mm/kVMin. creepage distance7.

    156kV320kVCorona Extinction voltage6.

    Effectively earthedSystem neutral earthing5.

    33Number of phases4.

    50Hz50HzRated frequency3.

    245kV420kVMax. operating voltage2.

    220kV400kVNominal system voltage1.

    220kV400kVDescriptionSr.

  • 8/2/2019 Design of Substation

    5/62

    System parameters Contd..

    Remarks220kV400kVDescriptionSr.

    (Line-ground)

    (open terminals)

    460kV

    460kV

    530kV

    460kV

    680kV

    520kV

    610kV

    630kV

    iii) One min. power freq.

    withstand voltage (dry/wet)-- for lines

    -- for CB / Isolator

    -- for other equipments

    1050kVpii) Switching impulse

    withstand voltage (dry/wet)

    1050kVp

    950kVp1050kVp

    1550kVp

    1300kVp1425kVp

    Rated insulation levels

    i) Full wave impulse

    withstand voltage

    -- for lines

    -- for reactor/ Xmer-- for other equipments

    11.

  • 8/2/2019 Design of Substation

    6/62

    Substation Birds view

  • 8/2/2019 Design of Substation

    7/62

    400kV Circuit Breaker

  • 8/2/2019 Design of Substation

    8/62

    400kV Isolator

  • 8/2/2019 Design of Substation

    9/62

    400kV Current Transformer

  • 8/2/2019 Design of Substation

    10/62

    400kV CVT

  • 8/2/2019 Design of Substation

    11/62

    400kV Surge Arrester

  • 8/2/2019 Design of Substation

    12/62

    Shunt Reactor & NGR

  • 8/2/2019 Design of Substation

    13/62

    400/220 kV Auto Transformer

  • 8/2/2019 Design of Substation

    14/62

    400kV Bus Post Insulator

  • 8/2/2019 Design of Substation

    15/62

    Wave Trap

  • 8/2/2019 Design of Substation

    16/62

  • 8/2/2019 Design of Substation

    17/62

    Functions of substation equipments

    To discharge lightning over voltages and

    switching over voltages to earth

    7. Lightning Arrester

    To step-down voltages for measurement, control

    & protection

    6. Voltage Transformer

    To step-down currents for measurement, control

    & protection

    5. Current Transformer

    To discharge the voltage on dead lines to earth4. Earthing switch

    Disconnection under no-load condition for

    safety, isolation and maintenance.

    3. Isolators

    Automatic switching during normal or abnormal

    conditions

    2. Circuit Breaker

    Incoming & outgoing ckts. Connected to bus-bar1. Bus-Bar

    FunctionEquipment

  • 8/2/2019 Design of Substation

    18/62

    Functions of substation equipments Contd

    Compensation of long lines.14. Series Capacitor

    To step-up or step-down the voltage and

    transfer power from one a.c. voltage another

    a.c. voltage at the same frequency.

    13. Power Transformer

    To provide compensations to reactive loads of

    lagging power factors

    12. Shunt capacitors

    To prevent high frequency signals from entering

    other zones.

    11. Line Trap

    To provide connection between high voltage

    line & PLCC equipment

    10. Coupling capacitor

    To limit earth fault current9. Neutral-Grounding

    resistor

    To control over voltages by providing reactive

    power compensation

    8. Shunt reactor

  • 8/2/2019 Design of Substation

    19/62

    Functions of Associated system in substation

    3. Illumination system (lighting)

    -- for switchyard

    -- buildings

    -- roads etc.

    To protect the outdoor substation

    equipment from lightning strokes.

    2. Overhead earth wire

    shielding or Lightning masts.

    To provide an earthmat for connecting

    neural points, equipment body, support

    structures to earth. For safety of

    personnel and for enabling earth fault

    protection. To provide the path for

    discharging the earth currents fromneutrals, faults, Surge Arresters,

    overheads shielding wires etc. with safe

    step-potential and touch potential.

    1. Substation Earthing system

    -- Earthmat

    -- Earthing spikes

    -- Earthing risers

    FunctionSystem

  • 8/2/2019 Design of Substation

    20/62

    Contd..

    To provide alarm or automatic tripping offaulty part from healthy part and also to

    minimize damage to faulty equipment and

    associated system.

    4. Protection system-- protection relay panels

    -- control cables

    -- circuit breakers

    -- CTs, VTs etc.

    For Protective circuits, control circuits,metering circuits, communication circuits

    5. Control cable

    For communication, telemetry, tele-

    control, power line carrier protection etc.

    7. PLCC system power line

    carries communication system

    -- line trap

    -- coupling capacitor

    -- PLCC panels

    To provide supply path to various

    auxiliary equipment and machines.

    6. Power cable

  • 8/2/2019 Design of Substation

    21/62

    Contd

    To sense the occurrence of fire by

    sensors and to initiate water spray,

    to disconnect power supply to

    affected region to pin-point location

    of fire by indication in control room.

    8. Fire Fighting system

    -- Sensors, detection system

    -- water spray system

    -- fire prot. panels, alarm system

    -- watertank and spray system

    For internal and external

    communication

    10. Telephone, telex, microwave,

    OPF

    For supplying starting power,

    standby power for auxiliaries

    9. Auxiliary standby power system

    -- diesel generator sets

    -- switchgear

    -- distribution system

  • 8/2/2019 Design of Substation

    22/62

    Basic drawings for design/construction

    Single Line Diagram

    General Arrangement Drawing

    Electrical Plan and Section

    Control Room Architectural layout

  • 8/2/2019 Design of Substation

    23/62

    Supporting drawings

    Structural layout

    Earthmat layout

    Civil layout

    Erection Key Diagram

    Lighting Layout

  • 8/2/2019 Design of Substation

    24/62

    Single Line Diagram 220kV

  • 8/2/2019 Design of Substation

    25/62

    General arrangement layout

  • 8/2/2019 Design of Substation

    26/62

    Electrical layout

  • 8/2/2019 Design of Substation

    27/62

    Electrical Section

  • 8/2/2019 Design of Substation

    28/62

    Control room layout

  • 8/2/2019 Design of Substation

    29/62

    Control room layout

  • 8/2/2019 Design of Substation

    30/62

    Structural layout

  • 8/2/2019 Design of Substation

    31/62

    Earthmat Layout

    @

    @

    @

    @

    @

    @

    @

    @

    @

  • 8/2/2019 Design of Substation

    32/62

    Civil layout

  • 8/2/2019 Design of Substation

    33/62

  • 8/2/2019 Design of Substation

    34/62

    Lighting Design

    Adequate lighting is necessary for safety of working personnel and O&M

    activities

    Recommended value of Illumination level

    Control & Relay panel area - 350 Lux (at floor level)

    Test laboratory - 300 Lux

    Battery room - 100 Lux

    Other indoor area - 150 Lux

    Switchyard - 50 Lux (main equipment)

    - 20 Lux (balance Area / road @

    ground level)

  • 8/2/2019 Design of Substation

    35/62

    Single Bus arrangement

  • 8/2/2019 Design of Substation

    36/62

    Single Bus System

    4. Can be used only where

    loads can be interrupted or

    have other supply

    arrangements.

    3. Sectionalizing

    increases flexibility

    3. Bus cannot be extended

    without completely de-

    energizing substations

    3. Simple Protection

    2. Not used for large

    substations.

    2. Difficult to do any

    maintenance

    2. Simple to Operate

    1. Used for

    distribution

    substations upto 33kV

    1. Fault of bus or any

    circuit breaker results in

    shut-down of entire

    substation

    1. Low cost

    RemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    37/62

    Main & Transfer Bus

  • 8/2/2019 Design of Substation

    38/62

    Main & transfer busbar system

    3. Fault of bus or any

    circuit breaker results in

    shutdown of entire

    substation.

    3. Potential devices may

    be used on the main bus

    .2. Switching is

    somewhat complex

    when maintaining a

    breaker

    2. Any breaker can be

    taken out of service for

    maintenance.

    1. Used for 110kV

    substations where cost

    of duplicate bus barsystem is not justified

    1. Requires one extra

    breaker coupler

    1. Low initial & ultimate

    cost

    RemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    39/62

    Double Busbar arrangement

  • 8/2/2019 Design of Substation

    40/62

    Double Bus Bar Single Breaker system

    5. Bus couplers failure takes

    entire substation out of

    service.

    4. Line breaker failure takes

    all circuits connected to the

    bus out of service.

    3. High exposure to bus fault.

    2. Bus protection scheme

    may cause loss of substationwhen it operates.

    2. Half of the feeders

    connected to each bus

    1. Most widely

    used for 66kV,

    132kv, 220kV and

    important 11kv,

    6.6kV, 3.3kV

    substations.

    1. Extra bus-coupler circuit

    breaker necessary.

    1. High flexibility

    RemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    41/62

    Double Busbar with Double breaker

  • 8/2/2019 Design of Substation

    42/62

    Double Bus Bar Double Breaker system

    4. High reliability

    3. Any breaker can be

    taken out of service for

    maintenance.

    2. Used only for veryimportant, high power,

    EHV substations.

    2. Would lose half ofthe circuits for breaker

    fault if circuits are not

    connected to both the

    buses.

    2. Has flexibility inpermitting feeder

    circuits to be connected

    to any bus

    1. Not used for usual

    EHV substations due to

    high cost.

    1. Most expensive1. Each has two

    associated breakers

    RemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    43/62

    Double main & transfer

  • 8/2/2019 Design of Substation

    44/62

    Double main bus & transfer bus system

    7. Bus fault does not remove any

    feeder from the service

    6. Either main bus can be taken outof service at any time for

    maintenance.

    5. Simple operation, no isolator

    switching required

    4. All switching done with breakers

    3. Breaker failure on bus side

    breaker removes only one ckt.From service

    2. Highly reliable

    1. Preferred by

    some utilities for

    400kV and

    220kV

    important

    substations.

    1. High cost due to

    three buses

    1. Most flexible in operationRemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    45/62

    One & half breaker scheme

  • 8/2/2019 Design of Substation

    46/62

    One & half breaker scheme

    6. Selective tripping

    5. All switching by breaker.

    4. Each circuit fed by twobreakers.

    3. Requires 1 1/2 breaker per

    feeder.

    2. Preferred.2. Protection and

    auto-reclosing morecomplex since

    middle breaker must

    be responsive to

    both associated

    circuits.

    2. Any breaker can be removed

    from maintenance withoutinterruption of load.

    1. Used for 400kV

    & 220kV

    substations.

    1. One and half

    breakers per circuit,

    hence higher cost

    1. Flexible operation for breaker

    maintenance

    RemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    47/62

    Ring Bus

  • 8/2/2019 Design of Substation

    48/62

    Mesh (Ring) busbar system

    4. Breaker failure during fault on one

    circuit causes loss of additional

    circuit because of breaker failure.

    3. Requires VTs on all circuits

    because there is no definite voltage

    reference point.

    These VTs may be required in all

    cases for synchronizing live line orvoltage indication

    2.Auto-reclosing and protection

    complex.

    1. Most widely

    used for very

    large power

    stations having

    large no. ofincoming and

    outgoing lines

    and high power

    transfer.

    1. If fault occurs during bus

    maintenance, ring gets separated

    into two sections.

    1. Busbars gave

    some operational

    flexibility

    RemarksDemeritsMerits

  • 8/2/2019 Design of Substation

    49/62

    Minimum Clearances

    4300 mm6400 mm3. Sectional clearance

    2100 mm4200 mm

    (Rod-conductor configuration)

    4000 mm

    (Conductor-conductor configuration)

    2. Phase to phase

    2100 mm3500 mm1. Phase to Earth

    220kV400kV

  • 8/2/2019 Design of Substation

    50/62

  • 8/2/2019 Design of Substation

    51/62

  • 8/2/2019 Design of Substation

    52/62

    Clearance Diagram

  • 8/2/2019 Design of Substation

    53/62

    Bus Bar Design

    Continuous current rating. Ampacity caculation as per IEEE:738

    Short time current rating (40kA for 1 Sec.) IEC-865

    Stresses in Tubular Busbar

    Natural frequency of Tubular Busbar

    Deflection of Tube

    Cantilever strength of Post Insulator

    Aeolian Vibrations

  • 8/2/2019 Design of Substation

    54/62

    Gantry Structure Design

    ClearancesNo windMax.

    (ACSR 750C/ AAAC 850C)

    5.

    T

  • 8/2/2019 Design of Substation

    55/62

    Contd..

    Short Circuit Forces calculation

    As per IEC : 865

    Short circuit forces during short circuit

    Short circuit forces after short circuit

    Short circuit forces due to Pinch effect for Bundled conductor

    Spacer span calculation

    Factor of safety of 2.0 under normal condition and 1.5 under short

    circuit condition

  • 8/2/2019 Design of Substation

    56/62

    spacers

  • 8/2/2019 Design of Substation

    57/62

    Spacer span Vs Short Ckt. forces

    GRAPH OF SPACER SPAN Vs CONDUCTOR TENSION FOR

    400 KV TWIN MOOSE ACSR CONDUCTOR

    0.00

    2000.00

    4000.00

    6000.00

    8000.00

    10000.00

    12000.00

    0 2 4 6 8 10 12 14

    SPACER SPAN IN MTRS.

    CONDUC

    TOR

    TENSION

    PER

    PHASE

    INK

    G.

  • 8/2/2019 Design of Substation

    58/62

    Earthing Design

    Guiding standards IEEE 80, IS:3043, CBIP-223.

    400kV & 220kV system are designed for 40kA.

    Basic Objectives:

    Step potential within tolerable

    Touch Potential limit

    Ground Resistance

    Adequacy of Ground conductor for fault current

    (considering corrosion)

  • 8/2/2019 Design of Substation

    59/62

    Touch and step potential

  • 8/2/2019 Design of Substation

    60/62

    Lightning Protection Ground Wire

    FIG-4bFIG-4a

  • 8/2/2019 Design of Substation

    61/62

    Lightning Protection Lightning Mast

  • 8/2/2019 Design of Substation

    62/62