substation design physical and technical...

Download Substation Design Physical and Technical Considerations…iiee.org.ph/wp-content/uploads/2014/12/Substation-Design-by-Marvin... · Substation Design Physical & Technical Considerations

If you can't read please download the document

Upload: vankien

Post on 06-Feb-2018

256 views

Category:

Documents


8 download

TRANSCRIPT

  • Substation Design

    Physical & Technical

    Considerations

    I. Objectives

    II. Substation Design Introduction

    III. General Design Considerations

    Outline

  • Revision 00

    To be able to know:

    The general considerations in designing a distribution

    substation

    The physical layout considerations in developing a

    substation.

    Objectives

    I. Meralco Electric System & Planning

    Criteria

    II. Use of Gas Insulated Switchgear Substation

    Substation Design Introduction

  • Meralco Electric System

    Planning Criteria

    All substations shall have at least 2 subtransmission feeds.

    Limit maximum normal loading of power transformers to OA rating(FA1 for switching flexibility and FA2 during adjacent transformer failure)

    Improvement of reliability of existing substations.

    Substations must be near the load center depending on the load density of the substation service area

    Substation configuration must be single bus, ring bus, or breaker-and-a-half scheme

    Transformer capacity must be 83 MVA for 115-34.5 kV and 33 MVA for 69kV-13.8 kV or 115kV-13.8 kV

    USE OF GIS SUBSTATION The conventional substation is normally being used

    in substation development. However, in highly urbanized area where land is scarce and very costly, the use of GIS substation is considered. To justify this, the cost of the land should be at least Php 105,000 per sq.meter.

    In addition, some selected odd-voltage substations within Metro Manila are also programmed for conversion into major 115 kV substation by using either GIS equipment or a one bank/one line scheme. The rational is that their locations are already within the load center, and it is difficult to find and buy lots to be used as substation site within such developed areas.

  • I. Geographical / Site Considerations

    II. Environmental Considerations

    III. Maintenance Considerations

    General Design

    Considerations

    1. Drainage and soil conditions

    2. Cost of earth removal, earth addition, and earthmoving

    3. Space for future as well as present use

    4. Proximity to earthquake fault lines and floodplains

    5. Public concern; avoidance of schools, daycare centers, and

    playgrounds

    6. Atmospheric conditions: salt and industrial contamination

    7. Location of present and future load center

    8. Location of existing and future sources of power

    9. Availability of suitable right of way and access to site by overhead and underground sub-transmission and distribution circuits

    10.Location of existing distribution lines

    Geographical / Site Considerations

  • Revision 00

    AMADEO 230kV-115kV-13.8kVDELIVERY POINT SUBSTATION

    Revision 00

  • 1. Appearance

    2. Noise

    3. Effluent

    4. Electrostatic and electromagnetic

    effect

    5. Public Safety

    6. Weather

    Environmental

    Considerations

    Revision 00

    AESTHETICS / APPEARANCE

  • Revision 00

    MALIBAY 115KV-34.5KV SUBSTATION

    AESTHETICS / APPEARANCE

    MANDALUYONG 115KV 34.5KV SUBSTATION

  • Revision 00

    LEGAZPI 115KV-34.5KV GIS SUBSTATION

    AESTHETICS / APPEARANCE

    Legazpi 115KV 34.5KV

    GIS Substation

  • Revision 00

    SUBSTATION NOISE

    Revision 00

    SUBSTATION NOISE

    Sources of audible noise within a substation include transformers, voltage regulators, circuit breakers, other intermittent noise generators.

    Among the sources, transformers have the greatest potential for producing objectionable noise.

    The design engineer should consideraudible noise reference documents and regulations

  • Revision 00

    SUBSTATION NOISE

    At 550kV BIL,

    OA/FA1/FA2

    OA 76dB 50000

    FA1 79dB 66667

    FA2 80dB 83333

    Revision 00

    SUBSTATION NOISE

    At 550kV BIL,

    OA/FA1/FA2

    OA 76dB 50000

    FA1 79dB 66667

    FA2 80dB 83333

    MERALCO POWER TRANSFORMER SPECIFICATION ON

  • Revision 00

    Minimum Noise Level

    1 METER

    69 dB

    1 METER

    63 dB60 dB ( INCLUSIVE OF STREET NOISE )

    10 METERS

    POWER

    TRANSFORMER

    CONCRETE

    WALL

    BARRIER

    CONCRETE

    WALL

    BARRIER

    ROCKWELL SWITCHGEAR

    BUILDING

    SUBSTATION NOISE

    Revision 00

    EFFLUENT

  • Revision 00

    EFFLUENT

    IEEE STD 980-1994 (R2001) IEEE Guide for Containment and

    Control of Oil Spills in Substations

    RUS Bulletin 1724E-300 Design Guide for Rural Substation

    Water Quality Guidelines and General Effluent Standards

    of 2008, Revising DAO 34 and 35, Series of 1990

    Effluent refers to discharges from known source, which is passed into a

    body of water or land, or wastewater flowing out of a manufacturing plant,

    industrial plant including domestic, commercial, and recreational facilities.

    Revision 00

    ELECTRO-MAGNETIC FORCE (EMF)

  • Exposure (60 Hz) Electric field Magnetic field

    Occupational 8.3 kV/m 4.2 G (4,200 mG)General Public 4.2 kV/m 0.833 G (833 mG)

    International Commission on Non-Ionizing Radiation Protection (ICNIRP) is anorganization of 15,000 scientists from 40 nations who specialize in radiationprotection.Source: ICNIRP, 1998.

    ICNIRP Guidelines for EMF Exposure

    Revision 00

    ELECTRO-MAGNETIC FORCE (EMF)

    Electro-Magnetic Force (EMF) way below allowed international

    standard of 833 milli-Gauss

    0

    10

    20.8mG - Colored TV

    45mG - Aircon

    5.76 mG - Meralco Hillcrest Substation

    - taken March 7, 2003

    236mG - Hair Dryer

    Milli-Gauss

    5

    20

    40

    50

    200

    300

    1000International Limit=833mG

    11.6mG - Computer

  • Revision 00

    PUBLIC SAFETY

    Revision 00

    PUBLIC SAFETY

  • Revision 00

    DOORS WITH WARNING SIGN

    PUBLIC SAFETY

    METAL FENCEDOORS WITH APPROPRIATE

    GROUNDING

    GATE WITH CAUTION SIGN

    Revision 00

    WEATHER

  • Revision 00

    WIND

    It is important that

    substations operate

    more reliably in

    extremes of weathers.

    As a minimum, substations

    should be resistant to wind

    velocities as shown.

    Revision 00

    RAINFALL / FLOOD

    A substation

    should be designed to be

    operable under predictable

    conditions of rainfall.

    should have sufficient

    drainage to exhibit little

    standing water within a few

    hours after a heavy rainfall.

    The level of the substation

    site should be higher

    than the 1 in 50 year

    flood level.

  • Maintenance procedures should have minimal impact on

    the operation of the substation

    Adequate clearances provided for maintenance

    personnel, equipment and procedures are considered

    Maintenance

    Considerations

    TEMPLATE: RING BUS SUBSTATION

    AREA=4,180 SQ. METERS

  • LAGUNA BEL-AIR 115KV-34.5KVRING BUS SUBSTATION

    AREA=3,294 SQ. METERS

    Revision 00

    TEMPLATE: SINGLE BUS SUBSTATION

    AREA=3,000 SQ. METERS

  • Revision 00

    AREA=3,000 SQ. METERS

    SANTOLAN 115KV-34.5KVSINGLE BUS SUBSTATION

    For inquiries, email us: [email protected]