SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

DOYLE DRIVEConcept for P3, Procurement Schedule

and Key Issues

Geoffrey S. Yarema and Fredric W. KesslerNossaman LLP

July 6, 2009

Page 2: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

2

Overview

Public-private partnership (P3) authority in CaliforniaConcept for Doyle Drive P3• Screening for optimal Doyle Drive delivery

method• Doyle Drive as availability payment

concession• Other P3 options for Doyle Drive

Preliminary procurement scheduleReview of key issues

Page 3: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

3

P3 Authority in California

Senate Bill 4 (SBX2 4) amended Streets and Highways Code Section 143Authorizes Caltrans and regional transportation agencies (RTAs) to implement transportation projects through a P3 delivery methodTransportation projects include highways, streets and railNo limit on number of projectsDeadline of June 1, 2017 to execute P3 agreements

Page 4: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

4

P3 Authority in California

P3 Procurement Process under SBX2 4Caltrans/RTA screening and project nominationCTC approval of nominated projects

• Improved mobility• Improved operation or safety• Air quality benefits• Address known forecast demand

CTC approval of best value evaluation criteria and (for Caltrans projects only) certification of useful life determinationFurther CTC role and timing of involvement remain open

Page 5: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

5

P3 Authority in California

P3 Procurement Process under SBX2 4 (cont.)RFQ/RFP process and proposal submission Evaluation and selectionPublic hearing by procuring agency on P3 agreement60-day review and comment by Legislature and PIACConsideration of comments and execution of P3 agreement

Page 6: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

6

Screening for Optimal Doyle DriveDelivery Method

Caltrans and SFCTA currently engaged in screening processScreening compares which delivery method best achieves objectives:

Conventional project deliveryP3

Page 7: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

7

Screening for Optimal Doyle DriveDelivery Method

Caltrans/SFCTA objectives:Cure seismic safety risk as fast as possibleOn-time and within-budget delivery Minimize integration, interface and coordination risks of multiple contractsOptimize cash flow managementObtain life cycle cost efficiencyAssure compliance with requirements of cooperating stakeholders

Page 8: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

8

Screening for Optimal Doyle DriveDelivery Method

P3 would involve private party in project financing, design, construction and long-term operations and maintenanceWorking assumption for screening:

Wrap contracts 5-8 scope into a P3Place project O&M under a P3Use availability payment type of P3

Screening process is testing this working assumption

Page 9: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

9

Screening for Optimal Doyle DriveDelivery Method

Screening begins with evaluation of P3 suitability under the following criteria:

Institutional preparednessStakeholder concerns/requirementsProject size and complexityLocal political supportProject maturityRisk allocationMarket interest

Page 10: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

10

Screening for Optimal Doyle DriveDelivery Method

Screening includes evaluating: Value for money – financial comparison of (1) planned multiple design-bid-build contracts and pay-go financing with (2) concession and private financial support for portion of projectSchedule impacts if use P3Design approach, use of performance specificationsCaltrans retention of certain O&M functions

Page 11: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

11

Doyle Drive asAvailability Payment ConcessionAvailability payment concession structure to implement Doyle Drive

This approach was used on the I-595 project in Florida (reached financial close in March 2009)

Concessionaire Lenders

OperatorD-B Contractor

Government

Equity Investors

Avai

labi

lity

Paym

ent

Con

cess

ion

• Must be earned• Capped at amount bid

(adjusted for inflation)Availability Payments

Milestone Payments

Page 12: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

12

Doyle Drive asAvailability Payment ConcessionPublic owner:

Pays developer• To finance, design, construct, operate and

maintain project• Based on project availability and performance

over an extended period

Uses technical specifications to assure performance, facilitate innovation and life cycle cost efficiencies

Page 13: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

13

Doyle Drive asAvailability Payment ConcessionDeveloper:

Arranges debt and equity financing for some or all project capital costsMay be responsible for capital replacements Maintains project and manages traffic for a fixed termMay be responsible for maintenance and traffic management during constructionMay receive “tax ownership” and therefore depreciation benefitsReceives scheduled payments from public owner during the contract term as compensation for services and financing Hands project back in pre-agreed condition at the end of the contract term

Page 14: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

14

Doyle Drive asAvailability Payment ConcessionInvolves two types of payments:

Milestone payments – Payment made by the owner to the developer once the developer reaches a construction milestoneAvailability payments – Deferred unitary payment encompassing financing costs, O&M expenditures, and return on equity• Paid periodically (e.g., monthly, quarterly) after

substantial completion• Amount may be adjusted by changes in an

index (e.g., CPI)

Page 15: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

15

Doyle Drive asAvailability Payment Concession

Availability payments (cont.):• May be adjusted downward based on the

developer’s performance:– Unpermitted closures– Quality, safety or environmental standards are not

met– Other adjustment factors

• Encourages developer to manage its maintenance program to avoid traffic disruption at busy times

• Potential reduction in the availability payment provides the developer with incentive to perform

Page 16: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

16

Other P3 Options for Doyle DriveCaltrans and SFCTA considering other P3 structuresE.g., Design-Build-Finance

Caltrans retention of O&M functions remains under active considerationCan private sector really perform O&M at less expense compared to Caltrans’ economies of scale?Will design and construction quality suffer if private party does not shoulder O&M responsibility?

Page 17: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

17

Preliminary Procurement ScheduleActivity Date

CTC* Project and P3 Approval September 2009

Issue RFQ September 2009

SOQ Due Date November 2009

Issue Draft RFP November 2009

SOQ Evaluation and Shortlisting December 2009

CTC Approval of Evaluation Criteria and Certification of Useful Life Determination

December 2009

Issue Final RFP January 2010

First Round of One-on-One Meetings with Shortlisted Proposers Winter 2010

Second Round of One-on-One Meetings with Shortlisted Proposers Spring 2010

Proposal Due Date May-June 2010

Proposal Evaluation and Selection June-July 2010

Public Hearing on Final P3 Agreement July 2010

Legislative and PIAC Review of Final Agreement and Public Comments August-September 2010

Consideration of Comments, Execution of P3 Agreement October 2010

Financial Close December 2010

*CTC role subject to promulgation of guidelines

Page 18: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

18

Preliminary Procurement Schedule

Schedule Drivers for Start of ProcurementCTC guidelinesCompleting value for money analysisPreparing project report and business case for CTC

Page 19: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

19

Preliminary Procurement Schedule

Schedule Drivers for Completing ProcurementCompleting Presidio Trust agreementsCTC submission periods and hearingsPreparing and internally approving revised design and construction specifications, new O&M specificationsFHWA review and approval of specifications and RFPCompleting local funding agreementsStatutory hearing and 60-day review by Legislature and PIACSchedule to complete contracts 3 and 4 (February 2011), switch traffic and demobilize (June 2011)

Page 20: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

20

Review of Key Issues

Value for money – To what extent will an availability payment concession produce value beyond the conventional design-bid-build delivery method?Project scope – Is the proposed scope attractive to the industry?Type of P3 agreement – Is the type of P3 agreement and project financing mechanism attractive to the industry?

Page 21: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

21

Review of Key Issues

P3 agreement term – What is the right length of term to secure financing and optimize value? Construction schedule – What are the best options to manage the schedule for construction completion under contracts 1-4 with the handover of O&M and start of construction work under a P3 agreement for the balance of the project (contracts 5-8)?

Page 22: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

22

Review of Key Issues

O&M scope – What is the appropriate scope of O&M to delegate to the private entity?

Are certain responsibilities more appropriate for Caltrans?What is the best allocation of O&M responsibilities regarding the improvements constructed under contracts 1-4?Is assumption of O&M for contracts 1-4’s permanent improvements attractive to the industry?

• What approach should be considered with respect to patent and latent defects?

Page 23: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

23

Review of Key Issues

O&M standards – What are the appropriate standards and specifications for O&M?Proposal evaluation – What is the most appropriate method to evaluate and score final proposals?

Caltrans is considering using a best value selection methodWhile Caltrans would place primary weight on pricing, proposers’ technical solutions and construction schedule would be important factors

Page 24: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

24

Review of Key Issues

PABs and TIFIA financing – Would it be worthwhile for Caltrans to arrange the availability of PABs and/or TIFIA?Presidio Trust - What oversight and/or coordination issues exist regarding the Presidio Trust and what are possible solutions?Technical specifications – What is the right approach to technical specifications for this project?

Page 25: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

25

Questions?

Page 26: Dd P3 Wkshp Procurement Schedule Key Issues 0709

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE – DOYLE DRIVE

26

Contact Information

Geoffrey S. YaremaNOSSAMAN LLP

[email protected] 213.612.7842

Fredric W. KesslerNOSSAMAN LLP

[email protected]