ctc work packages ver 2.1
DESCRIPTION
CTC Work Packages ver 2.1. HS for CTC. Overview CTC Work Packages (1/3). Overview CTC Work Packages (2/3). Overview CTC Work Packages (3/3). CTC-001 DR SC wiggler. - PowerPoint PPT PresentationTRANSCRIPT
CTC Work Packagesver 2.1
HS for CTC
CTC-001 SC wigglers Cooling design, hor. or ver. Racetrack coilNb3Sn or NbTi cablePrototypes constructionExperimental test program at ANKA
CTC-002 Alignment Tunnel metrologyActive mechanical pre-alignmentSpecific Active pre-alignment of MDI
CTC-003 Quadrupole Stability Stabilization TechnologiesApplication to MB quadrupoleApplication to FF quadrupoles
CTC-004 TBA modules Prototype design and fabricationModelizationExperimental comparison of predicted and modeled performanceAlternative designsIndustrialization
CTC-005 Warm Magnet prototypes Normal conducting Compact Magnet DesignPermanent magnet High Gradient Quadrupole DesignPowering SchemesRad hard trimmers for strength
CTC-006 Beam Instrumentation Refinement of specificationsBPM designsEmittance MeasurementsBeam loss Monitoring
Overview CTC Work Packages (1/3)
CTC-007 MDI activities Detailed Studies Experimental work/Prototyping CTC-008 Post Collision lines and Beam Dumps Post Collision line design Water dump design Detailed studies/design of MB dump
Detailed studies/design of DB dumps/ preparation of CLIC0
CTC-009 Machine Protection/Machine Operation Studies and designsDevelopment of a Machine ModelExperimental workDefinition of Operational Scenario
CTC-010 Civil Engineering Studies DesignsLayouts
CTC-011 Controls Fs-Timing system master clockFs-Timing system site distributionIntegrated TBA module acquisition system
CTC-012 RF systems development of DB power source. Design of DB linaclow level Rf systemsprototype of DR Rf system
CTC-013 Powering Designs
Modulators for DB klystrons
Overview CTC Work Packages (2/3)
CTC-014 Vacuum Systems CTC-015 Magnetic Stray fields
CTC-016 BT equipment DR extraction kickers
Overview CTC Work Packages (3/3)
WP: CTC-001 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Choice of cooling technique/topology of wiggler winding: ho.r or ver. racetrack
Careful designs of liquid helium bath colled wiggler or cooled by conduction cooling
Designs 2011-2012
Task2:Choice of Sc cable (NbTi/Nb3Sn)
Higher field from Nb3Sn, more expensive and more difficult to machine
Designs 2011-2012
Task3: Production of prototype(s) Construction of one hor. and one ver. Racetrack wigglers from NbTi cable in 2 cryostats (in Novosibirsk through ANKA) ; one ver. Racetrack coil from Nb3Sn at CERN.
3 prototype coils, 2 full cryostats
First complete magnet end 2012 for installation in ANKA (Karlsruhe)
Task 4: Experimental program at ANKA
Confirmation of simulations, choice for task 1 and 2, measurements of heat loads etc
2012-2014
Lead collaborator(s): ANKA/KIT; Novosibirsk
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): (1) 2000
Personnel (FTE):
CTC-001 DR SC wiggler
To be ready for beam in ANKA in the year 2012 this program will need a temporary loan of a PM wiggler for ANKA (CERN charge to find one)
WP: CTC-002 Purpose/Objectives/Goals Deliverables Schedule
Task 1: development of sensors and actuators
Development of calibration benches Validation through inter-comparisonsQualification in accelerator environment, development of low cost versions, preparation of industrialization
Low cost precise and accurate sensors (WPS, inclinometers,…)Low cost linear actuators and cam movers
2011-2016
Task 2: tunnel metrology
Development of laser based alternativesConsolidation of stretched wire solutionValidation through inter-comparisons
Simulations + experimental validation of laser based and stretched wire solutions.
2011-2016
Task 3: active pre-alignment of TBA modules
Validation on two beam modules in lab and CLEXAdaptation to new designs and new configurationsIncreasing performance of fiducialisation techniques & strategies
Mock-ups with associated technical reports on experimental tests
2011-2016
Task 4:active pre-alignment & monitoring in MDI
Development & qualification of solutions for: the determination of the position of QD0 w.r.t the 500m last meters, the relative monitoring of QD0 through the detectors, the re-adjustment within 6 DOF
Mock-ups with associated technical reports on experimental tests
2011-2016
Lead collaborator(s): CERN (Helene Mainaud-Durand et al.)- NIKHEF
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 500 800 1200 1000 800 700 5000
Personnel (FTE): 5.4 7.6 9.1 8.4 7.4 7.4 45.3
http://indico.cern.ch/materialDisplay.py?contribId=54&materialId=slides&confId=115921
CTC-002 Survey and Alignment
WP: CTC-003 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Technology development Rad hard sensors+actuators, vibration measurements and studies
2011-2016
Task 2: Application to MB Quads Prototypes for TBA module program, reports on experiments
2011-2016
Task 3: Application to FF Quads Prototypes for FF mock-ups program, reports on experiments
2011-2016
Task 4: Integration Controler designs, contribution to ATF2 experiments for feed-forward on ground motion.
2011-2016
Lead collaborator(s): LAPP – Lavista, SYMME, ASL, irfu CEA saclay
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 5000
Personnel (FTE):
CTC-003 Quad stability
WP: CTC-004 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Prototype design and fabrication
Engineering design of the two-beam modules, including eng. design of fully integrated components. Fabrication and assembly of componentsGirder R&D, integration of all module technologies
4 two-beam modules to be mechanically tested in a lab (generation 1)3…6 two-beam modules to be mechanically tested in a lab (future generations )3 two-beam modules to be tested with RF and beam in CLEX (generation 1)3 two-beam modules to be tested with RF and beam in CLEX (future generations )
2011-2016
Task 2: Finite element simulations Thermo-mechanical simulation of two-beam module behavior under different load conditions: estimation of resulting forces, deformations and stresses.Application of results to engineering design
Technical report with results of simulations; feedback to taks 1
2011 - 2016
Task 3: Experimental comparison of predicted and modeled performance
Experimental tests of technical system performance (vacuum, cooling, alignment,..) Experimental of overall module behavior under different load conditionsComparison measured with expected resultsReview of results and application to the engineering design
Realization of testsAnalysis of results
2011-2016
CTC-004 two-beam module development CLIC Linkperson: G. Riddone
WP: CTC-004 Purpose/Objectives/Goals Deliverables Schedule
Task 4: Alternative designs - Study of alternative module layout- Longer girders, common DB-MB girders, different materials - Longer RF structures- Permanent DB magnets- Mini-pumps replacing vacuum reservoir
New engineering design for the different options
2012-2016
Task 5: Industrialization Towards cost optimization:- reduction of interconnections- reduction of components and module types Reduction of machining and assembly steps
New module layout
New procedures
2013-2016
http://indico.cern.ch/categoryDisplay.py?categId=1794
Lead collaborator(s): CERN (G. Riddone) , collaborators (HIP-K. Osterberg, NTUA-E. Gazis, CIEMAT-F. Toral, NCP-A.Nawaz,
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 1000 2000 3000 4000 3000 2000 15000
Personnel (FTE):
Resources comment: M foreseen; P: possible
CTC-004 two-beam module development
Other comments: total modules considered for construction: 13-16 (see task 1);All deliverables for modules (Alignment, Stabilization, BI, vacuum, RF structures etc) paid by TBA module budget.
WP: CTC-005 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Normal conducting Magnet Design
Optimization of designs for size, weight, power consumption, cost, series production.
Detailed integration studies for MB and DB quadrupoles. Prototypes of MB and DB quadrupoles, Beam tests.
2011-2016
Task2:Permanent magnet high gradient Quadrupole design
Design of magnets for MDI; detailed integration studies in MDI
Short prototype construction and full size prototye construction. Beam test for validation if possible
2011-2016
Task3:Powering schemes Alternatives electromagnets/permanent magnets with trims; optimization of total energy consumption; machine protection optimization
Designs 2011-2016
Task4:Rad Hard trimmers for strength
Design of trimmers for magnets in main tunnel (powered in series). Rad hard design and qualification
Design and qualification 2011-2016
Lead collaborator(s): CERN (J.Osborne et al); FNAL (V.Kuchler); KEK (A.Enomoto), DESY (W.Bialowons), JINR (G.Shirkov)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 3000
Personnel (FTE):
Resources comment: GS (J.Osborne) will co-ordinate the CES Work Package. Possible input from EPFL for environmental studies. Continued collaboration / resource sharing with ILC foreseen via Worldwide Laboratories
WP: CTC-005 Warm Magnet Prototypes
WP: CTC-006 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Refinement of specifications
- From parameter to Functional specifications
- R&D on intensity, polarization and luminosity measurements
- Development of Damping ring instrumentation in collaboration with B-factories and light sources
-Functional specifications
- Prototype of each monitor
- End of 2016
- End of 2016
Lead collaborator(s): CERN (T. Lefevre et al) – B-factory and
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 10 kCHF 40 KCHF 100 KCHF 150 KCHF 150 KCHF 150 KCHF
Personnel (FTE):
Resources comment: No Manpower assigned to the development of intensity-polarization-luminosity monitors for the moment
CTC-006 Beam Instrumentation-task1
WP: CTC-006 Purpose/Objectives/Goals Deliverables Schedule
Task 2: BPM development - Demonstrate the high resolution of CLIC cavity BPM prototype (linac and BDS) and its read-out electronic - lab and beam test
- Build and test DB decelerator strip line BPM and its read-out electronic – lab and beam test – Iteration for Cost optimization
- Develop of narrow-band high frequency (1-2GHz) combiner diagnostic for Damping ring delay loop and test on CTF3
- RF simulations for estimation of wakefield effects and interference due to the presence of high field in PETS and Acc. Cav.
- Prototype of 14GHz cavity BPM
- Prototype of a DB decelerator BPM
- Prototype of a combiner BPM
- End of 2015
- End of 2014
- End of 2015
- End of 2013
Lead collaborator(s): CERN (L. Soby, S. Smith et al) – RHUL (S. Boogert et al) – Fermilab (M. Wendt)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 300 kCHF 400 kCHF 400 kCHF 400 kCHF 400 kCHF
Personnel (FTE):
Resources comment: Manpower budget used to paid Project associate in 2011. This includes the CLIC-UK funding
CTC-006 beam instrumentation -task2
WP: CTC-006 Purpose/Objectives/Goals Deliverables Schedule
Task 3: Emittance measurement - Design and integration of Laser Wire Scanner in BDS and Drive Beam complex
Technology development for high power fibre laser
- Study alternative option for high spatial resolution non-destructive profile monitors (UV Diffraction radiation)
-Develop and test imaging techniques for the high energy spread beam at the end of the DB decelerator
- Experimental validation of a CLIC Laser Wire Scanner on ATF2 with BPM
- Experimental validation of a CLIC UV DR monitor on CESRTA
- Experimental validation of a DB decelerator imaging system on CTF3
- End of 2016
- End of 2013
-End of 2014
Lead collaborator(s): CERN (T. Lefevre et al) – RHUL (G. Blair , P. Karataev et al) – CESRTA (M. Palmer, M. Billing)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 300 kCHF 400 kCHF 400 kCHF 400 kCHF 400 kCHF 300 kCHF
Personnel (FTE):
Resources comment: This includes the funding of CLIC-UK packages
CTC-006-beam instrumentation task3 (1/2)
WP: CTC-006 Purpose/Objectives/Goals Deliverables Schedule
Task 3: Emittance measurements
- Development of 20fs time resolution longitudinal profile monitor using EO techniques
- Development and test of cheap high resolution bunch length monitor based on Coherent Diffraction Radiation
- Prototype of each monitor - End of 2014
- End of 2016
Lead collaborator(s): CERN (T. Lefevre et al) – RHUL (P. Karataev et al) – U. Dundee (A. Gillespie) – Daresbury (S. Jamison)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 300 kCHF 350 kCHF 350 kCHF 350 kCHF 350 kCHF 300 kCHF
Personnel (FTE):
Resources comment: This includes funding for CLIC-UK packages
CTC-006-beam instrumentation task3 (2/2)
WP: CTC-006 Purpose/Objectives/Goals Deliverables Schedule
Task 4: BLM development - Monte carlo Simulations
- Develop a BLM only sensitive to charged particle for the Damping rings
-Develop and Qualify a cost effective detector technology for CLIC modules
- Functional specifications
-Prototype of each monitor
- End of 2016
- End of 2014
-End of 2015
Lead collaborator(s): CERN (T. Lefevre et al) – B-factory and light sources
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 100 kCHF 150 KCHF 150 KCHF 200 KCHF 200 KCHF
Personnel (FTE):
Resources comment: Including funding for project associate
CTC-006-beaminstrumentation-task4
WP: CTC-007 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Detailed studies for MDI integration
QD0 integration and stabilization, (pre-)alignment integration, pre-isolator, IP-feedback, push-pull studies, backgrounds, radioprotection, safety, luminosity monitoring, polarization, shielding, anti-solenoid, vacuum, L*, cryogenics, services, cavern layout, post-collision line integration, costs, data-transfer to experiments, environmental noise, stray fields, access, interlocks, surface buildings.
Feasibility Report of MDI stability by end 2012
Designs end 2014
Feedback from calculation of experiments background to machine design
2011-2014
Task2:Experimental work/Prototyping
QD0 prototypes, field measurements, validation of quad stability with beam
Prototype by 2012, measurements and Improvements until 2016
2011-2016
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 2000
Personnel (FTE):
WP: CTC-07 MDI activities
WP: CTC-008 Purpose/Objectives/Goals Deliverables Schedule
Task 1:Post Collision Line Design Detailed designs by simulations/calculations
Feasibility Report of MB water dump by end 2012Feedback from simulations on experiments background to dump line design.Integration study with BDS.Designs end 2014
2011-2014
Task2: Luminosity instrumentation
Choice of luminosity instrumentation;Evaluation of expected performance
Report on choice; simulations; signal quality of Luminosity signals. Feedback to beam dynamics.
Task3: Water dump designs:-studies /design of MB dump-studies/design of DB dump- preparation of CLIC0
Detailed designs by simulations/calculations. Collaboration with ILC
Specifications for DB dumps (full DB power?)Designs, engineering for CLIC0 dump
2011-2016
Lead collaborator(s): Possibility in Minsk (SOSNY institute)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 1000
Personnel (FTE):
WP: CTC-008 Beams disposal(post collision line and dumps)
WP: CTC-009 Purpose/Objectives/Goals Deliverables Schedule
Task 1:Studies and Designs Detailed designs of subcomponents (masks). Simulation on radiation levels. Implementation of MP consequences for equipment (2ms fail-proof) and personal safety.
DesignsSafety Procedures and agreements
2011-2016
Task2:Development of a Machine Model
Reliability model of the machine, definition of SIL levels for components.
SIL level specificationsProvide models for integrated studies
2011-2014
Task3: Experimental verification Implementation of a model MP system in CTF3 for validation of the “Next Pulse Permit” concept.
Working prototype of MP system integrated into the control system.
2014-2016
Task4: Definition of operational scenario Coordinated discussions between RF experts, Beam dynamics experts and equipment experts in order to define a commissioning and operations scenario: writeup of results
2012-2013
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 1500
Personnel (FTE):
WP: CTC-009 MP-OP
Time
18 ms; post pulse analysis; confirms OK
2 ms: Machine save by construction
WP: CTC-010 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Site Studies Develop Site Criteria
Environmental Impact studies :
•Site layout, shaft positions, geological investigations etc•Choice of cooling technique (towers, water from lake)•Strategy for electrical network
1.Site selection matrix2.Outline document for Environmental Impact document3.Internal Siting Studies report4. Issue of Site Studies report to external authorities
Mid 2012 :Deliverables 1 & 2Mid 2013 :Deliverable 3End 2016 :Deliverable 4
http://indico.cern.ch/categoryDisplay.py?categId=1882
Lead collaborator(s): CERN (J.Osborne et al); FNAL (V.Kuchler); KEK (A.Enomoto), DESY (W.Bialowons), JINR (G.Shirkov)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 150 kCHF 200 KCHF 200 KCHF 200KCHF 150CHF 100KCHF 1000KCHF
Personnel (FTE): 1FTE 2.5FTE 3FTE 3FTE 2.5FTE 1FTE 13FTE
Resources comment: GS (J.Osborne) will co-ordinate the CES Work Package. Possible input from EPFL for environmental studies. Continued collaboration / resource sharing with ILC foreseen via Worldwide Laboratories
WP: CTC-010 Civil Engineering and Services (CES)
Other comments:
*Material Budget is for external consultancy services (e.g. geologist, environmental experts, design engineers, architects)**Personnel inside CERN will come from several departments, but mainly GS&EN. This staffing estimate needs to be discussed other departments.
WP: CTC-011 Purpose/Objectives/Goals Deliverables Schedule
Task1: Timing reference , timing distribution and 10 fs synchronization
Review of specifications, design of fine-timing system, first practical realization
Specifications, Designs, Lab set-up of master-clock and distribution system,Provide models for integrated studies
2011-2014
Task2 : Module read-out Design of a generic read-out system for all TBA module systems: low power, rad-hard, compact.
Prototypes tested in CTF3 2014-2016
Task3: Design of complete control system
Design of system, better cost estimate, interface specifications for equipment
Designs, interface specifications 2014-2016
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 1500
Personnel (FTE):
Collaborations (some planned) university of ANKARA, DESY, LNBL, PSI, LAPP
WP: CTC-011 Controls
WP: CTC-012 Purpose/Objectives/Goals Deliverables Schedule
Task1: Prototypes of 15 MW 1 GHZ klystrons for DB generation
Contracts with at least 2 industry partners for the development of one (each partner) working 15 MW klystron at 1 GHz and 70% efficiency.
2 working prototypes, options for the procurement of more units
2011-2016
Task2 : Designs of DB accelerator/cavities
Overall DB design as a large power plant
Designs 2011-2016
Task3: LLRF design Design of LLRF system for DB with optimization for phase and amplitude stabilty
Designs, measurements at other plants, modelization tools
2011-2016
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 4000
Personnel (FTE):
Just starting activity, needs people from BE-RF, needs dedicated WG with people from TE-EPC and EN-EG
WP: CTC-012 RF systems
WP: CTC-013 Purpose/Objectives/Goals Deliverables Schedule
Task1:Modulators for DB generation
Revision of specifications, design for highest efficiency for various pulse lengths, prototyping
Modelization toolsMeasurements at existing plants, development of high precision measurement systems2 working modulators for DB klystrons
2011-2016
Task2 : Contribution to Designs of whole DB complex
Overall DB design as a large power plant (building, energy supply, cooling, interface to French power plants).Main electricity consumer: modulators for klystrons.
Designs of modulators/racks/controls/infrastructure
2011-2016
Task3: Powering schemes for CLIC complex
Follow up of CLIC design changes, designs for powering systems, space reservation, cost estimate
Designs and updated cost estimate 2011-2016
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): (details task3)
50 50 0 0 50 200 4000
Personnel (FTE): (Details task 3)
0.5 0.2 0.2 0.2 0.2 1.5
Just starting activity, needs dedicated WG with people from BE-RF and EN-EL
WP: CTC-013 powering
WP: CTC-014 Purpose/Objectives/Goals Deliverables Schedule
Task 1 Vacuum system for TBA modules Designs, interconnections, vacuum systems, production of quadrupole vacuum chambers for up to 16 modules
2011-2016
Task 2 Contribution to RF structure production
Cleaning procedures, testing, procedure for structure production
2011-2016
Task 3 Vacuum chambers with low SEY (in particular for DRs)
Designs, experimental tests of coatings at CESR-TA
2011-2016
Task 4 Vacuum design for CLIC Specific designs for injectors, MB transport, combiner rings, DB transport and BDS/MDI
2011-2016
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 1500
Personnel (FTE):
WP: CTC-014 vacuum systems
Needs completion
WP: CTC-015 Purpose/Objectives/Goals Deliverables Schedule
Task 1: Simulation Study of stray fields on machine parameters, distinction between static effects and dynamic effects
Reports Done in BD team
Task 2: Measurements in accelerator environments of magnetic fields down to limits established in task 1Measurements on correlation between dynamic field changes as function of the distance of the measurements.
Reports, feedback to BD 2013-2016
Lead collaborator(s):
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 500
Personnel (FTE):
WP: CTC-015 Magnetic Stray fields Measurements
WP: CTC-016 Purpose/Objectives/Goals Deliverables Schedule
Task 1: DR extraction kickers Demonstration of power supply capable of generating pulse with extremely low ripple and droop
Preparation and Participation in ATF2 beam tests
Prototype inductive adder, possibly with sophisticated control system for droop and Ripple cancellation. Beam tests; Report
Prototype inductive adder available mid 2013 for installation in ATF2….
http://ilcagenda.linearcollider.org/materialDisplay.py?contribId=199&sessionId=77&materialId=slides&confId=4507
Lead collaborator(s): CERN (M. Barnes & J. Holma); LLNL (E. Cook)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): 160 kCHF 120 KCHF 120 KCHF 80 kCHF 60 kCHF 540
Personnel (FTE): 1.5 1.5 1.2 0.6 0.6 5.4
Resources comment: M foreseen; P: possible if present people stay. R&D at CERN with collaborators from LLNL.
CTC-016 DR Extraction System (1/2)
Other comments: The importance for CERN is: comparison and choice of technologies, validation of prototype in an operational facility. Extremely challenging technical specifications to be demonstrated: possible fallback solutions should also be investigated, including sophisticated control system for droop and ripple cancellation – but manpower and resources are limited.
WP: CTC-016 Purpose/Objectives/Goals Deliverables Schedule
Task 2: DR extraction kickers Demonstration of low beam coupling impedance, high field uniformity, impedance matched, striplines.
Prototype striplines, designed at University of Valencia and manufactured at TRINOS vacuum projects.
Prototype striplines available mid 2013 for installation in ATF
http://indico.cern.ch/getFile.py/access?contribId=3&resId=0&materialId=slides&confId=96743
Lead collaborator(s): CERN (M. Barnes); University of Valencia (A. Faus-Golfe & C. Belver Aguilar)
Resources: 2011 2012 2013 2014 2015 2016 Total Material (kCHF): CDTI CDTI + small
contribution?40 KCHF 20 kCHF ?+60 KCHF
Personnel (FTE): 1.2 1.2* 0.6 0.4 3.4
Resources comment: M foreseen; P: possible if present people stay. R&D at University of Valencia & manufacturing at TRINOS-VP.* Does not include manpower in Spanish Industry.
CTC-016 DR extraction system (2/2)
Other comments: The importance for CERN is: optimization of design of striplines for CLIC damping ring (e.g. cross-section, coverage angle, taper, beam pipe dimensions), verification of beam impedance; R&D mainly carried out by collaborators. Prototyping in Spanish industry. Main costs for R&D and manufacture are paid by CDTI, Spain (IDC-20101074): small contribution may be requested from CERN.Extremely challenging technical specifications to be demonstrated.
Beam
Feedthru
Ceramic support
CTC Summary TableCTC-01 SC Wigglers 2000 S.Russenschuck et al.CTC-02 Survey and Alignment 5000 45.3 Helene et al./ no formal WGCTC-03 Quadrupole Stability 5000 Kurt et al./Stability WGCTC-04 TBA module 15000 Germana et al./TBA WGCTC-05 Warm magnet prototypes 3000 Michele et al./ no formal WGCTC-06 beam instrumentation 5400 Thibaut et al./no formal WGCTC-07 MDI activities 2000 Lau et al./MDI WGCTC-08 Beams disposal 1000 Edda et al. /PCLD WGCTC-09 Machine Protection 1500 Michel et al./MPOP WGCTC-10 Civil Engineering and Services (CES) 1000 13 John et al./ CES WGCTC-11 Controls 1500 just startingCTC-12 RF systems 9000 Erk et al./ needs WGCTC-13 Powering 4000 David/Serge et al./needs WGCTC-14 Vacuum Systems 1500 S.Calatroni et al. WG needed?CTC-15 Magnetic Strayfields 500 activity to be startedCTC 16 DR extraction system 600 8.8 M.Barns et al.
58000