HYDROLOGY PROJECT -IICPCB COMPONENT

WATER QUALITY DOMAIN

CENTRAL POLLUTION CONTROL BOARD

Page 2: Cpcb hp ii final supervision mission

Major Activities and Achievements•Real Time Water Quality Monitoring- Installation of 10 stations on river Ganga (8 Stations) and Yamuna (2 Stations)•Renovation of CPCB Water Laboratory covering an area of about 660 square meter and procurement of laboratory and seating furniture•Development of GIS based Web Portal on Water Quality- Visualisation of existing and historical water quality data modules are being developed. •Development of Water Quality Criteria and Standards on surface, water, ground water and marine water. •Development of Decision Support System (DSS) Planning-Water Quality domain for River Bhima. •Development of specifications of Water Quality Lab Equipment/Instruments.• Organised 30 Trainings / Workshops on different aspects of Water Quality for Implementing Agencies. Each training programme was attended by 25 laboratory persons involved in water quality monitoring.

Page 3: Cpcb hp ii final supervision mission

Real Time Water Quality Monitoring of River Ganga and Yamuna

Real Time Water Quality Monitoring of River Ganga (at Haridwar- Upper Ganga Barrage-BhimGoda), Kannauj (Nanamau Bridge), Downstream, Kanpur (Jajmau Bridge Kanpur), Allahabad (Shastri Bridge), Upstream, Varanasi, Upstream, Varanasi, Downstream, Gandhi Ghat, Patna (floating platform), Garden Reach, Kolkata ) and River Yamuna (at Delhi Upstream, Wazirabad and Delhi Downstream Okhla) at 10 locations.Monitoring system is sensor basedSystem functioning for a period of 12 months System have telecommunication systemData transmission through telemetry in server installed in CPCB Delhi OfficeMonitoring data is under going verification through manual monitoringSystem has strengths and weaknessesPossibilities of improvement is being explored

Page 4: Cpcb hp ii final supervision mission

Monitoring Location

Page 5: Cpcb hp ii final supervision mission

Real Time Water Quality Monitoring of River Ganga and Yamuna

Page 6: Cpcb hp ii final supervision mission
Page 7: Cpcb hp ii final supervision mission

Limitations/Achievements of Monitoring System•Site selection and Timely clearance/permission for installation • Frequent calibration is required• Security in remote areas a cause of concern• Wide variation in real time values in respect of some parameters (BOD,COD and Nitrate) however relatively reliable observations in respect of other parameters (pH, DO, Temperature, Colour, Conductivity, Turbidity, Chloride and Ammonia) •System is workable however drop time observed invariably due to communication failure or power disruption•Data used during Maha Kumbh Event 2013/Magh Mela 2014 and issues with water quality intake point of Delhi on Yamuna for instant reporting•Direction issued to SPCB for corrective action on water quality deterioration at water intake point of Delhi and regularly used during Maha Kumbh event.

Page 8: Cpcb hp ii final supervision mission

8

Development of GIS based Web Portal on Water Quality

PROJECT TIME SCHEDULEGIS BASED WEB PORTAL ON WATER QUALITY FRAMEWORKGEOGRAPHIC INFORMATION SYSTEM(GIS)

LOGIN CREDENTIALSGIS PAGE VISUALIZATIONGIS MAP WITH MAP SERVICEAUTOMATIC MONITORING STATION VISUALIZATIONMAP TOOLS

LAYER MANAGEMENTINFORMATION TOOL WITH TREND ANALYSISCUSTOM DATA RETRIEVALPROXIMITY INFORMATIONBASIN ANALYSISRIVER WISE MONITORING STATIONSOFFLINE ANALYSIS TOOLS

USER MANAGEMENT INFORMATION SYSTEM(UMIS)FINANCIAL MANAGEMENT INFORMATION SYSTEM(FMIS)REMOTE SENSING DATA PROCESSING (RSDP)

Page 9: Cpcb hp ii final supervision mission

9

Project Time Schedule

Stocktaking, Initial consultation - Incep-

tion Report

Systems Require-ment Specifications

Development of UMIS,FMIS & GIS

Water Quality Frameworks and

presentation

Procurrment of Software and

Hardware

Deployment, Testing of Web Portal

Final Deployment on Main Server

Maintenance

Planned 30 120 180 210 360 420 NaN

50

150

250

350

450

30120

180 210

360420

Planned

Project Milestone

Days

# Project Milestone Status1 Stocktaking, Initial consultation - Inception Report

2 Systems Requirement Specifications

3 Development of UMIS,FMIS & GIS Water Quality Frameworks and presentation

4 Procurrment of Software and Hardware

5 Deployment, Testing of Web Portal

6 Final Deployment on Main Server

7 Maintenance

Milestone Completed

In-Process

Process yet to start

INTRODUCTION GIS UMIS FMIS RSDP

Page 10: Cpcb hp ii final supervision mission

10

Home Page

INTRODUCTION GIS UMIS FMIS RSDP

Page 11: Cpcb hp ii final supervision mission

11

GIS Based Web Portal on Water Quality Framework

Parameter wise Online Analysis

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 12: Cpcb hp ii final supervision mission

12

Data Visualization

Dissolved Oxygen (mg/L) Visualization for 2011 Data considered at minimum value

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 13: Cpcb hp ii final supervision mission

13

Login For Secure Site

Basin wise Login or Login for all basin at National Level

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 14: Cpcb hp ii final supervision mission

14

GIS River Basin Data Visualization

National Level Login for all basins visualization

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 15: Cpcb hp ii final supervision mission

15

GIS Ganga Basin Visualization

Ganga basins visualization

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 16: Cpcb hp ii final supervision mission

16

Map with Map Service View

ESRI Hybrid Map Service

Bhuvan Map Service

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 17: Cpcb hp ii final supervision mission

17

Automatic Water Quality Monitoring Station Integration

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 18: Cpcb hp ii final supervision mission

18

Layer ManagementGeographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 19: Cpcb hp ii final supervision mission

19

Information Tool with Trend AnalysisGeographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 20: Cpcb hp ii final supervision mission

20

Custom Data RetrievalGeographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 21: Cpcb hp ii final supervision mission

21

Proximity Information

100 KM Proximity Information

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 22: Cpcb hp ii final supervision mission

22

Sub-Basin Analysis

Selected Sub-basin

Geographic Information System

INTRODUCTION GIS UMIS FMIS RSDP

Page 23: Cpcb hp ii final supervision mission

23

User Management Information SystemUser Management Information System - UMIS

INTRODUCTION GIS UMIS FMIS RSDP

Page 24: Cpcb hp ii final supervision mission

24

User ManagementUser Management Information System - UMIS

INTRODUCTION GIS UMIS FMIS RSDP

Page 25: Cpcb hp ii final supervision mission

25

Password Management

Change Password

Reset Password

User Management Information System - UMIS

INTRODUCTION GIS UMIS FMIS RSDP

Page 26: Cpcb hp ii final supervision mission

Physical and Financial StatusActivities Project Cost Physical status Financial Status

Real Time Water Quality Monitoring Network of 10 stations

Rs. 561 Lacs INSTALLED & COMMISSIONED

Rs 261 Lacs released. Rs. 112 Lacs are under processing for release.Rs 188 Lacs as two year AMC to be borne under CPCB Funds/HP-III

Renovation of CPCB Water Laboratory

Rs. 152 Lacs COMPLETED PAYMENT RELEASED

Development of GIS based Web Portal on Water Quality

Rs.280 Lacs ONGOING 50% payment shall be released by 31st May,14,20% payment by September 14, Three years AMC to be borne under CPCB Funds/ HP-III

Training / Workshops

Officials of Implementing agencies trained

Pending payment of Rs. 6.50 lacs to be released

Development of Water Quality Criteria and Standards

Rs 21 LacsCOMPLETED Committee constituted to finalise the

process for publication.

Page 27: Cpcb hp ii final supervision mission

Overall Expenditure Status Allocation under the project as per PIP (Rs Crores)

Expenditure up to March 2014 (Rs Crores)

Likely expenditure by May 31,2014 (Rs. Crores)

16.70 crores Rs 6,47,07,729/- Rs 2,12,00,000/-

Page 28: Cpcb hp ii final supervision mission

Continuation of HP 2 activities…..

• Annual Maintenance Services Contract for Real Time Water Quality Monitoring Network of 10 stations - Annual maintenance contract is up to 2017 (Rs.2.0 Crore).

• Consultancy on GIS based Web Portal on Water Quality –

continuation of activity on development and hosting of website including Annual maintenance contract up to 2017 (Rs. 0.84 Crore).

Page 29: Cpcb hp ii final supervision mission

Proposed Activities for HP-IIIActivities Amount

(in Crore)

1. Consultancy services on development of software for Integration of Water Quality Monitoring Networks and data sharing protocol (Project for a period of 5 year along with AMC)

Rs.2.0 Crore.

2. Consultancy services on preparation of nationwide compendium based on Basin Sub Basin Inventory of Water Pollution & Development of Hardcopy Atlas and Web based System

Rs.15 Crore.

3. Consultancy services for Analytical Quality Assurance and Control to existing laboratories developed under Hydrology Project–I and II. (Project for a period of 5 year along with AMC)

Rs. 2 Crore.

Page 30: Cpcb hp ii final supervision mission

Total project cost for HP-III shall be Rs 28 Crore including manpower component.