construction of breakwaters

Upload: manu696

Post on 02-Jun-2018

259 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/11/2019 Construction of Breakwaters

    1/104

  • 8/11/2019 Construction of Breakwaters

    2/104

    Breakwaters are man made structures

    constructed to protect Port and Harbour

    structures from fury of ocean waves and

    provide tranquil conditions for ships at

    berth.

  • 8/11/2019 Construction of Breakwaters

    3/104

    BREAKWATERPROFILES

  • 8/11/2019 Construction of Breakwaters

    4/104

    Breakwaters are mainly classified

    under the following four groupsdepending upon their type of

    construction and sea-ward slope.

  • 8/11/2019 Construction of Breakwaters

    5/104

    Vertical breakwater - Type V

    Composite breakwater - Type C

    Special type of breakwaters

    Sloping breakwater - Type S

  • 8/11/2019 Construction of Breakwaters

    6/104

    Sloping breakwater - Type S:

    This has a sea-ward sloping face of 1:1 or

    flatter.

  • 8/11/2019 Construction of Breakwaters

    7/104

    Vertical breakwater - Type V:

    This has a vertical or near vertical sea-

    ward face

  • 8/11/2019 Construction of Breakwaters

    8/104

    Composite breakwater - TypeC:

    This consists of a vertical breakwaterconstructed on a rubble foundation

    with slope on both sides.

  • 8/11/2019 Construction of Breakwaters

    9/104

    Special type of breakwaterssuch as

    sub-merged breakwaters,

    floating breakwaters,

    bubble screen

    (compressed air) breakwaters

    are used for special applications.

  • 8/11/2019 Construction of Breakwaters

    10/104

    Typical cross sectionsof the first three types

    of breakwaters are shown in the Figure.

  • 8/11/2019 Construction of Breakwaters

    11/104

    TYPICAL CROSS SECTION OF BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    12/104

  • 8/11/2019 Construction of Breakwaters

    13/104

    Rubble Mound

    Conventional multi-layerrubble mound

    Multi-layer rubble mound

    with superstructure

    Berm Breakwater

    Reef Breakwater

  • 8/11/2019 Construction of Breakwaters

    14/104

    TYPES OF RUBBLEMOUND BREAKWATERS

    Conventional Rubblemound Breakwater

    Toe

    Core

    LeesideSeaside

    Filter

    Crest

    LWL

    HWL

  • 8/11/2019 Construction of Breakwaters

    15/104

    Berm Breakwater

    CORE

    CREST

    BERM

    SEA SIDE LEE SIDE

    FILTER

    LWL

    HWL

    N EPT F WIDE T E BERM IN DE I N

  • 8/11/2019 Construction of Breakwaters

    16/104

    N EPT F WIDE T E-BERM IN DE I N

    OF RUBBLEMOUND BREAKWATER

    Wide Toe Core

    LeesideSeasideCrest

    LWL

    HWL

    Filter

    Breakwater with Wide - Toe Berm

    +11 m7 m

    Lee SideSea Side

    20 m0.0 m Core

    35 t

    - 7 m

    Damage Profile

    COST COMPARISON

  • 8/11/2019 Construction of Breakwaters

    17/104

    Net Saving = Rs. 12 Crores

    COST COMPARISON

    OF CONVENTIONAL & WIDE TOE BERM BREAKWATER

    Conventional

    1) Tetrapod = 43 T ( 73 Cum / m)@ Rs. 6000/Cum = Rs. 4.38 Lakh / m

    2) Toe berm = ( 3-5 t stones)= 181 T/m

    @ Rs. 340/ T = Rs. 0.62 Lakh/ Rmt

    3) Secondary ( 0.75- 2t stones) = 566 T/m

    @ Rs. 340/ T = Rs. 1.92 Lakh / Rmt

    4) Core Stones ( 5-500 kg) = 600 T/m

    @ Rs. 250/ T = Rs. 1.40 Lakh / m

    Total = Rs. 8.32 Lakh / m

    Total Cost for 600 m = Rs 49.9 Crore

    Wide Toe Berm

    1) Tetrapod = 12 T ( 46 Cum / m)@ Rs. 4475/ Cum = Rs. 2.05 Lakh / m

    2) 20 m toe berm ( 3-5 t stones)= 275 T/m

    @ Rs. 340/ T = Rs. 0.94 Lakh/ Rmt

    3) Secondary ( 0.75- 2t stones) = 566 T/m

    @ Rs. 340/ T = Rs. 1.92 Lakh / Rmt

    4) Core Stones ( 5-500 kg) = 600 T/m

    @ Rs. 250/ T = Rs. 1.40 Lakh / m

    Total = Rs.6.31 Lakh / m

    Rs 37.9 Crore

  • 8/11/2019 Construction of Breakwaters

    18/104

    Various types of natural rock are

    normally used. However, when

    sufficiently large blocks are not available

    from the quarry or the wave conditions

    are very severe at the breakwater

    locations, the concrete artificial armour

    unitsare used.

  • 8/11/2019 Construction of Breakwaters

    19/104

    About 40 different types of artificial

    armour units have been developed.The important among them are

    shown in Figure.

    ARTIFICIAL CONCRETE BLOCKS FOR BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    20/104

    ARTIFICIAL CONCRETE BLOCKS FOR BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    21/104

    BREAKWATER DESIGN FORMULAE

  • 8/11/2019 Construction of Breakwaters

    22/104

    RUBBLE MOUND BREAKWATER SLOPES

    The stability of the Breakwater is

    dependent on its slope.

    The weight of the armour unit increases

    with the steepness in slope.

    Generally adopted slopes are 1:1.5 to 1:3

  • 8/11/2019 Construction of Breakwaters

    23/104

    STABILITY TESTS

    Though the cross section of the

    breakwater are evolved based on the

    Empirical Formulae, it is essential to carry

    out a Flume Test with Random Waves.

  • 8/11/2019 Construction of Breakwaters

    24/104

    MODEL TESTS

    Mathematical Model

    Physical Model

    Wave Basin and

    Wave Flume

  • 8/11/2019 Construction of Breakwaters

    25/104

    OPTIMISATION OF DESIGN OFRUBBLEMOUND BREAKWATERS

    Hydraulic Model Studies in Wave Flumes / Basins

  • 8/11/2019 Construction of Breakwaters

    26/104

  • 8/11/2019 Construction of Breakwaters

    27/104

  • 8/11/2019 Construction of Breakwaters

    28/104

  • 8/11/2019 Construction of Breakwaters

    29/104

  • 8/11/2019 Construction of Breakwaters

    30/104

  • 8/11/2019 Construction of Breakwaters

    31/104

  • 8/11/2019 Construction of Breakwaters

    32/104

  • 8/11/2019 Construction of Breakwaters

    33/104

  • 8/11/2019 Construction of Breakwaters

    34/104

  • 8/11/2019 Construction of Breakwaters

    35/104

    MODES OF FAILURES OF CONVENTIONAL

    RUBBLEMOUND BREAKWATER

    Slip FailureScour

    Berm & Toe

    Erosion Filter

    InstabilityCore Settlement

    Sub Soil Settlement

    Erosion, Breakage

    of Armour

    Overtopping

    Breaking, Sliding,

    Tilting of CoppingWall

    VentingSlip FailureSlip Failure

    RUBBLE MOUND BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    36/104

    RUBBLE MOUND BREAKWATERSRecommended three layer section

    (Shore Protection Manual1984)

    VERTICAL BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    37/104

    Conventional Caisson Type Breakwater

    Conventional Block Type Breakwater

    Sloping Top Type Breakwater

    VERTICAL BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    38/104

    Perforated Wall Type Breakwater

    Japanese Type Breakwater

    Composite Type Breakwater

  • 8/11/2019 Construction of Breakwaters

    39/104

    RUBBLE MOUND BREAKWATER

    CONSTRUCTION TECHNIQUES

  • 8/11/2019 Construction of Breakwaters

    40/104

    Land or Marine Haul of Material

    Land or Marine Placing of Materials

    Construction from Shore outwards and

    Construction from offshore towards shore

    One or all the above combination may be

    required in a particular project.

  • 8/11/2019 Construction of Breakwaters

    41/104

    Land Based Equipment

    Direct Dumping of Material

    Dump Trucks

    Loaders and

    Cranes

  • 8/11/2019 Construction of Breakwaters

    42/104

    Land Based Equipment

    Controlled Placing

    Cranes

    BREAKWATER CONSTRUCTION

  • 8/11/2019 Construction of Breakwaters

    43/104

    LAND BASED EQUIPMENT

  • 8/11/2019 Construction of Breakwaters

    44/104

    DIGITAL CHARACTERIZATION OF THE BLAST FACEBEFORE BLASTING.

  • 8/11/2019 Construction of Breakwaters

    45/104

    SORTING OF STONES IN QUARRY

  • 8/11/2019 Construction of Breakwaters

    46/104

    Q

    LOADING OF STONES INTO DUMPERS

  • 8/11/2019 Construction of Breakwaters

    47/104

  • 8/11/2019 Construction of Breakwaters

    48/104

    TRANSPORT OF STONES FROM

    QUARRY TO BREAKWATER

    CASTING OF ARTIFICIAL CONCRETE BLOCKS

    http://www.xbloc.com/htm/projects.php?projectid=10http://www.xbloc.com/htm/projects.php?projectid=10
  • 8/11/2019 Construction of Breakwaters

    49/104

    CASTING OF ARTIFICIAL CONCRETE BLOCKS

    STACKING OF ARTIFICIAL CONCRETE BLOCKS

    http://www.xbloc.com/htm/projects.php?projectid=10http://www.xbloc.com/htm/projects.php?projectid=10
  • 8/11/2019 Construction of Breakwaters

    50/104

    STACKING OF ARTIFICIAL CONCRETE BLOCKS

  • 8/11/2019 Construction of Breakwaters

    51/104

    ARTIFICIAL CONCRETE BLOCKSSTACKYARD

    HANDLING OF ARTIFICIAL CONCRETE BLOCKS

    http://www.xbloc.com/htm/projects.php?projectid=5http://www.xbloc.com/htm/projects.php?projectid=5
  • 8/11/2019 Construction of Breakwaters

    52/104

    HANDLING OF ARTIFICIAL CONCRETE BLOCKS

    HANDLING ATTACHMENT FOR ARTIFICIAL CONCRETE BLOCKS

    http://www.xbloc.com/htm/projects.php?projectid=5http://www.xbloc.com/htm/projects.php?projectid=5
  • 8/11/2019 Construction of Breakwaters

    53/104

    HANDLING ATTACHMENT FOR ARTIFICIAL CONCRETE BLOCKS

    HANDLING OF ARTIFICIAL CONCRETE BLOCKS IN STACKYARD

  • 8/11/2019 Construction of Breakwaters

    54/104

    HANDLING OF ARTIFICIAL CONCRETE BLOCKS IN STACKYARD

  • 8/11/2019 Construction of Breakwaters

    55/104

    PLACING OF ARMOUR STONES

  • 8/11/2019 Construction of Breakwaters

    56/104

    PLACING OF ARTIFICIAL CONCRETE BLOCKS

  • 8/11/2019 Construction of Breakwaters

    57/104

    PLACING OF ARTIFICIAL CONCRETE BLOCKS

  • 8/11/2019 Construction of Breakwaters

    58/104

    PLACING OF ARTIFICIAL CONCRETE BLOCKS

    PLACING OF ARTIFICIAL CONCRETE BLOCKS

  • 8/11/2019 Construction of Breakwaters

    59/104

    BREAKWATER CONSTRUCTION - LAND BASED TECHNIQUES

  • 8/11/2019 Construction of Breakwaters

    60/104

  • 8/11/2019 Construction of Breakwaters

    61/104

    Floating Equipment

    Direct Dumping of Material

    Split Barges

    Bottom Door Barges

    Tilting Barges

    Floating Equipment

  • 8/11/2019 Construction of Breakwaters

    62/104

    Floating Equipment

    Controlled Placing Side Stone Dumping Vessel

    Fall Pipe Vessel

    Flat Deck Barges with Bull Dozer

    Pontoon with a Crane

    BREAKWATER CONSTRUCTIONFLOATING EQUIPMENT

  • 8/11/2019 Construction of Breakwaters

    63/104

    Q

    Split Hopper Barge Dumping through a pipeSide Stone DumpingVessel

    CONSTRUCTION - GEOTEXTILE

  • 8/11/2019 Construction of Breakwaters

    64/104

    CONSTRUCTION - CORE

  • 8/11/2019 Construction of Breakwaters

    65/104

    CONSTRUCTION CORE

    CONSTRUCTION - TOE

  • 8/11/2019 Construction of Breakwaters

    66/104

    CONSTRUCTION - CORELOC

  • 8/11/2019 Construction of Breakwaters

    67/104

  • 8/11/2019 Construction of Breakwaters

    68/104

  • 8/11/2019 Construction of Breakwaters

    69/104

  • 8/11/2019 Construction of Breakwaters

    70/104

  • 8/11/2019 Construction of Breakwaters

    71/104

  • 8/11/2019 Construction of Breakwaters

    72/104

  • 8/11/2019 Construction of Breakwaters

    73/104

  • 8/11/2019 Construction of Breakwaters

    74/104

  • 8/11/2019 Construction of Breakwaters

    75/104

  • 8/11/2019 Construction of Breakwaters

    76/104

  • 8/11/2019 Construction of Breakwaters

    77/104

    VERTICAL BREAKWATER

    CONSTRUCTION TECHNIQUES

    CAISSON UNDER CONSTRUCTION

  • 8/11/2019 Construction of Breakwaters

    78/104

    CAISSON BEING TOWED TO POSITION

  • 8/11/2019 Construction of Breakwaters

    79/104

    CAISSON BEING TOWED TO POSITION

    CAISSON IN POSITION

  • 8/11/2019 Construction of Breakwaters

    80/104

  • 8/11/2019 Construction of Breakwaters

    81/104

    BREAKWATER CASE STUDIES

  • 8/11/2019 Construction of Breakwaters

    82/104

    PARADIP PORT

  • 8/11/2019 Construction of Breakwaters

    83/104

    PARADIP PORT

  • 8/11/2019 Construction of Breakwaters

    84/104

  • 8/11/2019 Construction of Breakwaters

    85/104

    PORT OF VISAKHAPATNAM LAYOUT OF OUTER HARBOUR

  • 8/11/2019 Construction of Breakwaters

    86/104

  • 8/11/2019 Construction of Breakwaters

    87/104

    CHENNAI PORT

  • 8/11/2019 Construction of Breakwaters

    88/104

  • 8/11/2019 Construction of Breakwaters

    89/104

    TUTICORIN PORT

  • 8/11/2019 Construction of Breakwaters

    90/104

    MORMUGAO PORT

  • 8/11/2019 Construction of Breakwaters

    91/104

  • 8/11/2019 Construction of Breakwaters

    92/104

    NEW MANGALORE PORT

  • 8/11/2019 Construction of Breakwaters

    93/104

    NEW MANGALORE PORT

  • 8/11/2019 Construction of Breakwaters

    94/104

    KAKINADA PORT BREAKWATER

  • 8/11/2019 Construction of Breakwaters

    95/104

    MOPLABAY CANNANORE

  • 8/11/2019 Construction of Breakwaters

    96/104

    FISHERIES HARBOUR

  • 8/11/2019 Construction of Breakwaters

    97/104

    REHABILITATION OF BREAKWATERS

  • 8/11/2019 Construction of Breakwaters

    98/104

  • 8/11/2019 Construction of Breakwaters

    99/104

    CONSTRAINTS IN REHABILITATION OFBREAKWATER

  • 8/11/2019 Construction of Breakwaters

    100/104

    BREAKWATER

    CAUSES OF DAMAGE

  • 8/11/2019 Construction of Breakwaters

    101/104

    Freak waves of 4 m to 8 m height attackedbreakwater on 10 April 1987

    Breakwater was in construction stage. Breakwater was designed for 4.0 m waves.

    Higher waves overtopped the breakwater.

  • 8/11/2019 Construction of Breakwaters

    102/104

    DAMAGED BREAKWATER AT PORBANDAR

  • 8/11/2019 Construction of Breakwaters

    103/104

    Causes of damage

    Severe cycloneof June 1998caused total damage to 600 mlength of breakwater from the

    roundhead.

    Higher waves than designwave lead to overtopping oflower crest

  • 8/11/2019 Construction of Breakwaters

    104/104