cleuson - dxei nce
TRANSCRIPT
CLEUSON - DIXENCEINTRODUCING A HYDROELECTRIC COMPLEX UNIQUE IN THE WORLD
CLEUSON-DIXENCE COMPLEXCONTEXT
3
The original three power plants at Chandoline, Fionnay and Nendaz, with a capacity of 800 MW, take 2200 hours to turbine the 400 million m3 of water stored in the Grande Dixence lake.
To optimise this tremendous potential which represents 20% of the stored energy in Switzerland, the Cleuson-Dixence facility was built to increase the production capacity by 1200 MW to 2000 MW.
This reduces production to approximately 1’000 hours and, when there is a high demand for energy, enables peak power to be provided to the distribution grid.
Cleuson-Dixence produces 2.5 times the power of the Alpiq-Grande Dixence complex.
In 1992, a partnership was founded to build and operate this new facility which cost 1300 million CHF. Alpiq Suisse SA has a 7/22 participation and Grande Dixence SA a 15/22 participation.
FIONNAY PLANT
NENDAZPLANT
BIEUDRONPLANT
CHANDOLINEPLANT
Nendaz
HérémenceMéribé
Plan Désert
Voua
sson
Zerm
att /
Aro
lla
Vex
RHÔNE RIVER
RIVER
PRINTZE
BORGNE RIVER
LA FARA
RIVER
DRAN
SE R
IVER
DIXENCE RIVER
Hérémence Valley
Nendaz Valley
Bagne
s Vall
ey
Hérens Valle
y
Mont Fort
Rosablanche
Pointed’Allèves
Pic d'Artsinol
GrepponBlanc
Mont Rouge
Sion
Dent deNendazMont
Gond
GRANDEDIXENCE
Le Chargeur
TortinTracouet
CLEUSON
CLEUSON-DIXENCE COMPLEXOVERVIEW
FIONNAY PLANT
NENDAZPLANT
BIEUDRONPLANT
CHANDOLINEPLANT
Nendaz
HérémenceMéribé
Plan Désert
Voua
sson
Zerm
att /
Aro
lla
Vex
RHÔNE RIVER
RIVER
PRINTZE
BORGNE RIVER
LA FARA
RIVER
DRAN
SE R
IVER
DIXENCE RIVER
Hérémence Valley
Nendaz Valley
Bagne
s Vall
ey
Hérens Valle
y
Mont Fort
Rosablanche
Pointed’Allèves
Pic d'Artsinol
GrepponBlanc
Mont Rouge
Sion
Dent deNendazMont
Gond
GRANDEDIXENCE
Le Chargeur
TortinTracouet
CLEUSON
5EXISTING FACILITIES
CLEUSON-DIXENCE FACILITY
TEMPORARY CONSTRUCTION CABLE CAR
PRODUCTION PLANTS
DAMS
CLEUSON-DIXENCE COMPLEXMAIN SPECIFICATIONS
7
Constructed entirely underground between 1993 and 1998, the Cleuson-Dixence facility includes the following main components :
1 A new water intake drilled through the Grande Dixence dam at Le Chargeur.
2 A 15.8 km long headrace tunnel from the dam to Tracouet.
3 A surge chamber at Tracouet, excavated in the Dent-de-Nendaz mountainside.
4 A 4.3 km long penstock connecting Tracouet to the Bieudron plant.
5 An underground plant equipped with three vertical generators each fitted with a 423 MW Pelton turbine and a 465 MVA generator.
(By way of comparison, the Gösgen nuclear power plant has an in-stalled power capacity of 970 MW and the Leibstadt plant, 1165 MW).
The energy produced across all the Alpiq-Grande Dixence- Cleuson-Dixence facilities reaches approximately 2000 million kWh per year, which corresponds to the average annual consumption of 400’000 households.
2500 m
R 2.20 m
Casing4.70 m R 2.915 m
Drill hole
5.60 mØ 3.80
mPrecast
segment
Ø 5.26 m
Lining
int. Ø
4.20
m
15'833 m
LOT B
Pressurised headrace gallery
Pressurised headrace gallery
LOT C LOTS D AND FLOT A
Concrete gallery 11’588 m Steel lining 2790 mSteel lining 1455 m
Le Chargeur
Water intake
DIX LAKE
Pte d'Allève
La Grande Arpette
Mont Gond
Tortin Tracouet Bieudron
SURGE CHAMBER
Dent de Nendaz
Penstock
4230 m BIEUDRON PLANT 1,200 MW
3000 m
2000 m
1500 m
1000 m
500 m
RHÔNE
CLEUSON LAKE
Max
. gro
ss h
ead
1883
m
F1
F2
F4
F5
F6
F7
TRACOUET
DZERDJONNA
PÉROUA
CONDÉMINES
4.40
m
4.40 m
R 2.63 m
R 2.40 m
CLEUSON-DIXENCE COMPLEXLONGITUDINAL PROFILE DIAGRAM
2500 m
R 2.20 m
Casing4.70 m R 2.915 m
Drill hole
5.60 mØ 3.80
mPrecast
segment
Ø 5.26 m
Lining
int. Ø
4.20
m
15'833 m
LOT B
Pressurised headrace gallery
Pressurised headrace gallery
LOT C LOTS D AND FLOT A
Concrete gallery 11’588 m Steel lining 2790 mSteel lining 1455 m
Le Chargeur
Water intake
DIX LAKE
Pte d'Allève
La Grande Arpette
Mont Gond
Tortin Tracouet Bieudron
SURGE CHAMBER
Dent de Nendaz
Penstock
4230 m BIEUDRON PLANT 1,200 MW
3000 m
2000 m
1500 m
1000 m
500 m
RHÔNE
CLEUSON LAKE
Max
. gro
ss h
ead
1883
mF1
F2
F4
F5
F6
F7
TRACOUET
DZERDJONNA
PÉROUA
CONDÉMINES
4.40
m
4.40 m
R 2.63 m
R 2.40 m
0 1 2 3 4 5km
9
Access tunnelsF1 F7
Lower carboniferousShaly sandstone"St Christophe" schists
15'833 m
LOT B LOT C LOTS D AND FLOT A
Le Chargeur
DIX LAKE
Pte d'Allève
La Grande Arpette
Mont Gond
Tortin Tracouet Bieudron
SURGE CHAMBER
Dent de Nendaz
Penstock
4230 m BIEUDRONPLANT1200 MW
3000 m
2500 m
2000 m
1500 m
1000 m
500 m
RHÔNE
Max
. gro
ss h
ead
1883
m
Concrete gallery 11'588 m Steel lining 2790 mSteel lining 1455 m
Pressurised headrace gallery
Pressurised headrace gallery
Schist
s of L
ower
Cas
anna
Gre
ensto
ne
Aug
en gn
eiss M
icasc
hists
Schi
sts o
f Upp
er C
asan
na
Ch
loriti
c Mica
schi
sts a
nd G
neiss
Chèq
ues
sync
line
Verr
ucan
o ph
ylitt
ic s
chis
ts
Tria
s bo
rder
Tria
s m
edia
n
Uppe
r car
boni
fero
us
Gra
velly
and
sla
ty s
chis
ts
Low
er c
arbo
nife
rous
Gr
avel
ly an
d sla
ty s
chis
ts
Tria
ssic
sca
le
An
hydr
ite
"L
e Té
légr
aph"
bre
ccia
Dent
de
Nen
daz
seri
es
Chl
oriti
c m
icas
chis
ts
Ph
ylitt
ic s
chis
t Q
uart
zite
TRACOUET
DZERDJONNA
PÉROUA
CONDÉMINES
CLEUSON LAKE
CLEUSON-DIXENCE COMPLEXLONGITUDINAL PROFILE AND GEOLOGY (CROSS SECTIONS)
Lower carboniferousShaly sandstone"St Christophe" schists
15'833 m
LOT B LOT C LOTS D AND FLOT A
Le Chargeur
DIX LAKE
Pte d'Allève
La Grande Arpette
Mont Gond
Tortin Tracouet Bieudron
SURGE CHAMBER
Dent de Nendaz
Penstock
4230 m BIEUDRONPLANT1200 MW
3000 m
2500 m
2000 m
1500 m
1000 m
500 m
RHÔNE
Max
. gro
ss h
ead
1883
m
Concrete gallery 11'588 m Steel lining 2790 mSteel lining 1455 m
Pressurised headrace gallery
Pressurised headrace gallery
Schist
s of L
ower
Cas
anna
Gre
ensto
ne
Aug
en gn
eiss M
icasc
hists
Schi
sts o
f Upp
er C
asan
na
Ch
loriti
c Mica
schi
sts a
nd G
neiss
Chèq
ues
sync
line
Verr
ucan
o ph
ylitt
ic s
chis
ts
Tria
s bo
rder
Tria
s m
edia
n
Uppe
r car
boni
fero
us
Gra
velly
and
sla
ty s
chis
ts
Low
er c
arbo
nife
rous
Gr
avel
ly an
d sla
ty s
chis
ts
Tria
ssic
sca
le
An
hydr
ite
"L
e Té
légr
aph"
bre
ccia
Dent
de
Nen
daz
seri
es
Chl
oriti
c m
icas
chis
ts
Ph
ylitt
ic s
chis
t Q
uart
zite
TRACOUET
DZERDJONNA
PÉROUA
CONDÉMINES
CLEUSON LAKE
2200 m
2364 m
Valve chamber
A
A B
B
A A B B
4.40
m
R 2.20 m
R 2.20 m R 1.90 m
4.40 m
R 1.90 m
0 1 2 3 4 5km
11WATER INTAKE AT LE CHARGEUR (CROSS SECTIONS)
9
10 11
12
13
14 15
16 17
18
19
8
6
1
5
4
7
32
CLEUSON-DIXENCE COMPLEXWATER INTAKE AT LE CHARGEUR (PLAN VIEW)
11
12
13
14
15
16
17
18
19
LOWER STATION FOR TOURIST CABLE CAR
« THE RITZ » HOTEL
EXHIBITION HALL
UPPER STATION FOR TEMPORARY CONSTRUCTION CABLE CAR (2 X 15 TONS)
MAIN DRAWOFF Q = 50 m3/s
PRESSURE REGULATION SHAFT ANDCLEUSON WATER INTRODUCTION
HEADRACE TUNNEL FOR THE CHANDOLINE PLANT Q = 10.5 m3/s
HEADRACE TUNNEL FOR THE FIONNAY PLANT Q = 45 m3/s
ACCESS TUNNEL TO PRESSURE REGULATION SYSTEMS AND VALVES
1
2
3
4
5
6
7
8
9
10
GRANDE DIXENCE DAM, HEIGHT 285 m
NEW WATER INTAKE, 4.40 m DIA., Q = 75 m3/s
GRANDE DIXENCE WATER INTAKE, 3.30 m DIA., Q = 45 m3/s
WATER INTAKE FOR LOW-LEVEL OUTLET
ACCESS TUNNEL TO THE NEW VALVE CHAMBER
NEW VALVE CHAMBER
ACCESS TUNNEL TO THE NEWHEADRACE TUNNEL
HEADRACE TUNNEL LOW POINT
HEADRACE TUNNEL BETWEEN LE CHARGEUR AND TRACOUET, LENGTH 15’833 km
DRAWOFF FOR THE HEADRACE TUNNEL
10
7 8
9 11
23
12
14
1
4
5
611
3
7 8 10 135
9
4
11
2
1
GRADIENT=32%
CHARGEUR
TRACOUET
13
32 TONS OVERHEAD CRANE
WALKWAY
BY-PASS
COUNTERWEIGHT
VALVE BODY, 3.30 m DIA.
SERVOENGINE
UPSTREAM PIPE, 3.30 m DIA.
REMOVABLE PIPE, 3.30 m DIA.
MANHOLE, 600 mm DIA.
VENT, 700 mm DIA.
BASES
INSPECTION WINCH
HEADRACE GALLERY
PENSTOCK INLET
BUTTERFLY VALVE CHAMBERS
8
9
10
11
12
13
14
1
2
3
4
5
6
7
2364 m2384 m
2559.23 m
2449.30 m
DAMPLANT
F4
20.20 m
65.3
0 m
104.
77 m
81.3
4 m
3.29
m
407.00 m
557.00 m7.55 m71.90 m
9.00 m
G=20%
150.00 m
71.90 m
407.00 m
557.00 m
150.00 m
A
A
B BA
A
CC
CLEUSON-DIXENCE COMPLEXSURGE CHAMBER
LONGITUDINAL CROSS SECTION
PLAN VIEW
DIX
ENCE
TRA
COU
ET
ACCESS DOOR
CHAMBER F2
CHAMBER F2
F2
A A
CROSS SECTION A-A CROSS SECTION B-B CROSS SECTION C-C
R 3.81
m
R 3.35 mR 5.1
0 m
R 4.50 m
4.45 m 4.45 m
R 2.
10
R 2.25
R 1.80
4.64
m
3.45 m
CROSS SECTION A-A
15ACCESS TUNNEL TO TORTIN F2
17
BIEUDRON POWER PLANT
19
Situated close to the Nendaz (Grande Dixence) power plant, the main cavern at Bieudron is over 100 m long, 39 m high and 25 m wide. The plant includes 3 caverns and several connecting tunnels and access tunnels representing an excavated volume of 150’000 m3.
It comprises 3 vertical generators operating at 428 rpm, with :
— 3 spherical valves with a diameter of 1.40 m
— 3 Pelton turbines with a unit power of 423 MW
— 3 x 465 MVA generators with water-cooled rotor windings and stator bars
— 3 x 465 MVA three-phase transformers
— 9 x 230/410 kV one-phase cables supplying power to the 410/230 kV station at Chamoson
The Bieudron power plant alone holds three world records, for : the drop height, the output of the Pelton turbines and the output per ge-nerator pole.
CHAMOSON SWITCHINGSTATION 410/230 kV
CHAMOSON SWITCHINGSTATION 230 kV
BIEUDRON PLANT 1200 MW
NENDAZ PLANT 390 MW
BIEUDRON POWER PLANTPLAN OF LOCATION
21
NENDAZ PLANT, 390 MW
PENSTOCK INLET, 75 m3/s
DISTRIBUTOR, 3 x 25 m3/s
SPHERICAL VALVES CHAMBER
BIEUDRON MACHINES ROOM
BAR TUNNELS
TRANSFORMER CELLS
COOLING WATER RESERVOIR, CAPACITY 21,000 m3
TAILRACE TUNNEL
410 kV CABLES TUNNEL AND ACCESS TO TRANSFORMERS
RESTITUTION WORK TO THE RIVER RHÔNE
CABLE GATEWAY
CHAMOSON SWITCHING STATION (410/230 kV)
CONNECTING TUNNELS
EMERGENCY TUNNEL
VENTILATION TUNNELS
ACCESS TUNNELS
COMMAND AND CONTROL SYSTEM FOR SWITCHING STATION
AUTO-TRANSFORMER (600 MVA/230/410 kV)
10
11
12
13
14
15
16
17
18
19
1
2
3
4
5
6
7
8
9
2021
22
23
23
23
24
26
27
25
19
18
11
12
17
16
9
9
7
6
15
15
14
5
10
4
3
14
1
8
2
13
BIEUDRON POWER PLANTOVERVIEW
2021
22
23
23
23
24
26
27
25
19
18
11
12
17
16
9
9
7
6
15
15
14
5
10
4
3
14
1
8
2
13
23PENSTOCK
DISTRIBUTOR
UNIT BRANCH (25 m3/s, PRESSURE 190 BAR)
VALVES CHAMBER
SPHERICAL VALVE (210 TONS PER UNIT)
MAIN CAVERN
423 MW PELTON TURBINE
465 MVA GENERATOR
CONTROL ROOM
250 TONS OVERHEAD CRANE
BUSBAR TUNNELS
21 kV 15’000 A BUSBARS
TRANSFORMER CELL
465 MVA THREE-PHASE TRANSFORMERS
230/410 kV ONE-PHASE CABLE OUTLET
TAILWATER BRANCH
MAINTENANCE AND STORAGE BUILDING
COOLING WATER RESERVOIR
16/0.4 kV AUXILIARY TRANSFORMERS
230/400 V SWITCHBOARDS
EMERGENCY TUNNEL
ASSEMBLY SITE
CONNECTING TUNNELS
ACCESS TUNNEL TO PLANT
ACCESS TUNNEL TO DISTRIBUTOR
TUNNEL FOR 410 kV CABLES AND ACCESS TO TRANSFORMERS
VENTILATION TUNNEL
15
16
17
18
19
20
21
22
23
24
25
26
27
1
2
3
4
5
6
7
8
9
10
11
12
13
14
9
10
8
6
1
5
4
7
3
2
BIEUDRON POWER PLANT SPHERICAL VALVE
1
2
3
4
5
6
7
8
9
10
11
GATE VALVE WITH BEARINGS
BODY OF THE VALVE
COVERS
BEARING BUSHES
UPSTREAM PIPE
DOWNSTREAM REMOVABLE PIPE
RECONDITIONING JOINT
SERVICE JOINT
SERVOENGINE
SERVOENGINE LEVER
160 TONS OVERHEAD CRANE
9
10
8
6
1
5
4
7
3
2
6
11
5
25
103 m
25 m
UNIT 1 UNIT 2 UNIT 3
ASSEMBLYSITE
25 m
39 m
BIEUDRON POWER PLANT LONGITUDINAL CROSS SECTION
103 m
25 m
UNIT 1 UNIT 2 UNIT 3
ASSEMBLYSITE
25 m
39 m
27
43 m 46 m25 m
1
2
4
6
5
5
7
8 9
10
11
3
BIEUDRON POWER PLANTTRANSVERSE CROSS SECTION
43 m 46 m25 m
1
2
4
6
5
5
7
8 9
10
11
3
291
2
3
4
5
6
7
8
9
10
11
DISTRIBUTOR
VALVES CHAMBER
250 TONS OVERHEAD CRANE
MACHINES ROOM
TUNNEL FOR LOW AND MEDIUM VOLTAGE CABLES
LOW WATER TUNNEL
BAR TUNNEL
FLAP GATE
TAILWATER BRANCH
TRANSFORMER CELLS
TAILRACE
9
6
4
7
582
3
1
BIEUDRON POWER PLANTTRANSFORMER
1
2
3
4
5
6
7
8
9
BUSBAR INPUT
THREE PHASE TRANSFORMER465 MVA - 21 kV/410 kV
CABLE-TRANSFORMER SF6 CONNECTION
230/410 kV CABLES
CABLE SUPPORTS
VENTILATION
CABLE GALLERY
CO2 FIRE PROTECTION
SMOKE EXTRACTION
XLPE INSULATION
COPPER CONDUCTOR
NON-INFLAMMPE SHEATH
CORRUGATEDALUMINIUM SHEATH
140 mm
Weight 32 kg/m
BAR SUPPORT
SHEATH
OCTOGONAL CONDUCTOR
1100 mm
31230/410 kV CABLE
21 kV BUSBAR CROSS SECTION
1
2
11
9
10
8
5
6
7
4
3
BIEUDRON POWER PLANTTURBINE-GENERATOR UNIT
GENERATOR SHAFT
EXCITER
ROTOR – COOLING WATER
ROTOR
STATOR
TURBINE GUIDE BEARING
PELTON TURBINE
RACK AND PLATFORM
INJECTOR
BUSBARS
COMBINED TRUST ANDBEARING SUPPORT
7
8
9
10
11
1
2
3
4
5
6
33
ROLE OF COMMAND AND CONTROL SYSTEM
— Automatically control all components in the power plant, locally or remotely from the Alpiq control centre
— Guarantee maximum safety of individuals and property— Ensure the optimum availability of production generators
GENERAL SPECIFICATIONS OF THE COMMAND AND CONTROL SYSTEM
Division into decentralised elementary systems each including :
— A direct mode or local service— An automatic mode, local or remote control— Control panels— Redundant automated devices
Number of elementary systems :
— 12 systems for general power plant operations and headgates— 18 systems for each unit Total systems across facility :
— 85 CPUs— approx. 8000 digital inputs— approx. 8500 digital outputs— approx. 500 analogue inputs— approx. 100 analogue outputs
COMMAND AND CONTROL SYSTEM
35
PENSTOCK REHABILITATION WORK
RHÔNEBIEUDRON
1714.63
1713.97
2156.90
1485.531416.16 1280.95
481.00
2000 m
1500 m
1000 m
500 m450.00
Upper Fontanettes
BY-PASS
F4 TRACOUET
F5 DZERDJONNA
F6 PÉROUA
F7 CONDÉMINES
1413.98
1207.85 Lower Fontanettes
37Following the rupture of the Cleuson-Dixence penstock on 12th De-cember 2000, EOS Holding and Grande Dixence SA, the owners of the facility, decided to set up a company in 2003 to plan and manage the rehabilitation works.
Based on consultation and advice from an international panel of experts, Cleuson-Dixence Construction SA has studied several reha-bilitation schemes : repair of the current penstock, lining, alternative solutions comprising new deep or semi-deep wells, open air penstocks and combination scenarios.
The solution which appeared to be the most suitable, both in terms of feasibility and high level of safety, was to line the inside of the penstock.
The « old » shielding provides a seal for the new lining against the groundwater and no longer plays a structural role. The total cost of rehabilitation was 365 million CHF.
Access tunnelsF4 F7
Upper Fontanettes windowL = -340 m
Lower Fontanettes windowL = -126 m
Site platformAlt. 1263 m
Chamber at head of vertical penstock
Site platformAlt. 1205 m
68.2
0 m
6.50
m9.
50 m
13.15 m
Concrete conduit
Lining of existing conduit
Section of abandoned penstock/
Concreting/
Filling of existing conduit
Conduit laid on platesVert
ical
pen
stoc
k
40 m33 m
Chamber at foot of bypass
Lining of existing conduit
1200 m
1220 m
1240 m
1260 m
1280 m
1340 m
1320 m
1300 m
Chamber at foot of vertical penstock
Access tunnel at foot of verticalpenstock
PENSTOCK REHABILITATION WORKDESCRIPTION OF THE VARIOUS OPERATIONS
BY-PASS : LONGITUDINAL PROFILE
Ø2.85
m
NEW LINING
PACKING MORTAR 130 mm THICK
PREFABRICATED SEGMENTAL RINGS 300 mm THICK
CONCRETE FILLING 400 mm THICK
CONCRETE FILLING 130 mm THICK
EXISTING LINING INT. DIA. 3.20 m
SERVICE-PIPES INT. DIA. 5’’ FOR CONTROLCOMMAND AND ELECTRICITY
WATER
39LINING : CROSS SECTION
The first work started in 2005. The entire length Tracouet – Dzerdjonna – Péroua – Condémines – Bieudron was rehabilitated.Outside the area affected by the accident, the repair was done by lining the penstock. This means that a new steel tube was inserted inside the existing penstock. In total, 400 pipes, 12’500 tons of steel and 16’400 m of welds were required to create the lining.
In the area where the accident occurred, a workaround solution using a deep by-pass was adopted. The damaged section of the penstock, a length of 117 m, was filled.
Two additional acces tunnels were excavated upstream and downstream of the damage section, to create the access points required for the construction of the bypass. Lining was carried out using steels with a high elastic limit, selected to optimise the quality and performance of the work.
To minimize head loss, the space separating the old penstock from the lining was reduced to the minimum (approximately 10 to 15 cm). This space was filled with concrete.
The commissioning tests for the Cleuson-Dixence facility started in the middle of 2009 and the Bieudron power plant produced its first kilowatt-hours in January 2010. The rebuilding of the Cleuson-Dixence penstock took 4 ½ years, involving 600 people working around the clock, 7 days a week.
4141
VISITS / CONTACTS
43From the power of the mountains to the power of men, experience the story of electricity !
At the Bieudron and Nendaz hydroelectric power plants, buried underneath the mountain, turbines are driven by the water from the Grande Dixence lake.
Come and discover these constructions, which are unique in the world, their history and their features.
Guided visits available, must be prebookedOpen from January to December, working days onlyDuration of the visit : 1 hour 30 minutes
CONTACT INFORMATION
Grande Dixence SA+41 27 328 43 [email protected]
esse
nced
esig
n.co
m