CBE Capital Projects Update November 13, 2015

Page 2: CBE Capital Projects Update

Our Mission and Values

Our Mission

Each Student, in keeping with his or her individual gifts, will complete high school with a foundation of learning to function effectively in life, work and continued learning.

Our Values

• Students come first

• Learning is our central purpose

• Public education serves the common good

2

Page 3: CBE Capital Projects Update

Capital Projects Update

CBE has 31 major capital projects underway: 21 New schools 3 Replacement schools 6 Major modernizations 1 Modular extension

The target date for completion of these projects is between September 2016 and September 2018.

3

Page 4: CBE Capital Projects Update
Page 5: CBE Capital Projects Update

School Names

The Board of Trustees continues to name new schools. The following schools have been named:

Buffalo Rubbing Stone School (Panorama Hills)

Eric Harvie School (Tuscany)

Hugh A. Bennett School (Saddle Ridge)

Peter Lougheed School (Saddle Ridge)

William D. Pratt School (Rocky Ridge/Royal Oak)

Marshall Springs School (Evergreen)

McKenzie Highlands School (McKenzie Towne)

Dr. Martha Cohen School (New Brighton/Copperfield)

Nelson Mandela High School (North East Calgary)

5

Page 6: CBE Capital Projects Update

Capital Projects Update (#3 to #7)

June 2014 Project Announcements

Construction is progressing and is currently on schedule: Evanston Elementary School Peter Lougheed Middle School Copperfield Elementary School New Brighton Elementary School William D. Pratt Middle School

6

Page 7: CBE Capital Projects Update

Evanston School

7

Page 8: CBE Capital Projects Update

William D. Pratt School

8

Page 9: CBE Capital Projects Update

Capital Projects Update (#8)

Nelson Mandela High School (NE Calgary)

Alberta Infrastructure is project managing this development

Construction continues as scheduled

A request for a gymnasium addition has been submitted to the Provincial Government

9

Page 10: CBE Capital Projects Update

Capital Projects Update (#9 and #10)

January 2014 Project Announcements

Aboriginal Learning Centre (Harold W. Riley School) Construction is currently behind schedule. Delivery of structural steel was delayed and is scheduled for delivery and erection in November. Masonry installation is 50% complete in the gym area. Slab on grade installation is 80% complete.

Christine Meikle School – Construction remains on schedule. Structural steel is complete in the south wing. Decking and installation has begun in the south wing and masonry shear walls have commenced. Basement foundation walls are complete.

10

Page 11: CBE Capital Projects Update

Capital Projects Update (#11 & #12)

January 2014 Project Announcements

Bowness HS Modernization –Foundations are complete and some concrete elements such as stairs and elevator shafts are being cast. Structural steel arrival and installation to commence in November. Construction progress is slightly behind schedule.

Jack James HS Modernization – Structural steel and metal decking to Building Trades addition are complete. Structural steel is complete, with interior partitions and mechanical and electrical progressing on the Auto body expansion and modernization. The greenhouse structural steel is in place, with interiors to be completed in early 2016. Exterior concrete and canopies to child care area are being installed. Construction remains on schedule.

11

Page 12: CBE Capital Projects Update

Capital Projects Update (#13 to #18)

February 2014 Project Announcements

Site work has been slowed at Marshall Springs School and Eric Harvie School due to permitting delay issues.

Construction is currently progressing on track at: McKenzie Highlands School, Dr. Martha Cohen School, Buffalo Rubbing Stone School and Auburn Bay Elementary, where it is slightly behind schedule.

12

Page 13: CBE Capital Projects Update

McKenzie Highlands School

13

Page 14: CBE Capital Projects Update

Capital Projects Update (#19 & #20)

June 2013 Flood

Elbow Park School – The historic wall restraint work, together with all mass demolition activities has been completed. New foundations and concrete work have commenced. Construction is proceeding with a revised schedule to accommodate delays experienced in restraining the north wall foundations.

Rideau Park School – Flood Mitigation Options have been assessed and it is anticipated that the first phase of construction will commence in the first quarter of 2016.

14

Page 15: CBE Capital Projects Update

Capital Projects Update (#21- #24)

September 22, 2014 Project Announcements

Site grading and piling is complete and deep service installation is underway at West Springs/Cougar Ridge Middle School and Cranston Middle School. Both projects are on schedule.

Hugh A. Bennett School and Dr. Roberta Bondar School – Construction has commenced and is slightly behind schedule on both projects.

15

Page 16: CBE Capital Projects Update

Capital Projects Update (#26)

September 22, 2014 Project Announcements

A schematic design concept has been developed for the Southeast Calgary High School

A pre-application development permit meeting has been arranged prior to submitting the development permit application to the City

The Provincial Government has approved the full design development and construction of the school which is expected to open in September 2018

16

Page 17: CBE Capital Projects Update

Capital Projects Update (#27, 29 & 31)

October 8, 2014 Project Announcements

Full design development and construction documents will be prepared for tender in early 2016 for: Martindale Elementary School Springbank Hill/Discovery Ridge Elementary

/Middle School Silverado School Elementary School

17

Page 18: CBE Capital Projects Update

Capital Projects Update (#28 & 30)

October 8, 2014 Project Announcements

Steering committees have been set up and design development will commence immediately for Lord Beaverbrook High School and James Fowler High School with an expected phased completion date for both schools by December 2017.