gsa’s capital projects process

19
Mark Sears, Region 4 Capital Program Coordinator GSA’s Capital Projects Process Client Solutions Divisi 77 Forsyth Street, SW Suite 110 Atlanta, GA 30303 404.331.3584 www.gsa.gov March 29, 2012

Upload: louise

Post on 20-Jan-2016

59 views

Category:

Documents


0 download

DESCRIPTION

March 29, 2012. GSA’s Capital Projects Process. Mark Sears, Region 4 Capital Program Coordinator. Client Solutions Division 77 Forsyth Street, SW Suite 110 Atlanta, GA 30303 404.331.3584 www.gsa.gov. The “Prospectus” and Capital Program… What are they?. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: GSA’s Capital Projects Process

Mark Sears, Region 4 Capital Program Coordinator

GSA’s Capital Projects Process

Client Solutions Division77 Forsyth Street, SWSuite 110Atlanta, GA 30303404.331.3584www.gsa.gov

March 29, 2012

Page 2: GSA’s Capital Projects Process

The “Prospectus” and Capital Program…

What are they?

Page 3: GSA’s Capital Projects Process

What makes a project a “Prospectus Project”?

Any project that GSA PBS engages in that exceeds the prospectus threshold established by Congress/OMB:

– New Construction $2.79 Million– R&A $2.79 Million– New Lease $2.79 Million– Alts in Leased Space* $1.395 Million

*Only applies to alteration projects in leased space that occur after initial occupancy

The prospectus threshold designates the ceiling of GSA’s blanket authority that we cannot exceed on our own

Page 4: GSA’s Capital Projects Process

What makes a project a “Prospectus Project”?

How do we determine if a project is above prospectus?

•New construction projects = ECC $ + Site Acquisition $

•R&A projects = ECC $

•New Lease projects = Net annual rent $

•Alts in Leased Space projects = TEPC $

“ECC” = Estimated Cost of Construction

“TEPC” = Total Estimated Project Cost

Projects determined to be above prospectus must be

submitted through the GSA Capital Investment & Leasing

Program (CILP).

Page 5: GSA’s Capital Projects Process

What makes a project a “Prospectus Project”?

When going through the CILP process, all prospectus-level projects, with the exception of new leases, will ultimately require 2 things:

•Appropriation = Funding from Congress specifically for the project

•Authorization = Permission from Congress; specific authority to engage in a project that exceeds GSA’s normal blanket level of authority (i.e. below the prospectus threshold)

New leases only require authorization

Page 6: GSA’s Capital Projects Process

The CILP & the Budget Process &

Schedule

Page 7: GSA’s Capital Projects Process

The CILP & Budget Process & Schedule

The CILP Call is issued by GSA Central Office two (2) years in advance of target budget year (example: FY2014 CILP Call issued in FY2012)

– Details requirements for submissions of R&A projects, new construction projects, new lease projects, and lease alteration projects

– Specifies submission due dates/schedule for the program

– Sets expectations for review and approval of submissions

Page 8: GSA’s Capital Projects Process

The CILP & Budget Process & ScheduleAnticipated schedule for this year’s FY14 CILP Call:

Feb-Mar 2012 GSA regions refresh & update project information

May 2012 GSA Central Office issues directed call to regions

July 2012 GSA regions submit prospectuses to GSA Central Office for owned construction/R&A

September 2012 GSA submits FY14 owned program to OMB

October 2012 GSA regions submit lease prospectuses to GSA Central Office

November 2012 GSA receives “passback” from OMB

December 2012 Passback appeal; resubmit prospectuses

January 2013 GSA submits FY14 owned program to Congress

Feb-Apr 2013 GSA submits FY14 leased program to OMB

May 2013 GSA submits FY14 leased program to Congress

Page 9: GSA’s Capital Projects Process

The CILP & Budget Process & Schedule

Preparation of President’s FY14 budget in January 2013

President’s FY14 budget to go to Congress first Monday in February 2013

When GSA submits prospectuses to Congress, they are sent concurrently to GSA’s authorizing and appropriations committees (4 total)

ALL 4 committees must approve

President signs the FY14 budget (ideally before October 1, 2013)

Once we have an approved FY14 budget from Congress, signed by the President, and all required signed resolutions, we have an active FY14 project

Page 10: GSA’s Capital Projects Process

FY2014CILP

Page 11: GSA’s Capital Projects Process

FY14 CILP

Setting realistic expectations for the FY14 CILP In the FY11 and FY12 CILPs, GSA planned between

$2-2.5 billion (incl. new construction, major R&A, and minor R&A)

In both FY11 and FY12, GSA managed to get roughly $1.5 billion included in the President’s budget

In the final FY11 Budget, GSA received $408 million in construction/R&A appropriations

In the final FY12 Budget, GSA received $330 million in construction/R&A appropriations

Going into FY13, GSA has planned less than $2 billion Current expectations: FY13 Budget will only include no

more than the level of appropriations received in FY12, and probably less

Page 12: GSA’s Capital Projects Process

FY14 CILP

Due to ever decreasing levels of appropriations, GSA cannot fund every project identified by the regions and requested by the client agencies.

In response to dwindling appropriations for construction and R&A, GSA’s CILP has evolved to deal with backlog in the capital project “pipeline”:

• Up thru FY09 – Traditional CILP Calls• FY10 thru FY13 – “Directed CILP Calls”• FY14 – “Decision Lens Modeling” & “Review,

Refresh, READY”

Page 13: GSA’s Capital Projects Process

FY14 CILP

• Traditional “Open” Call = GSA Regions determined on their own what their capital priorities would be, & submitted those priorities to GSA Central Office. GSA Central Office prioritized on a national level based on critical need and availability of appropriations

• Directed Call = GSA Central Office “directs” Regions on what projects to submit, and does not allow for non-approved submissions, except conditionally in cases of emergency or critical urgency. Designed to curtail the flood of “new start” projects and focus on projects already in the “pipeline”.

Page 14: GSA’s Capital Projects Process

FY14 CILP

Directed calls typically specify submissions for the following:

– Partially funded projects– Priorities of US Courts 5-Year Plan for new

courthouses– Priorities in DHS CBP-LPOE program– Submissions for specific projects, as designated

by Central Office– Approved exceptions for “critical” new-start

projects– Opportunity Purchase candidates

Page 15: GSA’s Capital Projects Process

FY14 CILP

New for FY14 CILP – “Review, Refresh, READY”

•GSA began work on a new 5-Year plan for all owned capital construction and renovation projects as part of the FY13 CILP effort.

•For FY14, GSA will review universe of projects identified in the 5-Year plan and similar efforts and refresh their data and support information.

•Potential projects identified will be weighed through the new “Decision Lens Modeling Tool”

– Designed to weigh and prioritize each project via a set of critical measures and criteria

•Results of the Decision Lens Modeling analysis will determine the FY14 directed call

Page 16: GSA’s Capital Projects Process

FY14 CILP

FY14 “Review, Refresh, READY” effort will include:

•Outstanding FY11/12/13 projects not fully funded

•GSA 5-Year Plan projects

•Established program priorities from client agencies (like the Courts’ 5-Year Plan & DHS CBP LPOE program)

•Exigent need project submissions

New approach will focus on:

•Ensuring that GSA puts forward the best program possible given our limited resources

•Developing capability to quickly adjust to changing priorities and readiness to offer a range of different project submissions.

Page 17: GSA’s Capital Projects Process

What can you do to help?

Page 18: GSA’s Capital Projects Process

FY14 CILP

Be ready to respond to requests from GSA for requirements, justifications, etc. Short window for prospectus preparation – May to July We may request information and need it quickly

Be prepared GSA will provide schedule and budgeting estimates to

help you plan on rent, relocation, etc But be prepared for possible shifts in those plans (i.e.

delays in appropriations, changes in Administration priorities, etc)

Be patient The Capital Program is a long, slow process, and we

cannot guarantee support or timeliness from our approvers (i.e. OMB & Congress)

Page 19: GSA’s Capital Projects Process

FY14 CILP

QUESTIONS?

Feel free to contact me: Mark Sears

(404) 562-0698

[email protected]