  • 2016/2017 Capital Projects9-Month Update

    Forest Preserve District of Kane CountyMarch 2017

    Prairie seeding at Pingree Grove Forest Preserve

  • 4/20/2017

    M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 1 of 75

    Contents ADA Barriers Corrections .......................................................................................................................................... 3

    Bridge Evaluations ................................................................................................................................................... 19

    Building Repairs & Upgrades................................................................................................................................... 21

    Burnidge Forest Preserve and Paul Wolff Campground Repaving Project ............................................................. 30

    Carpentersville Dam Removal Engineering IDNR Grant* ....................................................................................... 35

    Dick Young Forest Preserve Giant Reed Control ..................................................................................................... 37

    Fabyan Forest Preserve Bridges and Island Improvements Project Phase II* ........................................................ 40

    Fabyan Forest Preserve Causeway Removal Engineering IDNR Grant* ................................................................. 45

    Fabyan Forest Preserve Japanese Garden Pond Engineering ................................................................................. 48

    Fox River Trail - Raymond Street Re-Route* ........................................................................................................... 49

    Freeman Kame Forest Preserve Prairie Reconstruction ......................................................................................... 54

    Freeman Kame Forest Preserve RTP Grant* ........................................................................................................... 56

    Grunwald Forest Preserve South Operations Maintenance Facility Parking Improvements ................................. 59

    Johnson’s Mound Forest Preserve Sled Hill Reconfiguration* ............................................................................... 61

    Natural Resources Facility* ..................................................................................................................................... 63

    Pingree Grove Forest Preserve Wetland Restoration Project - NAWCA Grant* .................................................... 67

    Settlers Hill Golf Course Improvements Phase II* .................................................................................................. 70

    Trail Resurfacing: Virgil Gilman Trail at Aurora West Forest Preserve .................................................................. 73

    ∗ Indicates project continues from past fiscal year

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 2 of 75

    This page intentionally left blank.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 3 of 75

    ADA Barriers Corrections Fiscal Year: 2016-2017

    Funding Forest Preserve District: $100,000 Other: $ 0 Total Budget: $100,000

    Budget Breakdown Engineering: $ 0 Construction: $100,000

    Project Description With the passing of the Federal 2010 ADA Standards for Accessibility and Design, the District approved funding for the first phase of an extensive ADA evaluation of our facilities in September 2011 and completed the District’s full ADA evaluations by 2012.

    Since completion of the evaluation, funding has been budgeted annually to complete the accessibility projects as prioritized.

    In 2015, a multi-year plan was implemented to complete the ADA requirements in all of the District’s picnic areas including making all drinking fountains, hydrants, grills and picnic shelters accessible. This fiscal year the following projects will be completed:

    South North Fabyan West Forest Preserve Burnidge Forest Preserve Flush Restroom Shelter – Burnidge Shelter #1 Paul Wolff Campground Shelter #2 Replace fountain Shelter – Campground Fabyan East Forest Preserve Equestrian Shelter Shelter #3 Flush Restroom fountain replacement Shelter #4 Johnson’s Mound Forest Preserve Hampshire Forest Preserve Shelter #1 Shelter #1 relocate hydrant Shelter #2 Shelter #2 accessible pad and replace hydrant Shelter #3 Tyler Creek Forest Preserve Grunwald Farms Forest Preserve Shelter #1 Flush Restroom Flush Restroom Shop fountains Shelter #2 Big Rock Campground Freeman Kame Flush Restroom Tomo Chi-Chi Lodge Lodge fountain Muirhead Springs Shop fountain

    Contacts

    Staff Project Manager: Jerry Culp Contractors: Mendel Plumbing

    Project Complete December 2016

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 4 of 75

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Bid Letting August 2016 August 2016 Bid Approval

    • Utilization Committee August 2016 August 25, 2016 • Executive Committee September 2016 September 2, 2016 • Full Commission September 2017 September 13, 2016

    Project Start August 2016 September 2016 Project Completion June 2017 December 2017

    2016 – 2017 Fiscal Year Updates

    Jul 16 Staff is preparing the bid for the drinking fountain upgrades.

    Aug 16 The bid for the drinking fountain upgrade has opened and once approved by the board, staff will work with the contractor to start the project. Staff is currently working with the trades department on the accessibility upgrades for the picnic shelters and restrooms.

    Sept 16 Drinking fountain bid has been approved. Staff is working with the contractor to set a schedule for the drinking fountain upgrade work.

    Oct 16 Contractor has started upgrade work on the drinking fountains and is scheduled to be completed in November

    Nov 16 Contractor has completed work, staff is reviewing project and billing before closing out project. Projects that were not completed as part of the priority for this year will be moved to next fiscal year. Dec 16 Paving is complete at Johnsons Mound and Fabyan, staff is working with contractor on punch list Jan 17 Paving projects are complete, staff is working on project list and budgeting for next year’s projects.

    Financial Summary

    Budget: $100,000

    Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project # $ 10,600 $ 10,600 Champion Paving Fabyan east accessible Route 10402.A $ 2,560 $ 2,560 Misc Drinking Fountains 10402.B $ 59,204 $ 59,204 Evans and Sons Johnson Monnd/Fabyan Routes 10402.D

    28,625$ 28,625$ Mendel Plumbing Drinking Fountains Fabyan East 10402.C100,989$ 100,989$ Total to date Project #10402 03-21-24-6090

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 5 of 75

    SOUTH: 1. Fabyan West FP A. Shelter #1 − create accessible route from NW parking and flush restroom

    − replace outdated drinking fountain with accessible hydrant and expand concrete pad

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 6 of 75

    1. Fabyan West FP B. Flush Restroom

    − replace single bowl drinking fountain with double bowl

    C. Shelter #2 (Bear Cage) -review accessible route from west asphalt road and north gravel road -determine feasibility for ramp to the shelter -create accessible sidewalk and grill pad -remove outdated drinking fountain between Shelter #2 and the Japanese Gardens

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 7 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 8 of 75

    2. Fabyan East FP A. Shelter #3 (by FR Trail)

    − replace outdated drinking fountain with accessible double bowl drinking fountain

    − -assure clear distance around fountain when replaced − -determine location of the new block restroom to replace the 2

    Romtecs currently onsite

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 9 of 75

    B. Shelter #4 (east of Route 25) - replace outdate drinking fountain with accessible hydrant and expand/re-pour concrete pad

    BEFORE: Outdated drinking fountain (left) was replaced. AFTER: The restroom was renovated with a new concrete pad and accessible hydrant. (right and below)

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 10 of 75

    3. Johnson’s Mound FP A. Shelter #1 − extend water line to consolidate water and grill into one area − replace existing with accessible hydrant and expand concrete pad − create accessible route from east parking lot

    Before (above) and After (below)

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 11 of 75

    B. Shelter #2 (Scout Cabin) − redesign and rebuild cabin for ADA compliance (future) (review septic and

    fireplace) − address hydrant issue during rebuilding

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 12 of 75

    3. Johnson’s Mound FP

    C. Shelter #3 (top of hill) − replace concrete sidewalk from accessible parking space (when paving is

    completed) − move water line to by grill − install accessible hydrant and concrete pad

    Additionals – 4. Grunwald Farms FP and Big Rock Campground

    A. Flush Restrooms

    - replace single bowl drinking fountain with double bowl

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 13 of 75

    NORTH: 1. Burnidge FP /Paul Wolff Campground FP

    A. Burnidge Shelter

    − review location of hydrant and consolidate by grill or by kiosk − replace existing with accessible hydrant and expand concrete pad

    B. Paul Wolff Campground Shelter − replace existing with accessible hydrant and create concrete pad

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 14 of 75

    C. Paul Wolff Campground Equestrian Shelter

    − relocate hydrant by shelter on accessible route − replace existing with accessible hydrant and create concrete pad

    D. Paul Wolff Campground Flush Restroom

    − replace single bowl drinking fountain with double bowl

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 15 of 75

    2. Hampshire FP A. Shelter #1

    − relocate hydrant and kiosk by shelter/restroom along accessible route − replace existing with accessible hydrant and create concrete pad

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 16 of 75

    B. Shelter #2 − create accessible pad to connect hydrant to grill area

    − replace existing with accessible hydrant

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 17 of 75

    3. Tyler Creek FP A. Shelter #1

    - replace existing with accessible hydrant

    B. Flush Restroom

    - replace single bowl drinking fountain with double bowl

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 18 of 75

    C. Shelter #2 − picnic site under review for accessibility

    − revise parking areas, restroom, grill, hydrant and accessible routes

    − replace existing with accessible hydrant

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 19 of 75

    Bridge Evaluations Fiscal Year: 2016-2017

    Funding Forest Preserve District: $121,200 Other: $ 0 Total Budget: $121,200

    Budget Breakdown Engineering: $121,200 Construction: $ 0

    Project Description This project involves the evaluation of the District’s existing bridge structures; seventy-two (72) manufactured corten steel and twenty-nine (29) wooden bridges on the linear and internal trail systems. An Architectural/Engineering company will be hired to inspect and evaluate each bridge and provide the District with a report as to the priority and estimated cost for the maintenance of each structure.

    (South) 48 bridges x $1,200/bridge = $ 57,600 (North) 53 bridges x $1,200/bridge = $ 63,600 $121,200

    Contacts

    Staff Project Manager: John Goreth

    Engineer: Alfred Benesch & Co.

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Bid Letting October 2016 Bid Approval

    • Utilization Committee December 2016 February 24, 2017 • Executive Committee December 2016 March 3, 2017 • Full Commission January 2017 March 14, 2017

    Project Start March 2017 March 2017 Project Completion June 2017

    2016 – 2017 Fiscal Year Updates Jul 16 Staff completing specifications for bidding process. Aug 16 Staff completing specifications for bidding process. Sep 16 Specifications complete and turned in to Finance for bidding process. Oct 16 Packet being completed for RFP (Request for proposal) Nov 16 Packet being reviewed for RFP (Request for proposal) Dec 16 Packet sent to engineering firms and deadline set for response. Jan 17 Completing memo and Committee approval for project. Feb 17 Preparing for P/U Committee approval.

    Mar 17 Project approved by Commission, and documents sent to vendor, Alfed Benesch and Company of Naperville, IL to begin project.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 20 of 75

    Financial Summary

    Total Budget: $121,200: $57,600 South; $63,600 North Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project #

    84,968$ -$ Alfred Benesch & Co. Bridge assessments of 79 birdges Res. 2519

    84,968$ -$ Total to date Project # 10401 03-21-24-7050

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 21 of 75

    Building Repairs & Upgrades Fiscal Year: 2016 - 2017

    Funding Forest Preserve District: $101,073 Other: $ 0 Total Budget: $101,073

    Budget Breakdown Engineering: $ 0 Construction: $101,073

    Project Description Funds for contracted and In-house repairs as part of the Phase One and Phase Two building evaluations performed by Kluber Architects and Engineering in 2015.

    (PHASE 1) Building Evaluations PRIORITY 1 (Immediate) Belding Lodge, Brewster Creek Forest Preserve: $ 4,000 Creek Bend Nature Center, Leroy Oakes Forest Preserve: $ 16,929 Scout/Rental Cabin, Johnsons Mound Forest Preserve: $ 8,644

    Subtotal $ 29,573

    (PHASE 2) Building Evaluations PRIORITY 1 (Immediate) Brunner Family Forest Preserve Garage/Shop: $ 1,500 Brunner Family Forest Preserve Hangar: $ 1,000 Fabyan Villa Museum: $ 69,000

    Subtotal $ 71,500 Total $101,073

    The building summary pages from Kluber Arch./Eng. noting the work and cost estimates for the remaining priority 1 items are attached. Cost estimates above will differ from the Kluber report in that the Kluber report costs are based on all contract services while the budget includes savings relative to some projects planned for in-house staff completion and only account for materials. This project will conclude all priority 1 items from both Phase I and Phase II reports.

    Contacts

    Staff Project Manager: John Goreth Kluber Arch./Engineering Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Brewster Creek Belding Lodge Complete July 2016 August 2016 LeRoy Oakes Creek Bend Nature Center Complete March 2016

    Johnson’s Mound Scout Cabin Complete August 2016 September 2016 Brunner Family FP Garage Complete June 2017 Brunner Family FP Hangar Complete June 2017 Fabyan Villa Museum Complete June 2017

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 22 of 75

    2016 – 2017 Fiscal Year Updates Jul 16 Ordered new entrance door for lower level at Brewster Creek.

    Aug 16 Installed new entrance door for lower level at Brewster Creek. Completed repairs to stair railing and steps at the Fabyan Villa. Sept 16 Installed new door and concrete stoop at the Johnsons Mound scout cabin. Oct 16 Installed new exit light, battery pack and water vacuum breaker at Brewster creek.

    Nov 16 Installed low voltage cable, exit light battery and applied sealant to areas around doors and windows. Replaced window at the Fabyan Villa. Dec 16 Completed temporary chimney repairs at the Creek Bend Nature Center. Jan 17 Proposals received and waiting for conducive weather to finish chimney masonry work at creek Bend. Feb 17 Proposals received and waiting for conducive weather to finish chimney masonry work at Creek Bend. Mar 17 Proposals received and waiting for conducive weather to finish chimney masonry work at Creek Bend.

    Financial Summary

    Budget: $101,073

    Expenses: Encumbered Actual Spent Vendor Product / Service Rendered Project #

    $ 720 $ 720 Security Builders Entrance doors Belding Lodge 10405.A $ 329 $ 329 Chimney repairs Creek Bend NC 10405.B

    $ 1,194 $ 1,194 Menardsconcrete stoop Johnson's Mound

    Cabin 10405.C

    10405.D

    $ 133 $ 133 Hangar Brunner Family FP 10405.E

    $ 376 $ 376 MenardsMaterials for stair repairs Fabyan

    Villa Museum10405.F

    $ 2,752 $ 2,752 Total to date Project # 10405.A-F 03-21-24-5070

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 23 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 24 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 25 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 26 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 27 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 28 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 29 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 30 of 75

    Burnidge Forest Preserve and Paul Wolff Campground Repaving Project Fiscal Year: 2016-2017

    Funding Forest Preserve District: $299,000 Other: $ 0 Total Budget: $299,000

    Budget Breakdown Engineering: $ 0 Construction $299,000

    Project Description

    Burnidge and Paul Wolff are two of the North Operations busier preserves. Both of these preserves are very popular for equestrian use, bird viewing, cross country running, skiing, jogging, hiking, and walking. Additionally, Paul Wolff is one of two locations where primitive and RV camping are offered by the District.

    The following are the sections of roadway and parking to be resurfaced:

    Section 1: Paul Wolff Forest Preserve/Campground; main entrance road, parking lot, and the RV dump station. Estimated cost for this section is $110,000.

    Section 2: Burnidge Forest Preserve; center parking lot and a reconfiguration of the intersection connecting the parking lot to the main entry road. Due to the visibility concerns with the current road alignment, the intersection will be reconfigured to have the parking lot entry road T into the main drive. This will allow for easier and safer navigation. Estimated cost for this section is $123,500.

    Section 3: Burnidge Forest Preserve; main entry drive (from Combs Rd.) small sections patching. Resurfacing of two (2) small sections of the roadway that have failed as well as the installation of a culvert with asphalt repair to improve drainage in a small section close to the wetland/pond. The remainder of the roadway is in good shape and these repairs should extend the useful life of the road 3-5 more years. Estimated cost for this section is $26,500.

    For all the sections, the old asphalt will be recycled; and the grindings left in place as new base material, the material compacted and graded, and then new paving added with 2-1/4” of binder course asphalt and 1-1/2” of surface course asphalt. All parking spaces will be painted, including handicap stalls and loading/unloading zones. The base project is estimated at $260,000. An additional 15% allowance ($39,000) was added to address any unsuitable soils that are found or other unforeseen circumstances. The final estimate totals $299,000.

    Contacts Staff Project Manager: John Goreth Contractor: Champion Paving

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 31 of 75

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Bid Letting September 2016 August 2016 Bid Approval

    • Utilization Committee September 2016 September 29, 2016 • Executive Committee October 2016 October 7, 2016 • Full Commission October 2016 October 11, 2016

    Construction Start October 2016 October 2016 Construction Completion May 2017

    2016 – 2017 Fiscal Year Updates Jul 16 Operations staff is working with the Planning Department to prepare specifications and bid packet. Aug 16 Bid packet sent for public bid. Sep 16 Bid opening September 9, 2016. Presented to Planning & Utilization Cmte. 9/29/16 Oct 16 Project beginning at Paul Wolff. Low bid from Champion Paving Corp. for $256,602 Nov 16 Project complete on Paul Wolff side. Dec 16 Project to be completed in spring 2017. Jan 17 Project to be completed in spring 2017. Feb 17 Project to be completed in spring 2017. Mar 17 Burnidge section of the paving project to begin this month weather permitting.

    Financial Summary

    Total Budget: $299,000 Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project #256,602$ 111,589$ Champion Paving Paul Wolff side complete 10403.A

    190$ 88$ Various Misc. materials 10403.B256,792$ 111,677$ Total to date Project # 10403 03-21-24-7050

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 32 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 33 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 34 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 35 of 75

    Carpentersville Dam Removal Engineering IDNR Grant* Fiscal Year: 2015 – 2016

    Funding Forest Preserve District: $ 0 Other: IDNR $ 500,000 Total Budget: $ 500,000

    Budget Breakdown Engineering: $500,000 Construction: $ 0

    Project Description The Carpentersville Dam has a long history in Kane County. Originally constructed to divert water to provide power for the growing industrial businesses along the Fox River, the dam has been a focal point along the river and now serves as a destination for fishing, picnicking, canoeing, and just enjoying the riverside atmosphere. The businesses are now gone and research shows that the removal of the dam will improve the river corridor by providing better habitat for the plants and animals that live around the dam. The District has received funding in the amount of $500,000 from the Illinois Department of Natural Resources to perform the engineering.

    In the agreement, ratified by the Forest Preserve Commission on Jan. 13, 2015; the IDNR agreed to provide $2.4 million to remove the Carpentersville dam. The funding will cover costs for engineering and removal of the structure as well as shoreline restoration.

    The District set the standard many years ago in dam removal when we took out the South Batavia Dam. Fisheries biologists have demonstrated through their sampling that removing dams is the most positive thing we can do to improve the rivers for fish. Holistic restoration is still in process, but even removing the dams one at a time works to restore the structure and function of the entire Fox River corridor.

    Contacts: Staff Project Manager: Jerry Culp Engineer: TBD Contractor: TBD

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE INDR Grant Approved January 2015 Phase I Engineering RFP Letting Schedule pending IDNR approval

    Utilization Committee Executive Committee Full Commission Engineering Start Engineering Completion

    2015 – 2016 Fiscal Year Updates

    Jul 15 Staff is working with IDNR on RFP for engineering services. The District is waiting for first installment funding from the IDNR. Total Project cost is $2,500,000, budgeted for this year is Engineering cost of $500,000 Aug 15 Staff is waiting for approval from IDNR to move forward on project. Nov 15 Waiting for first installment from the IDNR before project begins.

    Dec 15 Staff submitted the RFP to IDNR for review, changes have been made based on comments from IDNR. Staff will sent out RFP once approval to move forward from the IDNR is received. Jun 16 No update, the District is waiting for the State to pass an approved budget.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 36 of 75

    2016 – 2017 Fiscal Year Updates

    Sept 16 No update, the District is still waiting for the state to approved the budget.

    Dec 16 Project on hold until State budget approval.

    Mar 17 No update

    Financial Summary Budget: $500,000 Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project #-$ -$ -$ -$

    -$ -$ Total to date Project # 30321 03-35-35-5070

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 37 of 75

    Dick Young Forest Preserve Common Reed Control Fiscal Year: 2016-2017

    Funding Forest Preserve District: $40,000 Other: $ 0 Total Budget: $40,000

    Budget Breakdown Engineering: $ 0 Construction $40,000

    Project Description The Nelson Lake Marsh complex, located in the Dick Young Forest Preserve, contains a diverse mixture of ecosystems. There are sections of sedge meadow, cattail marsh and open water. The entire complex measures roughly 230 acres, approximately 150 acres of which is designated as State Nature Preserve. This distinction flows from the incredibly diverse floral assembly present, as well as the importance of the marsh as a stopover for migratory bird populations. Additionally, populations of at least eight Plants of Concern are located in the marsh including flatleaf bladderwort, sageleaf willow and poison sumac.

    Many of these populations are currently threatened by the presence of giant reed (Phragmites australis). Giant reed is a large perennial grass that is native to Europe. Once introduced, this plant will often form very dense stands that prevents the growth of other plants and can eventually dominate an area entirely. As there are numerous stands of giant reed already present in Nelson Lake Marsh, it is imperative that action is taken now to limit the spread and reduce the current population size.

    Control of giant reed is often very difficult. Access can be an issue with the plant often growing in standing water. The plant can spread through the germination of seed and the spreading of horizontal runners that root into the ground at several locations. It is for these reasons that herbicide application is often the most efficient control method.

    The current population of giant reed in Nelson Lake Marsh must be controlled. This will be accomplished through the hiring of a contractor to apply herbicide. This will increase the ability of the native species to compete and reduce the threat of giant reed invasion.

    Contacts Staff Project Manager: Ben Haberthur Contractor: Integrated Lakes Management Tallgrass Restoration LLC V-3 Construction Group

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE PHASE I Bid Letting September 2016 N/A Bid Approval

    • Utilization Committee October 2016 N/A • Executive Committee November 2016 N/A • Full Commission November 2016 N/A

    PHASE I Completion March 2016 August 2016

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 38 of 75

    STAGE PROJECTED DATE ACTUAL DATE PHASE II Control April 2017 April 2017 Bid Approval

    • Utilization Committee January 2017 March 24, 2017 • Executive Committee February 2017 April 7, 2017 • Full Commission February 2017 April 11, 2017

    Project Completion July 2017

    2016 – 2017 Fiscal Year Updates Jul 16 Phase I: RFQ for first treatment of Giant Reed 7/21. Awarded to Integrated Lakes Management for $10,916 Aug 16 First treatment occurred across 17.2 acres of project area. Dec 16 Phase II released for bids Jan 17 Phase II bids were received. Mar 17 Phase II bid to Planning and Utilization Committee for approval March 24, 2017

    Financial Summary

    Total Budget: $40,000 Expenses:

    Encumbered Actual Spent Product / Service Rendered Project #10,916$ 10,916$ Herbicide Treatment Phase I 20402

    12,185$ Tallgrass Restoration Common Reed control

    9,350$ -$ Reed Control East and South

    VendorIntegrated Lakes

    V-3 Construction Group

    32,451$ 10,916$ Total to date Project # 20402 03-31-31-7060

    Common Reed grass

    Reed Canary grass

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 39 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 40 of 75

    Fabyan Forest Preserve Bridges and Island Improvements Project Phase II* Fiscal Year: 2014-2015

    Funding Forest Preserve District: $700,000 Other: $ 0 Total Budget: $700,000

    Budget Breakdown Engineering: $150,000 Contractor: $360,000 Architect $190,000

    Project Description Fabyan Forest Preserve is without question our most heavily used preserve. The 198 acre preserve hosts many events each year and thousands more walk, jog and ride the trails, as well as visit the historic Villa Museum, and picturesque gardens. In 2012, a section of the concrete bridge that crosses over to the island failed. Staff closed the bridge to public use while completing an evaluation of the bridge. It was determined that the bridge was in such poor condition that the section that failed could not be repaired without replacing the entire bridge. Because of its condition, the District closed the bridge and hired an engineer to develop a plan for its removal while Staff prepared a plan for future improvements to the preserve. Additionally, the causeway culverts are failing preventing water flow on the west side of the island, the condition of the light house and the bridge abutments on the bridge connecting the island to the east side of Fabyan are deteriorating.

    The existing bridge abutment on the east shore of the east Fabyan Fox River bridge has been undermined over the years by the river. The abutment has cracked and the concrete has fallen away from under one of the base plates of the bridge. The existing wing walls are also cracked on both sides and are separating from the main abutment and the river has scoured around the back side of the north side wing wall. Due to the existing conditions of the bridge, it is unsafe for vehicle traffic. Repairs are required before further damage is incurred.

    Recognizing the importance of the Fabyan Forest Preserve and its historical and cultural significances, Staff is currently working on a plan for improving and preserving these site characteristics. Funding remaining in the Fox River Trust Fund in the amount of $495,000 will be dedicated to this project. Approximately $225,000 was expensed in 2013/14 for engineering, bid documents and permitting, as well as the removal of the failed concrete bridge and abutment repair of the east bridge. The remaining funding of approximately $270,000 will be used for future construction phases and as matching funding for future grant applications to preserve a bridge connection, shoreline stabilization and lighthouse restoration. Contacts:

    Staff Project Manager: Jerry Culp Engineer: Gewalt Hamilton Assoc. (GHA) Contractor: Illinois Constructors Corps Architect Williams Architects

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 41 of 75

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Phase I Engineering Firm Hiring RFP Letting October 2013 October 2013 Utilization Committee October 2013 October 31, 2013 Executive Committee November 2013 November 1, 2013 Full Commission November 2013 November 12, 2013 Permits Submitted December 2013 Bid Letting March 2014 March 2014

    Bid Approval April 2014 April 2014 Foot Bridge Removal -Demo Utilization Committee April 2014 July 24, 2014 Executive Committee May 2014 August 1, 2014 Full Commission May 2014 August 8, 2014 Demolition Start August 2014 October 2014 Completion October 2014 November 2014

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 42 of 75

    Phase II GHA Engineering Bridge Replacement

    Engineering Firm Hiring RFP Letting June 2014 Utilization Committee July 2014 July 24, 2014 Executive Committee August 2014 August 1, 2014 Full Commission August 2014 August 8, 2014 Permits Pending Grants Construction Start Pending Grants Construction Completion Pending Grants Bridge Re-installation Bid Letting May 2016 Utilization Committee June 2016 Executive Committee July 2016 Full Commission July 2016 Permits Construction Start August 2016 Construction Completion December 2016 Lighthouse Restoration Bid Letting January 2016 March 2016 Utilization Committee February 2016 March 24, 2016 Executive Committee March 2016 April 8, 2016 Full Commission March 2016 April 12, 2016 Permits Construction Start May 2016 May 2016 Construction Completion August 2016

    2013 – 2014 Fiscal Year Updates

    Jul 13 Staff is working with Gewalt Hamilton engineers on the bridge removal plans, once competed staff will start the permit application process. Aug 13 Staff is working on the permit application for the removal of the concrete bridge.

    Sep 13 Completed a conceptual plan for the proposed bridge repair work at Fabyan. The plan calls for reviewing structures and developing a plan to repair the bridges, it also includes options for replacing the concrete bridge and removing the causeway to allow the restoration of the riparian areas within the preserve.

    Oct 13 Application for the concrete bridge removal is complete staff is working with various agencies to answer questions before submitting the permit.

    Nov 13 The permit application for the removal of the concrete bridge has been submitted to the Army Corp of Engineers for approval, this process can sometimes take several months. During this time staff will prepare a final plan for the proposed improvements for the bridges and river bank restoration work.

    Dec 13 Staff is working on conceptual plan for bridge work and causeway repairs or removal, once complete staff will submit to Commission for review.

    Jan 14 Staff is working with engineers on plans for bridge removal for permit submittal. Applying for grant assistance for construction of a new bridge.

    Feb 14 Presented bridge replacement plan and request for approval to submit grant assistance for the bridge replacement plan. Finalized plans for bridge removal and submitted to CORPs for permits.

    Mar 14 Waiting to hear from Illinois Historic Preservation Agency for approval of bridge replacement, once that is complete staff will work with engineer to complete bid documents for removal. Apr 14 Illinois Historic Preservation approved the removal, once army CORP permit is received staff will begin the bidding process May 14 Staff received the permit from the Army Corps of Engineers and is preparing to bid specification for project

    Jun 14 Project is out to bid, and bids are due the first week of July, staff will be presenting bids at the July Planning and Utilization for review and approval.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 43 of 75

    2014 – 2015 Fiscal Year Updates

    Jul 14

    The District awarded a contract to Gewalt Hamilton Engineering for $13,450, to develop the necessary plans for its removal. Because the bridge was closed to public access, staff requested permission to move forward with the project in two phases; Phase 1 to remove the bridge while preparing plans for Phase 2 which would be the bridge replacement, causeway removal and shoreline restoration. Phase 1, the concrete bridge removal was advertised and bid with 4 vendors responding.

    Aug 14

    Illinois Constructors Corporation from Elburn, Illinois was awarded the lowest qualified bidder with a total bid of $167,000. Staff is currently working on documenting the construction of the boathouse and the lighthouse to allow for new drawings to be completed as part of the renovation. In order to protect the light structure on top of the light house, staff is requesting permission to remove it during this process. As-built drawings will be completed and a set of architectural plans will be developed and once the base structure is rebuilt, the light will be reinstalled.

    Sep 14 Signs have been posted – lighthouse has been temporarily removed.

    Oct 14 Bridge removal has begun, contractor schedule to be completed first week of November. Staff is working with engineer on bridge replacement drawings Nov 14 Bridge has been removed contractor working on restoration

    Dec 14 Restoration for bridge removal complete, the next phase of engineering has been approved, staff will be working with the engineer on bridge reinstallation and causeway removal plans and permitting.

    Jan 15 Staff is working with engineer on second phase of engineering which is the installation bridge and the causeway removal. Feb 15 Staff is getting proposals from contractors to remove the balance of the lighthouse

    Mar 15 Staff has contracted Bird Inc. to remove the balance of the concrete from the lighthouse, the removal is scheduled to be completed by the end of March

    2015 – 2016 Fiscal Year Updates

    Jul 15 Staff is working with engineer on preparing bridge plans and causeway removal plans. Once plans are complete permits will be applied for. Project scheduled to bid for next summer work Aug 15 Bridge installation and Causeway removal plans are still underway. Sep 15 Bridge removal is complete Oct 15 Bridge installation will be included in the bid for the Causeway Removal Nov 15 Staff and Engineer are working on paperwork for permits submittal

    Dec 15 Staff and the engineer are working with the IDNR on plan revisions for the causeway removal, permits are in and being reviewed for the bridge installation and the causeway removal. The bid for the lighthouse restoration is complete and will be advertised in January

    Jan 16 The bid for the lighthouse restoration is out and is due beginning of February, staff has submitted plans for approvals.

    Feb 16 The bid for the lighthouse has been delayed until beginning of March, staff is working with the Illinois Historic Preservation Agency on material specifications for the restoration. The new bid date is March 3rd.

    Mar 16 The lighthouse bid is moving forward. The bid amount was $128,900 it has been submitted to the Commission for review and approval Apr 16 The bid for the light house has been approved. Construction is scheduled to begin in May

    May 16 The contractor has started the repairs on the lighthouse foundation and has found some bad concrete, so staff and consultants are working on a solution.

    Jun 16 The foundation for the lighthouse has been repaired. The contractor is now is moving forward on the installation of the structural steel and the framing.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 44 of 75

    2016 – 2017 Fiscal Year Updates

    Jul 16 The Concrete for the lighthouse has been completed, staff is working with the contractor on the punchlist and site restoration. Bridge installation – staff is working with the engineer and IDNR office of water resources on changes to the plans before the bid preparation can begin.

    Aug 16 Concrete contractor is complete, staff has re-installed the light structure and the roof on the lighthouse. Staff is working on changes based on the review by the IDNR.

    Sept 16 Staff is currently working on getting the railing restored before installation and working with an electrician on the solar light system. Oct 16 Staff is researching companies that can restore the lighthouse railing

    Nov 16 Staff is working with a consultant on a solar light installation that will restore the original look of the light fixture in the lighthouse

    Dec 16 The railing for the lighthouse is currently being evaluated by Horn Steel and they are preparing a proposal for the restoration. Jan 17 Met with Horn Steel, working on restoration ideas for Lighthouse railings. Feb 17 Change order complete for additional engineering work needed for bridge and causeway work.

    Financial Summary FY16-17 Budget: $700,000 Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project #13,450$ 13,345$ Gewalt Hamilton Assoc. (GHA) Bridge Demo Engineering Services 30042

    167,000$ 167,000$ Illinois Constructors Inc. Foot Bridge Removal 20101.B

    26,000$ 22,000$ Gewalt Hamilton Assoc. (GHA)Engineering & permit fees for new bridge abutments, relocation and installation of bridge sections

    20101.C

    2,685$ 2,685$ Williams Architects Boathouse & lighthouse evaluations 20101.A157$ 157$ Menards - Batavia Misc. materials 20101.D

    9,460$ 9,460$ Bird Inc. Concrete removal 20101.E

    20,000$ 19,756$ Williams ArchitectsLighthouse architectural design/engineering for lighthouse

    20101.F

    1,750$ 1,750$ Kane/DuPage Soil & Water erosion control 20101.G128,900$ 128,900$ Schafges Brothers Lighthouse Construction 20101.I

    350$ 350$ Davis Crane Rental Set light on lighthouse 20101.J512$ 512$ EcoCAT Consultation 20101.H

    370,264$ 365,915$ Total to date Project #s 20103:20101 A-J :30042 03-31-31-7040

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 45 of 75

    Fabyan Forest Preserve Causeway Removal Engineering IDNR Grant* Fiscal Year: 2015 – 2016 Funding

    Forest Preserve District: $ 0 Other: IDNR Grant $700,000 Total Budget: $700,000

    Budget Breakdown Engineering: $ 100,000 Construction: $ 600,000

    Project Description Fabyan Forest Preserve is without question our most heavily used preserve. The 198 acre preserve hosts many events each year and thousands more walk, jog and ride the trails, as well as visit the historic Villa Museum, and picturesque gardens. In 2012, a section of the concrete bridge that crosses over to the island failed. Staff closed the bridge to public use while completing an evaluation of the bridge. It was determined that the bridge was in such poor condition that the section that failed could not be repaired without replacing the entire bridge. Because of its condition, the District closed the bridge and hired an engineer to develop a plan for its removal while Staff prepared a plan for future improvements to the preserve. Additionally, the causeway culverts are failing preventing water flow on the west side of the island, the condition of the light house and the bridge abutments on the bridge connecting the island to the east side of Fabyan are deteriorating.

    The removal of the causeway is being coordinated in conjunction with the Fabyan Forest Preserve bridges and island improvement project in that the causeway will be removed following the installation of the new pedestrian bridge.

    In the agreement, ratified by the Forest Preserve Commission on Jan. 13, 2015; the IDNR agreed to provide $1 million to remove the causeway at the Fabyan Forest Preserve. The funding will cover costs for engineering and removal of the two structures as well as shoreline restoration. The IDNR has provided $500,000 of the funding for the engineering. Once a final construction design and estimated cost is approved by the IDNR, they will provide the remaining funding to bid the project.

    The dams are major barriers for fish and other aquatic animals. By removing the structure, animals could more freely move throughout the river corridor. This would greatly improve water quality and fish habitat.

    The District set the standard many years ago in dam removal when we took out the South Batavia Dam. Fisheries biologists have demonstrated through their sampling that removing dams is the most positive thing we can do to improve the rivers for fish. Holistic restoration is still in process, but even removing the dams one at a time works to restore the structure and function of the entire Fox River corridor. Contacts:

    Staff Project Manager: Jerry Culp Engineer: Gewalt Hamilton Assoc. (GHA) Contractor: Illinois Constructors Corps

    Project Schedule STAGE PROJECTED DATE ACTUAL DATE

    Causeway Removal Engineering Firm Hiring RFP Letting June 2014 GHA Engineering Causeway Removal Utilization Committee July 2014 July 24, 2014 and Shoreline Restoration Executive Committee August 2014 August 1, 2014 Full Commission August 2014 August 8, 2014 INDR Grant Approved January 2015 Permits Construction Start Construction Completion

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 46 of 75

    2015 – 2016 Fiscal Year Updates

    Jul 15 Staff is working with engineer on preparing bridge plans and causeway removal plans. Once plans are complete permits will be applied for. Project scheduled to bid for next summer work Aug 15 Bridge installation and causeway removal plans are still underway. Sep 15 Engineering plans are at 50%, staff is working with engineer on starting the application process for permits Oct 15 Staff and engineer working with permitting agencies to get preliminary review of project before submittal Nov 15 Staff is submitting 95% drawings to IDNR for review and approval Dec 15 The drawings have been submitted to IDNR for review, staff and the engineer are waiting comment

    Jan 16 The IDNR has reviewed the drawings and returned comments, the engineer is reviewing and completing suggested changes. Staff and the engineer are also working through the COPR permit process and will modify drawings once comments are received.

    Feb 16 The Engineer has submitted the drawings for permits including the CORP and Department of Water Resources

    Mar 16 The Engineer is working on comments from IDNR and awaiting comments from the CORP before resubmitting the plans to IDNR. April16 Drawing change have been completed and sent to IDNR for review and Approval

    May 16 Received CORP permit and OWR permit. Staff is finalizing bid and preparing for advertisement and has set the bid specification to IDNR for review

    June 16 Staff has sent copies of the permits to IDNR as part of the review process. As soon as the IDNR signs off on the specifications and drawings staff will finalize and advertise for bid.

    2016 – 2017 Fiscal Year Updates

    Jul 16 Staff is still working with the IDNR on the revised plans for the causeway removal.

    Aug 16 The Engineer received additional comments for the causeway removal plans from the IDNR and is working on making the changes to resubmit.

    Sep 16 Staff is working with the engineer on separating the engineered drawings for the causeway, from the bridge for the IDNR, because the IDNR is funding the causeway it will work better to separate them.

    Oct 16

    The estimate for the installation of the bridge over the Fox River is higher than what is available in the budget, so staff is looking for additional funding for this phase of the project. The bridge needs to be install before or at the same time as the causeway removal so the causeway removal is delayed at this time. Staff is also still working with the IDNR office of water resources on the propose changes.

    Nov 16 Working with the IDNR on proposed review comments on the engineering drawings.

    Dec 16 Additional engineering work needed based on IDNR review, staff is working with engineer to get change order submitted Jan 17 Change order submitted for engineering changes needed per IDNR review

    Feb 17 Change order approved for additional engineering, staff will be setting up meeting with IDNR as a follow up to confirm changes and proceed with final drawings.

    Financial Summary FY16-17 Budget: $700,000 Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project #85,232$ 85,232$ Gewalt Hamilton Assoc. Engineering for causeway removal 20103.A

    5,000$ 5,000$ IDNR Premit Fee 20103.B

    9,000$ -$ Gewalt Hamilton Assoc.Change Order #1 DNR requirments for

    permits

    1,750$ 1,750$ Kane/DuPage Soil Erosion Control Review 20103.C

    100,982$ 91,982$ Total to date Project # 20103 03-35-35-7050

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 47 of 75

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 48 of 75

    Fabyan Forest Preserve Japanese Garden Pond Engineering Fiscal Year: 2016-2017 Funding

    Forest Preserve District: $10,000 Other: $ 0 Total Budget: $10,000

    Budget Breakdown Engineering: $10,000 Construction: $ 0

    Project Description For the last two years, the water level of the pond has not been able to be maintained at an appropriate level. Staff installed water pumps and hoses to fill the pond on numerous occasions. The garden areas of Fabyan are highly visible and highly used, as well as a source of revenue for the District. The cause for the drainage of the pond is unknown at this time. Monies will be used to begin the investigation of a possible leak and potential repair/ redesign to bring the pond back to the standard patrons have known and expected

    Contacts

    Staff Project Manager: John Goreth Engineer: TBD

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Bid Letting/RFP October 2016 Bid Approval

    • Utilization Committee January 2016 N/A • Executive Committee February 2017 N/A • Full Commission February 2017 N/A

    Construction Start March 2017 Construction Completion June 2017

    2016 – 2017 Fiscal Year Updates Jul 16 Staff working with Planning Department to evaluate engineering project. Aug 16 Staff working with Planning Department to evaluate engineering project. Sep 16 Staff working with Planning Department to evaluate engineering project. Oct 16 Staff putting together specifications for engineering. Nov 16 Staff putting together specifications for engineering. Dec 16 Specifications complete. Contacting engineering firms for proposals. Jan 17 Specifications complete. Contacting engineering firms for proposals. Feb 17 Specifications complete. Contacting engineering firms for proposals. Mar 17 Proposals received. Waiting for conducive weather to evaluate pond levels.

    Financial Summary Total Budget: $10,000 Expenses:

    Encumbered Actual Spent Product / Service Rendered Project #-$ -$ -$ -$ Project # 10404 03-21-24-7050

    Vendor

    Total to date

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 49 of 75

    Fox River Trail - Raymond Street Re-Route* Fiscal Year: 2015-2016

    Funding Forest Preserve District: $1,358,000 Other: CMAP-TAP Grant $1,774,896 Total Budget: $3,132,896

    Budget Breakdown Engineering: $ 237,906 Construction: $2,894,990

    Project Description

    In the fall of 2008, flood waters eroded and washed out the footings for the Fox River Trail Bridge near Raymond Street in South Elgin. In March of 2014, the Planning and Utilization Committee reviewed the status of repairs to the current bridge that connects the Fox River Trail to the Elgin branch of the Illinois Prairie Path at the Raymond Street Forest Preserve. Additional damage to the bridge and its abutments was sustained, the Committee approved staff’s recommendations to remove the bridge and continue to research an alternative route for the bike trail connections. Staff presented plans that proposed three different routes to reconnect the trail.

    The proposed concepts contemplated 1) routing the trail through the Fox River Water Reclamation District (FRWRD) property over the current at grade crossing and building a new bridge over Poplar Creek west of the current bridge, 2) rebuilding Raymond Street and Riverview Drive to accommodate a bike lane and route to a point where an at grade crossing could be constructed or 3) constructing a tunnel approximatel 200 feet south of the existing bridge. All three options were viable options, but preliminary conversations with the railroad ruled out the at grade crossings at FRWRD and on Riverview Drive so staff moved forward to prepare a request for proposal for engineering services to construct a tunnel under the railroad to reconnect the Fox River Trail to the Elgin branch of the Illinois Prairie Path.

    In 2014, Wills Burke Kelsey Associates (WBK) of St. Charles, IL was contracted to complete the phase I engineering for the project which includes working with the District on applying for grants to fund the construction of the project in January of 2016.

    WBK’s contract was extended to complete the phase II engineering which will include permits, construction drawings, and project observation.

    The contract for phase I engineering was approved for $106,559.12, based on a $1.3-million-dollar project. During the IDOT reviews and preliminary engineering, the scope of the project changed requiring additional engineering studies.

    The District was notified in October of 2015 that it had been awarded a Transportation Alternatives Program (TAP) grant through the Chicago Metropolitan Agency for Planning (CMAP). This federal grant will reimburse 80% of the cost of the project estimated at $2.3 million dollars including the Phase II engineering estimated at $180,000.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 50 of 75

    Contacts Staff Project Manager: Jerry Culp Engineering: WBK Engineering William Hanna Western Survey Contractor: TBD

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE

    Original Bridge Repair

    Engineering Firm Hiring September 2009 February 2013 RFP Letting

    • Utilization Committee October 2009 October 29, 2009 • Executive Committee November 2009 November 6, 2009 • Full Commission November 2009 November 9, 2009

    Former Bridge Repair

    Bid Approval for Construction • Utilization Committee July 2010 March 2012 January 28, 2013 • Executive Committee August 2010 April 2012 February 1, 2013 • Full Commission August 2010 April 2012 February 13, 2013

    New Tunnel Design Project Construction Start

    TAP grant awarded October 2015, Construction start

    June 2017

    Construction Completion June 2018

    2009 – 2010 Fiscal Year Updates

    Jul 09 Staff is working with operations on proposals from engineers to redesign project so shoreline can be stabilized and abutments will remain in place.

    Oct 09 Utilization Committee approved the engineering contract with Western Surveying & Engineering for a price of $38,895. Moving to Executive and Full Commission for approval in November Dec 09 Contract let – Engineering has sent letter to IDNR. Working on cross sections. Jan 10 Weather delays. Feb 10 Cross sections are completed. Mar 10 Bridge inspected – working on the engineering repair plans Apr 10 No progress due to weather. May 10 Borings were taken around bridge site to determine soil stability. Jun 10 Waiting for report on soil stability to complete the IDNR permit application.

    2010 – 2011 Fiscal Year Updates Jul 10 Western Engineering hired and working on engineering plan.

    Sep 10 Received a report on the site mapping and borings. Due to lack of performance by Western Surveying and Engineering, letter sent requesting contact. Oct 10 Communication sent to WE requesting meeting. Nov 10 Meeting with WE scheduled. Dec 10 All parties met regarding project. WE committed to continuing project and have bid spec ready by Jan. 15, 2011 Jan 11 Bid specifications not yet received. Spenader has hired Terracon to do the specification work. Feb 11 The bridge permit application has been sent in to the IDNR by Western Engineering (Spenader).

    Mar 11 IDNR requested more information, Spenader to send. Elevation diagrams and engineering diagrams. Waiting to prepare bid specs.

    May 11 Terracon has been working on plans for the bridge footings. Western is working with other engineers to develop a bracket for the bridge to fasten it to the footings and sheet pilings. Jun 11 Waiting on plans for the bridge abutments, sheet pilings, and brackets.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 51 of 75

    2011 – 2012 Fiscal Year Updates Aug 11 Received first draft of plan sets and reviewed at the end of August.

    Sept 11 Met with John Spenader of Western Engineering (WE) to discuss plan set. Provided WE with specifications for asphalt trail and seeding work. Awaiting final specifications for bid process to begin. Oct 11 Awaiting final specifications for review.

    Dec 11 Western Engineering has delivered final specifications. Staff is waiting to hear from the Army Corps about the need for a permit. Documents will be sent for bid in January 2012.

    Feb 12 Permission granted from Kane/DuPage Soil & Water Conservation District to proceed. Waiting for IDNR approval, subsequent to the Army Corps permit and then bid process can then begin. Apr 12 Engineer working with IDNR for additional permitting. May 12 Waiting for permits and meeting with ACE.

    Jun 12 Engineer working with USACE for permitting information and submission of maintenance plan. Letter drafted to USACE to declare Western Engineering as liaison on behalf of FPD.

    2012 – 2013 Fiscal Year Updates Jul 12 Waiting for WSE to deliver information to the IDNR and USACE for permit processing.

    Aug 12 IDNR and USACE reviewing documents from Western S&E. District provided an inspection and maintenance schedule /plan to the IDNR as requested.

    Sep 12 Waiting for permit review and permits from USACE. Additionally, IDNR has received the requested easement grant documentation from the RR to install the original bridge. Dec 12 Blueprints for the project and all permits have been obtained. Preparing bid specs.

    Feb 13

    Due to poor soils to a depth of 40’, the footings and shoreline stabilization materials will be driven-steel piles with an engineered bracket welded to it to hold the bridge. The bid was sent out to 15 vendors with 4 vendors responding. The qualified lowest bidder was Herlihy Mid-Continent of Romeoville, IL with a bid price of $98,858.26 to repair the Fox River Trail bridge. Initial budget funds were anticipating conventional concrete footings. Due to unstable soils, conventional footings were not feasible and the Army Corps approved the modification to specify steel piles to be driven as bridge support and bank stabilization. The steel piles require no excavation or coffer dams to divert water flow, therefore the construction costs is substantially less expensive.

    Apr 13 Waiting for railroad permit and material delivery.

    Jun 13

    The project was awarded to Herlihy Mid-Continent in March, 2013. Herlihy was unable to find the steel specified in the bid documents prepared by Terracon Engineers. Additionally, the District contacted steel manufacturers and was also unable to locate the specified steel. Herlihy was able to obtain six sections of the steel but at a length 5’ longer than specified. Terracon Engineers has approved the use of the additional length steel in the abutment design of the bridge repair. For those six sections of steel, Herlihy is requesting an increase to cover the additional length of the material. For the remaining sheets required for the repair of the wing wall, an alternative, thinner steel has been approved by Terracon Engineers. Herlihy is providing a credit for the reduced cost of the thinner steel. Therefore, with the credits subtracted from the increase, the cost of the change order totals $1,003.32 for the modified steel. Waiting for railroad permit to begin construction.

    2013 – 2014 Fiscal Year Updates

    Aug 13

    There were some additional issues from the storm event that followed the bid award. Additional damage was identified when the contractor was dismantling portions of the bridge; the ledge that was supporting the bridge was sheared off completely. Revised plans were developed from the Engineer; the Army Corps of Engineers has issued a permit for the revised plans. There is approximately $100,000 still remaining in the budget as contingency for this item.

    Sep 13 Revised plans have been submitted to the railroad for review/approval. A bid is being prepared for the additional work to be released once approval is received from the railroad. Oct 13 Railroad denied proposed plans

    Nov 13 Committee approved the removal of the two existing bridge spans. Staff researching alternative routes for the Fox River Trail in this area. Staff is meeting with FRWRD (Fox River Water Reclamation District) and South Elgin.

    Dec 13 No update at this time.

    Jan 14

    Staff prepared plans to research rerouting the trail and worked with engineering firms to determine the best long term plan for the trail. Based on the research the best long term solution for the trail reroute is to construct a tunnel under the railroad and reconnect the trail. Staff presented the proposed reroute to the Planning & Utilization Committee and it was approved.

    Feb 14 Staff is working on preparing a request for proposals for the engineering needed to construction the trail reroute.

    Mar 14 The request for proposal has been advertised and is due in April, once the RFPs are submitted and staff has reviewed them the most qualified submittal will be presented to the Planning & Utilization Committee for review and approval.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 52 of 75

    2013 – 2014 Fiscal Year Updates (cont.)

    Apr 14 Staff set up a kick off meeting with Wills Burke Kelsey to layout the scope of the project and to begin preparing a schedule for the project. May 14 WBK reviewed project with the Union Pacific Railroad engineers to layout the process for approvals for the re-routed trail June 14 WBK is currently collecting data, topo, tree survey etc. as they begin preparing plans for the trail re-route.

    2014 – 2015 Fiscal Year Updates

    Jul 14 Staff met with WBK to review collected data and issue related to the reroute and set schedules for preparing the new layout, phase I drawings and approval process for applying for funding

    Aug 14 Staff met with WBK to review the preliminary layout of the trail reroute, after the field visit, staff and engineers adjusted the layout to reduce impact to the trees and wetlands in the area. Sep 14 Staff met with IDOT to begin review and approval process for the Phase I engineering. Oct 14 Engineers are finalizing new trail route and preparing drawings to submit to the railroad

    Nov 14 Plans for the re-route have been submitted to the railroad, waiting for comments, staff is also working with WBK on funding opportunities and grants. Dec 14 Staff attended a CMAP meeting regarding grant funding opportunities for the project. Jan 15 Staff and engineer attended a meeting with IDOT to present the project and prepare for grant submittal

    Feb 15 Staff and engineer met with CMAP representatives to review project and discuss how it meets grants qualifications. Staff also started the process with Union Pacific for the easement needed to construct the underpass

    Mar 15 Grant application has been submitted, site analysis and data gathering work will continue as we continue to complete the phase I engineering.

    Apr 15

    During the IDOT review and preliminary engineering, the scope of the project changed requiring additional engineering studies. These include environmental site assessments, hydraulic modeling, additional surveys and tree inventories due to enlarged project boundaries to accommodate changes determined through the IDOT review. A change order was submitted for Commission approval in the amount of $35,541.54.

    May 15 Suggested changes by IDOT and the Union Pacific Railroad have increased the cost of the project, staff and the engineers are reviewing project items to see if changes can be made to reduce costs

    Jun 15 Staff and engineer and still adjusting the project based on input from IDOT and the railroad, all changes and final submittals will be completed by July. The District should be notified this fall regarding the TAP grant application applied for through CMAP.

    2015 – 2016 Fiscal Year Updates Jul 15 FY2015/16 budget includes Fox River Trail South Elgin improvements.

    Aug 15 Phase I engineering is complete, staff and engineer are continuing to work with the railroad on modifications to the plan. The CMAP TAP grant application is in and notification is scheduled for October Sep 15 Railroad has reviewed plan and provided comments, the engineer is revising drawings for resubmittal

    Oct 15 The TAP funding for the grant has been approved. Project is estimated to cost $2,325,179.12 of which the District will receive $1,774,896 in reimbursement for the project. Project cost after reimbursement $550,283.12

    Nov 15 Staff attended a kick off meeting with CMAP regarding the TAP funding. This meeting set guidelines and milestones for the project. Staff has scheduled a meeting with the engineer in December to start preparing for Phase II engineering.

    Dec 15 Staff received proposal from engineer for phase II engineering, this will be presented at the January Planning and Utilization Committee for review and approval Jan 16 Phase II engineering was approved, staff will be presenting to IDOT for their approval

    Feb 16 Staff has submitted the Phase II engineering to IDOT for approval, this is the first step in meeting a series of timelines for the grant project. Mar 16 Staff and engineer are still working with IDOT for approval on phase II engineering Apr 16 Engineer has made minor changes to the plans per IDOT recommendations and resubmitted.

    May 16 IDOT has approved the phase II engineering work the next miles stone we need to meet is submitting of pre-final plans to IDOT before the end of June.

    Jun 16 Pre-final plans have been submitted and approved by IDOT our next milestone is to get federal authorization for construction by September.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 53 of 75

    2016 – 2017 Fiscal Year Updates

    Jul 16 Staff is working with the engineer on finalizing the drawings to prepare them for our next authorization. Staff is also getting the legal description to the engineer and working to finalize the compensatory storage areas.

    Aug 16 The legal description have been prepared for the site and incorporated into the drawings, staff will begin working with FRWRD on the easements needed for the compensatory storage and construction easements.

    Sep 16 Staff is working on the tree replacement plans and mitigation requirements for the construction. Oct 16 Staff is working with the engineer requested documents for IDOT approval of the project Nov 16 Staff is working with FRWRD on the proposed easement agreement for the compensatory storage area

    Dec 16 Staff is reviewing an alternate location for the comp storage and preparing for final acquisition of easements to complete the project.

    Jan 17 Alternative location for comp storage didn’t pan out, staff is finalizing the easement agreement with FRWRD for the comp storage easement agreement.

    Feb 17 Staff has started contact with the UP’s Real Estate Department to complete new or relocated easement for the tunnel. Current District funding budgeted total is $700,000. Additional funding will be budgeted in 2017/18 fiscal year.

    Financial Summary Budget: $700,000 Expenses:

    Encumbered Actual Spent Vendor Product / Service Rendered Project #38,895$ 38,895$ Western Survey & Engineering Engineering Services 3032059,861$ 59,171$ Herlihy Mid-Continent Bridge Repair & change order 10021

    142,101$ 139,840$ Wills Burke Kelsey (WBK) Engineering for re-route 30303.A12,362$ 12,362$ Union Pacific Railroad Engineering review of tunnel 30303.B

    2,500$ 2,500$ William Hanna Survey Work 30303.C136,173$ 66,300$ Wills Burke Kelsey (WBK) Phase II Engineering work 30320.A

    391,892$ 319,068$ Total to dateProject #s 30303 A-C : 30320:

    1002103-35-35-7050 03-35-35-5070

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 54 of 75

    Freeman Kame Forest Preserve Prairie Reconstruction Fiscal Year: 2016-2017

    Funding Forest Preserve District: $20,000 Other: $ 0 Total Budget: $20,000

    Budget Breakdown Engineering: $ 0 Construction $20,000

    Project Description Freeman Kame Forest Preserve encompasses 1,335 acres and is located along Freeman Road, in Rutland Township. The most notable features of the preserve are the rolling terrain and diverse wetland and upland habitats created by glacial activity. A 35-acre portion of the preserve including a gravel kame has been a dedicated Illinois State Nature Preserve since 1994. In 2015, 101 acres of additional nature preserve and buffer were dedicated at the site, giving further protection to prairie, savannah, marsh and sedge meadow habitats.

    The marsh and sedge meadow habitats are home to a variety of species including a population of state endangered reptiles. An approximately 18-acre farm field was removed from agricultural production in 2011 for the following reasons: its proximity to the wetland complex, the fields suitability for turtle nesting and the fact that a nesting female of an endangered species of turtle was crushed by farm equipment.

    The field has been fallow for several years and dominated by species of weeds. This project will establish prairie habitat in this formerly farmed area with the goal of creating quality turtle nesting habitat in close proximity to the wetland habitats. The project would also benefit grassland birds. Funds will be used to have the field disked and harrowed, herbicide treatment of the weeds that emerge, and to purchase native seed for the project area.

    Contacts Staff Project Manager: Ben Haberthur Contractor: Shooting Star Native Seed

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Bid Letting September 2016 September 2016 Bid Approval

    • Utilization Committee October 2016 October 27, 2016 • Executive Committee November 2016 November 4, 2016 • Full Commission November 2016 November 8, 2016

    Construction Start March 2017 Construction Completion May 2017

    2016 – 2017 Fiscal Year Updates Jul 16 Site reconnaissance to determine weed control needs. Aug 16 Whole site mowing in preparation for follow-on herbicide and disc treatment. Sep 16 Prairie mix specifications included in annual seed bid. Dec 16 Bid approved by Commission awaiting delivery. Jan 17 Seed order delivered and sown by Staff. Feb 17 No work required until late spring weed control.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 55 of 75

    Financial Summary

    Total Budget: $20,000 Expenses:

    Encumbered Actual Spent Product / Service Rendered Project #20,000$ 20,000$ Native Seeds 2040120,000$ 20,000$ Total to date Project # 20401 03-31-31-7060

    VendorShooting Star

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 56 of 75

    Freeman Kame Forest Preserve RTP Grant* Fiscal Year: 2015 – 2016

    Funding Forest Preserve District: $ 80,000 Other: RTP Grant $200,000 Total Budget: $280,000

    Budget Breakdown Engineering: $ 70,000 Construction: $210,000

    Project Description Freeman Kame-Meagher Preserve has some of Kane County's most picturesque topography - situated on the northern flank of the kettle-moraine complex north of Gilberts. There are wet kettle pockets defined by the wooded kames and numerous hills and drumlins that create a panorama of habitats ranging from the spectacular to the cozy secluded nooks. The Preserve (1,264 acres) is also home to Camp Tomo Chi-Chi Youth Camp and Lodge, as well as, a State Dedicated Nature Preserve on the north side of Freeman Road.

    Given the attractive setting and high horse traffic in the area, Freeman is a natural for equestrian trail development. Based on both 2006 and 2013 public input the District seeks assistance to 1) open new areas for riding; 2) build connecting trails to link the camp area and 3.5 miles of existing hiking trails; and 3) address potential user conflict with way-finding and interpretive signs.

    The project begins along Tower Hill Road where a proposed new entrance and equestrian trailer parking area offers first time access to the southern preserve. Features are a 15 car/trailer parking, well and drinking fountain, interpretive and way-finding signs, shelter and restroom – including solar panels. A 10’ wide screened trail will loop through the southern preserve area for 0.66 miles and then 6’ wide mown trail (1.12 miles) will meander north through the hills, woods and open areas to join an existing 3.5 trails leading to and around the camp area. No riding is permitted north of Freeman Road – where the INAI site is located. The trail skirts the ponds and avoids the wetlands on site. The District proposes solar panels at the restrooms which will not only generate power to the facility, but will also feed back into the power grid – resulting in a negative power usage. The project is ready to begin immediately upon IDNR approval. Development is planned for a 6-month construction period. The project incorporates input from public for trails, connections and water at the site.

    The District was awarded an IDNR RTP grant which totals $280,000. The grant will reimburse the District $200,000 upon completion.

    Contacts

    Staff Project Manager: Jerry Culp Engineer: Bono Engineering Contractor: Evans & Son

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Grant Approval 2014 September 2014 Bid Letting March 2015 June 2015

    • Utilization Committee April 2015 June 2015 • Executive Committee May 2015 July 2015 • Full Commission May 2015 July 2015

    Construction Start June 2015 August 2015 Construction Completion December 31, 2016 December 2016

    Project Complete December 2016

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 57 of 75

    2014 – 2015 Fiscal Year Updates Jul 14 Grant was submitted in February 2013. Aug 14 Awaiting approval process. Sep 14 Grant approved by IDNR. Received agreement to begin September 17, 2014 – December 31, 2016.

    Oct 14 Staff will begin preparing drawings to bid the proposed improvements scheduled for bidding in fall of 2015 Nov 14 Working with IDNR to finalize contract and paperwork. Dec 14 Reviewing and preparing site drawings to begin final layout of site plans.

    Mar 15 Site plans are complete; they are currently out to staff for final review. Project is scheduled to be bid in May and construction starting in July. Apr 15 Staff is preparing bid documents.

    May 15 The bid for the parking lot, drive and trail is out to bid and due in June. The Shelter restroom and well bids will go out in July and August for completion this fall.

    Jun 15 Consultant hired to make detention calculations. Bids for the parking lot, drive and trail are in and staff has submitted for review and approval. Low bidder for the bid is Evans and Sons with a bid of $135,630. Once approved staff will work with contractor to schedule construction

    2015– 2016 Fiscal Year Updates

    Jul 15 Bids for the parking lot, drive and trail have been approved and scheduled to begin in August, staff is working on bids for the shelter, restroom and well.

    Aug 15 The trail and parking lot are complete; staff is working on bids for the shelter. Staff is also working on the restroom and well installation Sep 15 Staff is preparing bids for winter letting and spring construction for the shelter

    Oct 15 Staff is evaluating the existing well on site if usable will upgrade existing well if not will prepare bid for new well.

    Nov 15 Bids are ready for shelter, staff will advertise and bid the shelter. Bids will be submitted for review and approval at the January Planning and Utilization meeting.

    Dec 15 Bids for the shelter have been advertised and scheduled to opened in January and submitted to the Utilization Committee in January for review and approval.

    Jan 16 Bids for the shelter have been approved, staff will work with the contractor to get the shelter ordered and scheduled for installation this spring

    Feb 16

    Shelter contractor has submitted all necessary paperwork and shelter structure has been ordered. Staff is also working on testing the well to see if it is acceptable for use or a new well is needed. Once the well test results are in staff will begin preparing bids for the drinking fountain installation. Staff is also submitted permit applications for the restrooms and is scheduling the restroom installation once the shelter is complete.

    Mar 16 Staff is preparing for the construction of the shelter as soon as weather permits, and working with the trades department on scheduling the restroom construction Apr 16 The contractor has started excavating the area in preparation for the shelter construction May 16 The contractor has completed the shelter construction, staff is working with them on punch list items.

    Jun 16 The contractor has completed the shelter and restoration work is complete. The restroom construction is scheduled to begin late July early August.

    2016– 2017 Fiscal Year Updates

    July 16 Restroom construction is underway, staff is working on well rehabilitation, water hydrant and shelter electric installation.

    Aug 16 Restroom construction is complete. Trades has install the electric and water line to the shelter and staff is coordinating the well contractor to compete well upgrades.

    Sept 16 Well contractor has completed the upgrades to the well, staff is working on finalizing all contractor work and restoration of the site. Oct 16 Solar powered gate has been installed, this completes the balance of the project. Nov 16 Staff is working with the contractor on punch list items and will review project billing and closeout. Dec 16 Project is complete, staff will be working on grant reimbursement paperwork.

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 58 of 75

    Financial Summary Budget: $280,000 Expenses:

    Interpretive signs on trails

    Shelter

  • M:\General\FY_2016-17\CAPITAL PROJECTS\Capital Projects_FY1617_March2017_MASTER_DRAFT1a.docx Page 59 of 75

    Grunwald Forest Preserve South Operations Maintenance Facility Parking Improvements Fiscal Year: 2016-2017

    Funding Forest Preserve District: $22,000 Other: $ 0 Total Budget: $22,000

    Budget Breakdown Engineering: $ 0 Construction $22,000

    Project Description This project is to pave a portion of the existing gravel parking lot at the South Operations Maintenance Facility within the Grunwald Farms Forest Preserve. The gravel lot holds moisture that negatively effects vehicles and equipment parked there. The moisture creates rust on all metal surfaces. This rust destroys the vehicles and equipment at a much faster rate than normal. The scope of the paving project is approximately 9,900 sq. ft.

    Contacts Staff Project Manager: John Goreth Contractor: Meyer Paving

    Project Schedule

    STAGE PROJECTED DATE ACTUAL DATE Bid Letting/Quotes September 2016 February 2017 Bid Approval/Quote Accepted March 2017

    • Utilization Committee January 2017 N/A • Executive Committee February 2017 N/A • Full Commission February 2017 N/A

    Construction Start April 2017 Construction Completion May 2017

    2016 – 2017 Fiscal Year Updates Jul 16 Staff continuing to work on specifications and proposals. Aug 16 Staff continuing to work on specifications and proposals. Sep 16 Staff continuing to work on specifications and proposals. Oct 16 Staff continuing to work on specifications and proposals. Nov 16 Staff continuing to work on specifications and proposals. Dec 16 Specifications are complete, and waiting on more proposals. Jan 17 Specifications are complete, and waiting on more proposals. Feb 17 Specifications are complete, and waiting on more proposals. Mar 17 Meyer Paving proposal