caerphilly county borough council's budget proposals 2012/2013
TRANSCRIPT
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
1/18
Appendix
AGENDA ITEM NO. 2(C)
COUNCIL 23RD FEBRUARY 2012
SUBJECT: BUDGET PROPOSALS 2012/2013
REPORT BY: DEPUTY CHIEF EXECUTIVE
1. PURPOSE OF REPORT
1.1 To seek Councils approval for the budget proposals contained within this report.
2. SUMMARY
2.1 The Welsh Governments (WG) Revenue Support Grant Settlement (RSG) for CaerphillyCounty Borough Council for the financial year 1.4.2012 to 31.3.2013 is an uplift of 1.06 % i.e.a cash increase of 2.656m on the previous year. However, this includes a one year increaseof circa 0.500m relating to a free school meal (FSM) data set adjustment which is likely to belost in 2013/14. It is proposed that the 0.5m be considered as a one off revenue contributionto capital.
2.2 The capital allocations available to Caerphilly in the RSG and from the General Capital Granthave been cut by a further 7.5% in 12/13, a reduction of 0.725m on the previous year.
2.3 The proposals contained within the report identifies (excluding external grant funding) theneed to achieve cash savings for 2012/13 of 3.410m i.e.
2.170m whole Authority Cost pressures (see Section 5.2) 3.896m inescapable Service Pressures and (see Section 5.3) 2.656m RSG allocation from WG (see Section 5.4)
Table 1 - Summary
Section Description +m -m5.1 Whole Authority Cost Pressures - 2.1705.2 Inescapable Service Pressures - 3.8965.3 WG RSG Funding 2.6565.4 Savings Achieved in advance 6.8115.5 Revenue Contribution to Capital 3.401
TOTAL 9.467 (9.467)
2.4 Section 5.5 of the report identifies a total of 6.811m in efficiencies which have been achievedin preparation for the 2012/13 budget which will provide a surplus in the year of3.401m, which is proposed to contribute to the Capital Programme (see Section 6). This willprotect employment opportunities, which would otherwise have been lost and address theWelsh Government cut to capital funding.
2.5 The indicative savings target to be achieved by March 2015 is 9.578m and proposals withinthe report show that all but 1.081m is already identified and achieved.
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
2/18
Appendix
2.6 The net revenue budget for the Council, if approved, would be 315.240m for 2012/13(including transfers in). This figure was 312.666m for 2011/12 (see Appendix 1).
3. LINKS TO STRATEGY
3.1 Budget decisions impact on all Council strategies. This report relates primarily to the efficientand effective use of the Councils revenue and capital resources.
4. ECONOMIC OUTLOOK MEDIUM TERM FINANCIAL PLANNING (2013/14 2014/15)
4.1 The indicative RSG from the WG for Caerphilly County Borough Council for 2013/14 is afurther uplift of 1.37% and a further uplift of 0.62%; in 2014/15. Given inflation is running atnearer 5%, this is a real terms cash cut not only for this year but for the years ahead.
4.2 The Provisional Settlement includes a provision of a 1% protection above the percentageapplied by Central Government to the WGs block grant each year, for the next 3 years for
schools and 1 year (re: 13/14) for social care. However, the Medium Term Plan proposedfor Social Care provides for additional growth in 12/13 to meet service pressures and acontinuation of the pledge of 1% plus growth for 13/14 and 14/15.
4.3 A revised Medium Term Financial Plan has been produced for the period 2012/13 to 2014/15based on the assumptions highlighted above and are detailed in Appendix 2 (2a and 2b) ofthis report.
4.4 The revised Cash Savings targets for the Council for the period are summarised as follows:-
Annual Cash Savings Target Cumulative Cash Savings Targetm m
2012/13 - 3.410 - 3.4102013/14 - 3.685 - 7.0952014/15 - 2.483 - 9.578
5. BUDGET STRATEGY PROPOSAL 2012/13
5.1 This section of the report sets out the key strategic proposals for consideration for thefinancial year 1.4.12 to 31.3.13.
5.2 Whole Authority Cost Pressures (2.170m)
5.2.1 The whole Authority cost pressures totalling 2.170m are set out in Table 2 below:-
Table 2 Whole Authority Cost Pressures
mWhole Authority Cost Pressures 2012/13
Pay (excluding Teachers; Social Services and other school staff)@ 1%
0.770
Supported Borrowing (capital financing) 0.500
Energy Tax 0.400
Revenue Contribution to Capital (free school meals data change) 0.500
TOTAL 2.170m
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
3/18
Appendix
5.3 Service Commitments/Pressures (3.896m)
5.3.1 The Council continues to manage within its means and is projected to deliver a balancedbudget overall for this financial year to 31.3.12. However, this budget recognises the extremedemographic pressures with Social Care.
5.3.2 Whilst there continues to be pressure on services and new responsibilities for the Council,Table 3 below identifies the inescapable service pressures and commitments that need to beprovided.
Table 3 Inescapable Service Pressures and Service Commitments
mRevenue Contribution to Capital 0.106Libraries/Customer First Development(Bargoed/Risca/Caerphilly/Newbridge)
0.500
Landfill Tax (0.080)Meeting the Schools Pledge (see Appendix 2) 1.570
Meeting the Social Services Pledge (see Appendix 3) 1.100Additional Social Services Pressures 700
TOTAL 3.896
5.4 WG Funding (2.656m)
5.4.1 The WG RSG Settlement provides additional funding of 1.06% for 2012/13, which provides anadditional amount for Caerphilly of 2.656 m in cash terms.
5.4.2 The RSG increase for Caerphilly of 2.656m includes an estimated amount of 0.5m relatingto FSM data set changes. It is considered to be prudent not to commit this 0.5m as ongoing
revenue as it is unlikely to be available in the RSG for 2013/14. Consequently, this 0.5m oneoff additional funding will be treated as a revenue contribution to capital. An additional0.106m is provided as a revenue contribution to capital for 12/13 from the RSG, which willform part of the Savings Strategy in 2014/15.
5.5 Savings Achieved (6.811m)
5.5.1 As part of the Medium Term Financial Strategy (MTFP) placed before Members on 24February 2011, a number of proposals have already been achieved and approved inaccordance with the Strategy. In readiness for April 2012/13; 2013/14 financial years, thefollowing savings have already been achieved as a consequence of decisions already taken.
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
4/18
Appendix
Table 4(a) - Service Cuts/Efficiency Already Achieved/Approved which contribute to2012/13
m mSavings Carried Forward from 2011/12 3.355 3.355
Education and LeisureLEI - Additional Support 0.030 Behaviour Support 0.060 Vacancy Management 0.080 Efficiency Savings Back Office 0.046 Reconfiguring of Statements Provision 0.028Community and Leisure Vacancy Management 0.105 Pension Strain 0.021 Reduction in operational expenses 0.042
Reduction in Training Support Grants 0.036 0.448
Environment Street Lighting 0.050 Highway Maintenance 0.050 Car Park Maintenance 0.020 Winter Maintenance 0.040 Llancaich Fawr Running Costs 0.130 Vacancy Management 0.121
0.411
Corporate Services/Corporate Efficiencies Vacancy Management 0.435 Pension Strain 0.080 Job Evaluation (Collective Agreement) 1.280 Council Tax Net Increase in Band D equivalent properties 0.155 Demographic Savings School Pupil Numbers 0.239 Fire Service Levy 0.133 Essential User plus 55p mile (excluding Schools and Social Services) 0.275
2.597
TOTAL 6.811
5.5.2 In addition to the 6.811m already achieved for 2012/13 financial year, approval has alreadybeen achieved for 2013/14 of 1.686 m (see Table 4(b))
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
5/18
Appendix
Table 4(b) Savings Approved 2013/14 (1.686m)
2013/14 TOTAL
m mEducation & LeisureLEI
Additional Support 0.140 Behaviour Support 0.099 Misc 0.041Community & Leisure Vacancy Management 0.062 Repayment of Invest to Save 0.077 Review of Pricing Structure 0.137 Reconfiguration of Operational H/S 0.050 Pension Strain 0.007Planning & Strategy Vacancy Management 0.147
0.760
Environment
Street Lighting 0.050
Highway Maintenance 0.050
Drainage Maintenance 0.030
Canal Maintenance 0.030
Subsidised Bus Service 0.075
Vacancy Management 0.121
0.356
Corporate Services Vacancy Management 0.170 School Demographic 13/14 0.400
0.570
1.686
5.5.3 Table 4 (c) The balance of savings to be found by 31March 2015 is therefore 1.081m i.e.-
mSavings Target by 31.3.2015 9.578Less 2012/13 Savings (6.811)
Less 2013/14 Savings (1.686)Savings Target by 2014/15 1.081 m
5.5.4 The strategy to achieve savings in advance to utilise towards capital, allows better planning,more time to consult and implement which provides stability to the Authority, its staff andresidents throughout a very difficult fiscal period.
5.5.5 The proposals identified to achieve the target figure of 1.081m by 2014/15 will be broughtforward in the coming year, will include:-
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
6/18
Appendix
Table 4(d) Savings Targets to be identified by 31.3.15
m
Education and Leisure (non schools) 31% 0.148Environment 48% 0.228Corporate Services 21% 0.100
Schools Demographic 14/15 0.299Office Accommodation Rationalisation(excludes Social Services)
0.200
RCCO from 12/13 0.106
TOTAL 1.081
5.6 Deprivation Grant and Outcome Agreement
5.6.1 The allocation of Deprivation Grant remains unchanged i.e. 2.466 m for 2012/13. Membersare reminded that this allocation could reduce in future years, albeit that there are noproposals currently.
5.6.2 The proposals for the allocation of Deprivation Grant are:-
m
Contribution to Capital 1.666
Highway Maintenance 0.400
Community Assets 0.400
5.6.3 The allocation of the Outcome Agreement of 1.882m submitted to the Welsh Government(WG) in line with WG requirements support the 10 strategic themes as set out in Appendix 4of this report.
5.6.4 The proposals for the use of Grant are as follows:-
m
Social Services (Theme 1,2,4) 0.500
Education attainment (Theme 5,9) 0.300
Community Safety Partnership (Theme 6) 0.050
Highways investment (Theme 3) 0.350
Carbon reduction initiatives (Theme 7) 0.200
Revenue contribution to capital (Theme 3,8) 0.482
6. CAPITAL PROGRAMME 1.4.2012 to 31.3.2015
6.1 The proposed Capital Programme for the period 2012/2015 is detailed in Appendix 3 of thisreport, and is summarised below:-
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
7/18
Appendix
Table 5 - Summary Capital Programme Funding 2011/14
2012/13000
2013/14000
2014/15000
Capital Programme Proposals 16,700 12,055 9,135
Funding Required 16,700 12,055 9,135WG Funding Available 8,944 7,947 7,947
Capital Funding Gap (7,756) (4,108) (1,188)
Funded By:Surplus (Deficit) c/fwd 3,787 1,187Revenue Contributions Capital 3,401 1,402 0RCCO (one-off FSM increase in RSG)plus RCCO from RSG
500106
0106
00
Council Tax Surplus 10/11 1,000 0 0Treasury Management Surplus 11/12 300 - -Insurance Fund Surplus 11/12 500 - -Job Evaluation Surplus 11/12 350 - -
Icelandic Impairment Release 400Misc Capital Receipts/Release LAGBI (recd) 986 - -General Fund Virement 21st Century 4,000 - -
TOTAL ADDITIONAL FUNDING 11,543 5,295 1,187
Surplus (Deficit c/f) 3,787 1,187 (1)
7. GENERAL FUND BALANCES
7.1 The General Fund balances projected to 31 March 2012 are 11.050m and are detailed inTable 6 below.
7.2 It is proposed to allocate the following funding from the General Fund in 2011/12 and 2012/13.
(i) 1m for Capital Programme investment 2012/13(ii) 900k for LGPS 2011/12 (see paragraphs below) 2011/12
7.3 The Governments intended changes to the LGPS are not as yet concluded, therefore thepicture is still very much uncertain, although there is an acknowledgement that changes willneed to be negotiated to ensure the Fund is affordable and sustainable.
7.4 In December 2011 Torfaen Pensions Fund Administrators who manage the CCBC LGPSFunds, have advised that the Greater Gwent Areas Fund is heading for an under recovery of
the pension deficit. All the Authorities in the Fund have been notified of their share of thisdeficit, which for Caerphilly CBC is currently estimated at 900k for 2011/12. There is nolegal obligation to pay over this amount to the Torfaen Pensions Fund, but as it is a knownliability, it would be prudent to fund this shortfall.
7.5 Moving forward a number of the proposed changes to the LGPS could avoid the need toprovide growth in the MTFP for the Employers Superannuation payments in the short andmedium term.
7.6 To conclude, it is proposed that until the negotiations are finalised and agreed, no growth isprovided in the MTFP, albeit that it would be prudent if the pay award is lower than theanticipated 1% to increase the Employers Superannuation percentage for 2012/13 on a
voluntary basis. The situation will be reviewed as further updates are made available from theTorfaen Pension Fund Administrators. Members will be advised via the Scrutiny process. It isrecommended that Council agree to this approach.
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
8/18
Appendix
Table 6 Estimated Movement on General Fund Balances as at 31 March 2011
000 000Closing Balance 31.3.2011 16,620
2011/12 Commitments Carriageway/Footway
Resurfacing
(2,000)
Events (70) Bedwas RFC (200) 21st Century Schools (4,000)
(6,270) 10,350
In Year Increases/(Reductions) Estimated Service
Contributions0,600
Estimated Council TaxSurplus 2011/12
1,000
LGPS Payment (900)11,050
Proposed Allocation 12/13 Capital Programme (1,000)
10,050
8. COUNCIL TAX IMPLICATIONS 12/13
8.1 Given that:-
(i) The whole Authority budgetary position remains balanced;(ii) Service efficiencies previously proposed have been implemented;(iii) Savings for 2012/13 have been agreed.
It is proposed that the Council tax level for 2012/13 be frozen at 2010/11 prices re: CouncilTax Band D 897.84.
9. EQUALITY IMPACT ASSESSMENT
9.1 The proposals will serve to protect the most vulnerable through the protections afforded to
Education and the additional growth for Social Care and will therefore not disproportionatelyimpact on protected groups for the purpose of Equalities legislation.
9.2 The Training and Apprenticeship initiative will continue at the same level as 11/12 and istargeted at increasing the employment opportunities of young people, who are currently underrepresented in the Councils workforce.
10. PERSONNEL IMPLICATIONS
10.1 A Workforce Strategy was approved by Cabinet on 30 March 2010 designed to reduce impacton staff and avoid, where possible, compulsory redundancies. Additionally, a number of key
policy changes have been implemented through the year to ensure we have robust processesto redeploy and retrain staff where necessary. This strategy continues to prove successful.
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
9/18
Appendix
10.2 The reinvestment of savings to the Capital Programme also provides opportunities foremployment in the County Borough, which would otherwise have been lost.
10.3 The current programme of investment in the Councils Apprenticeship Programme is protectedfor a further year i.e. 2012/13 and in so doing, can support the already successful initiative inattracting young people into employment.
10.4 The successful conclusion of negotiations with Trade Unions around these arrangements andthe continued prudent financial management of the Council will allow services to meet thedemanding savings targets required through continued managed downsizing, restructuringsand use of Voluntary Early Retirements. It is anticipated this budget represents a prudentapproach to managing reductions in staff without the need to resort to mass or high volumecompulsory redundancies.
11. CONSULTATIONS
11.1 A draft was circulated to all Members of the Council and the recognised Trade Unions on 19
January 2012.
11.2 The Deputy Chief Executive and the Head of Corporate Finance met with each of theCouncils Political Groupings.
11.3 The principles of the Medium Term Financial Plan, which was previously considered by theViewpoint Panel have been further considered.
11.4 Trade Unions all consultation responses received have been included in the report.Caerphilly UNISON and GMB have commented that the Budget proposals appear to be aprudent approach in light of the current climate.
12. RECOMMENDATIONS
12.1 Council are asked to consider the report and its Appendices and approve the followingrecommendations:-
12.1.1 The Revenue Budget proposals for 2012/13 of 315.240m as set out in this yearsreport be approved
12.1.2 The Council Tax level for the financial year 2012/13 be frozen at 2010/11 prices i.e:Council Tax Band D 897.84, be approved (see Appendix 1)
12.1.3 The indicative proposals contained in the Medium Term Financial Planningassumptions be approved as the basis for delivering a balanced budget over thecoming 3 financial years (i.e. 2012/13 to 2014/15)
12.1.4 The Capital Programme for the period 1 April 2012 to 31 March 2015 as set out inAppendix 4 be approved
12.1.5 The use of general fund balances as detailed in Section 7 (Table 6) be approved.
13. REASONS FOR THE RECOMMENDATIONS
13.1 The Council is required annually to approve proposals to set a balanced budget, agree aCouncil Tax rate and agree a Medium Term Financial Strategy.
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
10/18
Appendix
13.2 Council is required to put in place a sound and prudent financial framework to support servicedelivery.
14. STATUTORY POWER
14.1 The Local Government Finance Act 1998. The Local Government Act 2003.
Author: Nigel Barnett, Deputy Chief ExecutiveConsultees: Anthony OSullivan, Chief Executive
Corporate Management TeamCouncillor A Pritchard, Leader of the CouncilCouncillor C Mann, Deputy Leader and Cabinet Member for Corporate Finance,Procurement and SustainabilityNicole Scammell Head of Corporate Finance and S151 Officer
Background Papers:
Provisional Local Government Settlement (18 October 2011)Final Local Government Settlement (7 December 2011)
Appendices:
Appendix 1 Net Revenue Budget 2012/13Appendix 2 Medium Term Financial Plan ProposalsAppendix 2a Schools Medium Term Financial PlanAppendix 2b Social Services Medium Term Financial PlanAppendix 3 Capital ProgrammeAppendix 4 Outcome Agreement
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
11/18
Appendix
APPENDIX 1
NET REVENUE BUDGET 2012/13
' 000 ' 000
Base Budget 2011-12 312,666Adjustment for PFI Schemes (202)
Adjustment for Outcome Improvement Grant 9
Revised Base Budget 2011-12 312,473
Transfers Out 2012-13
Mapping Services (90)
(90)Transfers In 2012-13
Sun Bed Regulations 2
Mental Health Act & Deprivation of Liberty Safeguards 4446
New Responsibilities 0
Whole Authority Cost Pressures
Pay (Excludes Schools and Social Services) 1 %;1 %, 2 %) 770
Supported Borrowing (Capital Financing) 500
Energy Tax 400
Revenue Contribution to Capital (free school meals data change) 500
2,170
Inescapable Service Pressures and Service Commitments
Revenue Contribution To Capital 106
Libraries/Customer First Development(Bargoed/Risca/Caerphilly/Newbridge) 500
Landfill Tax -80
Meeting the Schools Pledge (See Appendix 2) 1,570
Meeting the Social Services Pledge (See Appendix 3 ) 1,600
Additional Social Services Pressures 200
3,896
Service/Efficiency already achieved/approved whichcontribute to 2012/13
Savings Carried Forward from 2011/12 (3,355)
Education and Leisure
Learning, Education and Inclusion
Additional Support (30)
Behavioural Support (60)
Vacancy Management (80)
Efficiency Savings Back Office (46)
Reconfiguring of Statements Provision (28)
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
12/18
Appendix
000 000
Community and Leisure
Vacancy Management (105)
Pension Strain (21)
Reduction in Operational Expenses (42)
Reduction in Training Support Grants (36)
(448)
Environment
Street Lighting (50)
Highways Maintenance (50)
Car Park Maintenance (20)
Winter Maintenance (40)
Llancaich Fawr Running Costs (130)
Vacancy Management (121)
(411)
Corporate Services/Corporate EfficienciesVacancy Management (435)
Pension Strain (80)
Job Evaluation (Collective Agreement) (1,280)
Council Tax - Net increase in Band D equivalent properties 0
Demographic Savings (239)
Fire Service Levy (133)
Essential User plus 55p mile (excluding schools and SocialServices) (275)
(2,442)
Deprivation Grant 1,666.00
Improvement Agreement Grant / Outcome Agreement Grant 482.00
Revenue : Balance of Funding 1,253.00
3,401
Total in year movement 2,767
Proposed Expenditure 315,240
Funded by -
WG Support (253,636)
Council tax ( 0.00%) (52,212)
Use of Outcome Agreement Grant (1,882)
Private Finance Initiative Grant (7,510)
Total Funding (315,240)
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
13/18
Appendix
APPENDIX 2
MEDIUM TERM FINANCIAL PLAN PROPOSALS 1.4.12 31.3.15
2012/13
m
2013/14
m
2014/15
mFunding RSG Increase 2.656 3.483 1.590 Council Tax 0 1.300 1.300
Total Funding 2.656 4.783 2.890
Whole Authority Cost Pressures Pay (excludes Schools and
Social Services) 1%; 1%, 2%)0.770 0.770 1.540
RCCO FSM one-off 0.500 - -
Teachers Pay (See SchoolsPledge) 0.000 0.000 0.000
Non Pay 1% 0.000 0.500 0.500 Pension Deficit WHQS - 1.000 - Corporate Impact WHQS - 1.500 - Energy - 0.500 0.500 Capital Financing 0.500 0.500 0.500 Energy Tax 0.400 - -
Totals 2.170 4.770 3.040
Inescapable Service Pressures Revenue Contribution to Capital 0.106 - -
Libraries/Customer First 0.500 - - Landfill Tax (0.080) 0.305 0.290 Schools Pledge (see Appendix
2)1.570 2.143 1.363
Social Services Pledge (SeeAppendix 3)Re-profile Pledge
1.100
0.500
1.500
(0.250)
0.930
(0.250) Further additional growth Social
Services 0.200
Total Inescapable 3.896 3.698 2.333
Total Shortfall (3.410) (3.685) (2.483)
Cumulative Shortfall (3.410) (7.095) (9.578)
NOTE:
In addressing the requirement to achieve 9.578 m of cash savings proposals within thisreport, this will provide for savings to be achieved if 3.355 m is carried forward from 2011/12and additional savings of 3.456 m in 2012/13; 1.686 in 2013/14 and 1.081 m in 2014/15.
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
14/18
Appendix
APPENDIX 2a
SCHOOLS MEDIUM TERM FINANCIAL PLAN 2012/13 2014/15
2012/13 2013/14 2014/15000 000 000
Cash Pledge growth 1.570 2.143 1.363
Service Pressures Pay Award Teachers 1%, 1%, 2% 667 674 1.360 Pay Award APTC 1%, 1%, 2% 117 118 239 Non Pay 1% 241 215 220 Estimated FSM (Free School
Meals) numbers growth200 50 50
Estimated floor area growth/lumpsum
0 173 110
Real terms cash growth (savings) 345 913 (616)
1.570 2.143 1.363
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
15/18
Appendix
APPENDIX 2b
SOCIAL SERVICES MEDIUM TERM FINANCIAL PLAN 2012/13 2014/15
2012/13 2013/14 2014/15000 000 000
Cash Pledge growth 1,100 1,500 930
Reprofile of Cash Pledge 500 (250) (250)Further Additional Growth 200 0 0
Funding Available 1,800 1,250 680
Service Pressures Pay 1%, 1%, 2% 365 369 745 Non Pay 332 336 339 WG Minimum Fostering Allowances 93 0 0 Adult Services (increased demand) 1,694 689 500 North Resource Centre 0 180 0
Total Service Pressures 2,484 1,574 1,584
Net Surplus (Deficit) (684) (324) (904)
Savings Essential User + 55p 300 0 0 Office Accommodation 0 0 300 Service Reconfiguration 110 110 0 Community Living 65 0 0 Review of Charges 109 109 0 Adult Placement Scheme 100 100 0 Caerphilly/Blaenau Gwent
Collaboration0 0 300
Other 0 5 304684 324 904
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
16/18
Appendix
APPENDIX 3
CAPITAL PROGRAMME
Indicative
SCHEME 2012/13 2013/14 2014/15
000 000 000
Education and Leisure
Demographic/legislative additional purchase ofdemountable classrooms
200 200 200
School Security new CCTV installations, new fencing andalarms
100 100 100
Demountable Classrooms 150 - -
Asset Management Enhancement and/or additional 600 750 1,000
Health & Safety Enhancement and/or additional 300 300 375
Contribution 21st Century Schools 4000 - -
Refurbishment of school kitchens Enhancement and/oradditional
600 600 500
Leisure & Libraries potential match funding - 250 -
School Boiler replacement programme. Improved energyefficiency
450 500 250
Fochriw Youth Centre Match Funding - 126 -
Relocate Community Education to Risca Palace newaccommodation
126 - -
Ystrad Mynach New Sports Facility 1,400 1,400 -
7,926 4,226 2,425
Social Services
Service Re-provision Heol Aneurin 260 - -
Condition Survey Works (To be Prioritised) 490 600 500
750 600 500
Corporate Services
New and/or enhanced schemes to Corporate ITinfrastructure
250 250 250
Asset Management (including DDA)
Enhancement and/or additional 1,430 1,114 750
Public ServicesLand acquisition and infrastructure developmentRhymney Cemetery 40 260 50
Land acquisition and infrastructure Bedwellty Cemetery 95 120 90
Contribution to Bargoed Bowls Pavilion new build 29 - -
Caerphilly Basin infrastructure works 25 - -
New Cemetery Caerphilly - 360 250
Provision of toilet block Ystrad Mynach Park (Assist withGreen Flag Award)
45 - -
MUGA - Machen 87 - -321 740 390
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
17/18
Appendix
Indicative
2012/13 2013/14 2014/15
000 000 000
Highways
Bridge strengthening/refurbishment 350 350 250
Fothergills Road, Phillipstown Landslip Remediation 300 - -
Additional car parking spaces Oakdale and BedwasTrethomas
64 - -
Land drainage 70 70 70
Bus Station replacement and refurbishment - Caerphilly 100 - -
Forward Programme Advanced Design 50 50 50
Highways Improvement 250 500 250
Puffin Crossings Ystrad Mynach 60 - -
Culverts/Retaining Walls major works 550 300 300
1,794 1,270 920
Countryside/Tourism
Environment Schemes Match Funding 230 285 250
Improvements to events field - Caerphilly 60 - -
Match Funding new signage - Tourism 33 - -
323 285 250
Urban Renewal
Match Funding Bargoed and Newbridge 186 - -
Bargoed Plateau Development 244 20 -
Bargoed Pocket Park Match Funding 46 - -
Match Funding EU Structural - - 100
Town Centre Action Plan 130 200 200
Commercial Improvement Grants 50 100 100
Community Cohesion Projects (villages) 50 50 50
706 370 450
Economic Development
Match Funding (Cwmcarn; Rhymney; Oakdale schemes) 100 100 100
Voluntary Sector Budget
Match Funding 200 200 200
Private Sector Housing
Mandatory Disabled facilities grant 1,300 1,300 1,300
Home improvement grants 350 400 400
Support for renewal area activities 400 400 400
Minor works grant vulnerable persons 800 800 800
Home improvement grants/empty homes/loans 50 - -
2,900 2,900 2,900
TOTAL 16,700 12,055 9,135
-
8/3/2019 Caerphilly County Borough Council's BUDGET PROPOSALS 2012/2013
18/18
Appendix
APPENDIX 4
Theme 1
Improve availability, accessibility and quality of existing mental health services and providenew ones to tackle inequities in mental health provision
Theme 2
Use a preventative approach to Protection of Vulnerable Adults working with Statutory,Independent and Voluntary partners to improve the quality of the response to abuse referralsby co-ordinating the POVA process
Theme 3
Help sustain and where possible, increase employment opportunities, by working inpartnership with programmes that provide adults and young people with skills, education andsupport networks to help them to obtain and maintain employment
Theme 4
Children and young people who have emerging needs have their needs met as early aspossible and in the most appropriate and holistic way
Theme 5
Strengthen our focus on early interventions, basic skills, raising aspirations for higher andfurther education and re-engaging with those groups and individuals who have becomedisaffected with the educational system.
Theme 6
Work with Community Safety Partnership to develop the anti-social behaviour Four StrikeProcess and better services for witnesses of anti-social behaviour so the community is lessaffected
Theme 7
Implement several initiatives, which impacts on our communities, with better future energyand water consumption levels, carbon dioxide and recycling outputs. This will also deliverenergy and efficiency savings.
Theme 8
In partnership with the Countryside Council for Wales, Communities First and other membersof the Living Environment Partnership, we run a 3 year programme using the Come Outside!approach to engage residents in healthy physical activity in their local natural green spaces
Theme 9
A culture where our children and young people undertake sport and physical activity as aregular part of daily life and a thriving infrastructure to support sport and active recreationexists across our county borough.
Theme 10
A set of 4 projects demonstrating collaborative working resulting in benefits that would begreater than procuring alone (where business case dictates, this is the right approach).