  • 8/10/2019 Bondstrand Bonder Training

    1/60

    Fiberglass Pipe

    Bondstrand Bonder Training

  • 8/10/2019 Bondstrand Bonder Training

    2/60

    Bondstrand Bonder Training for PTSC M&C - 2009 2

    Contents

    Part-1: General

    Part-2: AMERONs Bondstrand Products

    Part-3: HSE & Product handling

    Part-4: Fabrication & Installation

    Part-5: Hydro-testing

  • 8/10/2019 Bondstrand Bonder Training

    3/60

    Bondstrand Bonder Training for PTSC M&C - 2009 3

    Part-1 : General

    Training Purpose

    To provide knowledge of AMERONs

    Bondstrand Products To qualify bonder for bonding certification

    required for fabrication and installation of

    AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    4/60

    Bondstrand Bonder Training for PTSC M&C - 2009 4

    Part-1 : General

    Understanding AMERONs BondstrandProducts

    Understanding product data and QC form

    Pass hydrotest on practice

    Achievements : Trainee must complete

    below points to get certi f icate

  • 8/10/2019 Bondstrand Bonder Training

    5/60

    Bondstrand Bonder Training for PTSC M&C - 2009 5

    Part-1 : General

    Issued by AMERON to trainee who passhydrotest on spool practice

    2-year validity

    Bonding certif icate

  • 8/10/2019 Bondstrand Bonder Training

    6/60

    Bondstrand Bonder Training for PTSC M&C - 2009 6

    RTRP - Reinforced Thermosetting Resin Pipe

    FRP - Fiberglass Reinforced Pipe

    GRE - Glass Reinforced Epoxy

    GRV - Glass Reinforced Vinylester

    GRP - Glass Reinforced Polyester (in some

    specifications it means Glass Reinforced Pipe)

    Part-2 : AMERONs Bondstrand Products

    Abbreviations

  • 8/10/2019 Bondstrand Bonder Training

    7/60

    Bondstrand Bonder Training for PTSC M&C - 2009 7

    QLF - Quick Lock Female

    QLM - Quick Lock Male

    TF - Taper Female

    TM - Taper Male

    B&W - Butt & Wrap

    Spigot - Bondstrand Male Pipe End

    Bell - Bondstrand Female Pipe End

    Part-2 : AMERONs Bondstrand Products

    Abbreviations

  • 8/10/2019 Bondstrand Bonder Training

    8/60

    Bondstrand Bonder Training for PTSC M&C - 2009 8

    Part-2 : AMERONs Bondstrand Products

    Epoxy (GRE)

    Vinylester (GRV)

    F ilament-wound pipe & fittings withadvanced resins

    Bondstrand Product L ines

    Bondstrand 2000/2000M

    Bondstrand 7000/7000M Bondstrand 2400/3400 series

  • 8/10/2019 Bondstrand Bonder Training

    9/60

    Bondstrand Bonder Training for PTSC M&C - 2009 9

    Bondstrand 2000

    A lined epoxy system

    for applications where

    corrosion resistance

    and light weight are of

    paramount

    importance.

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    10/60

    Bondstrand Bonder Training for PTSC M&C - 2009 10

    A lined epoxy systemfor applications where

    corrosion resistanceandexternal pressureare of paramountimportance.

    Part-2 : AMERONs Bondstrand Products

    Bondstrand 2000M

  • 8/10/2019 Bondstrand Bonder Training

    11/60

    Bondstrand Bonder Training for PTSC M&C - 2009 11

    Bondstrand 7000/7000MAn epoxy system with

    conductiveelements

    incorporated in the wall

    of the pipe to prevent

    accumulation of static

    electricity produced by

    the flow of liquids inside,and external effects

    outside the pipe.

    Design equal to B onds trand

    2000/2000M

    Unique patented pipe saddle drains

    off static charge build-up

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    12/60

    Bondstrand Bonder Training for PTSC M&C - 2009 12

    Bondstrand Series 2400/3400An epoxy system where corrosion

    resistance and light weight are of

    paramount importance.

    Pressure class determined by

    internal pressurerequirements.

    No external pressure requirements.

    Internal pressure class : 10, 12, 14,16, 20 and 25 bar.

    * Also con duct ive

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    13/60

    Bondstrand Bonder Training for PTSC M&C - 2009 13

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    14/60

    Bondstrand Bonder Training for PTSC M&C - 2009 14

    Joining SystemQuick-Lock Joint

    An adhesive-bonded joint with

    straight spigot and tapered bell.The integral pipe stop in theQuick-Lock bell ensuresaccurate laying lengths in closetolerance piping.

    Sizes : 25-400 mm (1-16)

    Sizes : 450-600 mm (18-24)

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    15/60

    Bondstrand Bonder Training for PTSC M&C - 2009 15

    Taper/Taper Joint

    An adhesive-bonded joint with

    matching tapered male andfemale ends offering superiorstrength by controlled adhesivethickness. Available in sizes :50-1000 mm (2- 40).

    Internal pressure class : 10, 12,14, 16, 20, 25 bar.

    Part-2 : AMERONs Bondstrand Products

    Joining System

  • 8/10/2019 Bondstrand Bonder Training

    16/60

    Bondstrand Bonder Training for PTSC M&C - 2009 16

    Flanged Joint

    A mechanical joint. Available

    in sizes: 25-1000 mm (1-40).

    Various drilling patternsavailable (e.g. CL150, JIS10K, DIN 10, etc.) -Compatible to Steel flanges.

    Part-2 : AMERONs Bondstrand Products

    Joining System

  • 8/10/2019 Bondstrand Bonder Training

    17/60

    Bondstrand Bonder Training for PTSC M&C - 2009 17

    Joining SystemButt & Wrap Joint

    A lamination joint. Available

    in sizes: 25-1000 mm (1-40).

    Time costly.

    Versatile. Most use on repair.

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    18/60

    Bondstrand Bonder Training for PTSC M&C - 2009 18

    Adhesive SystemRP-34C

    A two-part amine cured

    epoxy resin systemNon-conductive

    Use on Quick-Lock joint

    Available in 3 oz. kit and 6

    oz. kit

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    19/60

    Bondstrand Bonder Training for PTSC M&C - 2009 19

    Adhesive SystemRP-60B

    A two-part thermosetting,

    electrically conductive epoxyresin system

    Conductive

    Use on Quick-Lock joint and

    Taper/Taper jointAvailable in 3 oz. kit and 6

    oz. kit

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    20/60

    Bondstrand Bonder Training for PTSC M&C - 2009 20

    Adhesive SystemRP-48

    A two-part amine cured

    epoxy resin systemNon-conductive

    Use on Taper/Taper joint

    Available in 3 oz. kit and 6

    oz. kit

    Part-2 : AMERONs Bondstrand Products

  • 8/10/2019 Bondstrand Bonder Training

    21/60

    Bondstrand Bonder Training for PTSC M&C - 2009 21

    Special Tools Pipe Shaver & Power Drive

    Heating Blanket

    Other Accessories Band Clamp

    Lever Hoist

    Bore Polisher (Flapper Wheel)

    Common Pipe Tools

    Part-2 : AMERONs Bondstrand Products

    Tools & Equipment

  • 8/10/2019 Bondstrand Bonder Training

    22/60

    Bondstrand Bonder Training for PTSC M&C - 2009 22

    !!! Pipe Shaver: Machine of pipe end to obtain

    appropriate spigot end for bonding, shaver shall beselected based on type of joint, pipe diameter, withconsideration of total project scope.

    B-1F Shaver: , , 1, 1 , 2, 3, 4, 5 & 6

    Cutting Insert

    For detail guide, See FP376F, Ameron B-1F Pipe End Preparation Tool

    To individual size only;

    Straight Spigot (For Quick-Lock Joint) only.

    Driven by common electricaltools or air tools, such as hand

    drill.

    Special ToolsPipe Shaver & Power Drive

  • 8/10/2019 Bondstrand Bonder Training

    23/60

    Bondstrand Bonder Training for PTSC M&C - 2009 23

    M-74 Shaver

    For detail guide, See FP696A, M-74 Pipe Shaver

    For 2 16 pipes

    Use with arbor set

    Straight Spigot (For

    Quick-Lock Joint) only. Driven by hand or

    electrical tools (RIDGID-700).

    Special ToolsPipe Shaver & Power Drive

  • 8/10/2019 Bondstrand Bonder Training

    24/60

    Bondstrand Bonder Training for PTSC M&C - 2009 24

    Maintenance and Store

    Shall be kept in original tool box after use;

    Keep it in dry location, away from rain and

    moisture; Do not use oil and/or grease as dust will

    accumulate on oil and grease;

    Remove of dust/dirt using brush.

    Special ToolsPipe Shaver & Power Drive

  • 8/10/2019 Bondstrand Bonder Training

    25/60

    Bondstrand Bonder Training for PTSC M&C - 2009 25

    !!! Heating Blanket: For accelerating joint curing, as

    well as preheat of jointing surface

    Available in 115V and 230V, to be specified;

    Size depends on pipe size;

    Equipped with thermostat;

    For 1 to 28 Pipe For 30 to 40 Pipe

    Special ToolsHeating Blanket

  • 8/10/2019 Bondstrand Bonder Training

    26/60

    Bondstrand Bonder Training for PTSC M&C - 2009 26

    Description of Heating Blanket

    Special ToolsHeating Blanket

  • 8/10/2019 Bondstrand Bonder Training

    27/60

    Bondstrand Bonder Training for PTSC M&C - 2009 27

    Using Heating Blanket Wrap the pipe using the

    end with thermostat;

    Tie down accessoryshall be used;

    Do NOTpull the cable;

    Special ToolsHeating Blanket

  • 8/10/2019 Bondstrand Bonder Training

    28/60

    Bondstrand Bonder Training for PTSC M&C - 2009 28

    Packing, Storage and Transporting Always roll up the heating blanket when not in used;

    Do NOTpack and transport heating blanket in foldedform;

    Any heavy object fall on it may damage the heatingblanket;

    Special ToolsHeating Blanket

  • 8/10/2019 Bondstrand Bonder Training

    29/60

    Bondstrand Bonder Training for PTSC M&C - 2009 29

    Band Clamp with D-Rings Shall be used when making joints, Quick-Lock,

    Taper, Mechanical O-Ring,

    Available in 2 width x 6 length, and

    Available in 2 width x 13 length, and

    Available in 3 width x 13 length

    Other Accessories

  • 8/10/2019 Bondstrand Bonder Training

    30/60

    Bondstrand Bonder Training for PTSC M&C - 2009 30

    Lever Hoist Shall be used when making joints,

    Quick-Lock, Taper, Mechanical O-Ring,

    Available in Ton and 1 Ton,

    Alternatively, ratchet puller (chainblock) can be used

    Bore Polisher (Flapper Wheel) Sanding bonding surface

    Grid 40~60 Driven by electrical drill or air tool

    Other Accessories

  • 8/10/2019 Bondstrand Bonder Training

    31/60

    Bondstrand Bonder Training for PTSC M&C - 2009 31

    Hacksaw or abrasive wheel;

    Paint marker; Pipe wraparound;

    Baby grinder;

    Electric or Air drill;

    Level Gauge;

    Paint Brush;

    Nylon/Rubber Mallet;

    Cotton Roller;

    Adjustable Pipe Stands; Sanding Disc;

    Screw Driver;

    Scissors;

    Air Release Roller;

    There are many other common piping tools might be

    required for fiberglass piping fabrication and installation

    work, such as:

    Common Piping Tools

  • 8/10/2019 Bondstrand Bonder Training

    32/60

    Bondstrand Bonder Training for PTSC M&C - 2009 32

    Part-3 : HSE & Product handling

    !!! To prevent injuries & occupational diseases,

    property damages through needless industrial

    accidents and inefficient environment via waste

    management.

    Personal Protection Equipment (PPE)

    Chemical and Dust Hazards

  • 8/10/2019 Bondstrand Bonder Training

    33/60

    Bondstrand Bonder Training for PTSC M&C - 2009 33

    Personal Protection Equipment (PPE)

    !!! PPE is any device or appliance designed to be wornby an individual when exposed to one or more healthand safety hazards.

    Overall

    Safety Helmet Safety Boots

    Safety Glasses

    Gloves

    Dust Mask Etc

  • 8/10/2019 Bondstrand Bonder Training

    34/60

    Bondstrand Bonder Training for PTSC M&C - 2009 34

    !!! Resin, curing agent, catalyst, adhesive and other

    chemical products could cause irritation, some couldbe harmful to eyes.

    Quick access to water in case of chemical contact !!

    No eating, drinking and smoking during handling of

    above products; Maintain personal hygiene at all time;

    Safe glasses during handling above products;

    Dust mask to prevent inhalation of glass-fiber dust;

    Long sleeve shirts with long pants, or overall toprevent skin irritation due to fiber dust;

    Chemical and Dust Hazards

  • 8/10/2019 Bondstrand Bonder Training

    35/60

    Bondstrand Bonder Training for PTSC M&C - 2009 35

    Maintain personal hygiene at all time;

    Do not rub or scratch irritated area if occurred;

    Shower in lukewarm water with soap and awashcloth at days end to remove loose fiber;

    Wash work clothes separately;

    Good ventilation in workplace to keep dustconcentration below the MAC value (10mg/m3);

    Rinsing workplace with water or sweeping withbrushes or brooms;

    Refer to relevant MSDS and product literature forunfamiliar products.

    Chemical and Dust Hazards

  • 8/10/2019 Bondstrand Bonder Training

    36/60

    Bondstrand Bonder Training for PTSC M&C - 2009 36

    !!! GRP piping components can be susceptible tomechanical damage from impact, sharp edges or

    scratching. Special consideration should be given to

    protecting components and to ensuring that all

    personnel involved are given training in the relevantprocedures. ISO14692-4:2002

    Goods Receiving Inspection

    Handling and Transportation Storage

    Receiving and Handling

  • 8/10/2019 Bondstrand Bonder Training

    37/60

    Bondstrand Bonder Training for PTSC M&C - 2009 37

    Verify goods receiving conform to shipping andpacking document and compliance to purchase order.

    Packing condition.

    Spools and components condition.

    Adhesive Kits condition including shelf life, visibledamage and/or leaking, completeness of kit packing.

    Reporting of any deviation and/or issue.

    FP167D, Shipping, Handling, Storage and Inspection

    of Bondstrand Fiberglass Pipe.

    Good Receiving Inspection

  • 8/10/2019 Bondstrand Bonder Training

    38/60

    Bondstrand Bonder Training for PTSC M&C - 2009 38

    Handling and Transportation Proper support and protection with protection pad.

    Securely fastened.

    Forklifts should have at least a 6-foot carriage,spacer of at least 2-inch thickness are located.

    Fittings shall be loaded onto pallets, crates orbaskets with sufficient protection.

    3m or less pipe and spool could be lifted by single4 wide canvas or suitable plastic.

    Pipe and spool greater than 3m (in length) shall belifted in using two or more canvas or suitableplastic.

    Handling and Transportation

  • 8/10/2019 Bondstrand Bonder Training

    39/60

    Bondstrand Bonder Training for PTSC M&C - 2009 39

    Prohibitions Being thrown or dropped from any height.

    Using chains, wire ropes or clamps for lifting

    Handling and Transportation

    S

  • 8/10/2019 Bondstrand Bonder Training

    40/60

    Bondstrand Bonder Training for PTSC M&C - 2009 40

    !!! Carrying out inspection for good storage preparation and

    carrying out periodical inspection.

    Fiberglass Pipe Well supported (side support and spacer support), not more

    than 10-ft Interval, 6-ft from each end, the support shouldhave 4-in wide bearing surface.

    Side supports; not exceed 5-ft height; proper tie down. Protective end cover must be in place.

    Storage

    S

  • 8/10/2019 Bondstrand Bonder Training

    41/60

    Bondstrand Bonder Training for PTSC M&C - 2009 41

    Fiberglass Fitting and Accessories

    Shall be kept in shipping box/pallet. Protective end cover must be in placed.

    Accessories such as Nylon Key and O-Ring, shall be keptin shed store.

    Fiberglass Fabricated Spools Shall be kept in shipping pallet or skid.

    End cover / protection shall not be removed untilinstallation.

    Adhesive Kit, Resin and Curing Agent Shall be kept in original packing.

    Shall be kept in specified control condition.

    Shall be used before expiry date.

    Storage

    P 4 F b i i d I ll i

  • 8/10/2019 Bondstrand Bonder Training

    42/60

    Bondstrand Bonder Training for PTSC M&C - 2009 42

    Drawings

    Product data & Pipe length calculation

    QC form : Log sheet

    Fabrication and Installation Tolerances

    Hook-up to Equipment / Other Material

    Part-4 : Fabrication and Installation

    D i

  • 8/10/2019 Bondstrand Bonder Training

    43/60

    Bondstrand Bonder Training for PTSC M&C - 2009 43

    Spool Drawing Contain detail dimensions, fabrication materials, and

    erection materials.

    Isometric Drawing Contain all details of design (Pressure, fluid, system,

    temperature,..), fabrication and erection (Materials),installation (Coordinates, connections) and testing.

    Layout Drawing Background, surrounding, piping routing, supporting,

    interface, equipment, etc.

    Piping and Instrument Diagram Principle such as size, flow direction, design

    information, materials specification.

    Drawings

    S l D i S l 1

  • 8/10/2019 Bondstrand Bonder Training

    44/60

    Bondstrand Bonder Training for PTSC M&C - 2009 44

    Sample DrawingSpool 1

    S l D i S l 2

  • 8/10/2019 Bondstrand Bonder Training

    45/60

    Bondstrand Bonder Training for PTSC M&C - 2009 45

    Sample DrawingSpool 2

    Sample Drawing Spool 3

  • 8/10/2019 Bondstrand Bonder Training

    46/60

    Bondstrand Bonder Training for PTSC M&C - 2009 46

    Sample DrawingSpool 3

    Sample Drawing ISO

  • 8/10/2019 Bondstrand Bonder Training

    47/60

    Bondstrand Bonder Training for PTSC M&C - 2009 47

    Sample DrawingISO

    Sample Drawing Layout

  • 8/10/2019 Bondstrand Bonder Training

    48/60

    Bondstrand Bonder Training for PTSC M&C - 2009 48

    Sample DrawingLayout

    Product data & Pipe length Calculation

  • 8/10/2019 Bondstrand Bonder Training

    49/60

    Bondstrand Bonder Training for PTSC M&C - 2009 49

    Product data Assembling dimension of fittings

    Pipe length calculation

    To produce pipe cutting table To calculate pipe length for spool adjustment

    To verify installation

    Product data & Pipe length Calculation

    Exercise : calculate pipe length.

    QC Form : Log sheet

  • 8/10/2019 Bondstrand Bonder Training

    50/60

    Bondstrand Bonder Training for PTSC M&C - 2009 50

    To record bonding history for fabrication and siteinstallation

    Part of QC documentation

    QC Form : Log sheet

    Fabrication and Installation Tolerances

  • 8/10/2019 Bondstrand Bonder Training

    51/60

    Bondstrand Bonder Training for PTSC M&C - 2009 51

    Good tolerances control could ensure success in installation;reduce the possibility of leak at field joint; reduce the

    possibility of damage due to force on mismatched pipes;

    reduce/eliminate modification work,

    Recommended Fabrication Tolerances

    Installation Dimensional Tolerances Refer to tolerance of different type of joints such as

    flange joint, mechanical o-ring joint.

    Project specification

    Fabrication and Installation Tolerances

    Recommended Fabrication Tolerances

  • 8/10/2019 Bondstrand Bonder Training

    52/60

    Bondstrand Bonder Training for PTSC M&C - 2009 52

    1. Face/center to face/centerdimension, or location of

    attachment

    2. Lateral translation of branch or

    connection

    3. Rotation of flange

    4. End preparation

    5. Alignment of flange face

    6. Angular deflection

    7. Reference: ISO14692-4:2002

    Recommended Fabrication Tolerances

    Recommended Fabrication Tolerances

  • 8/10/2019 Bondstrand Bonder Training

    53/60

    Bondstrand Bonder Training for PTSC M&C - 2009 53

    DN(Inch)

    Tolerances / Dimension Number

    1 (mm) 2 (mm) 3 (Degree) 4 (mm) 5 (mm) 6 (Degree)

    -8 5 3 0.5 3 1 0.5

    10-12 5 3 0.3 3 1 0.5

    14-16 5 3 0.3 3 1.6 0.5

    18-24 6 5 0.3 3 2.0 0.5

    26-36 6 5 0.2 4 2.4 0.5

    40-48 6 5 0.15 5 2.4 0.5

    Reference: ISO 14692-4:2002 and Ameron PF-01.

    Recommended Fabrication Tolerances

    Hook-up to Equipment / Other Material

  • 8/10/2019 Bondstrand Bonder Training

    54/60

    Bondstrand Bonder Training for PTSC M&C - 2009 54

    To prevent damage to both equipment and fiberglass pipingsystem, attention shall be given when fiberglass piping is

    hooked up to equipment and other piping materials.

    Hook-up to Equipment

    Equipment (Including fire hydrant, ballast eductor, .)shall be independently anchored,

    Allowable alignment to avoid excessive stress,

    Control torque value strictly if equipment connection iscast iron material,

    Dismantle piece is recommended for testing andequipment maintenance.

    Hook up to Equipment / Other Material

    Part-5 : Hydro-testing

  • 8/10/2019 Bondstrand Bonder Training

    55/60

    Bondstrand Bonder Training for PTSC M&C - 2009 55

    Fabricated Spool Testing

    System Hydro-testing

    Part 5 : Hydro testing

    Fabricated Spool Testing

  • 8/10/2019 Bondstrand Bonder Training

    56/60

    Bondstrand Bonder Training for PTSC M&C - 2009 56

    Spool Testing is normally used to verify quality of

    fabrication joints (if applicable).

    Test pressure determination: 1.5 times of design pressure ofthe weakest component on the spool.

    Recommended Test Duration: 10 minutes

    Special end blind/plug required for variety of spool endconfiguration

    Limitation: Some fabricated spools could not be tested dueto end configuration and size : Spool with Taper Male end,

    Spool with QL Female and Taper Female and greater than 16

    .

    Fabricated Spool Testing

    System Hydro-testing

  • 8/10/2019 Bondstrand Bonder Training

    57/60

    Bondstrand Bonder Training for PTSC M&C - 2009 57

    System Hydrotesting is carried out on installed

    piping system to verify fabricated joints, site joints,as well as the integrity of the installed piping system.

    Prior to Hydro-Testing All piping supports must be completed;

    For underground piping, sufficient partial backfill andtemporary block must be in place to prevent excessivemovement;

    High point vents / low point drains in place;

    Removing/isolating components that shall be excluded

    from hydro-testing;

    System Hydro testing

    System Hydro-testing

  • 8/10/2019 Bondstrand Bonder Training

    58/60

    Bondstrand Bonder Training for PTSC M&C - 2009 58

    Test Pressure 1.5 times of design pressure

    1 hour holding minimum, or sufficient time to carry outline check, or project specification whichever is longer

    Testing Equipment

    Quick closing valve and booster pump without suitablecontrol shall not be used, to avoid surge;

    Pressure gauges and instrument must be calibrated;

    Appropriate pressure gauges shall be selected, the testpressure shall be between 30% to 75% of reading range

    If possible, pressure recorder shall be used;

    y y g

    System Hydro-testing

  • 8/10/2019 Bondstrand Bonder Training

    59/60

    Bondstrand Bonder Training for PTSC M&C - 2009 59

    Hydro-Testing

    Pressure build up process: The test pressure shall be raised over a period of

    30minutes of longer.

    Slowly and gradually to allow for equalizing forstrain, and also in stages to allow for inspection.

    Inspection Instrument reading

    Visual inspection of joints, pipes and fittings

    24 hour holding @ 1.1 design pressure (ISO14692:4)

    Acceptance criteria

    No sign of leaking or weepingNo significant pressure lost

    y y g

    System Hydro-testing

  • 8/10/2019 Bondstrand Bonder Training

    60/60

    Bondstrand Bonder Training for PTSC M&C - 2009 60

    Possible causes of pressure change

    Effect of joint expansion and material creep; Effect of temperature (Morning, afternoon, night, under

    sun, and so on), take precaution to prevent over-pressure

    Other Concerns Glycol antifreeze shall be added when test is carry out

    in subzero temperature. Instrument to prevent from buckling in case of sudden

    depressurization

    Safety aspects, such as qualified operator, signs andnotices, operation procedures . Shall be in placed.

    Reference: AME/INS-004Hydro-Testing Procedure for

    Bondstrand GRE / GRV Pipe

    y y g