basics of design of piled foundations-bengt h.fellenius

151
BASICS OF DESIGN OF PILED FOUNDATIONS Bengt H. Fellenius Brisbane November 28, 2008

Upload: raghu-mahadevappa

Post on 04-Sep-2015

230 views

Category:

Documents


3 download

DESCRIPTION

Basics of Design of Piled Foundations-Bengt H.Fellenius

TRANSCRIPT

  • 1BASICS OF DESIGN OF PILED

    FOUNDATIONS

    Bengt H. Fellenius

    Brisbane November 28, 2008

  • 22

    Morning

    08:00h Registration

    08:30h The Static Loading Test and Other Testing Methods

    09:40h Break

    10.00h The Bi-directional Test the O-cell

    11:00h Brief Background to Basic PrinciplesApplicable to Piled Foundations

    12.00h LUNCH

    SCHEDULE

    Afternoon

    13:00h Piles and Pile GroupsLong-term Behaviorand How We Know What We Know

    14:10h Break

    14:30h Analysis of Load Transfer and Capacity of Piles

    15:40h Unified Design of Piles and Pile Groups

    16.45h Questions and Discussions

    17:30h End of Day

  • 33

    www.Fellenius.net

  • 44

    Brisbane

    Power Point Slides1-Static_Test.pdf 2-Background.pdf 3-Case_Histories.pdf 5-Analysis.pdf 6-Unified_Method.pdf

    UniSoft ProgramsInformation and Order Form UniBear.zip UniCone.zipUniPhase.zip UniPile.zip UniSettle.zip

  • 55

    BASICS OF DESIGN OF PILED

    FOUNDATIONS

    Bengt H. Fellenius

    The Static Loading TestPerformance, Instrumentation, Interpretation

    Brisbane November 28, 2008

  • 66

  • 77

  • 88

  • 99

    Candidates for Darwin Award, First Class

  • 1010

    ! ! !Testing piles is a risky business.

  • 1111

    4. JACK

    3. LOAD CELL

    2. SPACER

    1. SWIVEL PLATE

    What do you think could happen to the stack of four pieces on the pile head when the load is applied? And, therefore, to the three oblivious persons next to the pile?

  • 1212This is how experience taught the three, and others, to arrange the units on the pile head

  • 1313

    Better safe than sorry!

  • 1414

  • 1515

  • 1616

  • 1717

  • 1818

  • 1919

  • 2020

  • 2121

    Fellenius 1984

  • 2222

    0

    50

    100

    150

    200

    250

    300

    350

    0 2,000 4,000 6,000 8,000 10,000Loadcell (KN)

    E

    r

    r

    o

    r

    i

    n

    J

    a

    c

    k

    L

    o

    a

    d

    (

    K

    N

    )

    Head-down O-cell Pile

    August 2006

    2.5% Error

    The error can be small or it can be large. Here are results from two tests at the same site using the same equipmenttesting two adjacent piles, one after the other.

    0

    500

    1,000

    1,500

    2,000

    0 5,000 10,000 15,000Loadcell load (KN)

    E

    r

    r

    o

    r

    (

    K

    N

    )

    15% Error

    2.5% Error

    Shinho-Pile August 2006

    Note, the test on the pile called "O-cell pile" is a head -down test after a preceding O-cell test.

  • 2323

    A routine static loading test provides the load-movement of the pile head...

    and the pile capacity?

  • 2424

    The Offset Limit MethodDavisson (1972)

    OFFSET (inches) = 0.15 + b/120

    OFFSET (SI-unitsmm) = 4 + b/120

    b = pile diameter (inch or mm)

    LLEAQ

    Q

    L

  • 2525

    The Decourt ExtrapolationDecourt (1999)

    0 100 200 300 400 5000

    500,000

    1,000,000

    1,500,000

    2,000,000

    LOAD (kips)

    L

    O

    A

    D

    /

    M

    V

    M

    N

    T

    -

    -

    Q

    /

    s

    (

    i

    n

    c

    h

    /

    k

    i

    p

    s

    )

    Ult.Res = 474 kips

    Linear Regression Line

    Q

    1

    2

    CC

    Qu C1 = Slope

    C2 = Y-intercept

    Q

  • 2626

    Other methods are:

    The Load at Maximum Curvature

    Mazurkiewicz Extrapolation

    Chin-Kondner Extrapolation

    DeBeer double-log intersection

    Fuller-Hoy Curve Slope

    The Creep Method

    Yield limit in a cyclic test

    For details, see Fellenius (1975, 1980)

  • 2727

    DECOURT 235

  • 2828

    0

    500

    1,000

    1,500

    2,000

    2,500

    0 5 10 15 20 25 30 35 40

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Offset-LimitLine

    Definition of capacity (ultimate resistance) is only needed when the actual value is not obvious from the

    load-movement curve

  • 2929

    Pile E29.5-inch closed-toe pipe

    Some results from Jones Island, Milwaukee

    on 30 m to 50 m long driven piles (Fellenius et al., 1983)

  • 3030

    Pile B212HP63

  • 3131

    Pile Toe Movement

    0 5 10 15 20 25 300

    1,000

    2,000

    3,000

    4,000

    MOVEMENT (mm)

    L

    O

    A

    D

    A

    T

    P

    I

    L

    E

    H

    E

    A

    D

    (

    K

    N

    ) HEAD

    HEAD LOAD vs. TOE MOVEMENT 65 ft long, 14 inch pipe pile.

    With a telltale to the toe arranged to determine pileshortening. Dont have it measure toe movement directly.

  • 3232

    Analysis of toe resistance

    An adjacent pull test on a similar instrumented pile established that the pile shaft resistance is about 2,000 KN approximately fully mobilized just short of 5-mm toe movement. The thereafter applied load in the push test goes to toe resistance, only.0 5 10 15 20 25 30

    0

    1,000

    2,000

    3,000

    4,000

    MOVEMENT (mm)

    L

    O

    A

    D

    A

    T

    P

    I

    L

    E

    H

    E

    A

    D

    (

    K

    N

    )

    HEAD

    HEAD LOAD vs. TOE MOVEMENT

    ESTIMATED TOE LOAD vs.

    TOE MOVEMENT(Based on the assumption thatshaft resistance is 2,000 KN)

    +10 %

    -10 %

    PILE SHORTENING

  • 3333

    20 inch square diameter, prestressed concrete pile driven to 58 ft embedment, through about 45 ft of soft silt and

    clay, 5 ft of sand, and to bearing 6 ft into hard clay

    0

    100

    200

    300

    400

    500

    600

    0.0 0.2 0.4 0.6 0.8 1.0 1.2

    MOVEMENT (in)

    L

    O

    A

    D

    (

    k

    i

    p

    s

    )

    Push test three months after driving

    Pull test five

    months after

    driving

    Data from AATech Scientific Inc.

    PUSH and

    PULLTo separate

    shaft and toe resistances. The pile is

    equipped with a toe telltale.

    Unloading-reloading once or a couple of times on the way upserves no purpose and may result in distorted analysis results

  • 3434

    Combining the push and pull test results with the telltale measurements to calculate the load-movement for the pile toe

    Data from AATech Scientific Inc.

    0

    100

    200

    300

    400

    500

    600

    0.0 0.2 0.4 0.6 0.8 1.0 1.2

    MOVEMENT (in)

    L

    O

    A

    D

    (

    k

    i

    p

    s

    )

    PUSH; HEAD

    TOE

    "Toe Telltale "

    PULL; HEADSHAFT

  • 3535

    It is not possible to interpret more than very approximately from the load-movement curve how much of the pile capacity that is toe resistance and how much is shaft resistance.

    Suggestions for Routine Testing

    Adding occasional unloading and re-loading cycles only distorts the figure. Cyclic loading requires a multitude of identical cycles maybe cycle 100 times at each load and unload magnitude, and cycle at several load levels. This is not practical for routine tests, but anything less is waste of effort.

    The standard method of eight increments up to a maximum load is probably the worst method of the lot. Instead of applying one increment each hour (as a shock to the pile), use one a quarter of the increment size and apply one every 15 minutes a much more gentle approach. Or, one small increment every 10 minutes aim for a total of about 30 increments; a five-hour test duration.

    On reaching the maximum load and holding it (say, for 10 minutes), unload in, say five or six decrements.

  • 3636

    The routine static loading test with load applied to the pile head and movement measured only at the pile head provides very limited information Good enough for proof testing. However, if more information is desired, instrument the test pile, or run an O-cell test.

  • 3737

    Instrumentation

    and

    Interpretation

  • 3838

    T e l l t a l e s A telltale measures shortening of a pile and must never be arranged

    to measure movement. Let toe movement be the pile head movement minus the pile

    shortening. For a single telltale, the shortening divided by the distance between

    the pile head and the telltale toe is the average strain over that length.

    For two telltales, the distance to use is that between the telltale tips. The strain times the cross section area of the pile times the pile

    material E-modulus is the average load in the pile.

    To plot a load distribution, where should the load value be plotted? Midway of the length or above or below?

  • 3939

    Load distribution for constant unit shaft resistance

    0

    50

    100

    0 100

    h A2

    LOAD, Q

    A1

    Midheight

    Average Load 0

    LoadDistribution

    Q = az

    DEPTH, z

    PILE HEAD

    PILE TOE

    ars

  • 4040

    Linearly increasing unit shaft resistanceand its load distribution

    00 Unit Shaft

    Resistance

    h

    az

    DEPTH, z

    31

    3axA

    21 AA hhX 58.0

    3X is where the average load should be plotted

    6)23(2

    323 xhxhaA

    00 Average

    LoadLOAD, Q0

    A1

    A2

    LoadDistribution

    Q = az2/2

    x

    h

  • 4141

    Today, telltales are not used for determining strain (load) in a pile because using strain gages is a more assured, more accurate, andcheaper means of instrumentation.

    However, it is good policy to include a toe-telltale to measure toe movement. If arranged to measure shortening of the pile, it can also be used as an approximate back-up for the average load in the pile.

    The use of vibratory strain gages (sometimes, electrical resistance gages) is a well-established, accurate, and reliable means for determining loads imposed in the test pile.

    It is very unwise to cut corners by field-attaching single strain gages to the re-bar cage. Always install factory assembled sister bar gages.

  • 4242

  • 4343

    Rebar Strain Meter Rebar Strain Meter Sister BarSister Bar

    Reinforcing Rebar

    Rebar Strain Meter

    Wire Tie

    Instrument Cable

    or Strand

    Tied to Reinforcing Rebar

    Hayes 2002

    Three bars?!

    Wire Tie

    Tied to Reinforcing Rings

    Reinforcing Rebaror Strand

    (2 places)

    Rebar Strain Meter

    Instrument Cables

    (3 places, 120 apart)

  • 4444

    We have got the strain.How to we get the load?

    Load is stress times area

    Stress is Modulus (E) times strain

    The modulus is the key

    E

  • 4545

    For a concrete pile or a concrete-filled bored pile, the modulus to use is the combined modulus of concrete,

    reinforcement , and steel casing

    cs

    ccsscomb AA

    AEAEE

    Ecomb = combined modulus Es = modulus for steelAs = area of steelEc = modulus for concreteAc = area of concrete

  • 4646

    The modulus of steel is 200 GPa (207 GPa for those weak at heart)

    The modulus of concrete is. . . . ?

    Hard to answer. There is a sort of relation to the cylinder strength and the modulus usually appears as a value around 30 GPa, or perhaps 20 GPa or so, perhaps more.

    This is not good enough answer but being vague is not necessary.

    The modulus can be determined from the strain measurements.

    Calculate first the change of strain for a change of load and plot the values against the strain.

    Values are knowntE

  • 4747

    0 200 400 600 8000

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    MICROSTRAIN

    T

    A

    N

    G

    E

    N

    T

    M

    O

    D

    U

    L

    U

    S

    (

    G

    P

    a

    )

    Level 1

    Level 2

    Level 3

    Level 4

    Level 5

    Best Fit Line

    Example of Tangent Modulus Plot

  • 4848

    baddEt

    ba

    22

    sE

    Which can be integrated to:

    But stress is also a function of secant modulus and strain:

    Combined, we get a useful relation:

    baEs 5.0

    In the stress range of the static loading test, modulus of concrete is not constant, but a more or less linear relation to the strain

    and Q = A Es

  • 4949

    0 200 400 600 8000

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    MICROSTRAIN

    T

    A

    N

    G

    E

    N

    T

    M

    O

    D

    U

    L

    U

    S

    (

    G

    P

    a

    )

    Level 1

    Level 2

    Level 3

    Level 4

    Level 5

    Best Fit Line

    Example of Tangent Modulus Plot

    Intercept is

    b

    Slope is a

  • 5050

    Note, just because a strain-gage has registered some strain values during a test does not guarantee that the data are useful. Unavoidable errors and natural variations amount to about 50 microstrain to 100 microstrain. Therefore, the test must be designed to achieve strain values at least of about 500 microstrain and beyond. If the imposed strain are smaller, the relative errors and imprecision will be large, and interpretation of the test data becomes uncertain, causing the investment in instrumentation to be less than meaningful. The test should engage the pile material up to at least half the strength. Preferably, aim for reaching close to the strength.

  • 5151

    Example of evaluation and assessment of strain-gage values

    Bored Pile, Singapore, 2007

    #1

    #13

    #8

    #7

    #6

    #5

    #4

    #3

    #2

    #9

    #12

    #11

    3

    7

    .

    5

    m

    (

    1

    2

    3

    f

    t

    )

    1,000 mm (39 in )

    S

    t

    i

    f

    f

    m

    a

    r

    i

    n

    e

    c

    l

    a

    y

    S

    a

    p

    r

    o

    l

    i

    t

    e

    S

    a

    n

    d

    ,

    S

    i

    l

    t

    ,

    a

    n

    d

    c

    l

    a

    y

    a

    s

    m

    a

    t

    r

    i

    x

    i

    n

    w

    e

    a

    t

    h

    e

    r

    e

    d

    g

    r

    a

    n

    i

    t

    i

    c

    b

    e

    d

    r

    o

    c

    k

    Pair of Vibrating-WireStrain Gages (Sister Bars)

    1,000 mm (39 in.)

    0

    2

    4

    6

    8

    10

    12

    0 5 10

  • 5252

    UTP-3 Load-Movement

    0

    5

    10

    15

    20

    25

    0 5 10 15 20 25

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    M

    N

    )

    UTP-3 Load-Strain

    0

    5

    10

    15

    20

    0 200 400 600 800 1,000STRAIN ()

    P

    I

    L

    E

    H

    E

    A

    D

    L

    O

    A

    D

    (

    M

    N

    )

    SG-1

    SG-2

    SG-3

    SG-4

    SG-5

    SG-6

    SG-7

    SG-8

    SG-9

    SG-11

    SG-12

    SG-13

    1 2 3 4 5 7 6 8 11 9 12 13 Gage Levels

  • 5353

    STAGE II, Tangent ModulusPile diameters are all equal to nominal value (1.00 m)

    10

    15

    20

    25

    30

    35

    40

    45

    50

    0 200 400 600 800 1,000 1,200

    STRAIN ()

    /

    SG-13

    SG-12

    SG-11

    SG-9

    SG-8

    SG-7

    SG-6

    Tangent Modulus Lines

    Strains are as measured; all pile diameters are assumed to be equal to the nominal area

  • 5454

    UTP-3 Load-Strain for adjusted areas

    0

    5

    10

    15

    20

    25

    0 200 400 600 800 1,000 1,200STRAIN ()

    P

    I

    L

    E

    H

    E

    A

    D

    L

    O

    A

    D

    (

    K

    N

    )

    SG-13

    SG-12

    sg-(11)

    sg-(9)

    SG-8

    sg-(7)

    sg-(6)

    SG-5

    SG-4

    SG-3

    3 4 5 6 7 8 9 11 12 13 ////

    //

    In a trial-and-error approach, the piles diameters (pile areas) were adjusted, and the strains were proportioned to the adjusted pile areas to ensure parallel slope of load-strain curves and equal tangent modulus lines.

    Adjustments ranged from increasing the diameter by 110 mm (#6) through 280 mm (#7)

  • 5555

    STAGE II, Tangent ModulusPile diameters are adjusted

    10

    15

    20

    25

    30

    35

    40

    45

    50

    0 200 400 600 800 1,000 1,200

    STRAIN ()

    /

    SG-13

    SG-12

    SG-11

    SG-9

    SG-8

    SG-7

    SG-6

    Note, you can also plot the tangent-modulus lines as tangent-stiffness (AE) lines, i.e., plot change of load over change of strain as opposed to change of stress over change of strain. Then, use the AE-values directly in the load calculation. However, this does give you less reference to what the actual differences are along the pile.

  • 5656

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 5 10 15 20 25

    LOAD (MN)

    D

    E

    P

    T

    H

    (

    m

    )

    UTP-3

    Shaft Resistance is not fully mobilized below 20 m depth.

    Now, having determined the

    relation between strain and

    secant modulus (from knowing

    the tangent-modulus), we are

    ready to convert measured

    strain to measured load in the

    pile: The load distribution.

    Marine clay

    Saprolitic soil

  • 5757

    What we measure is the increase of

    load in the pile due to the load applied

    to the pile head. What about the

    external-origin load in the pile that

    was there before we started the test?

    That is, the Residual load.

  • 5858

    Normalized Applied Load

    D E P T H

    Load distributions in

    static loading tests on

    four instrumented

    piles in clay

  • 5959

    B. Load and resistance in DA

    for the ultimate load applied

    Sand

    Example from Gregersen et al., 1973

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    0 50 100 150 200 250 300

    LOAD (KN)D

    E

    P

    T

    H

    (

    m

    )

    Pile DA

    Pile BC, Tapered

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    0 100 200 300 400 500 600

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    ) True

    Residual

    True minus Residual

    A. Distribution of residual load in DA and BC

    before start of the loading test

  • 6060

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    0 500 1,000 1,500 2,000 2,500LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    Fellenius et al. 2004

    Static Loading Testat Pend Oreille,

    Sandpoint, Idaho, for the realignment of US95

    406 m diameter,45 m embedment,

    closed-toe pipe pile driven in soft clay

    Clay

    200+ m

  • 6161

    Distribution of Measured Loads (False Resistance)and True Resistance

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    0 500 1,000 1,500 2,000 2,500LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    True ResistanceFrom Test data and from Calculations

    Residual LoadFrom Test data and from Calculations

    Measured LoadFrom Test data and from Calculations

    Fellenius et al. 2004

  • 6262

    FHWA tests on 0.9 m diameter bored pilesOne in sand and one in clay

    (Baker et al., 1990 and Briaud et al., 2000)

    0

    2

    4

    6

    8

    10

    12

    0 10 20 30 40

    Cone Stress and SPT N-Index(MPa and bl/0.3 m)

    D

    E

    P

    T

    H

    (

    m

    )

    Silty Sand

    Sand

    Pile 4

    0

    2

    4

    6

    8

    10

    12

    0 10 20 30 40

    Cone Stress (MPa)

    D

    E

    P

    T

    H

    (

    m

    )

    Pile 7

    N

    qc

    ClaySilty

    Sand Clay

  • 6363

    RESULTS: Load-transfer curves

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    0 1,000 2,000 3,000 4,000 5,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    PILE 4SAND

    Measured Distribution

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    0 1,000 2,000 3,000 4,000 5,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    PILE 4SAND

    True Distribution

    Residual Load

    Measured Distribution

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    0 1,000 2,000 3,000 4,000 5,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    PILE 7CLAY

    Measured Distribution

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    0 1,000 2,000 3,000 4,000 5,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    PILE 7CLAY

    True Distribution

    Residual Load

  • 6464

    Results of analysis of a Monotube pile in sand(Fellenius et al., 2000)

    0

    5

    10

    15

    20

    25

    0 1,000 2,000 3,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    True Resistance

    Measured Resistance

    Residual Load

  • 6565

    Method for evaluating the residual load distribution

    0

    2

    4

    6

    8

    10

    12

    14

    16

    0 500 1,000 1,500 2,000

    RESISTANCE (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    Measured Shaft ResistanceDivided by 2

    Residual Load

    Measured Load

    True Resistance

    ExtrapolatedTrue Resistance

    Shaft Resistance

  • 6666

    Analysis Procedure0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    0 500 1,000 1,500

    LOAD (KN)

    D

    e

    p

    t

    h

    (

    m

    )

    Residual Load

    True Resistance

    Measured Load

    Extension of Matching

    Shaft ResistanceDistributionDivided by 2

    Fellenius 2002

  • 6767

    Results

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    0 500 1,000 1,500 2,000

    LOAD (KN)

    D

    e

    p

    t

    h

    (

    m

    )

    CAPWAPDeterminedResistance

    True Resistance

    Residual

    CAPWAP ShaftDivided by 2

    True ShaftResistance

    Fellenius 2002

  • 6868

    0

    200

    400

    600

    800

    1,000

    0 5 10 15 20 25 30

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    No Residual Load

    Residual Load present

    OFFSET LIMIT LOAD

    No Strain Softening

    Presence of residual load is not just of academic interest

    0

    200

    400

    600

    800

    1,000

    0 5 10 15 20 25 30

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    With Strain Softening

    Residual Load present

    No Residual Load

    OFFSET LIMIT LOAD

  • 6969

    0

    200

    400

    600

    800

    1,000

    1,200

    0 5 10 15 20 25

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    HEAD

    TOE

    TOE TELLTALEA

    Does not this shape of measured toe movement suggest that there is a distinct toe capacity?

    Toe Resistance

  • 7070

    0

    200

    400

    600

    800

    1,000

    1,200

    0 5 10 15 20 25

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    HEAD

    TOE

    TOE TELLTALEA

    0

    200

    400

    600

    800

    1,000

    1,200

    0 5 10 15 20 25

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    HEAD

    "Virgin" Toe Curve

    TOE

    B

    No, it only appears that way when we forget to consider the residual toe load (also called the initial, or virgin toe movement)

  • 7171

    Residual Load is the same as Drag Load. The distinction made is that by residual load we mean the locked-in load present in the pile immediately before we start a static loading test. By drag load we mean the load present in the pile in the long-term

    Residual load

    Residual load as well as drag load can develop in coarse-grained soil just as it does in clay soil

    Both residual load and dragload develop at very small movements between the pile and the soil

  • 7272

    But, is the no-load situation really the reading taken at the beginning of the test? What is the true zero-reading to use?

    The strain-gage measurement is supposed to be the change of strain relative the no-load situation (i.e., when no external load acts at the gage location).

  • 7373

    We often assume somewhat optimistically or naively that the reading before the start of the test represents the no-load condition.

    However, at the time of the start of the loading test, loads do exist in the pile and they are often large.

    For a grouted pipe pile or a concrete cylinder pile, these loads are to a part the effect of the temperature generated during the curing of the grout.

    Then, the re-consolidation (set-up) of the soil after the driving or construction of hte pile will impose loads on the pile.

  • 7474

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    55

    60

    -300 -200 -100 0 100 200 300 400

    STRAIN ()

    D

    E

    P

    T

    H

    (

    m

    )

    9d

    15d

    23d

    30d

    39d

    49d

    59d

    82d

    99d

    122d

    218d Day ofTest

    At an E- modulus of 30 GPa, this strain change corresponds to a load change of 3,200 KN

    Strain measured during the 218-day wait-period between driving (grouting) and testing.

    Do these strains really represent load in the pile, as present before the start of the static loading test?

  • 7575

    Concrete curing temperature measured in a grouted concrete cylinder pile

    0

    10

    20

    30

    40

    50

    60

    70

    0 24 48 72 96 120 144 168 192 216 240

    HOURS AFTER GROUTING

    T

    E

    M

    P

    E

    R

    A

    T

    U

    R

    E

    (

    C

    )

    Temperature at various depths in the grout of a 0.4 m center hole in a 56 m long, 0.6 m diameter, cylinder pile.

    Pusan Case

  • 7676

    10

    20

    30

    40

    50

    60

    70

    0 5 10 15 20 25 30 35

    DAY AFTER GROUTING

    T

    E

    M

    P

    E

    R

    A

    T

    U

    R

    E

    (

    C

    )

    Start of Static Loading Test

    Temperatures measured in a 74.5 m long, 2.6 m diameter bored pile

    10

    20

    30

    40

    50

    60

    70

    0 1 2 3 4 5

    DAY AFTER GROUTING

    T

    E

    M

    P

    E

    R

    A

    T

    U

    R

    E

    (

    C

    )

    Temperatures measured in a 74.5 m long, 2.6 m diameter bored pile

    Temperature records during curing of grout in the Golden Ears Bridge test pile, Vancouver, BC. Data courtesy of Trow Engineering Inc. and Amec Inc.

  • 7777

    -400

    -300

    -200

    -100

    0

    100

    0 5 10 15 20 25 30 35DAY AFTER GROUTING

    C

    H

    A

    N

    G

    E

    O

    F

    S

    T

    R

    A

    I

    N

    (

    )

    Rebar ShorteningSlight Recovery of Shortening

    Change of strain measured in a 74.5 m long, 2.6 m diameter bored pile

    Change of strain during the curing of grout in the Golden Ears Bridge test pile

  • 7878

    -200

    -150

    -100

    -50

    0

    50

    100

    0 100 200 300 400 500Time (days)

    S

    T

    R

    A

    I

    N

    (

    )

    SNEW

    Pile piece submerged

    INCREASING TENSION

    Concrete Cylinder Piece

    Submerging the short pile segment, letting it swell from absorption of water

  • 7979

    The strain gages are not temperature sensitive, but the strain measurements may be!

    The vibrating wire and the rebar have almost the same temperature coefficient. However, the coefficients of steel and concrete are slightly different. This will influence the strains during the cooling of the grout. More important, for lower quality vibrating wire gages, the rise of temperature in the grout could affect the zero reading of the wire and its strain calibration. It is necessary to heat-cycle (anneal) the gage before calibration. (A routine measure of Geokon, US manufacturer of vibrating wire gages).

  • 8080

    Readings should be taken immediately before (and after) every event of the piling work and not just during the actual loading test

    A series of No-Load Readings will tell what happened to the gage before the start of the test and will be helpful in assessing the possibility of a shift in the reading value representing the no-load condition

    If the importance of the No-Load Readings is recognized, and if those readings are reviewed and evaluated, then, we are ready to consider the actual readings during the test

  • 8181

    Of course,

    we must consider also other aspects:

  • 8282

    Interpretation of a series of testsperformed at different times

    0 10 20 30 40 50 60 700

    10

    20

    30

    40

    50

    60

    70

    Movement (mm)Ch

    a

    n

    g

    e

    o

    f

    H

    o

    r

    i

    z

    o

    n

    t

    a

    l

    S

    t

    r

    e

    s

    s

    (

    K

    P

    a

    )

    5 Days1 Day8 Days4 Months22 Months

    Cell D1

    Results thought due to set-up and explained as Increase inHorizontal Effective Stress

    Fellenius 2002

    Results plotted According to Movement Path

    0 50 100 150 200 2500

    10

    20

    30

    40

    50

    60

    70

    Movement (mm)

    5 Days1 Day8 Days4 Months22 Months

  • 8383

    Also the best field work can get messed up if the analysis and

    conclusion effort loses sight of the history of the data

    The dynamic test (CAPWAP) was performed after the static test.

    The redriving (ten blows) forced the pile down additionally about 45 mm.

    0

    500

    1,000

    1,500

    2,000

    0 100 200 300

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    STATIC TEST

    DYNAMIC TEST

    0

    500

    1,000

    1,500

    2,000

    0 100 200 300

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    DYNAMIC TEST

    0

    500

    1,000

    1,500

    2,000

    0 100 200 300

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    DYNAMIC TEST in a series of blows

    Repeated STATIC TEST

  • 84

    Result on a test on a 2.5 m diameter, 85 m long bored pile

    0 50 100 150 200 2500

    10

    20

    30

    Movement (mm)

    L

    o

    a

    d

    (

    M

    N

    )

    LEVEL A Downward, STAGES 1 and 5

    Test Data

    FE analysis

    Does unloading/reloading add anything of value to a test?

  • 8585

    The above series of unloading/reloading has added nothing but cost the client a lot of money.

    0

    500

    1,000

    1,500

    2,000

    0 1 2 3 4

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

  • 8686

    Good measurements do not guarantee good conclusions!

    A good deal of good thinking is necessary, too

  • 8787

    Results of loading tests on 40 m long,

    instrumented steel piles in a saprolite soil

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 50 100 150 200 250

    UNIT SHAFT SHEAR (KPa)

    D

    E

    P

    T

    H

    (

    m

    ) ?

  • 8888

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    = 0.3

    = 0.4

    A more thoughtful analysis of the data

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 50 100 150 200 250

    UNIT SHAFT SHEAR (KPa)

    D

    E

    P

    T

    H

    (

    m

    )

    = 0.3

    = 0.4

  • 8989

    And a second pile:

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 50 100 150 200 250 300 350 400 450

    UNIT SHAFT SHEAR (KPa)

    D

    E

    P

    T

    H

    (

    m

    )

    = 0.3

    = 0.5

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    = 0.3

    = 0.5

  • 9090Jorj Osterberg 2001

    The Bi-Directional

    Static Loading Test

    The O-cell Test

  • 9191

    Schematics of the Osterberg O-Cell Test(Meyer and Schade 1995)

    Upward Load

    Downward Load

    THE O-CELL

    Telltales

    and

    Grout Pipe

    Pile Head

  • 9292

    Three O-Cells inside the reinforcing cage(My Thuan Bridge, Vietnam)

  • 9393

  • 9494

    The O-cell can also be installed in a driven pile (after the driving).Here in a 600 mm cylinder pile with a 400 mm central void.

  • 95O-cell in a pipe pile inserted in a augercast pile after grouting.

  • 9696Inchon, Korea

  • 9797

    -60-50-40-30-20-10

    010203040506070

    0 5,000 10,000 15,000 20,00M

    o

    v

    e

    m

    e

    n

    t

    (

    m

    m

    )

    Load (KN)

    Upward

    Downward

    Upward

    Approximate extension of the toe movement to the zero conditions

    EXAMPLE 1Results of an O-cell test on a 2.8 m by 0.8 m, 4 m deep barrette in Manila, Philippines

  • 9898

    O-Cell test on a 1,250 mm

    diameter, 40 m long, bored pile at US82 Bridge in Washington,

    Mississippi installed into dense sand

    -80

    -60

    -40

    -20

    0

    20

    40

    60

    80

    100

    120

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    UPPER PLATE UPWARD MVMNT

    LOWER PLATE DOWNWARD MVMNT

    Weightof

    Shaft

    Residual Load

    Shaft

    Toe

    EXAMPLE 2

  • 9999

    Resistance Distribution

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    Strain-Gage Level #4

    Strain-Gage Level #3

    Strain-Gage Level #2

    Strain-Gage Level #1

    O-Cell Level

    Pile Toe

    Clay Silt

    Sandy Silt

    Dense Sand with

    Gravel

    The unit shear resistance at shaft failure corresponds to a beta coefficient of about 1.0.

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 100 200 300 400AVERAGE UNIT SHAFT RESISTANCE (KPa)

    D

    E

    P

    T

    H

    (

    m

    )

    G.W.

  • 100100

    Load-Movement Curves

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    0 20 40 60 80 100 120

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Strain-Gage Level #4

    Strain-Gage Level #2

    Strain-Gage Level #1

    O-Cell

  • 101101

    Searching for the Residual Load

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    0.0 0.5 1.0 1.5 2.0

    PILE COMPRESSION (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    INDICATED RESIDUAL LOAD

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    0.0 25.0 50.0 75.0 100.0 125.0 150.0

    PLATE SEPARATION (OPENING) (mm)L

    O

    A

    D

    (

    K

    N

    )

    O-Cell LoadO-Cell Load

  • 102102

    From the O-Cell results, one can produce the load-movement curve that one would have obtained in a routine Head-Down Test

    Head down

  • 103103

  • 104104

    O-Cell Results Shown Two Ways

    -80

    -60

    -40

    -20

    0

    20

    40

    60

    80

    100

    120

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    0 20 40 60 80 100 120

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Shaft Movement

    Toe Movement

    Weight of Shaft

    Residual Load

  • 105105

    O-Cell test on a 43 ft long pile socketed into chalk bedrock

    at US82, Bridge at

    Oktebbeha, MS

    -1

    0

    1

    2

    3

    4

    5

    0 500 1,000 1,500

    LOAD (tons)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    i

    n

    c

    h

    e

    s

    )

    LOWER PLATE DOWNWARD MVMNT

    UPPER PLATE UPWARD MVMNT

    EXAMPLE 3

  • 106106

    Measured Resistance Distribution

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 400 800 1,200 1,600

    LOAD (tons)

    D

    E

    P

    T

    H

    (

    f

    e

    e

    t

    )

    Clay and

    Sand

    ChalkBed-rock

    Strain-Gage Level #3

    Strain-Gage Level #2

    Strain-GageLevel #1

    O-Cell Level

  • 107107

    Shaft Shear Distribution

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 5 10 15AVERAGE UNIT SHAFT RESISTANCE (ksf)

    D

    E

    P

    T

    H

    (

    f

    e

    e

    t

    )

    Clay and

    Sand

    ChalkBed-rock

    O-Cell Level

    O-Cell & Level #1

    Levels #2 & #3

    Level #1 & #2

    Ground & Level #1

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 5 10 15 20 25

    AVERAGE UNIT SHAFT RESISTANCE (ksf)

    D

    E

    P

    T

    H

    (

    f

    e

    e

    t

    )

    ChalkBed-rock

    Clay and

    Sand

    O-Cell

    #1 to Cell

    #2 to #1

    #3 to #2

    AFTER CORRECTION FOR

    RESIDUAL LOAD

    Estimated Residual Shear

    Ground to #3

    Residual Load not considered Corrected for Residual Load

  • 108108

    0 2 4 6 8 10 12 14 16-80

    -70

    -60

    -50

    -40

    -30

    -20

    -10

    0

    10

    20

    APPLIED LOAD (MN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    RE

    BO

    UN

    D W

    HE

    NU

    NL O

    AD

    ING

    COMPRESSION OFSOFT SOIL AT TOE

    Toe load-movement for a pile with a soft toe at Albuquerque, New Mexico (Data from Osterberg and Hayes, 1999)

    Example 4

    Finding a soft toe

  • 109109

    Kahuku Bridge across Kamehameha Highway, Hawaii

    Test on 600 mm, 17 m long, bored pile in hard clay and weathered rock

    EXAMPLE 5

    -1

    0

    1

    2

    3

    4

    5

    6

    7

    0 50 100 150 200 250 300 350 400

    O-cell Load (kips)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    i

    n

    c

    h

    e

    s

    )

    UPWARD

    DOWNWARD

  • 110

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 100 200 300 400 500 600 700 800

    LOAD (kips)

    D

    E

    P

    T

    H

    (

    f

    t

    )

    DATA FROM O-CELL TEST

    O-cell

    Shaft and toe resistances are not fully mobilized below the O-cell

    Silty hard clay

    Weathered rock

    Silty stiff clay

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 100 200 300 400 500 600 700 800

    LOAD (kips)

    D

    E

    P

    T

    H

    (

    f

    t

    )

    CONVERTED TO HEAD-DOWN "TEST"

    APPROXIMATED

    SPECULATIVE FULLY MOBILIZED

    O-cell

    1,000

    The load distribution after tangent-modulus evaluation of pile stiffness

    The "head-down" load distribution and speculative fully mobilized resistance

    Buoyant Weight

  • 111111

    EXAMPLE 6

    Test at Bangkok Airport

  • 112112

    Stage 1Lower Cell activatedUpper cell closed

    Stage 2Lower Cell openUpper Cell activated

    Stage 2Lower Cell closedUpper Cell activated

    Data fromFox, I., Du, M. and Buttling,S. (2004)Buttling, S. (2006)

  • 113113

    Downward load-movements during test phases 1, 2, and 3.

    Concern was expressed (Buttling 2006) that the toe resistance (Phase 1) was 3,000 KN and the shaft resistance for the lower segment was 5,000 KN (Phase 2), while in Phase 3 the combined shaft and toe resistances were only 6,000 KN. Should not the Phase 3 resistance be 8,000 KN rather than 6,000 KN (i.e., the sum of the values 5,000 KN and 3,000)?

    0

    25

    50

    75

    100

    125

    150

    175

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Active CellInactive, Open CellInactive, Closed Cell

    P1 P2P3

    1 2 3

    3,000 KN

    5,000 KN6,000 < 8,000 KN??

  • 114114

    Downward toe movements

    0

    25

    50

    75

    100

    125

    150

    175

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Active CellInactive, Open CellInactive, Closed Cell

    P1 P2P3

    1 2 30

    25

    50

    75

    100

    125

    150

    175

    0 2,000 4,000 6,000 8,000 10,000

    LOAD (KN)

    D

    O

    W

    N

    W

    A

    R

    D

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Active CellInactive, Open CellInactive, Closed Cell

    P2

    P1 and P2 data combined

    P3

    1 2 3

    are best plotted per sequence of testing. Particularly when considering the example toe resistance, one must evaluate the load-movement response in comparing Phase 1 + Phase 2 to Phase 3 (i.e., P2 shaft below cell plus P1 toe).

  • 115115

    O-Cell tests for Hacienda Elena Development, Guaynabo, Puerto Rico

    EXAMPLE 7

  • 116116

    Clayey Silt

    Saprolite

    Hard Clay

    Weathered Bedrock

    O-cell Test Results

    -80

    -70

    -60

    -50

    -40

    -30

    -20

    -10

    0

    10

    20

    0 1,000 2,000 3,000 4,000 5,000

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

  • 117117

    Measured load-movements can besimulated (fitting) to t-z and q-z relations

    Pile shaft by t-z relation; Pile toe by q-z relation

    0 20 40 60 80 1000

    20

    40

    60

    80

    100

    Movement (%)

    R

    e

    s

    i

    s

    t

    a

    n

    c

    e

    (

    %

    )

    Exp. = 0.75

    Exp. = 0.05

    R = MVMNT^Exp

    Exp. = 0.50

    Exp. = 0.33

    Exp. = 0.20

    Exp. = 0.10

    TOE

    SHAFT

    exp2

    1

    2

    1 )(

    RR

  • 118118

    O-cell Test Resultswith UniPile Simulation

    0

    5,000

    10,000

    15,000

    0 10 20 30 40 50 60 70

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Toe

    Shaft

    Exp.= 0.20

    Exp.= 0.55

    O-cell Test Resultswith UniPile Simulation

    0

    5,000

    10,000

    15,000

    0 10 20 30 40 50 60 70

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    ) Head

    Toe

    Shaft

    Extrapolation ofO-cell data

    Exp.= 0.20

    Exp.= 0.55

    Fitting Results

    O-cell Test Resultswith UniPile Simulation

    0

    5,000

    10,000

    15,000

    0 10 20 30 40 50 60 70

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    ) Head

    Toe

    Shaft

    Extrapolation ofO-cell data

    Exp.= 0.20

    Exp.= 0.55

    Combining the t-z and q-z

    curves

  • 119119

    Pensacola, Florida410 mm diameter, 22 m long, precast concrete pile driven into silty sand

    EXAMPLE 8

  • 120120

    Pensacola, Florida, USA

    -10

    0

    10

    20

    30

    40

    50

    60

    0 500 1,000 1,500 2,000 2,500

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

  • 121121

    Bridge over Panama Canal, Paraiso Reach, Republic of PanamaO-cell test on a 2.0 m (80 inches) diameter, 30 m (100 ft) deep shaft

    drilled into the Pedro Miguel and Cucaracha formations, February 2003.

    EXAMPLE 9

  • 122122

    O-cell

    Strain-Gage Locations

    -50

    -40

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    0 5,000 10,000 15,000 20,000

    LOAD (KN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Downward Movement

    Upward Movement

    Load-Movements. Measured and Fitted to UniPile Calculation.

  • 123123

    Test Results Processed for Design Analysis

    0

    5

    10

    15

    20

    25

    30

    0 5,000 10,000 15,000 20,000 25,000 30,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    5

    10

    15

    20

    25

    30

    0 5,000 10,000 15,000 20,000 25,000 30,000

    LOAD (KN)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    35,000

    0 10 20 30 40 50 60 70

    MOVEMENT (mm

    L

    O

    A

    D

    (

    K

    N

    )

    )

    Measured and Calculated Load-Movement Curvesplus Simulated Pile Head

    Load-Movement

    TOE

    SHAFT

    HEAD

    Offset Limit

    0.30

    0.45

    0.30

    ___

    1.20

  • 124124

    Torre Chapultepec, Mexico City, Mexico

    O-cell Test on a 700 mm diameter 34 m deep bored pile

    0 m - 26 m desiccated clayey silt

    5 m 34+ m dense sand and silt

    EXAMPLE 10

  • 125125

    Torre Chapultepec, Mexico City, Mexico

    -400

    -350

    -300

    -250

    -200

    -150

    -100

    -50

    0

    0 500 1,000 1,500 2,000 2,500

    LOAD (KN)

    D

    O

    W

    N

    W

    A

    R

    D

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    O-cell Test?

  • 126126

    Torre Chapultepec, Mexico City, Mexico

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    0 20 40 60 80 100 120 140

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Head-Down Test

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    0 20 40 60 80 100 120 140

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Head-Down Test

  • Torre Chapultepec, Mexico City, Mexico

    -400

    -350

    -300

    -250

    -200

    -150

    -100

    -50

    0

    0 500 1,000 1,500 2,000 2,500

    LOAD (KN)

    D

    O

    W

    N

    W

    A

    R

    D

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    O-cell Test

    -400

    -350

    -300

    -250

    -200

    -150

    -100

    -50

    0

    0 500 1,000 1,500 2,000 2,500

    LOAD (KN)

    D

    O

    W

    N

    W

    A

    R

    D

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    O-cell Test

    TOE MOVEMENT IN HEAD-DOWN TEST

  • 128128

    O-cell Tests on an 11 m long, 460 mm square precast concrete pile driven in silica sand in

    North-East Florida(Data from Data from Bullock et al. 2005)

    A study of Toe and Shaft Resistance

    Response to Loading

    EXAMPLE 11

  • 129129

    CPT sounding next to an 11 m long, 460 mm square precast concrete pile driven in silica sand in North-East Florida

    Data from Bullock et al. 2005

    0

    2

    4

    6

    8

    10

    12

    14

    0 10 20 30 40Cone Stress, qt (MPa)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    2

    4

    6

    8

    10

    12

    14

    0 100 200 300

    Sleeve Friction (KPa)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    2

    4

    6

    8

    10

    12

    14

    0.0 0.2 0.4 0.6 0.8 1.0

    Friction Ratio (%)

    D

    E

    P

    T

    H

    (

    m

    )

    PRES

    2b

  • 130130

    Load-movement curves for the pile toe.The two first cycles and beginning of the third cycleThe two first cycles and beginning of the third cycle

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    1,600

    -3 -2 -1 0 1 2 3 4 5 6 7 8

    TOE MOVEMENT (mm)

    C

    E

    L

    L

    L

    O

    A

    D

    (

    K

    N

    )

    1

    2

    3

    Toe Resistance Response

    Data from

    Bullock et al. 2005

  • 131131

    Load-movement curvesfor the pile toe during all four load cycles

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    1,600

    -5 5 15 25 35 45 55 65 75

    TOE MOVEMENT (mm)

    C

    E

    L

    L

    L

    O

    A

    D

    (

    K

    N

    )

    Data from Bullock et al. 2005

  • 132132

    0

    2

    4

    6

    8

    10

    12

    14

    0 10 20 30 40Cone Stress, qt (MPa)

    D

    E

    P

    T

    H

    (

    m

    )

    PRES

    2b

    Data from Bullock et al. 2005

  • 133133

    0

    200

    400

    600

    800

    1,000

    1,200

    1,400

    1,600

    0 5 10 15 20 25 30 35 40 45 50

    CELL EXTENSION (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    8 hours 4 days

    16 days

    SHAFT LOAD-MOVEMENT DIAGRAM FROM O-CELL TESTSPDA CAPWAP 18 min.BOR 1h BOR

    EOD

    Shaft Resistance Response

    UPWARD MOVEMENT (mm)

    Data from Bullock et al. 2005

  • 134134

    O-cell Tests on a 1.4 m diameter

    bored pile in North-West Calgary

    constructed in silty glacial clay till

    A study of Toe and Shaft Resistance Response to Loading and correlation to

    CPTU calculation of capacity

    EXAMPLE 12

  • 135135

    0

    5

    10

    15

    20

    25

    30

    0 10 20 30Cone Stress, qt (MPa)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    5

    10

    15

    20

    25

    30

    0 200 400 600 8001,00

    0

    Sleeve Friction, fs (KPa)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    5

    10

    15

    20

    25

    30

    -100 0 100 200 300 400 500

    Pore Pressure (KPa)

    D

    E

    P

    T

    H

    (

    m

    )

    0

    5

    10

    15

    20

    25

    30

    0 1 2 3 4 5

    Friction Ratio, fR (%)

    D

    E

    P

    T

    H

    (

    m

    )

    PROFILE

    The upper 8 m will be removed for basement

    uneutral

    14 m net pile length

    GW

    Cone Penetration Test with Location of Test Pile

  • 136136

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 1,000 2,000 3,000 4,000 5,000 6,000

    LOAD (KN)M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Pile Profile and O-cell Location O-cell Load-movement Up and Down

    ELEV.(m)

    #5

    #4

    #3

    #2 #1

  • 137137

    Stress-Strain

    0

    1

    2

    3

    4

    5

    0 10 20 30 40 50 60 70 80 90

    STRAIN ()

    S

    T

    R

    E

    S

    S

    (

    G

    P

    a

    )

    Level 1

    Level 2

    Level 3

    Level 4

    Level 5

    GL5 GL4

    GL1 GL2 GL3

    Results from Strain-gage Levels 1 through 5

    Tangent Modulus

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 10 20 30 40 50 60 70 80 90

    STRAIN ()

    T

    A

    N

    G

    E

    N

    T

    M

    O

    D

    U

    L

    U

    S

    ,

    M

    t

    (

    G

    P

    a

    )

    Level 1Level 2Level 3Level 4Level 5Avg.Line

    Et =39.5 - 0.06Es =39.5 - 0.03

  • 138138

    Load Distribution

    0

    5

    10

    15

    20

    25

    0 5 10 15 20LOAD (MN)

    D

    E

    P

    T

    H

    (

    m

    )

    O-cell

    0

    5

    10

    15

    20

    25

    0 5 10 15 20LOAD (MN)

    D

    E

    P

    T

    H

    (

    m

    )

    = 0.75

    = 0.35

  • 139139

    0

    5

    10

    15

    20

    25

    0 5 10 15 20LOAD (MN)

    D

    E

    P

    T

    H

    (

    m

    )

    = 0.75

    = 0.35

    = 0.65

    After consideration of potential presence of residual load and applying judgment

    Load Distribution

  • 140140

    0

    5

    10

    15

    20

    25

    0 5 10 15 20LOAD (MN)

    D

    E

    P

    T

    H

    (

    m

    )

    Schmertmann

    E-F

    LCPC withoutmax. limitsTEST

    LCPC withmax. limits

    Load Measured Distribution Compared to Distributions Calculated from the CPTU Soundings

  • 141141

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    14,000

    0 20 40 60 80 100 120

    MOVEMENT (mm)

    L

    O

    A

    D

    (

    K

    N

    )

    Loadtest's Curvefor the Pile Head

    Pile Head

    Pile Shaft

    Pile Toe

    Test range

    The Test Data for Shaft and Toe and Evaluation of Head-down Movement Using t-z and q-z evaluations

  • 142142

    #8

    #7

    #6

    #5

    #4#3

    #2

    #1

    121 m

    EXAMPLE 13

    O-cell Tests on a 2.5 m diameter, 121 m deep bored pile for the Sutong Bridge Project - Jiangsu Province, China, constructed in compact to dense to very dense sand.

    Note, two-level O-cell test

  • 143143

    TEST RESULTS

    Lower O-cell, Stages 1 and 2

    -130-120-110-100-90-80-70-60-50-40-30-20-10

    01020

    0 5 10 15 20 25 30LOAD (MN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Repeated test after grouting the pile toe

    Upper O-cell, Stage 3

    -20

    0

    20

    40

    60

    80

    100

    120

    0 10 20 30 40LOAD (MN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    Upper O-cellPile Head

  • 144

    Zambezi River Bridge, Caia, Mozambique

    1.5 m diameter60 m embedment

    Bored Pile

    EXAMPLE 14

  • 145-40

    -30

    -20

    -10

    0

    10

    20

    30

    0 1 2 3 4 5 6 7 8 9 10 11 12

    LOAD (MN)

    M

    O

    V

    E

    M

    E

    N

    T

    (

    m

    m

    )

    O-cell Down

    O-cell Up

    CLAY

    SAND

    SANDSTONE

    SAND

    Test Results

  • 146

    y = 0.0228x + 0.4653R2 = 0.9995

    y = 0.031x + 2.6804R2 = 0.9984y = 0.0352x + 3.9114

    0

    1

    2

    3

    4

    5

    6

    7

    0 50 100 150 200 250 300 350STRAIN ()

    S

    T

    R

    E

    S

    S

    (

    K

    P

    a

    )

    GL-1GL-2

    GL-3

    y = -0.0173x + 25.553R2 = 0.6372

    0

    20

    40

    60

    80

    0 50 100 150 200 250 300AVERAGE STRAIN ()

    T

    A

    N

    G

    E

    N

    T

    M

    O

    D

    U

    L

    U

    S

    ,

    M

    t

    (

    G

    P

    a

    )

    GL-1

    GL-2

    GL-3

    E-Modulus

    Tangent Modulus

  • 147

    0

    10

    20

    30

    40

    50

    60

    70

    0 5 10 15 20 25LOAD (MN)

    D

    E

    P

    T

    H

    (

    m

    )

    Effective stress fitted to data with =0.20 to 0.10

    Constant unit shaft resistanceequal to 42 KPa

    Load Distribution

  • 148148

    The O-Cell test with a couple of strain gages, judiciously placed, will provide:

    1. Separate values of shaft and toe resistances

    2. Estimate of residual load

    3. Load-transfer for the pile

    4. Pile-toe load-movement curves (q-z function)

    5. Results that can be extrapolated to other piles

    6. Data necessary for settlement analysis

  • 149149

    Not recognizing that test data can be affected by residual load is the reason for delusive concepts such as the Critical Depth.

    Closing remarks

    It is unfortunate that this fact is still not generally recognized. As should be obvious, this means that poorly thought-through results keep confusing the practice.

    The E-modulus is an important factor in the evaluation of the O-cell data that must not be left to chance.

    The analysis is not completed before the test data have been processed in an effective stress calculations and the t-z and q-zrelations have been evaluated.

    Instrumentation and taking the readings must be planned, executed, and evaluated by persons who are experienced in all the various phases.

  • 150

    The Absolute and Ultimate Bi-direction

  • 151151Vaughani Shores, Vanuatu www.DiveVanuatu.org