Antim Knit Composite Ltd.Barpa, Rupshi, Rupgonj, Narayangonj.
(23.747085N, 90.540857E)
29th MARCH 2014
8
10,000litre10,000litre
5,000litre
Water tanks supported on cantilever floor. Floor beginning to show some signs of distress. Building Engineer to review adequacy of floor to support the tanks.
Bldg 11
Building 11
No horizontal bracings observed in roof to Building 1.Stability of structure should be checked for lateral loads.
Horizontal bracings possibly required for stability
Building 1
No horizontal bracing observed in Buildings 5, 6, 7, 8 and 9
Horizontal bracings possibly required for stability
No diagonal member provided to the trusses in the access area to Buildings 5, 6, 7, 8 and 9. Building engineer to review adequacy of trusses.
Diagonal members possibly required
16
Problems Observed
1. Building 2 columns highly stressed2. Gable Wall in Buildings 5, 6, 7, 8 and 9 out of plumb3. Building 11 - Support Structure to water tanks4. Building 1 columns5. Roof Bracing - Building 16. Roof Bracing - Buildings 5, 6, 7, 8 and 97. Loading Plan – Building 38. Trusses Over Entrance Road
17
Item No. Observation Recommended Action Plan Recommended Timeline
1
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
Limit Live Load to 2.0kN/m2 on all floors immediately Immediate - Now
2
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
Factory Engineer to review design loads and column stresses in this zone
Immediate - Now
3
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
Verify insitu concrete strength and aggregate type from min. 4 no. 100mm dia. core samples from ground floor columns.
Immediate - Now
4
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
A Detail Engineering Assessment of Building 2 is to be commenced immediately in accordance with attached Scope
Immediate - Now
5
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
Complete Detail Engineering Assessment 6-weeks
6
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
Produce and actively manage a loading plan for all floor plates within the factory, giving consideration to floor capacity and column capacity
6-weeks
7
Building 2 Columns highly stressed – see Executive Summary for Immediate
Actions
Continue to implement loading plan. 6-months
18
This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment.The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team.
We expect that the following will be carried out:1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions , levels, foundations and framing on Plan,
Section and Elevational drawings .2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building
against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made.
3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed.4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied.5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated
loads.6. The Engineering team will prepare an assessment report that covers the following:
• As-Built drawings including• Plans at each level calling up and dimensioning all structural components • Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the
structure• Highlight any variation between As-built compared to the designed structure• Results of testing for strength and materials• Results of geotechnical assessment and testing/investigation• Details of loading, inputs and results of computer modelling• Commentary on adequacy/inadequacy of elements of the structure• Schedule of any required retrofitting required for safety or performance of Structure
Any proposals for Retrofitting to follow guidance developed in the Tripartite Document
Detail Engineering Assessment
19
Item No. Observation Recommended Action Plan Recommended Timeline
8Gable Wall in Buildings 5, 6, 7,
8 and 9 out of plumb
Building Engineer to survey wall to determine the line and plumb of wall. Wall foundations to be checked and reviewed. Cordon off adjacent areas if deemed necessary.
Immediate - Now
9Gable Wall in Buildings 5, 6, 7,
8 and 9 out of plumbImplement findings of review of wall and foundations 6-weeks
10Gable Wall in Buildings 5, 6, 7,
8 and 9 out of plumbContinue to monitor line and plumb of wall 6-months
11Building 11 - Support
structure to Water Tanks
Building Engineer to review design for water tank support structure and add temporary propping and back-propping as necessary.
Immediate - Now
12Building 11 - Support
structure to Water TanksImplement action items arising from review of support structure.
6-weeks
13Building 1 Columns highly
stressedFactory Engineer to review design loads and ground floor internal column stresses
6-weeks
14Building 1 Columns highly
stressedVerify insitu concrete strength from min. 4 no. 100mm dia. core samples from ground floor columns
6-weeks
15Building 1 Columns highly
stressed
Produce and actively manage a Loading Plan for all floor plates within the factory, giving consideration to floor capacity and column capacity.
6-months
20
Item No. Observation Recommended Action Plan Recommended Timeline
16 Roof Bracing Building 1Building engineer to review bracing requirements for steel roof.
6-weeks
17 Roof Bracing Building 1 Implement action items arising from engineering review. 6-months
18Roof Bracing Buildings 5,6,7,8
and 9Building engineer to review bracing requirements for steel roof.
6-weeks
19Roof Bracing Buildings 5,6,7,8
and 9Implement action items arising from engineering review 6-months
20 Building 3 - Loading PlansFactory Engineer to review design, loads and column stresses for Building 3. Fire protection to steelwork to be reviewed
6-months
21 Building 3 - Loading PlansProduce and actively manage a loading plan for all floor plates within the factory, giving consideration to floor capacity and column capacity.
6-months
22 Trusses over Entrance RoadRoof trusses over entrance road have no diagonal members . Building Engineer to carry out detailed calculations for trusses.
6-weeks
23 Trusses over Entrance Road Carry out any remedial works arising from calculations. 6-months