Sinha Knitting Ltd. (10185) Kanchpur, Sonargoan, Narayangonj. (+23.706211N, 90.519104E) 05 July.2014

Upload: truongnhan

Post on 18-Mar-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 3: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

Typical column at the ground floor through

the 2nd floor of WG-3 building are severely

overstressed. All storage from these floors

should be remove immediately.

1st Priority 1 Concern

Live load on all floors must be reduce to

0kPa until DEA report is finished.

Page 8: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

Bridge between buildings (SKL and a

neighbouring Opex building not part of this

factory) does not appear on the drawings.

Design & detailing of connections onto

each building requires checking. An

Engineering Assessment is required.

1st Priority 3 Concern

Page 11: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

The building did not feature any core or

shear walls. Stability was achieved

through sway action between beams and

columns and masonry infill walls.

We require that these items be

investigated in a Detail Engineering

Assessment

Page 13: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

No waterproofing membrane was visible on the

roof of the buildings (SKL, WG-1, WG-3,

Generator room). This means that any cracks in

the surface finishes on the roof will allow water

to seep into the concrete slab beneath the

finishes, and cause corrosion of the reinforcing

steel.

Presence of moisture on the wall below SKL

building water tank. Cause to be investigated.

Page 15: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

Problems Observed Summary

ITEM 1: (Priority 1) Overstress column in WG-3 building. Immediately reduce loading on all floors ITEM 2: (Priority 2) Overall lateral stability system for all buildings and steel roof is to be verified. ITEM 3: (Priority 2) None of the buildings have any loading plans. ITEM 4: (Priority 2) WG-3 Cracking at staircase slab. Deep cracks were found in slabs of several storeys. ITEM 5: (Priority 3) Bridge between buildings is not shown on the drawings. ITEM 6: (Priority 3) No fireproofing of mezzanine steel structure. ITEM 7: (Priority 3) Water ingress under SKL building water tank.

Page 16: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

Item No. Observation Recommended Action Plan Recommended Timeline

1Priority 1 - Overstress column in WG-3 building.

Immediately reduce loading on all floors

Immediately remove all loads from all floors.

Carry out a Detailed Engineering Assessment to confirm actual building

structural capacity.

Immediate – Now

2Priority 1 - Overstress column in WG-3 building.

Immediately reduce loading on all floorsImplement recommendations from the DEA. 6-weeks

3Priority 2 - Overall lateral stability system for all buildings

and steel roof is to be verified.

Carry out a Detailed Engineering Assessment for the lateral stability of

buildings and sheds as per BNBC.6-weeks

4Priority 2 - Overall lateral stability system for all buildings

and steel roof is to be verified. Implement recommendations from the DEA. 6-months

5 Priority 2 - None of the buildings have any loading plans. Generate loading plan for each floor of the buildings. 6-weeks

6 Priority 2 - None of the buildings have any loading plans.Clear indication displaying maximum storage height must be carried out

in all storey building.6-months

Page 17: Sinha Knitting Ltd. (10185) - Fair Factories Clearinghouseaccord.fairfactories.org/accord_bgd_files/1/Audit_Files/13705.pdf · Sinha Knitting Ltd. (10185) Kanchpur, ... Maintain standard

Item No. Observation Recommended Action Plan Recommended Timeline

7Priority 2 - WG-3 Cracking at staircase slab. Deep cracks

were found in slabs of several storeys.

Carry out a Engineering Assessment to verify the stairway stability and

the cause of crack in stairway slabs.6-weeks

8Priority 2 - WG-3 Cracking at staircase slab. Deep cracks

were found in slabs of several storeys. Carry out actions from Engineering Assessment recommendations. 6-months

9Priority 3 - Bridge between buildings is not shown on the

drawings.

Carry out engineering assessment on design connections of bridge

between buildings.

Carry out actions in engineering assessment

Update drawings to show bridge.

6-months

10 Priority 3 - No fireproofing of mezzanine steel structure.

Fireproofing material for structural steel element is recommended as

suggested in BNBC Codes.

Maintain standard of quality control and protection of the fire

protection.

6-months

11 Priority 3 - Water ingress under SKL building water tank. Factory Engineer to inspect water damaged structures and repair with a

suitable methods.6-months