![Page 1: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/1.jpg)
Hosted by
Anmore Village Centre Anmore Council Presentation + Cost Update
Stuart Rothnie
HCMA Architecture + Design
June 4th 2019
![Page 2: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/2.jpg)
Today’s Agenda
• Project Drawings
• Changes and adjustments
• Project Costs
• Exclusions
![Page 3: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/3.jpg)
Site Plan
Area of Building = 13,260sf
_________________________
Main Floor = 10,900sf
Lower Floor = 2,360sf
Existing Parking +
Roads
Portables
New Civic Facility
![Page 4: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/4.jpg)
Main Floor Plan
Municipal Offices
Administration Area
Public Foyer + Display Area
Meeting Space
Community Room +
Council Chamber
Main Floor = 10,900sf
![Page 5: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/5.jpg)
Lower Floor Plan
Unfinished Basement
under Community Room Above
Archives and Event Storage
Public Washrooms
(Accessed from Building or Park)
Lower (Finished) Floor = 2,360sf
2,150sf
![Page 6: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/6.jpg)
View of Civic Facility from Above
![Page 7: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/7.jpg)
View from Sunnyside Road
![Page 8: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/8.jpg)
ELEVATIONS
![Page 9: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/9.jpg)
View of Community room
![Page 10: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/10.jpg)
View to Park from Community Room
![Page 11: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/11.jpg)
Class D Estimate
A class “D” estimate is prepared when a project is at the Conceptual Design stage.
Conceptual design is defined as the beginning of a project when preliminary spatial needs have been identified, and a space program is being developed.
At this stage of a project, conceptual drawings of physical space layouts and elevations are being developed by the architect, and the remainder of the design team are developing and evaluating different ideas regarding the types of systems to be used in the project.
![Page 12: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/12.jpg)
Changes and Adjustments from Drawing Package
- CURTAIN WALL REDUCTION AND ADDITION OF WINDOWS
Curtain wall kept at Community room, Foyer and Boardroom only.
Other areas – allow for windows
- SBS ROOFING CONSIDERED FOR THIS ESTIMATE
- SKY LIGHT REDUCTION
6x double glazed skylights instead of whole glazed roof area
- ROOF OVERHANG REDUCTION
- COMMUNITY ROOM CEILING ALLOWED AS GYPSUM FINISH
($93,400)
($103,200)
($16,200)
($11,000)
- $ 223,800
![Page 13: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/13.jpg)
BUILDING COST $ 4,168,600 ($314 sf)
SITEWORK COST
Total Construction Costs
$ 6,105,900
CONTINGENCIES $ 619,900
$ 1,317,400
*AS PER RTA ESTIMATE DATED MAY 15 2019
![Page 14: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/14.jpg)
Sitework Costs
TOTAL SITEWORK COST
$ 1,317,400
*AS PER RTA ESTIMATE DATED MAY 15 2019
SITE IMPROVEMENTS
IMMEDIATE SITEWORK $ 308,900
$ 831,700
GENERAL REQ. or CM FEE $ 176,800
![Page 15: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/15.jpg)
*AS PER RTA ESTIMATE DATED MAY 15 2019
DESIGN PRICING CONTINGENCY $ 274,300DESIGN DEVELOPMENT & REFINEMENT (5%)
ESCALATION CONTINGENCY $ 345,60012 MONTHS ALLOWANCE (6%)
Contingencies
$ 619,900
NO CONSTRUCTION CONTINGENCY (5%)
![Page 16: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/16.jpg)
Excluded from current estimate:
Removal of Portables
Construction Contingency
10-12% of Construction Costs
Architectural and Consultant Fees
Change orders (5%)
Development Costs and Permits
Legal, Financing and Management Fees
Additional Site work outside scope
Site investigation, off-site utility upgrade, etc.
Additional Sustainability Features, Certification and Approvals
Furniture, Fixtures and Equipment
Allowance $100,000-$300,000
![Page 17: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/17.jpg)
Soft Costs to be added:
Removal of Portables
Construction Contingency
10-12% of Construction Costs = $610,600- $ 732,700
Architectural and Consultant Fees
Change Orders during Construction (5%) = $305,300
Development and Permit Fees
Legal, Financing and Management Fees
Additional Site Work
Site investigation, off-site utility upgrade, etc.
Furniture, Fixtures and Equipment
Allowance = $150,000-$300,000
$ 1,225,000 (Approximate)
Total Project Costs
$ 7,330,900
![Page 18: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/18.jpg)
Thank you
Option:
What if we finished the entire basement under the Community Room?
![Page 19: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/19.jpg)
BUILDING COST $ 4,168,600 ($314 sf)
SITEWORK COST
Total Construction Costs (Add Finished Basement)
$ 6,429,700
CONTINGENCIES $ 655,500
$ 1,317,400
*AS PER RTA ESTIMATE DATED MAY 15 2019
Finished Basement Storage $ 323,800 Total Project Costs
$ 7,654,700
![Page 20: Anmore Village Centre Plan · Lower Floor Plan Unfinished Basement under Community Room Above Archives and Event Storage Public Washrooms (Accessed from Building or Park) Lower (Finished)](https://reader034.vdocuments.us/reader034/viewer/2022052006/601a7bf3d0b9134159775a3e/html5/thumbnails/20.jpg)