analysis ii – façade redesign: architectural precast panels be posted/v analysis ii.pdf ·...
TRANSCRIPT
![Page 1: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/1.jpg)
Analysis II – Façade Redesign: Architectural Precast Panels
![Page 2: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/2.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
21
Analysis II – Façade Redesign: Architectural Precast Panels
Overview:
This analysis covers the comparison of the current EIFS façade and my
proposed change to architectural precast panels. It compares several important
factors and shows the results of a structural analysis showing that the existing
building can support the heavier façade. The precast is a higher quality and
more durable system that will last the life of the building. It has a greater cost
associated with it, but is well worth having confidence in the performance of the
façade when it needs to last for the life of the building.
Background:
The façade of a building is the main barrier between the outside weather, and the
interior of the building. It is crucial that the façade can keep water and moisture
out of the building, and that it can handle the type of weather it is going to be
exposed to. In the case of the Goizueta Foundation Center, the façade chosen
was an exterior insulating finish system, which I will refer to as EIFS from here
on. This system consists of several layers, shown in Figures 5 and 6 below.
A. Substrate/Sheathing
B. Adhesive
C. EPS Insulation Board
D. Reinforcing Mesh
E. Base Coat
F. Finish Coat
Figure 6: Isometric section of EIFS layers Figure 5: Layers of the EIFS system used on the Foundation Center
![Page 3: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/3.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
22
EIFS has several benefits, but also many drawbacks. Mainly, it is not a good
system to install in an area that receives a moderate amount of rainfall. This is
the case with Atlanta. The average annual rainfall in Atlanta is 51”. For a system
that can have problems in wet areas, Atlanta does not seem to be a good place
to be installing it. Not to say that EIFS may perform well in its initial testing for
moisture penetration, but over the life of the building it will certainly need
maintenance and/or repair. Moisture damage to a building with an EIFS façade
can be extremely expensive to repair and replace. In some cases, the
remediation costs more than the initial construction itself. The drawbacks of
EIFS certainly validate a redesign of the façade. The foundation center is an
educational building on a university campus. Universities build buildings that are
going to be in use for 100 years or more. With this in mind, the building must
then be exposed to 100 years of weather and storms. EIFS was first used in the
United States in 1969. It is barely more than 35 years old. There is no
guarantee that it can withstand 100 years of weather and storms because it
hasn’t been around even half that time for it to be tested. A university wants a
building with a high quality façade, and that is why I chose architectural precast
panels. I have compiled a list of factors that I feel are important when choosing a
façade (see Table 4 below).
Factors EIFS Precast Panels
Cost EIFS is very cost effective, at
about $10/sf.
More expensive, Architectural
Panels costing roughly $40/sf
Weight Second advantage, EIFS is a
very light façade system
Architectural Panels weight
62.5lb/sf
Insulation Value
The insulating board in the
EIFS system has an R-value
of 3.8 per inch thickness.
Concrete suffers here with an
R-value of only .1 per inch
thickness.
Ease of Installation
Labor intensive, requires
scaffolding and all work is
done from the exterior.
Panels are placed by crane,
and insulation is done from the
inside.
Water Tightness
Entirely dependent on the
quality of the installation.
Water tightness can be
achieved through sealants and
is very effective.
![Page 4: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/4.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
23
Time of Installation
In this case, 115 days, and
requires steel construction to
be completed before it can
begin.
Can be placed at a rate of 12
panels per day. Does not
require steel structure to be
complete to hang panels on
lower levels.
Maintenance Can be very costly, and is also
labor intensive.
Little to no maintenance
required.
Durability
EIFS has only been around for
35 years, no guarantee it can
last for the typical life of a
university building. Also only
comes with a 5 year warranty,
10 year was purchased for this
project.
Extremely durable, can easily
last 100 years under normal
weather conditions.
Fire Resistance Tested for fire resistance, but
materials are still combustible.
Concrete is noncombustible.
Quality Control
Left up to field installation.
Must be installed 100% per
specifications or water
penetration becomes a serious
issue.
All Panels are made in the
factory in a quality-controlled
environment.
Proposed Solution:
Through the use of a precast panel façade, I hope to show that it would be a
higher quality building that will last as long as the building will be expected to.
Precast concrete is an extremely durable material, withstands all types of
weather, and will be able to protect a building for 100 years. There are many
other advantages that precast has over EIFS. EIFS is a labor intensive system
to install. It requires scaffolding which increases the time it takes to install. Not
only does the scaffolding make the installation time longer, but the fact that the
steel erection must be completed before the EIFS can be installed. The
foundation center was erected in two sequences. After sequence A was
complete, the EIFS started installation there while the crane erected sequence B
(see Figure 7 on the following page).
Table 4: Comparison between EIFS and Precast Panels
![Page 5: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/5.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
24
The entire steel sequence was approximately 85 days, 40 for the first sequence,
and 45 for the second. The entire EIFS installation took a total of 115 days. This
is 115 days after the first steel sequence was completed (see Figure 8 on the
next page). Please refer to the schedule on the next page. The exterior skin
installation lasted from October through March, so the building was exposed for
the entire winter. If precast were being installed, there is no need for the steel
structure to be complete for panels to be hung. There are a few opportunities to
save schedule time here. First, a smaller crane could be used to hang panels on
the lower levels of the building until it is out of reach, at which time the tower
crane could take over placing panels. Second, the tower crane could set steel in
the morning and panels in the evening. Either way, the building would be
enclosed much sooner than in the case of the EIFS. It would likely be enclosed
by the end of the year, being that there is no wait for the structure to be
complete, and the precast would be insulated from the inside (see Table 5).
EIFS Precast Panels
115 Days 60 Days – 35, 25
Sequence A: 9/6/2004 – 10/22/2005 10/11/2004 – 3/18/2005
Sequence B: 10/25/2004 – 11/26/2004
Figure 7: Steel erection and building skin sequence
Table 5: EIFS and Precast Panel schedule comparison
![Page 6: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/6.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
25
Figure 8: Detailed schedule of structural steel and EIFS construction sequences
![Page 7: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/7.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
26
Cost:
Now to speak of the downsides of precast; its cost, weight, and insulation value.
For the cost comparison, Table 6 shows the difference between the systems:
Material Quantity Unit Unit Cost Total Cost
EIFS façade 57000 sf $9.73 $554,610.00
Architectural Preacast 57000 sf $40.00 $2,280,000.00
This is a substantial increase in cost. Not only does the material itself cost more
than the EIFS, but precast also requires additional framing and insulation. I have
added the rough cost of the framing and insulation into the per square foot cost
of the precast panels.
Insulation:
For insulation, the precast system will use R-19 batt insulation. This will have a
U-value around 0.05 vs. 0.04 for the EIFS system. To increase the efficiency of
the precast system, a thicker insulation could be used, such as R-22. This is an
important aspect of the façade because of its direct affect on heating and cooling
costs.
Structural Analysis:
Lastly, I will discuss the weight issue. The architectural precast panels I have
proposed to use are a solid 5” panel, made of normal weight concrete, and
weighing 62.5 lb/sf. I analyzed a column on the NW (rear) elevation (see
highlighted section in Figure 9 below).
Table 6: EIFS and Precast Panel cost comparison
Figure 9: NW (Rear) Elevation with the analyzed column and surrounding precast panels highlighted
![Page 8: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/8.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
27
The panel connections are column bearing, so the spandrel beams do not
require testing. I calculated the loads from the floor deck, beams and girders,
façade, and roof that are carried by that column. The specifications state that the
combined dead and live load carried to the columns from the floor deck is
225lb/sf. The composite deck is 3” 18 gage with 6-¼” lightweight structural
concrete and wwf 6x6 w1.4xw1.4. Using this information, I drew a model in the
structural program RAM Advanse, and applied the loads I calculated at each floor
level (see Table 7). I drew the column, defined the steel type and section sizes,
and then analyzed it. After analyzing, I ran the check for code compliance, and
the column was labeled ‘OK’ under the applied load scenario. Screenshots from
this analysis, as well as analysis reports can be found in the appendix of this
document. Figure 10 (on the following page) shows the column, beams, and
girders that were involved. Note that the column was spliced between the 3rd
and 4th levels, as the drawing is not clear in showing this.
Floor Level Load Type Loads Unit Total
Load
Roof 17.5
Façade 17.0 kip Lower Roof
Members 1.9
19.4
Slab 105.0
Façade 15.7 kip Level 5
Members 2.1
17.8
Slab 105.0
Façade 19.0 kip Level 4
Members 1.9
1.9
Slab 105.0
Façade 21.8 kip Level 3
Members 2.4
24.2
Slab 105.0
Façade 0.0 kip Level 2
Members 1.9
1.9
Table 7: Summary of loads from each level of the building transferred to the analyzed column
![Page 9: Analysis II – Façade Redesign: Architectural Precast Panels Be Posted/V Analysis II.pdf · installation lasted from October through March, so the building was exposed for the entire](https://reader030.vdocuments.us/reader030/viewer/2022033122/5e010a93011d7e40ed440190/html5/thumbnails/9.jpg)
Shawn Sambol Construction Management Goizueta Foundation Center for Research and Doctoral Education Emory University, Atlanta, GA
28
The column I selected to analyze was the smallest in the rear elevation that was
under the typical load I determined. Being that it was successful under the
additional load of the precast, the remainder of the exterior columns would be as
well.
Conclusions:
This analysis has brought to light the shortcomings of an EIFS façade and the
benefits of using precast panels. After comparing all the important factors that
are a part of façade selection, I feel that the precast panels would be a much
smarter choice for this building. The main reasons being that it is a university
building that will be standing and in use for the next 100 years, and precast is
more than capable of protecting a building for this amount of time. The additional
cost is a substantial increase, but to avoid repair and maintenance costs that will
come in due time with EIFS, it will be a very wise decision to pay the greater
initial cost.
W14x99
W14x99
W14x99
W14x61
W14x61
W21x68
W21x44
W21x44
W18x35
W21x44
W21x44
W21x44
W21x44
W18x35
W24x55
W24x55
W21x44
W24x55
W24x6815’-6”
18’-6”
16’
13’
14’
Level 2
Level 3
Level 4
Level 5
Lower Roof
Figure 10: Diagram of the analyzed column, with beams, girders, and floor heights shown