2019 Street Improvement ProjectNeighborhood Meeting

February 7. 2019

1

Agenda

2

- Update on Feasibility Report

- Project Overview

- Project Schedule

Project Location

- Birchwood Road

- Lost Lake Court

3

Background

- Feasibility Ordered by City Council December 4, 2018

- Birchwood Road

- Lake Links Trail Project affects the design of Birchwood Road

- Deteriorating & aging watermain along Birchwood Road

- Portion of sanitary sewer needs to be replaced

- High water table

- Lost Lake Court

- Deteriorating pavement conditions

- Feasibility Presentation Before City Council on March 5, 2019

4

Birchwood Road

- Watermain & service line replacements

- Sanitary sewer replacement near intersection of Birchwood Road and

Wildwood Beach Road.

- City will repair/reline remaining sanitary sewer as part of sewer lining

project in 2020.

- Surface reconstruction

- Bituminous surfacing with concrete curb & gutter

- Travel lanes reduced to 10 feet to accommodate Lake Links Trail

- Parking restricted on both sides

5

Proposed Improvements – Birchwood Road

Lost Lake Court

- Surface reconstruction

- Bituminous surfacing with concrete curb & gutter in place of existing

bituminous curb

- Minor storm sewer adjustments

6

Proposed Improvements – Lost Lake Court

7

8

9

Wood Fence for Lake Links Trail

10

Proposed Improvements

Construction

- Access to driveways and Birchwood Road will be restricted

- Expect detours during the day

- Road and driveway access will be restored at end of day

- Working hours are 7:00 AM to 7:00 PM Monday – Friday, 8:00 AM to 5:00

PM Saturday (if needed)

- The City will communicate with periodic newsletters and door hangers

- Neighborhood Meeting prior to construction

11

Special Assessments

12

Special Assessment Policy

Special Assessments are Proposed for Properties Receiving Benefit from Improvements

Surface Improvements

- Unit rate for single family homes & duplexes

- Front foot for commercial, industrial, tax-exempt and multi-family residential

13

Special Assessments: Surface Improvements Only

Single Family/Duplex Assessment

- Complete Roadway Reconstruction: $6,850/Unit

- Partial Roadway Reconstruction: $4,450/Unit

- May be paid up front or assessed with property taxes over 10 years

- Interest rate TBD at time of bond sale

- Senior citizen/disabled persons deferral available

14

Special Assessments

- Lots adjacent to streets receiving

improvements are proposed to be assessed

- Single Family/Duplex (Per Unit)

- Complete Reconstruction:

$6,850/Unit

- Partial Reconstruction:

$4,450/Unit

15

1 unit

Street A

1/2 unit

1/2

un

it

Street X

Stre

et Y

Special Assessments (cont.)

- Assessments will be considered at a separate hearing following construction.

- Assessments:

- May be prepaid or

- Levied over 10-year period to property taxes

- Deferment options are available for property owners age 65+ and on fixed

income

16

Project Schedule

17

Project Schedule

18

Action Date

Authorize Feasibility Report December 4, 2018

Neighborhood Meeting February 7, 2019

Accept Feasibility Report March 5, 2019

Public Hearing & Order Project- Time to voice concerns about the project to the City

Council

April, 2019

Construction Summer/Fall 2019 or Spring 2020

Assessment Hearing Following Construction

THANK YOU