80th REPORT ON MEGA PROJECTS
(Rs. 1000 Crore and above) January 2016
Koteshwar HEP
Government of India Ministry of Statistics and Programme Implementation
Infrastructure and Project Monitoring Division Sardar Patel Bhavan, Sansad Marg
New Delhi-110001 Website: www.cspm.gov.in
Abbreviations used in the report AAI Airport Authority of India Ltd. AERB Atomic Energy Regulatory Board AIBP Accelerated Irrigation Benefit Programme AIR All India Radio APW Active Process Water ATU Atomic Treating Unit BCM Billion Cubic Meter BHEL Bharat Heavy Electricals Ltd. BHPV Bharat Heavy Plates & Vessel Ltd. BLU Boiler Light Up BOLT Build , Operate, Lease & Transfer BPST Bureau of Parliamentary Studies & Training CCEA Cabinet Committee on Economic Affairs CCU Catalytic Cracking Unit CDS Crude Distribution System CDU Crude Distillation Unit CEA Central Electricity Authority CEC Central Empowered Committee CHP Coal Handling Plant CLW Chittaranjan Locomotive Works CMPDI Central Mine Planning & Design Institute COS Committee of Secretaries COR Cost Overrun CPP Captive Power Plant CRIS Centre for Railway Information System CRL Cochin Refinery Ltd. CSL Cochin Shipyard Ltd. CTU Crude Topping Unit DAE Department of Atomic Energy DB Dumb Barges DCME Digital Circuit Multiplexiing Equipment DGMS Director General Mines Safety DHDS Diesel Hydro Desulphurisation project DOA Date of Approval DOC Date of Commissioning DOT Department of Telecommunication DVC Damodar Valley Corporation ECL Eastern Coalfields Ltd. EIL Engineers India Ltd. EMP Enivronment Management Plan EOT Electrical Overhead Travelling crane ESP Electrostatic Precipitator FCCU Fluidised Catalytic Cracker Unit ERP Enterprise Resource Planning FE Foreign Exchange FOIS Freight Operation Information System FPU Feed Preparation Unit GAIL Gas Authority of India Ltd. GC Gauge Conversion GDS Gateway Digital Switch GIS Gas Insulated Station GT Gas Turbine GTPP Gas Turbine Power Plant HCU Hydro- cracker Unit HEC Heavy Engineering Corporation HEMM Heavy Equipment & Mining Machinery HEP Hydro Electric Project HPCL Hindustan Petroleum Corporation Ltd. HRT Head Race Tunnel HSCL Hindustan Steel Construction Ltd. HVDC High Voltage Direct Current IAAI International Airport Authority of India ICT Inter Connecting Transformer IDC Interest During construction IFFCO Indian Farmer Fertilizer Co-operative Ltd. IMG Inter Ministrial Group IOC Indian Oil Corporation Ltd. IPCL Indian Petrochemicals Ltd. KV Kilo Volts. L&T Larsen & Toubro
LEP Life Extension Program LOI Letter of Intent LPG Liquified Petroleum Gas LSTK Lump sum Turnkey contract MAMC Minning & Allied Machinery Corporation. MFL Madras Fertilizer Ltd. MGCL Madras Gas Cracker Complex MIS Management Information System MMSCMD Million Metric Standard Cubic Meter day MMT Million Metric Tonnes MOE&F Ministry of Environment & Forest MT Metric Tonnes MTY Metric Tonne per year MU Million Unit MW Mega Watts NAC New Anticipated Cost NALCO National Aluminium Company NBCC National Building Construction Corporation. NCL Northern Coalfields Ltd NEC North East Council NEEPCO North-Eastern Electric Power Corporation Ltd. NFL National Fertilizer Ltd. NH National Highway NHPC National Hydro-Electric Power Corporation NIRE National Institute of Renewable Energy NIT Notice Inviting Tender NJPC Nathpa Jhakri Power Corporation Ltd. NGN Next Generation Network NLC Neyveli Lignite Corporation Ltd. NMDC National Mineral Development Corporation Ltd. NPC Nuclear Power Corporation Ltd. NRL Numaligarh Refinery Ltd. OB Over Burden OC Opencast OECF Overseas Economic Co-operation Fund ONGC Oil & Natural Gas Commission OPGC Orissa Power Generation Corporation P & M Plant & Machinery PERT Project Evaluation & Review Technique PSTN Public Switched Telephone Network PHT Primary Heat Transport PIB Public Investment Board PSLW Powered Support Longwall QRC Quick Roll Changer RAPP Rajasthan Atomic Power Plant RCE Revised Cost Estimates RCF Railway Coach Factory ROB Road Over Bridge ROH Regular Overhauling RTU Remote Terminal Unit SAIL Steel Authority of India Ltd. SCI Shipping Corporation of India Ltd. SDH Synchronous Digital Hierarchy SG Steam Generator SP Self Propelled ST Steam Turbine STPS Super Thermal Power Station SUR Sulphur Recovery Unit SWSU Sour Water Stripping Unit TBM Tunnel Boring Machine TG Turbo Generator TPA Tonnes Per Annum TPS Thermal Power Station TOR Time Overrun TPY Tonnes per year UG Under Ground ULDCS Unified Load Despatch & Communication Scheme VDU Vaccum Distillation Unit WHRB Waste Heat Recovery Boiler WO_DOC With out Date of Commissioning WO_ODC With out original Date of Commissioning
EXECUTIVE SUMMARY
The Flash Report on Mega Projects costing 1000 crore and above for the month of
January 2016 contains information on the status of the 279 Central Sector Infrastructure Projects.
During January 2016, 2 projects (1 project each in Power and Urban Development sectors) have
reported completion.
2. During the reference month, out of 279 projects, 133 projects are delayed with respect to
original schedule and 13 projects have reported additional delay vis-à-vis the date of completion
reported in the previous month. The additional delay is in the range of 1 to19 months in respect of
projects relating to Atomic Energy, Petroleum and Power sectors.
S.l. No.
Sector Projects on Monitor
Delayed Projects w.r.t.
original schedule
Additionally delayed during the
month under report
1 RAILWAYS 85 21 0 2 POWER 63 41 7 3 ROAD TRANSPORT AND
HIGHWAYS 61 33 0
4 PETROLEUM 29 16 4 5 COAL 15 7 0 6 URBAN DEVELOPMENT 9 4 0 7 STEEL 7 3 0 8 ATOMIC ENERGY 4 4 2 9 TELECOMMUNICATIONS 2 2 0 10 MINES 1 1 0 11 PETROCHEMICALS 1 0 0 12 HEAVY INDUSTRY 1 1 0 13 SHIPPING AND PORTS 1 0 0 Total 279 133 13
3. The total original cost of the 279 projects was about 8,64,705.66 crore and latest reported
anticipated completion cost is 1,054,852.17 crore, which reflects an overall cost overrun of
1,90,146.51 crore (21.99% of the original cost), while during the last month, the overall cost
overrun for 277 projects was 1,85,478.53 crore (21.69 % of the original cost). The expenditure
incurred on these projects till January 2016 is 454,705.43 crore. Out of 279 projects, 100 projects
have cost overruns with respect to original cost. Cost overruns of these 100 projects is 93.28%
while during the last month, it was 91.49% in 99 projects out of 277 projects. In comparison with
the last month, the number of projects reporting cost overruns increases from 35.74% to 35.84%.
The sector wise list of projects (maximum five in numbers) having maximum percentage of cost
overruns is as below:-
SECTOR WISE LIST OF PROJECTS (MAXIMUM FIVE IN NUMBERS) HAVING MAXIMUM PERCENTAGE OF COST OVERRUNS (as on 31-01-2016)
SN PROJECT DATE OF
APPROVAL (month/year)
COST ORIGINAL
(Rs.in crore)
COST ANTICIPATED (Rs. In crore)
COST OVERRUNS
(%)
ATOMIC ENERGY 1 KUDANKULAM APP (NPCIL) 12/2001 13171.00 22462.00 70.542 PROTOTYPE FAST BREEDER
REACTOR (BHAVINI, 500 MWE) 09/2003 3492.00 5677.00 62.57
COAL 1 ADRIYALA SHAFT PROJECT 12/2009 212.34 1228.39 478.50 HEAVY INDUSTRY 1 NATIONAL AUTOMOTIVE TESTING
AND RD INFRASTRUCTURE PROJECT (NATRIP)
04/2011 1718.00 3827.30 122.78
PETROCHEMICALS 1 ASSAM GAS CRACKER PROJECT 04/2006 5460.61 9965.00 82.49 PETROLEUM 1 STRATEGIC CRUDE OIL STORAGE
PROJECT AT PADUR 01/2006 993.00 1693.00 70.49
2 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE
01/2006 732.00 1227.00 67.62
3 CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS)
03/2011 861.79 1256.72 45.83
4 UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE
09/2012 871.35 1200.00 37.72
5 INTEGRATED DEVELOPMENT OF B-127 FIELDS
12/2011 2059.63 2665.65 29.42
POWER 1 TUIRIAL HYDRO ELECTRIC PROJECT
(60MW) 07/1998 368.72 1381.71 274.73
2 SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC)
09/2003 6285.33 18063.89 187.40
3 KAMENG HYDROELECTRIC PROJECT (NEEPCO)
12/2004 2496.90 6085.84 143.74
4 TRIPURA GAS BASED POWER PROJECT
07/2009 421.01 1007.57 139.32
5 RAGHUNATHPUR THERMAL POWER STATION PHASE-I
04/2007 4122.00 9606.82 133.06
RAILWAYS 1 NEW BG RLY LINE FROM EKLAKHI-
BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR
04/1983 36.80 1336.57 3531.98
2 BANKURA - DAMODAR (GC) (SER) 03/1998 111.90 2371.85 2019.623 LALITPUR-SATNA-REWA-SINGRULI
NL, (NCR) 09/1998 247.66 3500.00 1313.23
4 AKOLA-KHANDWA GC AKOLA-AKOT 04/2008 184.26 2000.00 985.425 BANGLORE - SATYAMANGALAM
(NL)(SWR) 04/1996 138.00 1382.78 902.01
ROAD TRANSPORT AND HIGHWAYS1 PANIPAT-JALANDHAR 6 LANE(KM 96
TO 387.1 KM)
05/2009 1108.00 2288.00 106.50
STEEL 1 CONSTRUCTION OF MEDICAL
COLLEGE AND HOSPITAL AT GULBARGA
05/2005 768.88 1060.00 37.86
URBAN DEVELOPMENT 1 BANGALORE METRO RAIL PROJECT 05/2006 6395.00 13845.01 116.50
N.B.: The Chief Executive of the Project Implementing Agency, the Secretary and the Financial
Advisor of the concerned administrative Ministry may like to take a special review of these Projects in order to avoid further cost overruns.
4. The sector wise list of projects (maximum five in numbers) having maximum cost overruns in absolute term is as below:-
SECTOR WISE LIST OF PROJECTS (MAXIMUM FIVE IN NUMBERS) HAVING MAXIMUM COST OVERRUNS (as on 31-01-2016)
SN PROJECT DATE OF
APPROVAL (month/year)
COST ORIGINAL
(Rs.in crore)
COST ANTICIPATED (Rs. in crore)
COST OVERRUNS
(Rs in crore)
ATOMIC ENERGY 1 KUDANKULAM APP (NPCIL) 12/2001 13171.00 22462.00 9291.002 PROTOTYPE FAST BREEDER
REACTOR (BHAVINI, 500 MWE) 09/2003 3492.00 5677.00 2185.00
COAL 1 ADRIYALA SHAFT PROJECT 12/2009 212.34 1228.39 1016.05 HEAVY INDUSTRY 1 NATIONAL AUTOMOTIVE TESTING
AND RD INFRASTRUCTURE PROJECT (NATRIP)
04/2011 1718.00 3827.30 2109.30
PETROCHEMICALS 1 ASSAM GAS CRACKER PROJECT 04/2006 5460.61 9965.00 4504.39 PETROLEUM 1 PARADIP REFINERY PROJECT 02/2009 29777.00 34555.00 4778.002 INTEGRATED REFINERY EXPANSION
PROJECT 03/2012 14225.00 16504.00 2279.00
3 INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS
05/2013 4124.35 4941.49 817.14
4 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR
01/2006 993.00 1693.00 700.00
5 INTEGRATED DEVELOPMENT OF B-127 FIELDS
12/2011 2059.63 2665.65 606.02
POWER 1 SUBANSIRI LOWER H.E.P (8X250 MW)
(NHPC) 09/2003 6285.33 18063.89 11778.56
2 BARH STPP(3X660MW) NTPC 02/2005 8692.97 15095.67 6402.703 RAGHUNATHPUR THERMAL POWER
STATION PHASE-I 04/2007 4122.00 9606.82 5484.82
4 PARBATI HEP (4X200 MW) (NHPC) II 09/2002 3919.59 8398.76 4479.175 KAMENG HYDROELECTRIC PROJECT
(NEEPCO) 12/2004 2496.90 6085.84 3588.94
RAILWAYS 1 UDHAMPUR-SRINAGAR-BARAMULLA
(NL),NR 03/1995 2500.00 20000.00 17500.00
2 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR)
04/2003 727.56 6570.75 5843.19
3 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT
04/1996 1676.31 5500.00 3823.69
4 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR
09/1997 1500.00 4996.19 3496.19
5 LALITPUR-SATNA-REWA-SINGRULI NL, (NCR)
09/1998 247.66 3500.00 3252.34
ROAD TRANSPORT AND HIGHWAYS1 PANIPAT-JALANDHAR 6 LANE(KM 96
TO 387.1 KM) 05/2009 1108.00 2288.00 1180.00
STEEL 1 CONSTRUCTION OF MEDICAL
COLLEGE AND HOSPITAL AT GULBARGA
05/2005 768.88 1060.00 291.12
URBAN DEVELOPMENT 1 BANGALORE METRO RAIL PROJECT 05/2006 6395.00 13845.01 7450.01
N.B.: The Chief Executive of the Project Implementing Agency, the Secretary and the Financial
Advisor of the concerned administrative Ministry may like to take a special review of these Projects in order to avoid further cost overruns.
5. Out of the 279 projects, 2 projects are ahead of schedule, 57 projects are on schedule and
133 projects are delayed, with respect to original schedule. However, the number of delayed
projects decreases to 114 if delay is calculated on the basis of latest schedule of completion.
Further, 13 projects have been sanctioned without original date of commissioning and for 74
projects, neither the year of commissioning nor the tentative gestation period of the projects have
been reported but subsequently the dates of completion have been finalized in some cases. Out of
133 delayed projects, 24 projects have overall delay in the range of 1 to 12 months, 24 projects
have delay in the range of 13 to 24 months, 59 projects have delay in the range of 25 to 60 months
and 26 projects have delay of 61 months and above. The sector wise list of projects (maximum
five in numbers) having maximum time overruns is as below:-
SECTOR WISE LIST OF PROJECTS (MAXIMUM FIVE IN NUMBERS) HAVING MAXIMUM TIME OVERRUNS (as on 31-01-2016)
SN PROJECT DATE OF APPROVAL (month/year)
ORIGINAL DATE OF
COMMISSIONING (month/year)
ANTICIPATED DATE OF
COMMISSIONING (month/year)
TIME OVERRUNS (MONTHS)
ATOMIC ENERGY 1 KUDANKULAM APP (NPCIL) 12/2001 12/2008 05/2016 89 2 PROTOTYPE FAST BREEDER
REACTOR (BHAVINI, 500 MWE) 09/2003 09/2010 09/2016 72
3 RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW)
10/2009 12/2016 12/2019 36
4 KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4
10/2009 12/2015 11/2018 35
COAL 1 EXPANSION OF MINE-I (LEASE
AREA) AND MINE-I A (3.0 TO 7.0 MTPA)
04/2013 06/2015 08/2019 50
2 MOONIDIH XV SEAM UG 08/2011 04/2015 04/2019 48 3 ADRIYALA SHAFT PROJECT 12/2009 03/2013 03/2016 36 4 NEYVELI NEW THERMAL POWER
PROJECT(2X500 MW) 06/2011 12/2015 04/2018 28
5 GEVRA EXPANSION OCP (SECL) (25-35) MTY
06/2010 03/2014 03/2016 24
HEAVY INDUSTRY
1 NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP)
04/2011 09/2011 12/2017 75
MINES 1 EXPANSION OF MALANJKHAND
MINE-DEVELOPMENT OF UNDERGROUND MINE UNDER EXISTING OPEN CAST MINE OF CAPAC
09/2011 09/2017 04/2020 31
PETROCHEMICALS 1 ASSAM GAS CRACKER PROJECT 04/2006 04/2012 12/2015 44 PETROLEUM 1 PHUPLUR-HALDIA PIPELINE
PROJECT PHASE-I 07/2009 01/2013 12/2018 71
2 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE
01/2006 10/2011 03/2016 53
3 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR
01/2006 01/2012 05/2016 52
4 ASSAM RENEWAL PROJECT FOR GROUP A
03/2009 03/2013 03/2017 48
5 PARADIP-RAIPUR- RANCHI PIPELINE
08/2009 09/2012 05/2016 44
POWER 1 TUIRIAL HYDRO ELECTRIC
PROJECT (60MW) 07/1998 07/2006 10/2016 123
2 PARBATI HEP (4X200 MW) (NHPC) II
09/2002 09/2009 12/2018 111
3 KUNADANKULAM APP TRANS SYSTEM (PGCIL)
05/2005 11/2008 12/2016 97
4 BARH STPP(3X660MW) NTPC 02/2005 01/2011 05/2018 88 5 TEESTA LOW DAM HEP, STAGE-IV
(4X40 MW) (NHPC) 09/2005 09/2009 09/2016 84
RAILWAYS 1 GONDIA-JABALPUR(GC),(SECR) 02/1997 03/1998 12/2019 261 2 UDHAMPUR-SRINAGAR-
BARAMULLA (NL),NR 03/1995 11/2002 12/2017 181
3 BANKURA - DAMODAR (GC) (SER) 03/1998 03/2005 12/2019 177 4 TAMLUK DIGHA,LINE DOUBLING
(SER) 03/1984 06/2005 12/2019 174
5 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)
03/1996 03/2004 03/2016 144
ROAD TRANSPORT AND HIGHWAYS 1 PANIPAT-JALANDHAR 6 LANE(KM
96 TO 387.1 KM) 05/2009 11/2011 06/2016 55
2 GURGAON - KOTPUTLI - JAIPUR (SIX LANE)
02/2008 10/2011 01/2016 51
3 FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASS
04/2010 06/2012 08/2016 50
4 PUNE-SATARA(NH-4) 10/2010 03/2013 12/2016 45 5 GUJARAT/MAHARASHTRA
BORDERSURAT-HAZIRA PORT SECTION
03/2010 09/2012 02/2016 41
STEEL 1 EXPANSION OF BHILAI STEEL
PLANT 08/2010 03/2013 06/2016 39
2 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA
05/2005 02/2014 03/2016 25
3 NMDC INTEGRATED STEEL PLANT 01/2010 05/2015 12/2016 19 TELECOMMUNICATIONS 1 NETWORK FOR SPECTRUM (NFS)
OFC LAYING PROJECT, PACKAGE F AND G, A PART OF INTELLIGENT FIBER OPTIC C
09/2014 09/2014 03/2017 30
2 NETWORK FOR SPECTRUM
03/2012 07/2015 03/2017 20
URBAN DEVELOPMENT
1 BANGALORE METRO RAIL PROJECT
05/2006 06/2011 06/2016 60
2 BANGALORE METRO RAIL PROJECT PHASE-2
02/2014 02/2019 03/2020 13
3 MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ)
07/2013 01/2015 12/2015 11
4 DELHI MRTS PHASE-III 09/2011 03/2016 12/2016 9 5 CHENNAI METRO RAIL LTD
(PHASE 1) 02/2009 12/2015 08/2016 8
N.B.: The Chief Executive of the Project Implementing Agency, the Secretary and the Financial Advisor of the concerned administrative Ministry may like to take a special review of these Projects in order to avoid further time overruns.
6. Brief reasons for time overruns as reported by various project implementing agencies are
delay in land acquisition, delay in forest clearance, delay in supply of equipments, fund
constraints, geological surprises, problems in equipment erection, geo-mining conditions, slow
progress in civil works, shortage of labour, inadequate mobilization by the contractor, maoist
problems, court cases, contractual issues, ROU/ROW problems, law and order situation, etc.
7. The Online Computerized Monitoring System (OCMS) of this Ministry envisages
monitoring of milestones drawn from the PERT Charts of the various infrastructure projects.
The project authorities have been regularly requested to enter the list of milestones for each
project, to facilitate better monitoring. However, not all the project agencies are
reporting/providing the list of milestones. The sector wise list of oldest projects (maximum five
in numbers) without milestones is as below:-
SECTOR WISE LIST OF OLDEST PROJECTS (MAXIMUM FIVE IN NUMBERS) WITHOUT MILESTONES (as on 31-01-2016)
SN
PROJECTS DATE OF APPROVAL
COST ORIGINAL (Rs. Crore)
COST ANTICIPATED (Rs. Crore)
CUMULATIVE EXPENDITURE (Rs. Crore)
ORIGINAL DATE OF COMMISSIONING
ANTICIPATED DATE OF COMMISSIONING
COAL 1 MADANNAGAR
OCP 10/2015 1875.32 1875.32 0.00 03/2024 03/2024
HEAVY INDUSTRY 1 NATIONAL
AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT
04/2011 1718.00 3827.30 0.00 09/2011 12/2017
MINES 1 EXPANSION OF
MALANJKHAND MINE-DEVELOPMENT OF UNDERGROUND MIN
09/2011 1856.00 1176.00 2.86 09/2017 04/2020
PETROLEUM
1 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE
01/2006 732.00 1227.00 1029.66 10/2011 03/2016
2 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR
01/2006 993.00 1693.00 1446.59 01/2012 05/2016
3 DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERY
03/2014 3076.00 3076.00 164.88 09/2017 12/2017
4 POLYPROPYLENE PLANT AT PARADIP REFINERY
03/2014 3150.00 3150.00 111.66 09/2017 09/2017
5 DAMAN DEVELOPMENT PROJECT
08/2014 6086.08 6086.08 586.87 05/2019 03/2020
POWER 1 SUBANSIRI
LOWER H.E.P (8X250 MW) (NHPC)
09/2003 6285.33 18063.89 7934.88 09/2010 N.A.
2 BTPS-A 08/2006 2313.00 4237.67 3088.00 12/2011 03/2016 3 RTPS PH-I 04/2007 4122.00 9606.82 1353.36 02/2011 01/2017 4 PAKAL DUL
HYDRO ELECTRIC PROJECT (1000 MW)
10/2014 8112.12 8112.12 115.70 04/2020 04/2020
5 INSTALLATION OF STATCOMS IN WESTERN REGION
03/2015 1071.24 1071.24 0.10 09/2017 09/2017
RAILWAYS 1 HOWRAH-AMTA-
CHAMPADANGA NL (SER)
04/1974 393.46 1026.00 181.48 03/2007 03/2015
2 NANGALDAM-TALWARA(NL),NR
03/1981 450.00 2100.00 391.95 07/2012 N.A.
3 NEW BG RLY LINE FROM EKLAKHI-BALURGHAT
04/1983 36.80 1336.57 255.55 N.A. 03/2019
4 TAMLUK DIGHA,LINE DOUBLING (SER)
03/1984 293.97 1428.00 466.36 06/2005 12/2019
5 KHURDA ROAD-BOLANGIR(NL)ECOR
04/1994 470.21 1995.25 355.02 N.A. N.A.
ROAD TRANSPORT AND HIGHWAYS 1 BAKHTIYARPUR
- MOKAMA 01/1991 1167.45 1167.45 0.00 N.A. N.A.
2 HOSPET - CHITRADURGA
01/1991 1388.00 1388.00 0.00 N.A. N.A.
3 GURGAON - KOTPUTLI - JAIPUR
02/2008 1673.70 1673.70 2434.74 10/2011 01/2016
4 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM)
05/2009 1108.00 2288.00 3570.55 11/2011 06/2016
5 MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE
04/2010 1170.52 1170.52 1578.80 06/2012 08/2016
KANOON AND NAGPUR
SHIPPING AND PORTS 1 SETHUSAMUDR
AM SHIP CHANNEL PROJECT
06/2005 2427.40 2427.40 837.90 10/2008 N.A.
STEEL 1 MEDICAL
COLLEGE AND HOSPITAL AT GULBARGA
05/2005 768.88 1060.00 1070.97 02/2014 N.A.
2 GUA ORE MINES 02/2014 4749.00 4749.00 2.61 09/2017 09/2017 3 NEW SINTER
PLANT AT BSL 03/2015 1034.01 1034.01 0.00 10/2017 10/2017
4 NEW HSM AT RSP
04/2015 3127.30 3127.30 232.80 04/2018 04/2018
5 MODERNISATION OF SMS-1 AT BSL
05/2015 1154.18 1154.18 27.45 12/2017 12/2017
TELECOMMUNICATIONS 1 NETWORK FOR
SPECTRUM 03/2012 13334.0
0 13334.00 1360.00 07/2015 03/2017
URBAN DEVELOPMENT 1 DEVELOPMENT
OF STATE HIGHWAYS IN THE STATE OF BIHAR UNDER RS
11/2006 2727.89 2727.89 0.00 03/2010 N.A.
2 DELHI MRTS PHASE-III
09/2011 38585.00
38585.00 19388.91 03/2016 12/2016
3 KOCHI METRO RAIL PROJECT
07/2012 5181.79 5181.79 2562.95 07/2017 06/2017
4 MUMBAI METRO LINE 3(COLABA-BANDRA-SEEPZ)
07/2013 23136.00
23136.00 0.00 01/2015 12/2015
5 ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MED
10/2013 1219.21 1219.21 0.00 07/2017 07/2017
N.B.: The Chief Executive of the Project Implementing Agency, the Secretary and the Financial
Advisor of the concerned administrative Ministry may like to take a special review of these Projects in order to firm-up milestones.
8. It has also been observed that project agencies are not reporting revised cost estimates and
commissioning schedule for many projects, which suggests that time/cost overruns figures are
under-reported. The sector wise list of oldest projects (maximum five in numbers) without revised
cost estimates is as below:
SECTOR WISE LIST OF OLDEST PROJECTS (MAXIMUM FIVE IN NUMBERS) WITHOUT REVISED
COST ESTIMATES (as on31-01-2016)
SN PROJECT DOA COST ORIGINAL (Rs. Crore)
COST REVISED (Rs. Crore)
CUMULATIVE EXPENDITURE (Rs. Crore)
ATOMIC ENERGY 1 KUDANKULAM APP (NPCIL) 12/2001 13171.00 17270.00 21077.002 PROTOTYPE FAST BREEDER REACTOR
(BHAVINI, 500 MWE) 09/2003 3492.00 0.00 5150.14
PETROCHEMICALS 1 ASSAM GAS CRACKER PROJECT 04/2006 5460.61 8920.00 9175.15 POWER 1 SUBANSIRI LOWER H.E.P (8X250 MW)
(NHPC) 09/2003 6285.33 0.00 7969.14
2 PARBATI HEP (4X200 MW) (NHPC) II 09/2002 3919.59 0.00 5398.463 KISHANGANGA HEP (3X110 MW) 01/2009 3642.04 0.00 4402.954 TRANSMISSION SYSTEM
STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARH
11/2011 2127.51 0.00 2319.63
5 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC)
09/2005 1061.38 0.00 1956.52
RAILWAYS 1 UDHAMPUR-SRINAGAR-BARAMULLA
(NL),NR 03/1995 2500.00 0.00 10722.72
2 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT
04/1996 1676.31 0.00 4769.59
3 TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP)
03/2000 1049.69 3385.14 3551.53
4 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) 04/2003 727.56 727.56 2787.995 PATNA GANGA BRIDGE (NL), ECR 04/2001 624.47 0.00 2521.72 ROAD TRANSPORT AND HIGHWAYS1 PANIPAT-JALANDHAR 6 LANE(KM 96 TO
387.1 KM) 05/2009 1108.00 0.00 3619.94
2 SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547
11/2011 1535.00 0.00 2478.63
3 MURADABAD-BAREILY 04/2010 1267.00 0.00 2425.004 6-LANING OF DHANKUNI-KHARAGPUR
SECTION 04/2012 1396.18 0.00 2287.44
5 2 LANING OF SHILLONG NONGSTOIN SECTION OF NH 44 AND NONGSTOIN TURA STATE ROAD UNDER PHASE A OF SARDP NE IN THE STATE OF MEGHALAYA
12/2010 1494.48 0.00 2090.00
STEEL 1 CONSTRUCTION OF MEDICAL COLLEGE
AND HOSPITAL AT GULBARGA 05/2005 768.88 1060.00 1070.97
URBAN DEVELOPMENT 1 BANGALORE METRO RAIL PROJECT 05/2006 6395.00 11609.00 13525.81
N.B.: The Chief Executive of the Project Implementing Agency, the Secretary and the Financial
Advisor of the concerned administrative Ministry may like to take a special review of these Projects in order to firm-up revised cost estimates.
9. The sector wise list of earliest projects (maximum five in numbers) without revised
commissioning schedule is as below:
SECTOR WISE LIST OF OLDEST PROJECTS (MAXIMUM FIVE IN NUMBERS) WITHOUT REVISED COMMISSIONING SCHEDULE (as on 31-01-2016)
SN SECTOR/ PROJECT DATE OF APPROVAL
ORIGINAL DATE OF COMMISSIONING
REVISED DATE OF COMMISSIONING
ANTICIPATED DATE OF COMMISSIONING
PETROCHEMICALS 1 ASSAM GAS CRACKER
PROJECT 04/2006 04/2012 12/2013 12/2015
PETROLEUM 1 KOCHI-KOOTANAD
BANGALORE MANGALORE PIPELINE PROJECT
06/2009 12/2012 N.A. 06/2015
2 PARADIP HYDERABAD PIPLEINE
01/2015 N.A. N.A. N.A.
3 AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPUR
01/2015 N.A. N.A. N.A.
POWER 1 SUBANSIRI LOWER H.E.P
(8X250 MW) (NHPC) 09/2003 09/2010 N.A. N.A.
RAILWAYS 1 HOWRAH-AMTA-
CHAMPADANGA NL (SER)
04/1974 03/2007 03/2007 03/2015
2 NANGALDAM-TALWARA(NL),NR
03/1981 07/2012 N.A. N.A.
3 KHURDA ROAD-BOLANGIR(NL)ECOR
04/1994 N.A. N.A. N.A.
4 HARIDASPUR-PARADEEP(NL)
04/1996 N.A. 09/2009 N.A.
5 BANGLORE - SATYAMANGALAM (NL)(SWR)
04/1996 N.A. N.A. N.A.
ROAD TRANSPORT AND HIGHWAYS1 FOUR LANING OF
BAKHTIYARPUR - MOKAMA SECTION OF NH-31
01/1991 N.A. N.A. N.A.
2 FOUR LANING OF HOSPET - CHITRADURGA
01/1991 N.A. N.A. N.A.
3 SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502
02/2009 08/2011 N.A. N.A.
4 NEW 4 LANE ELEVATED ROAD FROM CHENNAI AIRPORT-MADURAVOYAL NH NO.4
09/2010 09/2013 N.A. N.A.
5 2 LANING OF SHILLONG NONGSTOIN SECTION OF NH 44 AND NONGSTOIN TURA STATE ROAD UNDER PHASE A OF SARDP NE IN THE STATE OF MEGHALAYA
12/2010 02/2011 N.A. N.A.
SHIPPING AND PORTS 1 SETHUSAMUDRAM SHIP
CHANNEL PROJECT 06/2005 10/2008 N.A. N.A.
URBAN DEVELOPMENT 1 MUMBAI METRO LINE 3
(COLABA-BANDRA-SEEPZ) 07/2013 01/2015 N.A. 12/2015
N.B.: The Chief Executive of the Project Implementing Agency, the Secretary and the Financial Advisor of the concerned administrative Ministry may like to take a special review of these Projects in order to firm-up revised commissioning schedule.
10. The Sector-wise details of additionally delayed projects are as under:
(i) In the Atomic Energy Sector, All 4 projects are delayed. During the month 2
projects ‘Kakrapar Atomic Power Project - 3 and 4, NPCIL’ and ‘Rajasthan Atomic
Power Project -7 and 8 (2X700 MW), NPCIL’ have reported additional delay of 13
months and 19 months respectively due to delay in supply of major equipments and
slow progress in civil works respectively.
(ii) In the Petroleum Sector, out of 29 projects, 16 projects are delayed. During the
month, 4 projects have reported additional delay in the range of 1-10 months. The
project ‘Paradip Refinery Project, IOCL’ has reported additional delay of 1 month
due to delay in delivery of equipment; project ‘Paradip-Raipur- Ranchi Pipeline
IOCL’ has reported additional delay of 2 months due to poor performance of
contractor; Project ‘Resid Upgradation project CPCL’ has reported additional delay
of 4 months due to change in scope of work and project ‘Development of C-26
Cluster Fields, ONGC’ has reported additional delay of 10 months due to slow
progress by contractors.
(iii) In the Power Sector, out of 63 projects, 41 projects are delayed. During the month, 7
projects have reported additional delay in the range of 1-3 months. Three projects
‘Northern Region System Strengthening Scheme-XXI PGCIL’, ‘Transmission
System for Phase-I Generation Projects in Jharkhand and West Bengal-Part-A2,
PGCIL’ and ‘Transmission System Associated with Krishnapatnam UMPP-Part B
PGCIL’ have reported additional delay of 1 month each due to severe RoW problem,
delay in land acquisition and severe RoW problem respectively ; project ‘Eastern
Region Strengthening Scheme-V, PGCIL’ has reported additional delay of 2 months
due to delay in land acquisition and 3 projects ‘Teesta Low Dam HEP, Stage-IV
(4X40 MW), NHPC’, ‘Transmission System for Development of Pooling Station in
NR Part of West Bengal and Transfer of Power PGCIL’ and ‘Eastern Region
Strengthening Scheme-III PGCIL’ have reported additional delay of 3 months each
due to local disturbance, non-receiving of forest clearance and RoW problem
respectively.
11. Ministry of Railways has discontinued the practice of furnishing monthly status
reports on all its on-going (85) projects to this Ministry w.e.f 1st January 2015. The Ministry of
Railways have provided latest information of their 20 projects only which have been identified to
be monitored at MoSPI level. Therefore, the available information/data (as on January 2015) has
been used in respect of remaining projects of Railways sector.
12. Ministry of Road Transport & Highways (MoRTH) & National Highways
Authority of India (NHAI) had stopped providing data on their project w.e.f. June 2015.
However, MoRTH & NHAI have voluntarily resumed updating of all their on-going projects
from the month of February 2016 (Reporting month December 2015). Both MoRTH and NHAI
have added 27 new mega projects under Road sector. This Ministry is separately classifying
PPP/BOT projects as per information given by NHAI.
13. During January 2016, there are 126 projects which are showing time overruns of
more than 6 months and 99 projects which are having cost overruns of more than Rs. 100 crore.
48 projects are having both time overruns of more than 6 months and cost overruns of more than
Rs. 100 crore.
14. The status as on 31.01.2016 in respect of projects costing 1000 crore and above in the
various sectors is indicated in the Report.
15. This has the approval of Secretary, Ministry of Statistics and Programme
Implementation.
EXECUTIVE SUMMARY
Sl.No. Sector Projects on Monitor Projects Additionally
Delayed 1 RAILWAYS 85 0 2 POWER 63 7 3 ROAD TRANSPORT AND HIGHWAYS 61 0 4 PETROLEUM 29 4 5 COAL 15 0 6 URBAN DEVELOPMENT 9 0 7 STEEL 7 0 8 ATOMIC ENERGY 4 2 9 TELECOMMUNICATIONS 2 0 10 MINES 1 0 11 PETROCHEMICALS 1 0 12 HEAVY INDUSTRY 1 0 13 SHIPPING AND PORTS 1 0 Total 279 13
Sectoral break up of on-going infrastructure projects
Month wise List of Completed Projects Costing Rs. 1000 crore and above during
2015-2016
Sl. No Project Name Original Cost
(Rs. crore) Original Date of commissioning
Cumulative Expenditure (Rs. crore)
April,2015 ROAD TRANSPORT AND HIGHWAYS 1 PUNE-SHOLAPUR,PKG1
(NATIONAL HIGHWAYS AUTHORITY OF INDIA) - [N24000127] 1,110.00 05/2012 1,802.00
May,2015 PETROLEUM 2 DEVELOPMENT OF B-193 CLUSTER FIELDS
(OIL & NATURAL GAS CORPORATION LIMITED) - [N16000033] 3,248.78 08/2010 5,933.42
3 DEVELOPMENT OF CLUSTER-7 FIELDS (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000104]
4,550.40 03/2013 2,583.55
4 PIPELINE REPLACEMENT PROJECT-3 (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000137]
2,547.26 05/2014 1,412.08
POWER 5 IMMEDIATE EVACUATION SYSTEM WITH BARH-II TPS
(POWER GRID CORPORATION OF INDIA LIMITED) - [N18000127] 901.77 08/2014 945.20
June,2015 STEEL 6 EXPANSION OF DURGAPUR STEEL PLANT
(STEEL AUTHORITY OF INDIA LIMITED (SAIL)) - [N12000074] 2,875.00 12/2012 2,640.00
POWER 7 KOLDAM HEP (NTPC)
(NATIONAL THERMAL POWER CORPORATION) - [180100211] 4,527.15 04/2009 6,622.00
8 TRANSMISSION SYSTEM FOR IPP GENERATION PROJECTS IN MP AND CHATTISGARH (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000105]
1,366.34 12/2013 1,320.96
RAILWAYS 9 GONDA-GORAKHPUR LOOP WITH ANAND NAGAR-NAUTANWA GC
(NER) (NORTH EASTERN RAILWAY) - [220100255]
863.23 - 888.87
10 RANGIA-MURKONGSELEK, (GC) ALONG WITH LINKED FINGERS NEFR (NORTH EAST FRONTIER RAILWAY) - [220100315]
915.70 - 3,198.30
July,2015 PETROLEUM
Month wise List of Completed Projects Costing Rs. 1000 crore and above during
2015-2016
Sl. No Project Name Original Cost
(Rs. crore) Original Date of commissioning
Cumulative Expenditure (Rs. crore)
11 SURAT PARADIP PIPELINE PROJECT
(GAS AUTHORITY OF INDIA LIMITED) - [N16000163] 10,281.00 04/2015 1.49
POWER
12 SYSTEM STRENGTHENING-XVIII IN SOUTHERN REGION GRID (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000130]
1,263.26 11/2014 1,131.58
August,2015 COAL
13 TPS-II EXPANSION (1470MW TO 1970MW) (NLC) (NEYVELI LIGNITE CORPORATION) - [060100087]
2,030.78 06/2009 3,215.91
14 TUTICORIN THERMAL POWER PROJECT- 2X500 MW (NEYVELI LIGNITE CORPORATION) - [N06000047]
4,904.54 03/2012 6,426.43
PETROLEUM
15 DEVELOPMENT OF G1 AND GS-15 (ONGCL) (OIL & NATURAL GAS CORPORATION LIMITED) - [160100231]
429.82 04/2006 3,439.38
16 STRATEGIC CRUDE OIL STORAGE PROJECT AT VIZAG (INDIAN STRATEGIC PETROLEUM RESERVES LTD) - [N16000156]
672.00 10/2011 1,082.12
POWER
17 BARH STPP STAGE -II (NATIONAL THERMAL POWER CORPORATION) - [N18000047]
7,341.04 10/2013 8,962.00
18 TRANSMISSION SYSTEM OF VINDHUACHAL -IV AND RIHAND -III GEN. PROJ. (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000076]
4,672.99 11/2012 3,769.57
19 TRANSMISSION SYSTEM FOR PHASE-I GEN.PROJ.IN ORISSA PART-C (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000096]
2,569.25 03/2014 2,876.57
20 VINDHYACHAL STPP STAGE-V (NATIONAL THERMAL POWER CORPORATION) - [N18000134]
3,180.40 08/2015 2,042.00
September,2015 STEEL
21 EXPANSION OF BOKARO STEEL PLANT (STEEL AUTHORITY OF INDIA LIMITED (SAIL)) - [N12000055]
6,325.00 12/2011 5,256.65
PETROLEUM
22 HEERA AND SOUTH HEERA REDEVELOPMENT PH-II (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000132]
5,608.40 05/2015 4,457.47
POWER
23 INTER-REGIONAL SYSTEM STRENGTHENING SCHEME IN WR AND NR (PART-A) (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000154]
1,315.90 10/2016 632.97
Month wise List of Completed Projects Costing Rs. 1000 crore and above during
2015-2016
Sl. No Project Name Original Cost
(Rs. crore) Original Date of commissioning
Cumulative Expenditure (Rs. crore)
October,2015 STEEL
24 EXPANSION OF LIQUID STEEL CAPACITY FROM 3MT TO 6.3MT (RINL) (RASTRIYA ISPAT NIGAM LIMITED) - [120100067]
8,692.00 10/2009 11,483.12
POWER
25 KAIGA 3 AND 4 TRANSMISSION SYSTEM (PGCIL) (POWER GRID CORPORATION OF INDIA LIMITED) - [180100246]
588.25 12/2007 1,020.81
26 TRANSMISSION SYSTEM FOR PHASE-I GENERATION PROJECTS IN ORISSA-PART B (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000093]
2,743.19 12/2013 2,827.00
URBAN DEVELOPMENT
27 FARIDABAD EXTENSION (DELHI METRO RAIL CORPORATION LTD) - [N28000057]
2,494.00 09/2014 1,311.53
November,2015 POWER
28 SYSTEM STRENGTHENING - XVII IN SOUTHERN REGIONAL GRID (POWER GRID CORPORATION OF INDIA LIMITED) - [N16000144]
1,508.74 03/2015 1,211.48
December,2015 PETROLEUM
29 REPLACEMENT OF CDU/VDU AT MUMBAI REFINERY (BHARAT PETROLEUM CORPORATION LIMITED) - [N16000142]
1,419.00 12/2014 1,291.63
30 REWARI KANPUR PIPELINE PROJECT (HINDUSTAN PETROLEUM CORPORATION LIMITED) - [N16000145]
1,210.64 11/2015 1,249.03
January,2016 POWER
31 TRANSMISSION SYSTEM FOR PHASE-I GEN PROJECT IN ORISSA - PART-A (POWER GRID CORPORATION OF INDIA LIMITED) - [N18000087]
2,074.86 03/2013 1,975.94
URBAN DEVELOPMENT
32 DEVELOPMENT OF STATE HIGHWAYS IN THE STATE OF BIHAR UNDER RSVY PATNA (CENTRAL PUBLIC WORKS DEPARTMENT) - [N28000078]
2,727.89 03/2010 0.01
Month wise List of Deleted Projects Costing Rs.1000 crore and above during
2015-2016
Sl. No Project Name
Original Cost (Rs. crore)
Original Date of Commissioning
Cumulative Expenditure (Rs. crore)
May,2015 PETROLEUM 1 AHMEDABAD REDEVELOPMENT PROJECT
(OIL & NATURAL GAS CORPORATION LIMITED) - [N16000120] 1,916.10 12/2014 1,160.14
2 MEHESANA REDEVELOPMENT PROJECT (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000121]
3,823.00 04/2015 1,076.57
3 ANKLESWAR REDEVELOPMENT (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000122]
2,189.63 12/2014 1,034.30
4 INTEGRATED DEVELOPMENT OF BASSEIN FIELD (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000160]
3,513.07 02/2016 .47
5 REVAMP OF UNMANNED PLATFORMS PH-II IN MH AND NH ASSETS (OIL & NATURAL GAS CORPORATION LIMITED) - [N16000181]
2,913.10 05/2016 13.86
June,2015 TELECOMMUNICATIONS 6 EXECUTION OF TELECOM NETWORK REQUIREMENT OF DEFENCE
FORCES (BHARAT SANCHAR NIGAM LIMITED) - [N26000065]
1,077.00 03/2009 .00
December,2015 PETROLEUM 7 INTEGRATED DEVELOPMENT OF BASSEIN FIELD
(OIL & NATURAL GAS CORPORATION LIMITED) - [N16000160] 3,513.07 02/2016 667.40
SHIPPING AND PORTS 8 CONSTRUCTION AND DEVELOPMENT OF 2 OFFSHORE
CONTAINER BERTHS AND TERMINAL (MUMBAI PORT TRUST) - [N25000016]
1,228.00 12/2010 1,038.00
Project Status with respect to OriginalSchedule: Out of 279 projects, 2projects are ahead of schedule, 57projects are on schedule 133 projectsare delayed. 74 projects do not havefixed dates of commissioning.13projects were sanctioned without anycommissioning date but subsequentlydates of completion were finalised.
Brief Analysis
Project Implementation - Current Status:
Investment Scenario
Total original cost of implementationof 279 projects when sanctioned, was ofthe order of Rs. 864705.66 crore butthis was subsequently revised to Rs.1054852.17 crore implying a costoverrun of 22%. The expenditureincurred on these projects till January,2016 is Rs. 454705.43 crore, which is43.1% of the revised cost of theprojects.
Summary of projects in the for the month of January, 2016
Number of Projects in Previous Month
Number of Projects completed/dropped/frozen in Current Month
Number of Projects Added in Current Month
Number of Projects in Current Month
278
2
3
279
Mega Report
Projects Added / Completed / Dropped / Frozen
Project status
Number of Projects
With Respect To
Delayed Ahead On
schedule
Without ODC but DOC available
Without D.O.C Total
Delayed Projects
(%) Original ( Date ) 133 2 57 13 74 279 47.67 Latest Approved ( Date ) 114 3 75 13 74 279 40.86
*Including one revived project of Telecommunication sector.
No of Projects in Previous Month 278* No of Projects Completed/Dropped/Frozen in Current Month 2 No of Projects added in Current Month 3 No of Projects in Current Month 279
Project cost (All Cost/ Expenditure in Rs. crore )
Cost overrun
No. of Projects
Sanctioned Cost
Anticipated Cost
Expenditure Cost
% cost w.r.t anticipated cost
Rs crore %
Project with No Revision in Cost
213 6,57,363.53 7,39,581.00 2,75,788.92 37.30 82,217.47 12.50
Project with Revision in Cost
66 2,78,993.72 3,15,271.17 1,78,916.51 56.80 36,277.45 13.00
Total 279 9,36,357.25 10,54,852.17 4,54,705.43 43.11 118494.92 12.65 Original Cost of All Projects
Original Cost 279 8,64,705.66 10,54,852.17 4,54,705.43 43.11 1,90,146.51 21.99
Delayed Project cost (All Cost/ Expenditure in Rs. crore )
Cost overrun With Respect to
No. of Projects
Sanctioned Cost
Anticipated Cost
Expenditure Cost
% cost w.r.t anticipated cost
Rs crore %
Original (OCE) 133 496,896.41 615,875.49 358,676.80 58.20 118,979.08
23.90
Latest Approved (RCE)
114 444,479.76 505,818.60 318,890.30 63.00 61,338.84 13.80
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level. ^ - Cost Overrun = Anticipated Cost minus Original Cost.
Additional Delayed Project cost
(All Cost/ Expenditure in Rs. crore )
No. of Projects
Sanctioned Cost
Anticipated Cost Expenditure
% cost w.r.t anticipated cost
Cost overrun Rs crore %
13 75,182.19 81,091.89 59,249.69 73.06 5909.7 7.86
Extent of cost overrun in projects with respect to original schedule(Sector Wise)
(All Cost/ Expenditure in Rs. crore )
Projects with cost overrun^
SI.No Sector No. of Projects
Original Cost
Anticipated cost
Cost overrun
(%)
No. Original Cost
Anticipated Cost
Cost overrun (%)
1 ATOMIC ENERGY 4 40,442.00 51,918.00 28.38 2 16,663.00 28,139.00 68.87 2 COAL 15 34,396.21 35,203.76 2.35 1 212.34 1,228.39 478.50 3 MINES 1 1,856.00 1,176.00 -36.64 0 0.00 0.00 0.00 4 STEEL 7 43,623.37 43,914.49 0.67 1 768.88 1,060.00 37.86 5 PETROCHEMICALS 1 5,460.61 9,965.00 82.49 1 5,460.61 9,965.00 82.49 6 PETROLEUM 29 116,156.37 125,588.13 8.12 10 61,021.81 71,737.33 17.56 7 POWER 63 284,164.56 332,227.47 16.91 18 59,707.89 107,770.80 80.50 8 HEAVY INDUSTRY 1 1,718.00 3,827.30 122.78 1 1,718.00 3,827.30 122.78 9 RAILWAYS* 85 97,661.81 203,275.92 108.14 64 55,635.86 163,501.42 193.88
10 ROAD TRANSPORT AND HIGHWAYS
61 92,888.02 94,067.51 1.27 1 1,108.00 2,288.00 106.50
11 SHIPPING AND PORTS
1 2,427.40 2,427.40 0.00 0 0.00 0.00 0.00
12 TELECOMMUNICATIONS
2 15,445.17 15,345.17 -0.65 0 0.00 0.00 0.00
13 URBAN DEVELOPMENT
9 128,466.14 135,916.02 5.80 1 6,395.00 13,845.01 116.50
Total 279 864,705.66 1,054,852.17 21.99 100 208,691.39 403,362.25 93.28
Extent of cost overrun in projects with respect to original schedule(State Wise)
(All Cost/ Expenditure in Rs. crore
Projects with cost overrun
SI.No State No. of Projects
Original Cost
Anticipated Cost
Cost overrun
(%)
No. Original Cost
Anticipated Cost
Cost overrun (%)
1 ANDHRA PRADESH 5 6,267.19 6,984.19 11.44 1 330.00 1,047.00 217.27 2 ARUNACHAL
PRADESH 3 9,356.22 25,412.00 171.61 3 9,356.22 25,412.00 171.61
3 ASSAM 7 17,380.14 31,820.63 83.09 5 13,883.62 28,410.37 104.63 4 BIHAR 10 35,743.29 48,337.68 35.24 5 11,233.11 23,827.50 112.12 5 GUJARAT 7 20,429.57 20,639.57 1.03 1 1,671.22 1,881.22 12.57 6 HARYANA 3 4,629.72 5,809.72 25.49 1 1,108.00 2,288.00 106.50 7 HIMACHAL PRADESH 3 6,883.26 13,282.54 92.97 2 4,966.47 11,365.75 128.85 8 JAMMU AND
KASHMIR 9 25,620.25 45,229.68 76.54 2 6,142.04 25,751.47 319.27
9 KARNATAKA 15 59,406.87 74,654.84 25.67 9 10,765.53 26,013.63 141.64 10 KERALA 4 20,949.79 24,944.79 19.07 3 15,768.00 19,763.00 25.34 11 MADHYA PRADESH 13 33,201.08 34,603.14 4.22 3 1,457.75 3,748.31 157.13 12 MAHARASHTRA 23 93,265.27 101,851.15 9.21 7 15,437.31 24,824.69 60.81 13 MANIPUR 1 727.56 6,570.75 803.12 1 727.56 6,570.75 803.12 14 MEGHALAYA 2 5,577.50 6,802.38 21.96 1 4,083.02 5,307.90 30.00 15 MIZORAM 2 988.06 4,201.96 325.27 2 988.06 4,201.96 325.27 16 NAGALAND 3 6,420.00 8,757.12 36.40 2 5,124.00 7,461.12 45.61 17 ODISHA 12 58,045.77 66,685.00 14.88 5 31,411.35 40,050.58 27.50 18 RAJASTHAN 3 16,382.21 16,381.70 -0.00 0 0.00 0.00 0.00 19 SIKKIM 1 1,339.48 4,190.00 212.81 1 1,339.48 4,190.00 212.81 20 TAMIL NADU 17 55,625.65 70,343.00 26.46 7 20,602.42 35,319.77 71.44 21 TRIPURA 3 2,129.35 5,125.82 140.72 3 2,129.35 5,125.82 140.72 22 UTTAR PRADESH 13 32,985.23 36,304.05 10.06 3 1,839.23 5,158.05 180.45 23 WEST BENGAL 22 41,286.54 53,333.13 29.18 7 7,069.20 21,367.24 202.26 24 D & N HAVELI 1 6,086.08 6,086.08 0.00 0 0.00 0.00 0.00 25 DELHI 4 45,462.73 45,462.73 0.00 0 0.00 0.00 0.00 26 CHHATISGARH 15 79,254.78 80,053.87 1.01 2 2,573.22 3,372.31 31.05 27 JHARKHAND 7 27,804.25 29,728.92 6.92 1 2,313.00 4,237.67 83.21 28 UTTARAKHAND 4 8,654.06 10,843.74 25.30 2 4,635.48 6,825.16 47.24 29 TELANGANA 4 3,714.11 4,730.16 27.36 1 212.34 1,228.39 478.50 30 MULTI STATE 63 139,089.65 165,681.83 19.12 20 31,524.41 58,612.59 85.93
Total 279 864,705.66 1,054,852.17 21.99 100 208,691.39 403,362.25 93.28
^ - Cost Overrun = Anticipated Cost minus Original Cost.
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level. ^ - Cost Overrun = Anticipated Cost minus Original Cost. $- Time overrun = Anticipated Date of Commissioning minus Original Date of Commissioning
Extent of time overrun in projects with respect to original schedule
(All Cost/ Expenditure in Rs. crore) Projects with time overruns$
SI.No Sector No. of
Projects Original
Cost Anticipated
Cost
Cost Overrun
^ (%)
No.
Original Cost
Anticipated Cost
Range of T.O.R
(in months)
1 ATOMIC ENERGY 4 40,442.00 51,918.00 28.38 4 40,442.00 51,918.00 35 - 89 2 COAL 15 34,396.21 35,203.76 2.35 7 14,482.27 15,498.32 3 - 50 3 MINES 1 1,856.00 1,176.00 -36.64 1 1,856.00 1,176.00 31 - 31 4 STEEL 7 43,623.37 43,914.49 0.67 3 33,558.88 33,850.00 19 - 39 5 PETROCHEMICALS 1 5,460.61 9,965.00 82.49 0 0.00 0.00 - 6 PETROLEUM 29 116,156.37 125,588.13 8.12 16 66,605.88 74,243.36 3 - 71 7 POWER 63 284,164.56 332,227.47 16.91 41 152,827.93 189,112.28 2 - 123 8 HEAVY INDUSTRY 1 1,718.00 3,827.30 122.78 1 1,718.00 3,827.30 75 - 75 9 RAILWAYS* 85 97,661.81 203,275.92 108.14 21 33,793.41 86,108.82 3 - 261
10 ROAD TRANSPORT AND HIGHWAYS 61 92,888.02 94,067.51 1.27 33 50,181.73 51,361.22 2 - 55 11 SHIPPING AND PORTS 1 2,427.40 2,427.40 0.00 0 0.00 0.00 - 12 TELECOMMUNICATIONS 2 15,445.17 15,345.17 -0.65 2 15,445.17 15,345.17 20 - 30 13 URBAN DEVELOPMENT 9 128,466.14 135,916.02 5.80 4 85,985.14 93,435.02 8 - 60
Total 279 864,705.66 1,054,852.17 21.99 133 496,896.41 615,875.49
^ - Cost Overrun = Anticipated Cost minus Original Cost. $- Time overrun = Anticipated Date of Commissioning minus Original Date of Commissioning.
Extent of time overrun in projects with respect to original schedule(State Wise)
(All Cost/ Expenditure in Rs. crore) Projects with time overruns$
SI.No State No. of
Projects Original
Cost Anticipated
cost
Cost Overrun
^ (%)
No.
Original Cost
Anticipated Cost
Range of T.O.R
(in months)
1 ANDHRA PRADESH 5 6,267.19 6,984.19 11.44 2 3,120.00 3,120.00 25 - 39 2 ARUNACHAL PRADESH 3 9,356.22 25,412.00 171.61 2 3,070.89 7,348.11 35 - 78 3 ASSAM 7 17,380.14 31,820.63 83.09 5 10,888.16 20,824.26 17 - 110 4 BIHAR 10 35,743.29 48,337.68 35.24 5 19,443.98 29,199.97 38 - 88 5 GUJARAT 7 20,429.57 20,639.57 1.03 4 16,101.84 16,101.84 6 - 41 6 HARYANA 3 4,629.72 5,809.72 25.49 1 1,108.00 2,288.00 55 - 55 7 HIMACHAL PRADESH 3 6,883.26 13,282.54 92.97 1 3,919.59 8,398.76 111 - 111 8 JAMMU AND KASHMIR 9 25,620.25 45,229.68 76.54 6 13,202.50 32,811.93 10 - 181 9 KARNATAKA 15 59,406.87 74,654.84 25.67 5 49,467.21 57,703.21 2 - 60 10 KERALA 4 20,949.79 24,944.79 19.07 1 993.00 1,693.00 52 - 52 11 MADHYA PRADESH 13 33,201.08 34,603.14 4.22 3 4,086.00 3,406.00 2 - 35 12 MAHARASHTRA 23 93,265.27 101,851.15 9.21 11 34,452.95 39,426.48 3 - 144 13 MANIPUR 1 727.56 6,570.75 803.12 1 727.56 6,570.75 96 - 96 14 MEGHALAYA 2 5,577.50 6,802.38 21.96 0 0.00 0.00 - 15 MIZORAM 2 988.06 4,201.96 325.27 2 988.06 4,201.96 47 - 123 16 NAGALAND 3 6,420.00 8,757.12 36.40 1 850.00 2,973.42 60 - 60 17 ODISHA 12 58,045.77 66,685.00 14.88 2 31,187.00 35,965.00 25 - 39 18 RAJASTHAN 3 16,382.21 16,381.70 -0.00 3 16,382.21 16,381.70 21 - 51 19 SIKKIM 1 1,339.48 4,190.00 212.81 1 1,339.48 4,190.00 51 - 51 20 TAMIL NADU 17 55,625.65 70,343.00 26.46 10 47,996.01 59,880.04 8 - 97 21 TRIPURA 3 2,129.35 5,125.82 140.72 3 2,129.35 5,125.82 30 - 108 22 UTTAR PRADESH 13 32,985.23 36,304.05 10.06 5 14,777.89 14,777.89 9 - 39 23 WEST BENGAL 22 41,286.54 53,333.13 29.18 12 29,658.84 38,060.63 3 - 177 24 D & N HAVELI 1 6,086.08 6,086.08 0.00 1 6,086.08 6,086.08 10 - 10 25 DELHI 4 45,462.73 45,462.73 0.00 1 38,585.00 38,585.00 9 - 9 26 CHHATISGARH 15 79,254.78 80,053.87 1.01 10 55,469.97 55,952.03 7 - 39 27 JHARKHAND 7 27,804.25 29,728.92 6.92 2 3,543.27 5,467.94 48 - 51 28 UTTARAKHAND 4 8,654.06 10,843.74 25.30 3 7,127.06 9,316.74 43 - 78 29 TELANGANA 4 3,714.11 4,730.16 27.36 1 212.34 1,228.39 36 - 36 30 MULTI STATE 63 139,089.65 165,681.83 19.12 29 79,982.17 88,790.54 2 - 261
Total 279 864,705.66 1,054,852.17 21.99 133 496,896.41 615,875.49
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level.
$- Time overrun = Anticipated Date of Commissioning minus Original Date of Commissioning ^ - Cost Overrun = Anticipated Cost minus Original Cost.
Extent of time overrun in projects with respect to latest schedule
(All Cost/ Expenditure in Rs. crore) Projects with time overruns$
SI.No Sector No. of Projects
Original Cost
Anticipated Cost
Cost Overrun
^ (%)
No.
Original cost
Anticipated Cost
Range of T.O.R
(in months)
1 ATOMIC ENERGY 4 40,442.00 51,918.00 28.38 4 40,442.00 51,918.00 35 - 89 2 COAL 15 34,396.21 35,203.76 2.35 5 7,344.89 8,360.94 3 - 50 3 MINES 1 1,856.00 1,176.00 -36.64 1 1,856.00 1,176.00 31 - 31 4 STEEL 7 43,623.37 43,914.49 0.67 2 18,033.88 18,325.00 25 - 39 5 PETROCHEMICALS 1 5,460.61 9,965.00 82.49 0 0.00 0.00 - 6 PETROLEUM 29 116,156.37 125,588.13 8.12 10 47,805.86 53,625.25 7 - 71 7 POWER 63 284,164.56 332,227.47 16.91 34 134,036.12 159,700.35 2 - 111 8 HEAVY INDUSTRY 1 1,718.00 3,827.30 122.78 1 1,718.00 3,827.30 75 - 75 9 RAILWAYS* 85 97,661.81 203,275.92 108.14 19 27,643.41 75,149.36 3 - 261
10 ROAD TRANSPORT AND HIGHWAYS
61 92,888.02 94,067.51 1.27 33 50,181.73 51,361.22 2 - 55
11 SHIPPING AND PORTS 1 2,427.40 2,427.40 0.00 0 0.00 0.00 - 12 TELECOMMUNICATIONS 2 15,445.17 15,345.17 -0.65 2 15,445.17 15,345.17 20 - 30 13 URBAN DEVELOPMENT 9 128,466.14 135,916.02 5.80 3 59,580.00 67,030.01 8 - 60
Total 279 864,705.66 1,054,852.17 21.99 114 404,087.06 505,818.60
Extent of cost overrun in projects with respect to latest schedule
(All Cost/ Expenditure in Rs. crore)
Projects with cost overruns
SI.No.
Sector No. of projects
Latest Approved
Cost
Anticipated Cost
Cost overrun
(%)
No. Latest Approved
Cost
Anticipated Cost
Cost overrun
(%)
1 ATOMIC ENERGY 4 44,541.00 51,918.00 16.56 2 20,762.00 28,139.00 35.53 2 COAL 15 35,203.76 35,203.76 0.00 0 0.00 0.00 0.00 3 MINES 1 1,856.00 1,176.00 -36.64 0 0.00 0.00 0.00 4 STEEL 7 43,914.49 43,914.49 0.00 0 0.00 0.00 0.00 5 PETROCHEMICALS 1 8,920.00 9,965.00 11.72 1 8,920.00 9,965.00 11.72 6 PETROLEUM 29 122,980.48 125,588.13 2.12 2 15,096.35 17,704.00 17.27 7 POWER 63 311,804.12 332,227.47 6.55 6 27,828.34 48,251.69 73.39 8 HEAVY INDUSTRY 1 1,718.00 3,827.30 122.78 1 1,718.00 3,827.30 122.78 9 RAILWAYS 85 120,978.80 203,275.92 68.03 57 56,906.56 141,455.13 148.57 10 ROAD TRANSPORT AND
HIGHWAYS 61 92,888.02 94,067.51 1.27 1 1,108.00 2,288.00 106.50
11 SHIPPING AND PORTS 1 2,427.40 2,427.40 0.00 0 0.00 0.00 0.00 12 TELECOMMUNICATIONS 2 15,445.17 15,345.17 -0.65 0 0.00 0.00 0.00 13 URBAN DEVELOPMENT 9 133,680.01 135,916.02 1.67 1 11,609.00 13,845.01 19.26
Total 279 936,357.25 1,054,852.17 12.65 71 143,948.25 265,475.13 84.42
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level. ^ - Cost Overrun = Anticipated Cost minus Original Cost.
Extent of time & cost overrun in projects with respect to latest schedule
(All Cost/ Expenditure in Rs. crore)
Projects with time $ & cost overruns
SI.No. Sector No. of projects
Original Cost
Anticipated Cost
Cost Overrun
^ (%)
No. Original Cost
Anticipated Cost
Range of T.O.R
(in months)
1 ATOMIC ENERGY 4 40,442.00 51,918.00 28.38 0 0.00 0.00 0- 0 2 COAL 15 34,396.21 35,203.76 2.35 0 0.00 0.00 0- 0 3 MINES 1 1,856.00 1,176.00 -36.64 0 0.00 0.00 0- 0 4 STEEL 7 43,623.37 43,914.49 0.67 0 0.00 0.00 0- 0 5 PETROCHEMICALS 1 5,460.61 9,965.00 82.49 0 0.00 0.00 0- 0 6 PETROLEUM 29 116,156.37 125,588.13 8.12 3 7,045.77 8,863.86 14- 35 7 POWER 63 284,164.56 332,227.47 16.91 6 18,370.80 28,404.36 35- 123 8 HEAVY INDUSTRY 1 1,718.00 3,827.30 122.78 0 0.00 0.00 0- 0 9 RAILWAYS* 85 97,661.81 203,275.92 108.14 1 5,300.00 7,986.04 60- 60
10 ROAD TRANSPORT AND HIGHWAYS
61 92,888.02 94,067.51 1.27 0 0.00 0.00 0- 0
11 SHIPPING AND PORTS 1 2,427.40 2,427.40 0.00 0 0.00 0.00 0- 0 12 TELECOMMUNICATIONS 2 15,445.17 15,345.17 -0.65 0 0.00 0.00 0- 0 13 URBAN DEVELOPMENT 9 128,466.14 135,916.02 5.80 0 0.00 0.00 0- 0
Total 279 864705.66 1054852.17 21.99 10 30716.57 45254.26
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level. $- Time overrun = Anticipated Date of Commissioning minus Original Date of Commissioning ^ - Cost Overrun = Anticipated Cost minus Original Cost.
Extent of time & cost overrun in projects with respect to original schedule
(All Cost/ Expenditure in Rs. crore)
Projects with time$ & cost overruns
SI.No. Sector No. of projects
Original Cost
Anticipated Cost
Cost Overrun
^ (%)
No. Original Cost
Anticipated Cost
Range of T.O.R
(in months)
1 ATOMIC ENERGY 4 40,442.00 51,918.00 28.38 2 16,663.00 28,139.00 72- 89 2 COAL 15 34,396.21 35,203.76 2.35 1 212.34 1,228.39 36- 36 3 MINES 1 1,856.00 1,176.00 -36.64 0 0.00 0.00 0- 0 4 STEEL 7 43,623.37 43,914.49 0.67 1 768.88 1,060.00 25- 25 5 PETROCHEMICALS 1 5,460.61 9,965.00 82.49 0 0.00 0.00 0- 0 6 PETROLEUM 29 116,156.37 125,588.13 8.12 7 39,419.12 47,538.86 14- 53 7 POWER 63 284,164.56 332,227.47 16.91 17 53,422.56 89,706.91 10- 123 8 HEAVY INDUSTRY 1 1,718.00 3,827.30 122.78 1 1,718.00 3,827.30 75- 75 9 RAILWAYS* 85 97,661.81 203,275.92 108.14 17 19,655.62 73,579.74 47- 261
10 ROAD TRANSPORT AND HIGHWAYS
61 92,888.02 94,067.51 1.27 1 1,108.00 2,288.00 55- 55
11 SHIPPING AND PORTS 1 2,427.40 2,427.40 0.00 0 0.00 0.00 0- 0 12 TELECOMMUNICATIONS 2 15,445.17 15,345.17 -0.65 0 0.00 0.00 0- 0 13 URBAN DEVELOPMENT 9 128,466.14 135,916.02 5.80 1 6,395.00 13,845.01 60- 60
Total 279 864705.66 1054852.17 21.99 48 139362.52 261213.21
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level. $- Time overrun = Anticipated Date of Commissioning minus Original Date of Commissioning ^ - Cost Overrun = Anticipated Cost minus Original Cost.
List of projects completed/dropped/Frozen during current month
(All Cost /Expenditure in Rs. crore )
Original
Now anticipated
SI.No Project
DOA*
Cost
DOC# Cost
DOC Final
Expenditure POWER 1 TRANSMISSION SYSTEM FOR PHASE-I
GEN PROJECT IN ORISSA - PART-A 09/2010 2,074.86 03/2013 2,348.37 01/2016 1,975.94
URBAN DEVELOPMENT 2 DEVELOPMENT OF STATE HIGHWAYS IN
THE STATE OF BIHAR UNDER RSVY PATNA
11/2006 2,727.89 03/2010 2,727.89 01/2016 .01
*DOA: Date of Approval #DOC: Date of Commissioning
List of projects added
(All Cost in Rs. crore )
Original
Anticipated
SI.No Project
DOA*
Cost
DOC# Cost
DOC
PETROLEUM 1 DIESEL HYDROTREATOR 7/2015 1,031.37 1/2018 1,031.37 1/2018 POWER 2 KHARGONE STPP STAGE I (1320 MW) 3/2015 9,870.51 9/2019 9,870.51 9/2019 3 SYSTEM STRENGTHENING XXIV IN SOUTHERN
REGION 1/2016 1,455.47 7/2018 1,455.47 7/2018
*DOA: Date of Approval #DOC: Date of Commissioning
Milestones (Cumulative due & achieved) Total 2093
Achieved up to month 1098
List of projects reporting additional delays
Cost ( Rs.crore)
DOC reported
SI. No Project name Original Anticipated Original
Last month
This month
Delay (in months)
ATOMIC ENERGY 1 KAKRAPAR ATOMIC POWER PROJECT - 3 AND
4 NPCIL 11,459.00 11,459.00 12/2015 10/2017 11/2018 13
2 RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW) NPCIL
12,320.00 12,320.00 12/2016 05/2018 12/2019 19
PETROLEUM 3 PARADIP REFINERY PROJECT
IOCL 29,777.00 34,555.00 11/2012 01/2016 02/2016 1
4 PARADIP-RAIPUR- RANCHI PIPELINE IOCL
1,793.00 1,793.00 09/2012 03/2016 05/2016 2
5 RESID UPGRADATION PROJECT CPCL
3,110.36 3,110.36 11/2015 07/2016 11/2016 4
6 DEVELOPMENT OF C-26 CLUSTER FIELDS ONGC
2,592.17 2,592.17 05/2014 05/2016 03/2017 10
POWER 7 NORTHERN REGION SYSTEM
STRENGTHENING SCHEME-XXI PGCIL
1,677.57 1,677.57 04/2013 01/2016 02/2016 1
8 TR SYSTEM FOR PHASE-I GENERATION PROJECTS IN JHARKHAND AND WEST BENGAL-PART-A2 PGCIL
2,422.66 2,422.66 08/2014 02/2016 03/2016 1
9 TRANSMISSION SYSTEM ASSOCIATED WITH KRISHNAPATNAM UMPP-PART B PGCIL
1,927.16 1,927.16 10/2014 02/2016 03/2016 1
10 EASTERN REGION STRENGTHENING SCHEME-V PGCIL
1,364.52 1,364.52 04/2016 04/2016 06/2016 2
11 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) NHPC
1,061.38 2,193.08 09/2009 06/2016 09/2016 3
12 TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER PGCIL
4,404.57 4,404.57 01/2015 12/2016 03/2017 3
13 EASTERN REGION STRENGTHENING SCHEME-III PGCIL
1,272.80 1,272.80 11/2012 12/2016 03/2017 3
Graphical Presentation of All Projects w.r.t. Original Schedule
Delay in Months
In December 2015, 278 Projects include one revived project of Telecommunication Sector.
Graphical Presentation of
ATOMIC ENERGY Sector
Delay in Months
Graphical Presentation of
COAL Sector
Delay in Months
Graphical Presentation of
STEEL Sector
Delay in Months
Graphical Presentation of
PETROLEUM Sector
Delay in Months
Graphical Presentation of
POWER Sector
Delay in Months
Graphical Presentation of
RAILWAYS Sector
Delay in Months
Graphical Presentation of
ROAD TRANSPORT AND HIGHWAYS Sector
Delay in Months
Graphical Presentation of
SHIPPING AND PORTS Sector
Delay in Months
Graphical Presentation of
TELECOMMUNICATIONS Sector
Delay in Months
Graphical Presentation of
URBAN DEVELOPMENT Sector
Delay in Months
Sector-wise analysis of projects Cost (Rs. crore)
Sector
Number of projects
Original
Latest
Anticipated
Cumulative Expenditure
ATOMIC ENERGY 4 40,442.00 44,541.00 51,918.00 39,455.14 COAL 15 34,396.21 35,203.76 35,203.76 8,771.29 MINES 1 1,856.00 1,856.00 1,176.00 4.59 STEEL 7 43,623.37 43,914.49 43,914.49 25,409.49 PETROCHEMICALS 1 5,460.61 8,920.00 9,965.00 9,175.15 PETROLEUM 29 116,156.37 122,980.48 125,588.13 62,431.79 POWER 63 284,164.56 311,804.12 332,227.47 164,180.57 HEAVY INDUSTRY 1 1,718.00 1,718.00 3,827.30 0.00 RAILWAYS* 85 97,661.81 120,978.80 203,275.92 60,680.15 ROAD TRANSPORT AND HIGHWAYS 61 92,888.02 92,888.02 94,067.51 31,639.97 SHIPPING AND PORTS 1 2,427.40 2,427.40 2,427.40 841.02 TELECOMMUNICATIONS 2 15,445.17 15,445.17 15,345.17 2,720.00 URBAN DEVELOPMENT 9 128,466.14 133,680.01 135,916.02 49,396.27 Grand total 279 864,705.66 936,357.25 1,054,852.17 454,705.43
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level.
(All Cost/ Expenditure in Rs. Crore)
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 ATOMIC ENERGY
1 KUDANKULAM APP (NPCIL) - [020100040]NPCIL,TAMIL NADU , .
12/2001 13,171.00 17,270.00
22,462.00 21,077.00 12/2008 10/2013
05/2016 89(O) 31(R)
54/102
2 PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE) - [020100044]BHAVNI,TAMIL NADU , .
09/2003 3,492.00 -
5,677.00 5,150.14 09/2010 -
09/2016 72(O) -
12/88
3 KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4 - [N02000010]NPCIL,GUJARAT , .
10/2009 11,459.00 -
11,459.00 7,715.00 12/2015 10/2016
11/2018 35(O) 25(R)
41/70
4 RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW) - [N02000027]NPCIL,RAJASTHAN , .
10/2009 12,320.00 -
12,320.00 5,513.00 12/2016 03/2017
12/2019 36(O) 33(R)
29/69
Total 40,442.00 -
51,918.00 39,455.14 136/329
COAL
5 GEVRA EXPANSION OCP (SECL) (25-35) MTY - [060100093]SECL,CHHATISGARH , .
06/2010 2,675.67 -
2,675.67 1,990.05 03/2014 -
03/2016 24(O) -
11/16
6 DIPKA EXPANSION OCP (SECL) (20-25) MTY - [060100094]SECL,CHHATISGARH , .
12/2009 1,943.66 -
1,943.66 1,713.30 03/2014 -
03/2016 24(O) -
11/13
7 KUSMUNDA EXPN.OCP(SECL)(15-50)MTY - [N06000008]SECL,CHHATISGARH , .
08/2013 7,612.33 7,612.33
7,612.33 798.52 03/2023 03/2023
03/2023 0(O) 0(R)
1/17
8 AMLOHRI EPR (NCL) (6 MTY , INCR.) - [N06000010]NCL,MADHYA PRADESH , .
12/2009 1,352.04 1,143.54
1,143.54 809.04 03/2016 -
03/2016 0(O) -
4/6
9 ADRIYALA SHAFT PROJECT - [N06000016]SCCL,TELANGANA , .
12/2009 212.34 1,228.39
1,228.39 866.79 03/2013 09/2012
03/2016 36(O) 42(R)
21/22
10 PELMA OCP(15.00MTY) - [N06000045]SECL,CHHATISGARH , .
11/2014 1,624.59 1,624.59
1,624.59 5.43 03/2023 03/2023
03/2023 0(O) 0(R)
1/10
11 RAMPUR BATURA OCP (4.0 MTY) - [N06000049]SECL,MADHYA PRADESH , .
08/2015 1,186.64 -
1,186.64 1.33 03/2023 -
03/2023 0(O) -
1/9
12 KHADIA EXPANSION OPENCAST PROJECT(4 TO 10 MTPA,6MTPA INCREMENTAL) - [N06000091]NCL,UTTAR PRADESH , .
06/2011 1,131.28 1,131.28
1,131.28 148.45 03/2018 -
03/2018 0(O) -
6/9
13 SIARMAL OCP (40.00MTY) - [N06000113]MCL,ODISHA , .
05/2014 3,756.36 -
3,756.36 620.94 03/2026 -
03/2026 0(O) -
3/15
14 GARJANBAHAL OCP - [N06000117]MCL,ODISHA , . 11/2014 1,375.38 -
1,375.38 179.10 03/2021 -
03/2021 0(O) -
1/9
15 MADANNAGAR OPENCAST PROJECT - [N06000140]SECL,CHHATISGARH , .
10/2015 1,875.32 -
1,875.32 - 03/2024 -
03/2024 0(O) -
0/0
16 NEYVELI NEW THERMAL POWER PROJECT(2X500 MW) - [N06000095]NLC,TAMIL NADU , .
06/2011 5,907.11 -
5,907.11 1,373.77 12/2015 04/2018
04/2018 28(O) 0(R)
11/35
17 MOONIDIH XV SEAM UG - [N06000098]BCCL,JHARKHAND , .
08/2011 1,230.27 -
1,230.27 47.76 04/2015 04/2019
04/2019 48(O) 0(R)
2/11
18 SONEPUR BAZARI (COMB) OCP (8.0 MTY) - [N06000109]ECL,WEST BENGAL , .
08/2012 1,055.05 -
1,055.05 202.22 03/2018 -
06/2018 3(O) -
1/15
19 EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA) - [N06000138]NLC,TAMIL NADU , .
04/2013 1,458.17 -
1,458.17 14.59 06/2015 -
08/2019 50(O) -
1/7
Total 34,396.21 -
35,203.76 8,771.29 75/194
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 MINES
20 EXPANSION OF MALANJKHAND MINE-DEVELOPMENT OF UNDERGROUND MINE UNDER EXISTING OPEN CAST MINE OF CAPAC - [N10000007]HCL,MADHYA PRADESH , .
09/2011 1,856.00 -
1,176.00 4.59 09/2017 -
04/2020 31(O) -
0/0
Total 1,856.00 -
1,176.00 4.59 0/0
STEEL
21 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA - [N12000101]HSCL,KARNATAKA , .
05/2005 768.88 1,060.00
1,060.00 1,070.97 02/2014 -
03/2016 25(O) -
0/0
22 INSTALLATION OF NEW HOT STRIP MILL AT RSP - [N12000094]SAIL,ODISHA , .
04/2015 3,127.30 -
3,127.30 297.93 04/2018 -
04/2018 0(O) -
0/0
23 EXPANSION OF BHILAI STEEL PLANT - [N12000057]SAIL,CHHATISGARH , .
08/2010 17,265.00 -
17,265.00 15,516.00 03/2013 03/2016
06/2016 39(O) 3(R)
32/35
24 EXPANSION OF GUA ORE MINES WITH BENEFICIATION FACILITIES AND INSTALLATION OF PELLET PLANT - [N12000097]SAIL,JHARKHAND , .
02/2014 4,749.00 -
4,749.00 2.61 09/2017 -
09/2017 0(O) -
0/0
25 NEW SINTER PLANT AT BOKARO STEEL PLANT - [N12000095]SAIL,JHARKHAND , .
03/2015 1,034.01 -
1,034.01 - 10/2017 -
10/2017 0(O) -
0/0
26 NMDC INTEGRATED STEEL PLANT - [N12000086]NMDC,CHHATISGARH , .
01/2010 15,525.00 -
15,525.00 8,493.78 05/2015 12/2016
12/2016 19(O) 0(R)
32/81
27 MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANT - [N12000096]SAIL,JHARKHAND , .
05/2015 1,154.18 -
1,154.18 28.20 12/2017 -
12/2017 0(O) -
0/0
Total 43,623.37 -
43,914.49 25,409.49 64/116
PETROCHEMICALS
28 ASSAM GAS CRACKER PROJECT - [N16000106]BCPL,ASSAM , .
04/2006 5,460.61 8,920.00
9,965.00 9,175.15 04/2012 12/2013
12/2015 - 21/26
Total 5,460.61 -
9,965.00 9,175.15 21/26
PETROLEUM
29 AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPUR - [N16000193]IOCL,MULTI STATE , .
01/2015 1,823.00 -
1,823.00 1.34 - -
- - 0/0
30 PARADIP HYDERABAD PIPLEINE - [N16000194]IOCL,MULTI STATE , .
01/2015 2,321.00 -
2,321.00 2.04 - -
- - 0/0
31 DEVELOPMENT OF WO-16 CLUSTER FIELDS - [N16000105]ONGC,MULTI STATE , .
06/2010 2,523.00 2,523.00
2,523.00 1,792.85 01/2014 12/2015
01/2016 24(O) 1(R)
4/13
32 DIESEL HYDROTREATOR - [N16000207]NRL,ASSAM , Central Sector Projects
07/2015 1,031.37 -
1,031.37 12.72 01/2018 -
01/2018 0(O) -
0/0
33 PARADIP REFINERY PROJECT - [N16000058]IOCL,ODISHA , .
02/2009 29,777.00 34,555.00
34,555.00 31,052.90 11/2012 11/2013
02/2016 39(O) 27(R)
96/100
34 ASSAM RENEWAL PROJECT FOR GROUP A - [N16000061]ONGC,ASSAM , .
03/2009 2,465.15 2,378.89
2,378.89 1,795.13 03/2013 03/2016
03/2017 48(O) 12(R)
5/15
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 35 DE-BOTTLENECKING OF SMPL -
[N16000089]IOCL,MAHARASHTRA , . 12/2009 1,584.00
- 1,584.00 1,399.90 08/2015
- 03/2016 7(O)
- 3/12
36 DEVELOPMENT OF C-26 CLUSTER FIELDS - [N16000133]ONGC,MAHARASHTRA , .
03/2012 2,592.17 2,592.17
2,592.17 832.22 05/2014 03/2017
03/2017 34(O) 0(R)
0/21
37 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE - [N16000157]ISPRL,KARNATAKA , .
01/2006 732.00 1,227.00
1,227.00 1,074.73 10/2011 -
03/2016 53(O) -
0/0
38 MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-III - [N16000197]ONGC,MAHARASHTRA , .
11/2014 6,068.80 -
6,068.80 648.01 04/2019 -
03/2019 -1(O) -
0/0
39 DAMAN DEVELOPMENT PROJECT - [N16000198]ONGC,D & N HAVELI , .
08/2014 6,086.08 -
6,086.08 592.92 05/2019 03/2020
03/2020 10(O) 0(R)
0/0
40 NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAY - [N16000204]ONGC,MAHARASHTRA , .
08/2015 2,818.88 -
2,818.88 - 03/2019 -
03/2019 0(O) -
0/0
41 CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS) - [N16000128]ONGC,MAHARASHTRA , .
03/2011 861.79 1,256.72
1,256.72 995.12 05/2013 04/2016
04/2016 35(O) 0(R)
1/5
42 PARADIP-RAIPUR- RANCHI PIPELINE - [N16000088]IOCL,MULTI STATE , .
08/2009 1,793.00 -
1,793.00 1,294.55 09/2012 -
05/2016 44(O) -
6/7
43 INTEGRATED DEVELOPMENT OF B-127 FIELDS - [N16000131]ONGC,MAHARASHTRA , .
12/2011 2,059.63 2,665.65
2,665.65 1,323.77 03/2015 05/2016
05/2016 14(O) 0(R)
0/17
44 INTEGRATED REFINERY EXPANSION PROJECT - [N16000143]BPCL,KERALA , .
03/2012 14,225.00 -
16,504.00 10,044.66 05/2016 -
05/2016 0(O) -
0/30
45 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR - [N16000169]ISPRL,KERALA , .
01/2006 993.00 1,693.00
1,693.00 1,447.43 01/2012 -
05/2016 52(O) -
0/0
46 MH NORTH REDEVELOPMENT PHASE III - [N16000188]ONGC,MAHARASHTRA , .
06/2014 5,706.47 5,813.25
5,813.25 2,689.65 05/2017 05/2017
05/2017 0(O) 0(R)
6/16
47 PIPELINE REPLACEMENT PROJECT -4 - [N16000203]ONGC,MAHARASHTRA , .
02/2015 2,899.93 2,098.43
2,098.43 641.31 05/2017 -
05/2017 0(O) -
0/0
48 KOCHI-KOOTANAD BANGALORE MANGALORE PIPELINE PROJECT - [N16000129]GAIL,MULTI STATE , .
06/2009 2,915.00 -
2,915.00 1,381.31 12/2012 -
06/2015 - 7/14
49 UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE - [N18000148]OIL,ASSAM , .
09/2012 871.35 -
1,200.00 537.65 03/2015 11/2015
08/2016 17(O) 9(R)
0/5
50 POLYPROPYLENE PLANT AT PARADIP REFINERY - [N16000179]IOCL,ODISHA , .
03/2014 3,150.00 -
3,150.00 111.66 09/2017 -
09/2017 0(O) -
0/0
51 RESID UPGRADATION PROJECT - [N16000184]CPCL,TAMIL NADU , .
02/2011 3,110.36 -
3,110.36 1,395.63 11/2015 07/2016
11/2016 12(O) 4(R)
45/52
52 GAMJI REDEVELOPMENT PROJECT - [N16000202]ONGC,GUJARAT , .
05/2015 1,671.22 1,881.22
1,881.22 - 11/2019 -
11/2019 0(O) -
0/0
53 PHUPLUR-HALDIA PIPELINE PROJECT PHASE-I - [N16000072]GAIL,MULTI STATE , .
07/2009 3,957.00 3,561.00
3,561.00 26.81 01/2013 -
12/2018 71(O) -
11/38
54 INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS - [N16000172]ONGC,MULTI STATE , .
05/2013 4,124.35 4,941.49
4,941.49 549.78 04/2016 12/2017
12/2017 20(O) 0(R)
0/6
55 DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERY - [N16000175]IOCL,WEST BENGAL , .
03/2014 3,076.00 -
3,076.00 188.44 09/2017 03/2018
12/2017 3(O) -3(R)
0/0
56 ADDITIONAL DEVELOPMENT OF VASAI EAST FIELD - [N16000183]ONGC,MULTI STATE , .
03/2014 2,476.82 -
2,476.82 599.26 12/2018 -
12/2018 0(O) -
3/8
57 INSTALLATION OF DIESEL HYDROTREATMENT UNIT (DHT) AND ASSOCIATED FACILITIES - [N16000205]BPCL,MAHARASHTRA , .
05/2015 2,443.00 -
2,443.00 - 12/2017 -
12/2017 0(O) -
0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 Total 116,156.37
- 125,588.13 62,431.79 187/359
POWER
58 TRIPURA GAS BASED POWER PROJECT - [N18000071]NEEPCO,TRIPURA , .
07/2009 421.01 1,007.57
1,007.57 958.83 07/2013 01/2016
01/2016 30(O) 0(R)
25/26
59 NPGCPL-NABINAGAR STPP - JV (3X660 MW) - [N18000192]NTPC,BIHAR , .
01/2013 12,964.60 -
12,964.60 4,914.20 01/2018 -
01/2018 0(O) -
23/25
60 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202]DVC,WEST BENGAL , .
04/2007 4,122.00 8,781.00
9,606.82 1,353.36 02/2011 -
01/2017 71(O) -
0/0
61 NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXI - [N18000095]PGCIL,MULTI STATE , .
08/2010 1,677.57 -
1,677.57 1,447.42 04/2013 -
02/2016 34(O) -
9/11
62 NORTH KARANPURA STPP (3X660 MW) - [N18000177]NTPC,JHARKHAND , .
02/2014 14,366.58 -
14,366.58 2,349.00 02/2019 -
02/2019 0(O) -
10/13
63 BONGAIGAON THERMAL POWER PROJECT - [N18000041]NTPC,ASSAM , .
01/2008 4,375.35 6,749.18
6,749.18 5,719.00 09/2011 -
03/2017 66(O) -
17/37
64 TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER - [N18000077]PGCIL,WEST BENGAL , .
04/2010 4,404.57 -
4,404.57 2,405.85 01/2015 -
03/2017 26(O) -
8/16
65 SYSTEM STRENGTHENING IN NR FOR SASAN AND MUNDRA (UMPP) - [N18000081]PGCIL,MULTI STATE , .
12/2009 1,216.83 -
1,216.83 1,062.99 08/2012 -
03/2016 43(O) -
3/5
66 TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-B - [N18000099]PGCIL,MULTI STATE , .
03/2011 1,585.12 -
1,585.12 1,578.86 11/2013 -
03/2016 28(O) -
8/12
67 EASTERN REGION STRENGTHENING SCHEME-III - [N18000100]PGCIL,MULTI STATE , .
07/2010 1,272.80 -
1,272.80 1,244.23 11/2012 -
03/2017 52(O) -
8/13
68 TR SYSTEM FOR PHASE-I GENERATION PROJECTS IN JHARKHAND AND WEST BENGAL-PART-A2 - [N18000113]PGCIL,MULTI STATE , .
12/2011 2,422.66 -
2,422.66 2,372.26 08/2014 -
03/2016 19(O) -
9/14
69 TRANSMISSION SYSTEM ASSOCIATED WITH KRISHNAPATNAM UMPP-PART B - [N18000122]PGCIL,MULTI STATE , .
02/2012 1,927.16 -
1,927.16 1,585.67 10/2014 -
03/2016 17(O) -
5/7
70 KUDGI STPP STAGE 1 - [N18000131]NTPC,KARNATAKA , .
01/2012 15,166.19 -
15,166.19 10,171.00 01/2017 -
03/2017 2(O) -
30/39
71 TRANSMISSION SYSTEM STRENGTHENING IN WR-NR TRANSMISSION CORRIDOR FOR IPPS IN CHHATTISGARH - [N18000168]PGCIL,MULTI STATE , .
06/2014 5,151.37 -
5,151.37 703.00 03/2018 -
03/2018 0(O) -
8/12
72 TANDA TPP STAGE-II (2X660 MW) - [N18000175]NTPC,UTTAR PRADESH , .
09/2014 9,188.98 -
9,188.98 1,000.00 03/2019 -
03/2019 0(O) -
14/15
73 KBUNL-MUZAFFARPUR TPP STAGE-II- SUBSIDIARY (2X195 MW) - [N18000191]NTPC,BIHAR , .
03/2010 3,984.03 -
3,984.03 3,178.09 01/2013 -
03/2016 38(O) -
0/1
74 BOKARO THERMAL POWER STATION-A - [N18000199]DVC,JHARKHAND , .
08/2006 2,313.00 4,139.00
4,237.67 3,088.00 12/2011 -
03/2016 51(O) -
0/0
75 PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) - [N18000172]CVPPPL,JAMMU AND KASHMIR , .
10/2014 8,112.12 -
8,112.12 120.00 04/2020 -
04/2020 0(O) -
0/0
76 INTER-REGIONAL SYSTEM STRENGTHENING SCHEME IN WR AND NR (PART-B) - [N18000179]PGCIL,MULTI STATE , .
12/2014 6,517.36 -
6,517.36 301.90 04/2018 -
04/2018 0(O) -
3/12
77 GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART B - [N18000196]PGCIL,MULTI STATE , .
04/2015 3,705.61 -
3,705.61 194.60 04/2018 -
04/2018 0(O) -
4/9
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 78 GREEN ENERGY CORRIDORS INTER-STATE
TRANSMISSION SCHEME (ISTS) - PART A - [N18000197]PGCIL,MULTI STATE , .
04/2015 1,479.30 -
1,479.30 78.90 04/2017 -
04/2017 0(O) -
2/8
79 BARH STPP(3X660MW) NTPC - [180100242]NTPC,BIHAR , .
02/2005 8,692.97 15,095.67
15,095.67 11,183.00 01/2011 10/2014
05/2018 88(O) 43(R)
27/48
80 TRANSMISSION SYSTEM ASSOCIATED WITH MAUDA STAGE-II - [N18000153]PGCIL,MULTI STATE , .
09/2013 1,575.30 -
1,575.30 709.90 05/2016 -
05/2016 0(O) -
8/13
81 WARDHA-HYDERABAD 765 KV LINK - [N18000183]PGCIL,MULTI STATE , .
01/2015 3,662.02 -
3,662.02 338.80 05/2018 -
05/2018 0(O) -
0/5
82 CREATION OF 400/220 KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-A) - [N18000188]PGCIL,DELHI , .
03/2015 1,394.52 -
1,394.52 1.70 05/2017 -
05/2017 0(O) -
0/9
83 KAMENG HYDROELECTRIC PROJECT (NEEPCO) - [180100239]NEEPCO,ARUNACHAL PRADESH , .
12/2004 2,496.90 6,085.84
6,085.84 4,362.53 12/2009 06/2016
06/2016 78(O) 0(R)
16/27
84 ESTABLISHMENT OF POOLING STATIONS AT CHAMPA AND RAIGARH FOR IPP GENERATION PROJECT IN CHHATTISGARH - [N18000101]PGCIL,CHHATISGARH , .
05/2011 1,961.87 -
1,961.87 1,798.15 05/2014 -
06/2016 25(O) -
8/12
85 COMMON SYSTEM ASSOCIATED WITH COASTAL ENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED L - [N18000103]PGCIL,TAMIL NADU , .
09/2011 1,940.13 -
1,940.13 1,938.06 09/2014 -
06/2016 21(O) -
8/13
86 TRANSMISSION SYSTEM STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARH - [N18000112]PGCIL,CHHATISGARH , .
11/2011 2,127.51 -
2,127.51 2,319.63 07/2014 -
06/2016 23(O) -
6/8
87 SYSTEM STRENGTHENING IN NORTH/WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARH - [N18000116]PGCIL,CHHATISGARH , .
12/2011 1,746.65 2,228.71
2,228.71 1,475.53 08/2014 12/2015
06/2016 22(O) 6(R)
7/11
88 SYSTEM STRENTHENING IN RAIPUR WARDHA CORRIDOR FOR IPP PROJECTS IN CHHATTISGARH - [N18000117]PGCIL,CHHATISGARH , .
01/2012 1,422.85 -
1,422.85 1,391.42 01/2015 -
06/2016 17(O) -
9/11
89 WR-NR HVDC INTERCONNECTOR FOR IPP PROJECTS IN CHHATTISGARH - [N18000125]PGCIL,CHHATISGARH , .
03/2012 9,569.76 -
9,569.76 5,724.59 06/2015 -
06/2016 12(O) -
21/30
90 TR. SYS. FOR PHASE-I PROJ. IN JHARKHAN AND WEST BENGAL PART-B - [N18000129]PGCIL,MULTI STATE , .
02/2012 3,201.44 -
3,201.44 2,996.11 10/2014 -
06/2016 20(O) -
8/17
91 LARA SUPER THERMAL POWER PROJECT STAGE-I (2 X 800 MW) - [N18000140]NTPC,CHHATISGARH , .
12/2012 11,846.00 -
11,846.00 5,564.00 06/2017 -
06/2017 0(O) -
22/40
92 EASTERN REGION STRENGTHENING SCHEME-V - [N18000155]PGCIL,MULTI STATE , .
10/2013 1,364.52 -
1,364.52 434.44 04/2016 -
06/2016 2(O) -
8/12
93 PARE HYDRO ELECTRIC PROJECT - [N18000045]NEEPCO,ARUNACHAL PRADESH , .
12/2008 573.99 1,262.27
1,262.27 1,093.23 08/2013 07/2016
07/2016 35(O) 0(R)
29/38
94 GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART C - [N18000200]PGCIL,MULTI STATE , .
07/2015 2,247.37 -
2,247.37 16.00 07/2018 -
07/2018 0(O) -
0/0
95 SYSTEM STRENGTHENING XXIV IN SOUTHERN REGION - [N18000208]PGCIL,MULTI STATE , .
01/2016 1,455.47 -
1,455.47 - 07/2018 -
07/2018 0(O) -
0/0
96 SOLAPUR STPP - [N18000133]NTPC,MAHARASHTRA , .
03/2012 9,395.18 -
9,395.18 5,881.00 11/2016 -
08/2017 9(O) -
26/30
97 LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MW - [N18000142]NTPC,UTTARAKHAND , .
07/2012 1,527.00 -
1,527.00 143.00 08/2017 -
08/2017 0(O) -
0/9
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 98 COMMON SYSTEM ASSOCIATED WITH EAST COAST
ENERGY PVT. LTD. AND NCC POWER PROJECTS LTD. LTOA GENERATI - [N18000145]PGCIL,MULTI STATE , .
06/2012 1,909.24 -
1,909.24 1,016.53 06/2015 -
08/2016 14(O) -
3/5
99 DARLIPALLI STPP STAGE-I (2X800 MW) - [N18000176]NTPC,ODISHA , .
02/2014 12,532.44 -
12,532.44 2,500.00 08/2018 -
08/2018 0(O) -
17/18
100 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) - [180100243]NHPC,WEST BENGAL , .
09/2005 1,061.38 -
2,193.08 1,956.52 09/2009 -
09/2016 84(O) -
3/6
101 TEHRI PUMPED STORAGE PLANT(1000MW) - [N18000010]THDCIL,UTTARAKHAND , .
07/2006 1,657.00 2,978.86
2,978.86 1,603.73 02/2016 09/2019
09/2019 43(O) 0(R)
10/21
102 GADARWARA SUPER THERMAL POWER PROJECT STAGE-I - [N18000151]NTPC,MADHYA PRADESH , .
03/2013 11,638.55 -
11,638.55 4,856.00 09/2017 -
09/2017 0(O) -
20/41
103 RAMMAM-III HEPP (3X40 MW) - [N18000178]NTPC,WEST BENGAL , .
09/2014 1,381.84 -
1,381.84 157.00 09/2019 -
09/2019 0(O) -
3/5
104 INSTALLATION OF STATCOMS IN WESTERN REGION - [N18000185]PGCIL,MULTI STATE , .
03/2015 1,071.24 -
1,071.24 0.10 09/2017 -
09/2017 0(O) -
0/0
105 BRBCL-NABINAGAR TPP- JV (4X250 MW) - [N18000190]NTPC,BIHAR , .
01/2007 5,353.00 -
5,353.00 5,298.06 05/2014 -
09/2017 40(O) -
0/4
106 MUNPL-MEJA TPP - JV (2X660 MW) - [N18000193]NTPC,UTTAR PRADESH , .
04/2012 9,750.89 -
9,750.89 4,529.23 12/2016 -
09/2017 9(O) -
25/28
107 KHARGONE STPP STAGE I (1320 MW) - [N18000205]NTPC,MADHYA PRADESH , .
03/2015 9,870.51 -
9,870.51 - 09/2019 -
09/2019 0(O) -
0/7
108 TUIRIAL HYDRO ELECTRIC PROJECT (60MW) - [N18000119]NEEPCO,MIZORAM , .
07/1998 368.72 1,381.71
1,381.71 951.92 07/2006 10/2016
10/2016 123(O) 0(R)
5/13
109 KISHANGANGA HEP (3X110 MW) - [N18000031]NHPC,JAMMU AND KASHMIR , .
01/2009 3,642.04 -
5,751.47 4,402.95 01/2016 -
11/2016 10(O) -
7/9
110 PARBATI HEP (4X200 MW) (NHPC) II - [180100210]NHPC,HIMACHAL PRADESH , .
09/2002 3,919.59 -
8,398.76 5,398.46 09/2009 -
12/2018 111(O) -
2/3
111 KUNADANKULAM APP TRANS SYSTEM (PGCIL) - [180100258]PGCIL,TAMIL NADU , .
05/2005 1,779.29 2,187.32
2,187.32 1,903.55 11/2008 01/2016
12/2016 97(O) 11(R)
20/22
112 TAPOVAN-VISHNUGAD HEP (4X130MW) - [N18000014]NTPC,UTTARAKHAND , .
11/2006 2,978.48 3,846.30
3,846.30 2,699.00 03/2013 -
12/2018 69(O) -
2/15
113 VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT - [N18000042]THDCIL,UTTARAKHAND , .
08/2008 2,491.58 -
2,491.58 789.89 06/2013 -
12/2019 78(O) -
5/8
114 TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECT - [N18000061]PGCIL,MULTI STATE , .
10/2008 4,824.12 -
4,824.12 4,237.58 10/2012 -
12/2016 50(O) -
7/11
115 NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECT - [N18000066]PGCIL,MULTI STATE , .
02/2009 11,130.19 13,762.80
13,762.80 11,463.30 08/2013 12/2017
12/2017 52(O) 0(R)
17/26
116 TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS. - [N18000080]PGCIL,MULTI STATE , .
02/2010 2,144.00 2,932.88
2,932.88 2,283.80 12/2012 12/2016
12/2016 48(O) 0(R)
11/23
117 MOUDA STPP STAGE 2 - [N18000132]NTPC,MAHARASHTRA , .
03/2012 7,921.47 -
7,921.47 4,904.00 09/2016 -
12/2016 3(O) -
28/35
118 COMMON SYS. ASSOCIATED WITH EAST COAST ENERGY PVT LTD AND NCC POWER PROJECTS LTD LTOA GEN PART- B - [N18000144]PGCIL,MULTI STATE , .
03/2013 2,514.88 -
2,514.88 1,043.56 12/2015 -
12/2016 12(O) -
15/18
119 FGUTPP, UNCHAHAR STAGE-IV (1X500 MW) - [N18000174]NTPC,UTTAR PRADESH , .
07/2013 3,363.12 -
3,363.12 1,018.00 12/2016 -
12/2016 0(O) -
16/20
120 SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) - [180100221]NHPC,ARUNACHAL PRADESH , .
09/2003 6,285.33 -
18,063.89 7,969.14 09/2010 -
- - 0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 Total 284,164.56
- 332,227.47 164,180.57 605/946
HEAVY INDUSTRY
121 NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP) - [N20000001]NATIS,MULTI STATE , .
04/2011 1,718.00 -
3,827.30 - 09/2011 -
12/2017 75(O) -
0/0
Total 1,718.00 -
3,827.30 .00 0/0
RAILWAYS*
122 LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) - [220100232]WCR,MULTI STATE , .
09/1998 247.66 3,500.00
3,500.00 1,007.95 05/2008 -
- - 0/0
123 PALANPUR-SAMAKHAYALI (DL) - [N22000144]WR,GUJARAT , .
04/2013 1,266.89 -
1,266.89 - - -
- - 0/0
124 KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION - [N22000261]SCR,MULTI STATE , .
04/2012 1,054.35 2,200.00
2,200.00 51.67 - -
- - 0/0
125 GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM) - [N22000345],UTTAR PRADESH , .
04/1997 836.26 -
1,072.51 - - -
- - 0/0
126 GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC) - [N22000148]NCR,MULTI STATE , .
04/2011 1,176.09 3,845.60
3,845.60 2.33 02/2020 -
02/2020 0(O) -
0/0
127 DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR & TANPUR-BANSI PAHARPUR - [N22000158]NCR,MULTI STATE , .
04/2010 622.41 2,030.50
2,030.50 3.61 02/2019 -
02/2019 0(O) -
0/0
128 NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR - [220100135]NFR,WEST BENGAL , .
04/1983 36.80 36.38
1,336.57 255.55 - -
03/2019 - -
0/0
129 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164]MRTP,MAHARASHTRA , .
03/1996 495.44 495.44
1,781.98 440.08 03/2004 -
03/2016 144(O) -
0/0
130 KANPUR KASGANJ MATHURA(GC) NER - [220100197]NER,UTTAR PRADESH , .
03/1997 677.97 1,062.36
1,651.54 1,621.40 - -
03/2018 - -
0/0
131 HOWRAH-AMTA-CHAMPADANGA NL (SER) - [220100208]SER,WEST BENGAL , .
04/1974 393.46 393.46
1,026.00 181.48 03/2007 03/2007
03/2015 - 0/0
132 KATIHAR - JOGBANI (GC)(NEFR) - [220100247]NFR,BIHAR , .
09/2001 492.98 -
1,727.27 743.74 12/2010 -
03/2018 87(O) -
0/0
133 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266]NFR,MULTI STATE , .
04/2000 733.00 733.00
2,531.34 1,732.43 12/2008 -
03/2018 111(O) -
0/0
134 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288]NFR,MANIPUR , .
04/2003 727.56 727.56
6,570.75 2,787.99 03/2011 03/2014
03/2019 96(O) 60(R)
0/0
135 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307]ECR,BIHAR , .
04/2002 921.00 3,040.00
3,040.00 1,834.31 03/2009 -
03/2016 84(O) -
0/0
136 RAMGANJMUNDI-BHOPAL (NL),WCR - [220100314]WCR,MADHYA PRADESH , .
04/2001 470.92 727.13
1,225.90 257.59 - -
03/2017 - -
0/0
137 CHHINDWARA - NAGPUR (GC)(SECR) - [220100324]SECR,MADHYA PRADESH , .
04/2005 383.79 663.67
1,101.16 194.91 - -
03/2017 - -
0/0
138 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092]MRTP,MAHARASHTRA , .
04/2008 5,300.00 6,821.29
7,986.04 2,443.62 03/2014 03/2019
03/2019 60(O) 0(R)
0/0
139 AGARTALA SABROOM, NL, NEFR - [N22000099]NFR,TRIPURA , .
04/2008 813.34 813.34
2,876.00 823.83 03/2014 -
03/2018 48(O) -
0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 140 BHAIRABI SAIRONG, NL, NEFR -
[N22000100]NFR,MIZORAM , . 04/2008 619.34
619.34 2,820.25 199.31 04/2014
03/2015 03/2018 47(O)
36(R) 0/0
141 SEVOK RANGPO, NEFR - [N22000102]NFR,SIKKIM , . 04/2008 1,339.48 1,339.48
4,190.00 88.56 12/2015 -
03/2020 51(O) -
0/0
142 NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124]NFR,NAGALAND , .
04/2006 850.00 -
2,973.42 10.44 03/2015 03/2020
03/2020 60(O) 0(R)
0/0
143 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127]NFR,ASSAM , .
04/1996 1,676.31 -
5,500.00 4,769.59 03/2009 -
03/2016 84(O) -
0/0
144 NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING - [N22000183]NFR,MULTI STATE , .
04/2013 1,798.00 1,798.00
1,887.90 - - -
03/2019 - -
0/0
145 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194]NFR,TRIPURA , .
04/1999 895.00 -
1,242.25 1,047.10 03/2007 -
03/2016 108(O) -
0/0
146 DIMAPUR-TIZIT NL - [N22000196]NFR,NAGALAND , . 04/2013 4,274.00 -
4,487.70 - - -
03/2020 - -
0/0
147 NEW BG LINE FROM BYRNIHAT TO SHILLONG - [N22000205]NFR,MEGHALAYA , .
04/2010 4,083.02 -
5,307.90 7.79 - 03/2016
03/2020 - 48(R)
0/0
148 NEW JALPAIGURI-SILIGURI-NEW BONGAIGAON INCLUDING BR. LINE AND MM FOR CHALSA-NAXAL& RAJABHATKHOWA-JAI - [N22000209]NFR,MULTI STATE , .
04/1999 523.17 380.60
1,653.55 1,040.11 - -
03/2018 - -
0/0
149 VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM) - [N22000313]RVNL,ANDHRA PRADESH , PPP (BOT)
03/2012 1,503.71 -
1,503.71 175.26 - -
03/2020 - -
0/0
150 KIRANDUL - JAGDALPUR DOUBLING - [N22000318]ECOR,CHHATISGARH , .
12/2012 826.57 -
1,143.60 189.12 - -
03/2018 - -
0/0
151 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201]NFR,ASSAM , .
09/1997 1,500.00 4,996.19
4,996.19 4,102.70 04/2008 12/2011
06/2017 110(O) 66(R)
0/0
152 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP) - [N22000108]RVNL,WEST BENGAL , .
04/2010 2,397.72 -
2,397.72 204.56 03/2016 -
06/2016 3(O) -
0/0
153 EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKE - [N22000135]MRTP,WEST BENGAL , .
03/2013 4,874.58 -
4,874.58 1,911.65 03/2016 -
06/2018 27(O) -
0/0
154 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133]NR,JAMMU AND KASHMIR , .
03/1995 2,500.00 -
20,000.00 10,722.72 11/2002 -
12/2017 181(O) -
0/0
155 GONDIA-JABALPUR(GC),(SECR) - [220100186]SECR,MULTI STATE , .
02/1997 386.30 -
1,544.40 - 03/1998 -
12/2019 261(O) -
0/0
156 BANKURA - DAMODAR (GC) (SER) - [220100277]SER,WEST BENGAL , .
03/1998 111.90 1,039.29
2,371.85 486.25 03/2005 12/2008
12/2019 177(O) 132(R)
0/0
157 PATNA GANGA BRIDGE (NL), ECR - [220100308]ECR,BIHAR , .
04/2001 624.47 -
2,921.00 2,521.72 10/2007 12/2012
12/2015 - 0/0
158 TAMLUK DIGHA,LINE DOUBLING (SER) - [N22000097]SER,WEST BENGAL , .
03/1984 293.97 1,013.74
1,428.00 466.36 06/2005 07/2011
12/2019 174(O) 101(R)
0/0
159 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP) - [N22000110]RVNL,WEST BENGAL , .
04/2010 3,951.98 -
3,161.58 878.29 03/2016 -
12/2020 57(O) -
0/0
160 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH. - [N22000111]RVNL,WEST BENGAL , .
04/2010 2,913.51 -
2,095.20 619.56 03/2016 -
12/2018 33(O) -
0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 161 DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRA
- [N22000160]SER,MULTI STATE , . 04/2010 553.63
651.17 1,009.00 7.50 -
- 12/2019 -
- 0/0
162 AHMEDNAGAR-PARLI VAIJNATH(NL) CR - [220100181]CR,MAHARASHTRA , .
02/1997 514.68 -
2,820.00 329.67 - -
- - 0/0
163 HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR - [220100183]SWR,KARNATAKA , .
02/1997 295.00 -
1,289.92 1,092.98 - -
- - 0/0
164 NANGALDAM-TALWARA(NL),NR - [220100188]NR,MULTI STATE , .
03/1981 450.00 -
2,100.00 391.95 07/2012 -
- - 0/0
165 HUBLI-ANKOLA(NL),SWR - [220100193]SWR,KARNATAKA , .
04/1997 227.00 997.58
2,135.00 117.24 - -
- - 0/0
166 KODERMA-RANCHI VIA BARKAKANA (NL),ECR - [220100222]ECR,JHARKHAND , .
03/1999 2,957.21 -
2,957.21 1,966.90 07/2005 -
- - 0/0
167 JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR - [220100240]ECR,BIHAR , .
04/1997 501.69 501.69
1,043.56 819.19 03/2012 -
- - 0/0
168 ANGAMALI-SABARIMALA (N.L.)(SR) - [220100252]SR,KERALA , .
10/1998 550.00 517.70
1,566.00 137.40 - -
- - 0/0
169 QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) - [220100263]SR,MULTI STATE , .
03/1998 280.00 -
1,122.00 889.95 - -
- - 0/6
170 KOTLPALLI-NARASAPUR (NL) (SCR) - [220100265]SCR,ANDHRA PRADESH , .
12/2001 330.00 -
1,047.00 1.29 - -
- - 0/0
171 TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP) - [220100268]MRTP,WEST BENGAL , .
03/2000 1,049.69 3,385.14
3,404.92 3,551.53 12/2006 -
- - 0/0
172 TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ER - [220100272]ER,WEST BENGAL , .
04/2000 1,188.91 -
1,188.91 687.63 - 12/2009
- - 0/0
173 BANGLORE - SATYAMANGALAM (NL)(SWR) - [220100274]SWR,KARNATAKA , .
04/1996 138.00 -
1,382.78 2.81 - -
- - 0/0
174 KHURDA ROAD-BOLANGIR(NL)ECOR - [220100284]ECOR,ODISHA , .
04/1994 470.21 -
1,995.25 355.02 - -
- - 0/0
175 HARIDASPUR-PARADEEP(NL) - [220100285]RVNL,ODISHA , .
04/1996 301.64 -
1,185.64 577.84 - 09/2009
- - 0/0
176 SUKINDA ROAD - ANGUL (NL)(ECOR) - [220100325]RVNL,ODISHA , .
04/1998 183.23 -
1,202.70 185.46 02/2015 -
- - 0/0
177 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI - [N22000079]SR,TAMIL NADU , .
09/2007 404.19 -
1,383.45 457.88 - -
- - 0/0
178 TIDIVANAM-NAGARI (NL) - [N22000085]SR,TAMIL NADU , .
09/2006 456.00 -
1,080.00 194.61 - -
- - 0/0
179 UTRATIA-ZAFRABAD, NR (LINE DOUBLING) - [N22000088]NR,UTTAR PRADESH , .
04/2006 325.00 2,434.00
2,434.00 419.45 03/2010 -
- - 0/0
180 BARDHAMAN-KATWA (GC) - [N22000091]ER,WEST BENGAL , .
04/2007 1,106.62 -
1,106.62 244.99 12/2010 -
- - 0/0
181 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP) - [N22000109]RVNL,WEST BENGAL , .
04/2010 2,298.42 -
1,655.68 38.46 03/2014 -
- - 0/0
182 RATLAM-MHOW-KHANDWA-AKOLA (GC) - [N22000120]WR,MADHYA PRADESH , .
04/2008 603.04 -
1,421.25 420.33 03/2012 -
- - 0/0
183 UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR) - [N22000122]WR,GUJARAT , .
04/2008 1,389.62 -
1,389.62 1,055.80 03/2014 -
- - 0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 184 CHOTTAUDEPUR-DHAR(NL) - [N22000138]WR,MULTI
STATE , . 04/2007 1,347.26
- 1,347.26 164.55 -
- - - 0/0
185 DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL) - [N22000139]WR,MULTI STATE , .
04/2007 1,640.04 -
1,640.04 187.84 - -
- - 0/0
186 RATLAM-DUNGARPUR VIA BANSWARA (NL) - [N22000147]NWR,MULTI STATE , .
04/2011 2,082.75 -
3,500.00 54.23 - -
- - 0/0
187 CHENNAI-CUDDALORE VIA MAMALLAPURAM - [N22000185]SR,MULTI STATE , .
04/2008 523.52 -
1,200.00 2.07 - -
- - 0/0
188 SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDUR - [N22000186]SR,TAMIL NADU , .
04/2013 839.00 -
1,500.00 0.01 - -
- - 0/0
189 VILLUPURAM-DINDIGUL WITH ELECTRIFICATION - [N22000189]SR,MULTI STATE , .
04/2008 822.39 -
1,280.83 1,031.83 - -
- - 0/0
190 WARDHA-NANDED MAHARASHTRA - [N22000231]CR,MAHARASHTRA , .
04/2008 499.30 -
2,501.05 84.11 - -
- - 0/0
191 TUMKUR-CHITRADURGA-DAVENGERE NL - [N22000256]SWR,KARNATAKA , .
04/2011 913.00 -
1,801.01 1.47 - -
- - 0/0
192 MUNIRABAD (GINGERA) -RAICHUR NL - [N22000257]SWR,KARNATAKA , .
04/2007 179.65 -
1,350.91 380.62 - -
- - 0/0
193 MANUGURU-RAMAGUNDAM - [N22000259]SCR,TELANGANA , .
04/2013 1,112.00 -
1,112.00 - - -
- - 0/0
194 AKOLA-KHANDWA GC AKOLA-AKOT - [N22000263]SCR,MULTI STATE , .
04/2008 184.26 -
2,000.00 17.32 - -
- - 0/0
195 DELHI-SOHNA-NUH-FIROZPUR-JHIRKA-ALWAR - [N22000271]NR,MULTI STATE , .
04/2013 1,239.00 -
1,239.00 - - -
- - 0/0
196 BHANUPALI-BILASPUR BERI NL - [N22000273]NR,HIMACHAL PRADESH , .
04/2008 1,046.88 -
2,966.99 40.80 - -
- - 0/0
197 RAYADURGA-TUMKUR NL - [N22000279]SWR,MULTI STATE , .
04/2007 970.34 -
1,743.00 359.06 - -
- - 0/0
198 NADIKUDE-SRI KALAHASTI - [N22000286]SCR,ANDHRA PRADESH , .
04/2011 1,313.48 -
1,313.48 5.13 - -
- - 0/0
199 KADAPA-BANGALORE (NL), KADAPA-PENDLIMARRI PH-I - [N22000288]SCR,MULTI STATE , .
04/2008 2,050.00 -
2,050.00 194.45 - -
- - 0/0
200 HOSPET-HUBLI-LONDA-VASCODAGAMA DL - [N22000297]SWR,KARNATAKA , .
04/2010 2,127.00 -
2,127.00 325.00 - -
- - 0/0
201 GADAG-WADI NL - [N22000299]SWR,KARNATAKA , . 04/2013 1,117.00 -
1,922.00 1.89 - -
- - 0/0
202 QUILON-TIRUNELVELI - TRICHENDUR, TENKASI - [N22000303]SR,TAMIL NADU , .
04/1999 460.94 -
1,030.00 - 01/1999 -
- - 0/0
203 SAMBALPUR-TALCHER DOUBLING - [N22000315]ECOR,ODISHA , .
03/2011 679.27 -
1,111.99 60.31 - -
- - 0/0
204 HUBLI- CHIKJAJUR - [N22000325]SWR,KARNATAKA , . 03/2015 1,900.00 -
1,900.00 - - -
- - 0/0
205 MIRAJ-LONDA - [N22000327]SWR,MULTI STATE , . 03/2015 1,830.00 -
1,830.00 - - -
- - 0/0
206 HOTGI-KUDGI-GADAG - [N22000333]SWR,MULTI STATE , .
03/2015 1,618.00 -
1,618.00 - - -
- - 0/0
Total 97,661.81 -
203,275.92 60,680.15 0/6
ROAD TRANSPORT AND HIGHWAYS
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 207 SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502 -
[N24000131]NHAI,MULTI STATE , PPP (BOT) 02/2009 1,693.75
- 1,693.75 - 08/2011
- - - 2/2
208 NEW 4 LANE ELEVATED ROAD FROM CHENNAI AIRPORT-MADURAVOYAL NH NO.4 - [N24000139]NHAI,TAMIL NADU , PPP (BOT)
09/2010 1,655.00 -
1,655.00 - 09/2013 -
- - 0/0
209 YADGIRI-WARANGAL OF NH 202(NEW NH 163) UNDER NHDP-IV - [N24000235]NHAI,TELANGANA , .
04/2014 1,123.17 -
1,123.17 - - -
- - 0/0
210 WIDENING OF 2(TWO) LANING OF LONGLENG-CHANTONGYA ROAD, MON-TAMLU-MERANGKONG ROAD, PHEK- PFUTSERO ROA - [N24000315]PWD,NAGALAND , ITEM RATE
12/2010 1,296.00 -
1,296.00 - 02/2011 -
- - 0/0
211 2 LANING OF SHILLONG NONGSTOIN SECTION OF NH 44 AND NONGSTOIN TURA STATE ROAD UNDER PHASE A OF SA - [N24000390]PWD,MEGHALAYA , ITEM RATE
12/2010 1,494.48 -
1,494.48 2,090.00 02/2011 -
02/2011 - 0/0
212 4 LANING OF AMRAVATI - CHIKHLI (PKG-I) - [N24000425]NHAI,MAHARASHTRA , PPP (BOT)
07/2015 2,288.18 -
2,288.18 - - -
- - 0/0
213 4 LANING OF BAHARAGORA - SINGHARA - [N24000427]NHAI,ODISHA , .
07/2015 1,282.94 -
1,282.94 - - -
- - 0/0
214 4 LANING OF FAGNE - MAH-GUJ BORDER ( PKG-3) - [N24000439]NHAI,MAHARASHTRA , EPC
07/2015 1,885.74 -
1,885.74 - - -
- - 0/0
215 8 LANING OF MUKARBA CHOWK TO PANIPAT - [N24000449]NHAI,HARYANA , PPP (BOT)
07/2015 2,128.72 -
2,128.72 - - -
- - 0/0
216 6 LANING OF AGRA - ETAWAH BYPASS - [N24000452]NHAI,UTTAR PRADESH , PPP (BOT)
07/2015 1,657.20 -
1,657.20 - - -
- - 0/0
217 4 LANING OF GUNA TO BIAORA - [N24000458]NHAI,MADHYA PRADESH , PPP (BOT)
06/2015 1,012.90 -
1,012.90 - - -
- - 0/0
218 FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31 - [N24000480]NHAI,BIHAR , .
12/2015 1,041.10 -
1,041.10 - - -
- - 0/0
219 FOUR LANING OF YADGIRI - WARANGAL - [N24000486]NHAI,WEST BENGAL , .
12/2015 1,423.96 -
1,423.96 - - -
- - 0/0
220 FOUR LANING OF HOSPET - CHITRADURGA - [N24000490]NHAI,KARNATAKA , PPP (BOT)
01/1991 1,388.00 -
1,388.00 - - -
- - 0/0
221 FOUR LANING OF BIAORA –DEWAS SECTION OF NH-3 FROM KM 426.100 TO KM 566.450 IN THE STATE OF MADHYA PR - [N24000505]NHAI,MADHYA PRADESH , PPP (BOT)
06/2015 1,583.79 -
1,583.79 - - -
- - 0/0
222 FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31 - [N24000507]NHAI,BIHAR , .
01/1991 1,167.45 -
1,167.45 - - -
- - 0/0
223 GURGAON - KOTPUTLI - JAIPUR (SIX LANE) - [N24000477]DORTH,RAJASTHAN , PPP (BOT)
02/2008 1,673.70 -
1,673.70 - 10/2011 -
01/2016 51(O) -
0/0
224 FOUR LANING OF KAITHAL - RAJASTHAN BORDER - [N24000487]NHAI,HARYANA , PPP (BOT)
07/2015 1,393.00 -
1,393.00 876.68 - -
01/2018 - -
0/0
225 FOUR LANING OF GWALIOR-SHIVPURI - [N24000494]DORTH,MADHYA PRADESH , PPP (BOT)
05/2013 1,055.00 -
1,055.00 - 11/2015 -
01/2016 2(O) -
0/0
226 FOUR LANING OF AURANGABAD - YEDISHI - [N24000508]NHAI,MAHARASHTRA , PPP (BOT)
07/2015 1,871.34 -
1,871.34 830.19 01/2018 -
01/2018 0(O) -
0/0
227 GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTION - [N24000125]NHAI,GUJARAT , PPP (BOT)
03/2010 1,509.10 -
1,509.10 - 09/2012 -
02/2016 41(O) -
2/3
228 INDORE-JHABUA-GUJRAT/MP - [N24000136]NHAI,MADHYA PRADESH , PPP (BOT)
10/2010 1,175.00 -
1,175.00 - 04/2013 -
03/2016 35(O) -
0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 229 MURADABAD-BAREILY - [N24000154]NHAI,UTTAR
PRADESH , PPP (BOT) 04/2010 1,267.00
- 1,267.00 2,425.00 06/2013
- 03/2016 33(O)
- 0/0
230 4 LANING OF NAGPUR-BETUL - [N24000155]NHAI,MULTI STATE , PPP (ANNUITY)
02/2011 2,498.76 -
2,498.76 - 08/2014 -
03/2016 19(O) -
0/0
231 BEAWAR PALI PINDWARA - [N24000199]NHAI,RAJASTHAN , PPP (BOT)
12/2011 2,388.51 -
2,388.00 2,301.00 06/2014 -
03/2016 21(O) -
0/0
232 SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWAR - [N24000205]NHAI,MULTI STATE , PPP (BOT)
12/2011 1,047.00 -
1,047.00 - 06/2014 -
03/2016 21(O) -
0/0
233 FOUR LANING OF ORISSA CHATTISHGARH BORDER - [N24000218]NHAI,MULTI STATE , PPP (BOT)
02/2013 1,232.00 -
1,232.00 927.19 08/2015 -
03/2016 7(O) -
0/0
234 WALAJAPET POONAMALEE KM 106.8 TO KM 13.8 - [N24000228]NHAI,TAMIL NADU , PPP (BOT)
06/2013 1,287.95 -
1,287.95 - 11/2015 -
03/2017 16(O) -
0/0
235 FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTION - [N24000481]NHAI,CHHATISGARH , .
02/2013 1,232.00 -
1,232.00 - 08/2015 -
03/2016 7(O) -
0/0
236 FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA - [N24000496]NHAI,MADHYA PRADESH , .
06/2015 1,012.90 -
1,012.90 - 03/2016 -
03/2016 0(O) -
0/0
237 GHAZIABAD-ALIGARH NH-91 - [N24000170]NHAI,UTTAR PRADESH , PPP (BOT)
02/2011 1,141.00 -
1,141.00 1,911.64 08/2013 -
04/2016 32(O) -
0/0
238 VARANASI-AURANGABAD KM.786 TO KM.978.40 - [N24000182]NHAI,MULTI STATE , PPP (BOT)
09/2011 2,848.00 -
2,848.00 504.51 03/2014 -
04/2017 37(O) -
0/0
239 DELHI AGRA APPROVED LENGTH 180.0 KM - [N24000224]NHAI,MULTI STATE , PPP (BOT)
10/2012 1,928.22 -
1,928.22 822.96 04/2015 -
04/2016 12(O) -
0/0
240 NASHRI- CHANANI - [N24000162]NHAI,JAMMU AND KASHMIR , PPP (ANNUITY)
05/2011 2,159.00 -
2,159.00 - 06/2015 -
05/2016 11(O) -
0/0
241 6-LANING OF DHANKUNI-KHARAGPUR SECTION - [N24000206]NHAI,WEST BENGAL , PPP (BOT)
04/2012 1,396.18 -
1,396.18 2,287.44 09/2014 -
05/2016 20(O) -
0/0
242 RANCHI-RARGA-JAMSETHPUR - [N24000215]NHAI,MULTI STATE , PPP (ANNUITY)
12/2012 1,479.00 -
1,479.00 461.94 06/2015 -
05/2017 23(O) -
0/0
243 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM) - [N24000133]NHAI,HARYANA , PPP (BOT)
05/2009 1,108.00 -
2,288.00 3,619.94 11/2011 -
06/2016 55(O) -
0/0
244 QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00 - [N24000161]NHAI,JAMMU AND KASHMIR , PPP (ANNUITY)
07/2010 1,987.00 -
1,987.00 - 07/2015 -
06/2016 11(O) -
0/0
245 JAMMU-UDHAMPUR KM.27.5 TO KM.67.00 - [N24000163]NHAI,JAMMU AND KASHMIR , PPP (ANNUITY)
07/2010 1,813.76 -
1,813.76 - 07/2013 -
06/2016 35(O) -
0/0
246 4 LANNING OF AHMEDABAD TO GODHARA - [N24000167]NHAI,GUJARAT , PPP (BOT)
12/2010 1,008.50 -
1,008.50 - 06/2013 -
06/2016 36(O) -
0/3
247 SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547 - [N24000183]NHAI,ANDHRA PRADESH , PPP (BOT)
11/2011 1,535.00 -
1,535.00 2,478.63 05/2014 -
06/2016 25(O) -
0/0
248 SRINAGAR TO BANIHAL - [N24000189]NHAI,JAMMU AND KASHMIR , PPP (ANNUITY)
06/2011 1,100.70 -
1,100.70 - 06/2014 -
06/2016 24(O) -
0/0
249 ETAWAH CHAKERI - [N24000219]NHAI,UTTAR PRADESH , PPP (BOT)
03/2013 1,573.00 -
1,573.00 1,840.00 09/2015 -
06/2016 9(O) -
0/0
250 AHMEDABAD TO VADODARA SECTION - [N24000222]NHAI,GUJARAT , PPP (BOT)
01/2013 2,125.24 -
2,125.24 - 12/2015 -
06/2016 6(O) -
0/3
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 251 4 LANING OF NH-31D FROM GHOSHPUKUR -
SALSALABARI ( KM 0.00 TO KM . 83.785) - [N24000463]NHAI,WEST BENGAL , .
12/2015 1,083.00 -
1,083.00 - 06/2018 -
06/2018 0(O) -
0/0
252 FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1A - [N24000471]NHAI,JAMMU AND KASHMIR , .
12/2015 2,168.66 -
2,168.66 - 06/2019 -
06/2019 0(O) -
0/0
253 FOUR LANING OF SULTANPUR TO VARANASI (PKG-I) - [N24000493]NHAI,UTTAR PRADESH , .
01/2016 1,027.53 -
1,027.53 - 06/2018 -
06/2018 0(O) -
0/0
254 CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KM - [N24000145]NHAI,ANDHRA PRADESH , PPP (BOT)
11/2010 1,585.00 -
1,585.00 1,050.90 05/2013 -
08/2016 39(O) -
0/0
255 4-LANING OF FARAKA-RAIGANJ - [N24000202]NHAI,MULTI STATE , PPP (BOT)
02/2011 1,078.84 -
1,078.84 - 08/2013 -
08/2016 36(O) -
0/0
256 WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50 - [N24000230]NHAI,MAHARASHTRA , PPP (BOT)
05/2013 1,348.20 -
1,348.20 1,267.57 02/2014 -
08/2016 30(O) -
2/2
257 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION - [N24000462]NHAI,KARNATAKA , PPP (BOT)
05/2014 1,655.01 -
1,655.01 - 08/2016 -
08/2016 0(O) -
0/0
258 FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASS - [N24000509]NHAI,MAHARASHTRA , .
04/2010 1,170.52 -
1,170.52 1,579.15 06/2012 -
08/2016 50(O) -
0/0
259 4 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9 - [N24000233]NHAI,TELANGANA , PPP (BOT)
04/2014 1,266.60 -
1,266.60 - 09/2016 -
09/2016 0(O) -
0/0
260 SIX-LANING OF BARWA ADDA-PANAGARH - [N24000515]NHAI,WEST BENGAL , PPP (BOT)
04/2014 1,665.00 -
1,665.00 994.21 - -
09/2016 - -
0/0
261 PANIKHOLI-RIMOLI - [N24000197]NHAI,ODISHA , PPP (BOT)
03/2012 1,410.00 -
1,410.00 - 09/2014 -
10/2016 25(O) -
0/0
262 FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM) - [N24000232]NHAI,HIMACHAL PRADESH , PPP (BOT)
11/2013 1,916.79 -
1,916.79 1,202.43 11/2016 -
11/2016 0(O) -
0/0
263 FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120 - [N24000349]NHAI,TAMIL NADU , .
05/2015 1,387.11 -
1,387.11 - 11/2017 -
11/2017 0(O) -
0/0
264 PUNE-SATARA(NH-4) - [N24000156]NHAI,MAHARASHTRA , PPP (BOT)
10/2010 1,724.55 -
1,724.55 1,742.94 03/2013 -
12/2016 45(O) -
0/0
265 SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46 - [N24000172]NHAI,TAMIL NADU , PPP (BOT)
09/2011 1,250.00 -
1,250.00 - 12/2013 -
12/2016 36(O) -
0/0
266 BAREILY-SITAPUR (NH-24) - [N24000200]NHAI,UTTAR PRADESH , PPP (BOT)
03/2011 1,046.00 -
1,046.00 425.65 09/2013 -
12/2016 39(O) -
0/0
267 FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A - [N24000488]NHAI,JAMMU AND KASHMIR , .
12/2015 2,136.97 -
2,136.97 - 12/2018 -
12/2018 0(O) -
0/0
Total 92,888.02 -
94,067.51 31,639.97 6/13
SHIPPING AND PORTS
268 SETHUSAMUDRAM SHIP CHANNEL PROJECT - [250100175]PORT TRUST,TAMIL NADU , Public Private (SPV)
06/2005 2,427.40 -
2,427.40 841.02 10/2008 -
- - 0/0
Total 2,427.40 -
2,427.40 841.02 0/0
Sector Wise Details (January 2016)
Date of Commissioning
SI.No Project Date of
Approval
Original / Revised
Cost Anticipated
Cost
Cumulative Expenditure
Cost
Original/
Revised Anticipated
Delay w.r.t. Original/ Revised
(in months)
Miles tones
Achieved/ Total
1 2 3 4 5 6 7 8 9 10 TELECOMMUNICATIONS
269 NETWORK FOR SPECTRUM - [N26000101]DOT,MULTI STATE , .
03/2012 13,334.00 -
13,334.00 1,360.00 07/2015 -
03/2017 20(O) -
0/0
270 NETWORK FOR SPECTRUM (NFS) OFC LAYING PROJECT, PACKAGE F AND G, A PART OF INTELLIGENT FIBER OPTIC C - [N26000102]ITI,MULTI STATE , Central Sector Projects
09/2014 2,111.17 -
2,011.17 1,360.00 09/2014 -
03/2017 30(O) -
0/70
Total 15,445.17 -
15,345.17 2,720.00 0/70
URBAN DEVELOPMENT
271 BANGALORE METRO RAIL PROJECT PHASE-2 - [N28000058]BMRCL,KARNATAKA , .
02/2014 26,405.14 26,405.01
26,405.01 217.54 02/2019 03/2020
03/2020 13(O) 0(R)
0/0
272 NAGPUR METRO RAIL - [N28000085]NMRCL,MAHARASHTRA , .
08/2014 8,680.00 -
8,680.00 74.92 03/2018 -
03/2018 0(O) -
0/0
273 BANGALORE METRO RAIL PROJECT - [N28000008]MRTP,KARNATAKA , .
05/2006 6,395.00 11,609.00
13,845.01 13,525.81 06/2011 12/2015
06/2016 60(O) 6(R)
3/3
274 KOCHI METRO RAIL PROJECT - [N28000081]KMRCL,KERALA , .
07/2012 5,181.79 -
5,181.79 2,562.95 07/2017 -
06/2017 -1(O) -
0/0
275 ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHI - [N28000071]CPWD,DELHI , .
10/2013 1,219.21 -
1,219.21 - 07/2017 -
07/2017 0(O) -
0/0
276 CHENNAI METRO RAIL LTD (PHASE 1) - [N28000084]CMRL,TAMIL NADU , .
02/2009 14,600.00 14,600.00
14,600.00 11,786.98 12/2015 -
08/2016 8(O) -
1/24
277 REDEVELOPMENT OF EAST KIDWAI NAGAR - [N28000080]NBCC,DELHI , .
06/2012 4,264.00 -
4,264.00 1,055.27 11/2019 -
11/2019 0(O) -
0/7
278 DELHI MRTS PHASE-III - [N28000056]DMRCL,DELHI , . 09/2011 38,585.00 -
38,585.00 20,172.80 03/2016 -
12/2016 9(O) -
0/0
279 MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ) - [N28000086]MMRCL,MAHARASHTRA , .
07/2013 23,136.00 -
23,136.00 - 01/2015 -
12/2015 - 0/0
Total 128,466.14 -
135,916.02 49,396.27 4/34
Grand Total 864,705.66 1,054,852.17 454,705.43 1098/2093
* - Information in respect of Ministry of Railways is as on 01.01.2015. Ministry of Railways is not updating the information. The Ministry of Railways has resumed data updation of 20 projects which have been identified to be monitored at MoSPI level.
Project Status with respect to OriginalSchedule: Out of 279 projects, 2projects are ahead of schedule, 57projects are on schedule 133 projectsare delayed. 74 projects do not havefixed dates of commissioning.13projects were sanctioned without anycommissioning date but subsequentlydates of completion were finalised.
Brief Analysis
Project Implementation - Current Status:
Investment Scenario
Total original cost of implementationof 279 projects when sanctioned, was ofthe order of Rs. 864705.66 crore butthis was subsequently revised to Rs.1054852.17 crore implying a costoverrun of 22%. The expenditureincurred on these projects till January,2016 is Rs. 454705.43 crore, which is43.1% of the revised cost of theprojects.
Summary of projects in the for the month of January, 2016
Number of Projects in Previous Month
Number of Projects completed/dropped/frozen in Current Month
Number of Projects Added in Current Month
Number of Projects in Current Month
278
2
3
279
Mega Report
Project Status with respect to OriginalSchedule: Out of 4 projects, 4 projectsare delayed.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 4 projects when sanctioned, was ofthe order of Rs. 40442 crore but thiswas subsequently anticipated to Rs.51918 crore implying a cost overrun of28.4%. The expenditure incurred onthese projects till January, 2016 is Rs.39455.14 crore, which is 76% of therevised cost of the projects.
Sector wise current status of projects on the
ATOMIC ENERGY
Mega Report
Number of Projects
Number of Projects Delayed
4
4
Project Status with respect to OriginalSchedule: Out of 15 projects, 8 projectsare on schedule 7 projects are delayed.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 15 projects when sanctioned, was ofthe order of Rs. 34396.21 crore but thiswas subsequently anticipated to Rs.35203.76 crore implying a cost overrunof 2.3%. The expenditure incurred onthese projects till January, 2016 is Rs.8771.29 crore, which is 24.9% of therevised cost of the projects.
Sector wise current status of projects on the
COAL
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
15
8
7
Project Status with respect to OriginalSchedule: Out of 7 projects, 4 projectsare on schedule 3 projects are delayed.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 7 projects when sanctioned, was ofthe order of Rs. 43623.37 crore but thiswas subsequently anticipated to Rs.43914.49 crore implying a cost overrunof .7%. The expenditure incurred onthese projects till January, 2016 is Rs.25409.49 crore, which is 57.9% of therevised cost of the projects.
Sector wise current status of projects on the
STEEL
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
7
4
3
Project Status with respect to OriginalSchedule: Out of 29 projects, 1 projectis ahead of schedule, 9 projects are onschedule 16 projects are delayed. 3projects do not have fixed dates ofcommissioning.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 29 projects when sanctioned, was ofthe order of Rs. 116156.37 crore butthis was subsequently anticipated toRs. 125588.13 crore implying a costoverrun of 8.1%. The expenditureincurred on these projects till January,2016 is Rs. 62431.79 crore, which is49.7% of the revised cost of theprojects.
Sector wise current status of projects on the
PETROLEUM
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
Number of Projects Ahead
Number of Projects Without Date Of Commissioning
29
9
16
3
1
Project Status with respect to OriginalSchedule: Out of 63 projects, 21projects are on schedule 41 projectsare delayed. 1 project does not havefixed dates of commissioning.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 63 projects when sanctioned, was ofthe order of Rs. 284164.56 crore butthis was subsequently anticipated toRs. 332227.47 crore implying a costoverrun of 16.9%. The expenditureincurred on these projects till January,2016 is Rs. 164180.57 crore, which is49.4% of the revised cost of theprojects.
Sector wise current status of projects on the
POWER
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
Number of Projects Without Date Of Commissioning
63
21
41
1
Project Status with respect to OriginalSchedule: Out of 85 projects, 2 projectsare on schedule 21 projects aredelayed. 51 projects do not have fixeddates of commissioning.11 projectswere sanctioned without anycommissioning date but subsequentlydates of completion were finalised.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 85 projects when sanctioned, was ofthe order of Rs. 97661.81 crore but thiswas subsequently anticipated to Rs.203275.92 crore implying a costoverrun of 108.1%. The expenditureincurred on these projects till January,2016 is Rs. 60680.15 crore, which is29.9% of the revised cost of theprojects.
Sector wise current status of projects on the
RAILWAYS
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
Number of Projects Without Date Of Commissioning
85
2
21
51Number of Projects Without Original Date of Commissioning 11
Project Status with respect to OriginalSchedule: Out of 61 projects, 10projects are on schedule 33 projectsare delayed. 16 projects do not havefixed dates of commissioning.2 projectswere sanctioned without anycommissioning date but subsequentlydates of completion were finalised.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 61 projects when sanctioned, was ofthe order of Rs. 92888.02 crore but thiswas subsequently anticipated to Rs.94067.51 crore implying a cost overrunof 1.3%. The expenditure incurred onthese projects till January, 2016 is Rs.31639.97 crore, which is 33.6% of therevised cost of the projects.
Sector wise current status of projects on the
ROAD TRANSPORT AND HIGHWAYS
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
Number of Projects Without Date Of Commissioning
61
10
33
16Number of Projects Without Original Date of Commissioning 2
Project Status with respect to OriginalSchedule: Out of 1 project, 1 projectdoes not have fixed dates ofcommissioning.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 1 project when sanctioned, was ofthe order of Rs. 2427.4 crore but thiswas subsequently anticipated to Rs.2427.4 crore The expenditure incurredon these projects till January, 2016 isRs. 841.02 crore, which is 34.6% of therevised cost of the projects.
Sector wise current status of projects on the
SHIPPING AND PORTS
Mega Report
Number of Projects
Number of Projects Without Date Of Commissioning
1
1
Project Status with respect to OriginalSchedule: Out of 2 projects, 2 projectsare delayed.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 2 projects when sanctioned, was ofthe order of Rs. 15445.17 crore but thiswas subsequently anticipated to Rs.15345.17 cr The expenditure incurredon these projects till January, 2016 isRs. 2720 crore, which is 17.7% of therevised cost of the projects.
Sector wise current status of projects on the
TELECOMMUNICATIONS
Mega Report
Number of Projects
Number of Projects Delayed
2
2
Project Status with respect to OriginalSchedule: Out of 9 projects, 1 project isahead of schedule, 3 projects are onschedule 4 projects are delayed. 1project does not have fixed dates ofcommissioning.
Brief Analysis
Current Status:
Investment Scenario
Total original cost of implementationof 9 projects when sanctioned, was ofthe order of Rs. 128466.14 crore butthis was subsequently anticipated toRs. 135916.02 crore implying a costoverrun of 5.8%. The expenditureincurred on these projects till January,2016 is Rs. 49396.27 crore, which is36.3% of the revised cost of theprojects.
Sector wise current status of projects on the
URBAN DEVELOPMENT
Mega Report
Number of Projects
Number of Projects On Schedule
Number of Projects Delayed
Number of Projects Ahead
Number of Projects Without Date Of Commissioning
9
3
4
1
1
ANNEXURE
STATUS OF CENTRAL SECTOR PROJECTS COSTING Rs.1000 CRORE AND ABOVE(All Cost /Expenditure in Rs. crore)
Annexure - I
STATE NO OFPROJECTS
COST ORIGINAL
COST ANTICIPATED
CUMULATIVEEXPENDITURE
S.NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
ANDHRA PRADESH
ARUNACHAL PRADESH
ASSAM
BIHAR
CHHATISGARH
D & N HAVELI
DELHI
GUJARAT
HARYANA
HIMACHAL PRADESH
JAMMU AND KASHMIR
JHARKHAND
KARNATAKA
KERALA
MADHYA PRADESH
MAHARASHTRA
MANIPUR
MEGHALAYA
MIZORAM
MULTI STATE
NAGALAND
ODISHA
RAJASTHAN
SIKKIM
TAMIL NADU
TELANGANA
TRIPURA
UTTAR PRADESH
UTTARAKHAND
WEST BENGAL
5
3
7
10
15
1
4
7
3
3
9
7
15
4
13
23
1
2
2
63
3
12
3
1
17
4
3
13
4
22
6,267.19
9,356.22
17,380.14
35,743.29
79,254.78
6,086.08
45,462.73
20,429.57
4,629.72
6,883.26
25,620.25
27,804.25
59,406.87
20,949.79
33,201.08
93,265.27
727.56
5,577.5
988.06
1,39,089.65
6,420
58,045.77
16,382.21
1,339.48
55,625.65
3,714.11
2,129.35
32,985.23
8,654.06
41,286.54
6,984.19
25,412
31,820.63
48,337.68
80,053.87
6,086.08
45,462.73
20,639.57
5,809.72
13,282.54
45,229.68
29,728.92
74,654.84
24,944.79
34,603.14
1,01,851.15
6,570.75
6,802.38
4,201.96
1,65,681.83
8,757.12
66,685
16,381.7
4,190
70,343
4,730.16
5,125.82
36,304.05
10,843.74
53,333.13
3,711.21
13,424.9
26,111.94
30,492.31
46,979.52
592.92
21,229.77
8,770.8
4,496.62
6,641.69
15,245.67
7,482.47
27,982.06
14,192.44
6,543.79
28,107.23
2,787.99
2,097.79
1,151.23
53,333.34
10.44
35,941.16
7,814
88.56
46,133.24
866.79
2,829.76
15,338.82
5,235.62
19,071.35
279 8,64,705.66 10,54,852.17 4,54,705.43TOTAL
LIST OF PROJECTS IN WHICH EXPENDITURE IS MORE THAN APPROVED COST(All Cost /Expenditure in Rs. crore)
Annexure - II
1
2
3
4
5
6
7
8
9
10
11
12
13
14
KUDANKULAM APP (NPCIL) PROTOTYPE FAST BREEDER REACTOR(BHAVINI, 500 MWE) PARBATI HEP (4X200 MW) (NHPC)II SUBANSIRI LOWER H.E.P (8X250MW) (NHPC) TEESTA LOW DAM HEP, STAGE-IV(4X40 MW) (NHPC) UDHAMPUR-SRINAGAR-BARAMULLA(NL),NR NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR KANPUR KASGANJ MATHURA(GC) NER JAYANAGAR-DARBHANGA-NARKATIAGANJ(GC),ECR KATIHAR - JOGBANI (GC)(NEFR) QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) NEW MAYNAGURI TO JOGIGHOPA VIACHANGRABANDHA (NL),NEFR TOLLYGANJ-GARIA WITH EXTENSIONTO DUM DUM-NOAPARA ANDNOAPARA-NSCB AIRPORT(MTP)
ATOMICENERGY
ATOMICENERGY
POWER
POWER
POWER
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
12/2001
09/2003
09/2002
09/2003
09/2005
03/1995
04/1983
02/1997
03/1997
04/1997
09/2001
03/1998
04/2000
03/2000
13,171
3,492
3,919.59
6,285.33
1,061.38
2,500
36.8
295
677.97
501.69
492.98
280
733
1,049.69
17270
-
-
-
-
-
36.38
-
1062.36
501.69
-
-
733
3385.14
S.NO. PROJECT DATE OFAPPROVAL
COSTORIGINAL
COSTREVISED
EXPENDITURECUMM
SECTOR
21,077
5,150.14
5,398.46
7,969.14
1,956.52
10,722.72
255.55
1,092.98
1,621.4
819.19
743.74
889.95
1,732.43
3,551.53
LIST OF PROJECTS IN WHICH EXPENDITURE IS MORE THAN APPROVED COST(All Cost /Expenditure in Rs. crore)
Annexure - II
15
16
17
18
19
20
21
22
23
24
25
26
27
28
HARIDASPUR-PARADEEP(NL) JIRIBAM TO IMPHAL(TUPUI)(NL)(NEFR) PATNA GANGA BRIDGE (NL), ECR SUKINDA ROAD - ANGUL(NL)(ECOR) CONSTRUCTION OF MEDICALCOLLEGE AND HOSPITAL ATGULBARGA ASSAM GAS CRACKER PROJECT KISHANGANGA HEP (3X110 MW) TRANSMISSION SYSTEMSTRENGTHENING IN WESTERN PARTOF WR FOR IPPS GENERATIONPROJECTS IN CHATTISGARH MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI AGARTALA SABROOM, NL, NEFR LUMDING-SILCHAR JIRIBAM,BADARPUR-BARAIGRAM KUMARGHATNATIONAL PROJECT VILLUPURAM-DINDIGUL WITHELECTRIFICATION CONSTRUCTION OF NL FROMKUMARGHAT-AGARTALA NEW JALPAIGURI-SILIGURI-NEWBONGAIGAON INCLUDING BR. LINEAND MM FOR CHALSA-NAXAL&RAJABHATKHOWA-JAI
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
STEEL
PETROCHEMICALS
POWER
POWER
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
04/1996
04/2003
04/2001
04/1998
05/2005
04/2006
01/2009
11/2011
09/2007
04/2008
04/1996
04/2008
04/1999
04/1999
301.64
727.56
624.47
183.23
768.88
5,460.61
3,642.04
2,127.51
404.19
813.34
1,676.31
822.39
895
523.17
-
727.56
-
-
1060
8920
-
-
-
813.34
-
-
-
380.6
S.NO. PROJECT DATE OFAPPROVAL
COSTORIGINAL
COSTREVISED
EXPENDITURECUMM
SECTOR
577.84
2,787.99
2,521.72
185.46
1,070.97
9,175.15
4,402.95
2,319.63
457.88
823.83
4,769.59
1,031.83
1,047.1
1,040.11
LIST OF PROJECTS IN WHICH EXPENDITURE IS MORE THAN APPROVED COST(All Cost /Expenditure in Rs. crore)
Annexure - II
29
30
31
32
33
34
35
36
37
38
39
MUNIRABAD (GINGERA) -RAICHURNL PANIPAT-JALANDHAR 6 LANE(KM 96TO 387.1 KM) MURADABAD-BAREILY PUNE-SATARA(NH-4) GHAZIABAD-ALIGARH NH-91 SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TOKM.1366.547 6-LANING OF DHANKUNI-KHARAGPURSECTION ETAWAH CHAKERI 2 LANING OF SHILLONGNONGSTOIN SECTION OF NH 44 ANDNONGSTOIN TURA STATE ROADUNDER PHASE A OF SAFOUR LANING FROM MPMAHARASHTRABORDER TO NAGPUR IC KAMPTEEKANOON AND NAGPUR BYPASS BANGALORE METRO RAIL PROJECT
RAILWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
ROADTRANSPORTAND HIGHWAYS
URBANDEVELOPMENT
04/2007
05/2009
04/2010
10/2010
02/2011
11/2011
04/2012
03/2013
12/2010
04/2010
05/2006
179.65
1,108
1,267
1,724.55
1,141
1,535
1,396.18
1,573
1,494.48
1,170.52
6,395
-
-
-
-
-
-
-
-
-
-
11609
S.NO. PROJECT DATE OFAPPROVAL
COSTORIGINAL
COSTREVISED
EXPENDITURECUMM
SECTOR
380.62
3,619.94
2,425
1,742.94
1,911.64
2,478.63
2,287.44
1,840
2,090
1,579.15
13,525.81
Annexure - III Details of Projects Ahead of Schedule w.r.t. Original Schedule
(January 2016)
Date of Commissioning
(Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost (Rs. crore)
Antici pated Cost
(Rs. crore)
Cumulative Expenditure (Rs. crore)
Original/ Revised
Antici pated
1 2 3 4 5 6 7 8 URBAN DEVELOPMENT
1 KOCHI METRO RAIL PROJECT - [N28000081
7/2012 5,181.79 -
5,181.79 2,562.95 07/2017 -
06/2017
Total 5,181.79 -
5,181.79 2,562.95
PETROLEUM
2 MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-III - [N16000197
11/2014 6,068.80 -
6,068.80 648.01 04/2019 -
03/2019
Total 6,068.80 -
6,068.80 648.01
Grand Total 11,250.59 11,250.59 3,210.96
Annexure - IV Details of On Schedule Projects w.r.t. Original Schedule
(January 2016)
Date of Commissioning
(Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure (Rs. crore)
Original/ Revised
Antici Pated
1 2 3 4 5 6 7 8
COAL 1 AMLOHRI EPR (NCL) (6 MTY , INCR.)
- [N06000010 12/2009 1,352.04
- 1,143.54 809.04 03/2016
- 03/2016
2 RAMPUR BATURA OCP (4.0 MTY) - [N06000049
8/2015 1,186.64 -
1,186.64 1.33 03/2023 -
03/2023
3 GARJANBAHAL OCP - [N06000117
11/2014 1,375.38 -
1,375.38 179.10 03/2021 -
03/2021
4 MADANNAGAR OPENCAST PROJECT - [N06000140
10/2015 1,875.32 -
1,875.32 - 03/2024 -
03/2024
5 PELMA OCP(15.00MTY) - [N06000045
11/2014 1,624.59 -
1,624.59 5.43 03/2023 03/2023
03/2023
6 KUSMUNDA EXPN.OCP(SECL)(15-50)MTY - [N06000008
8/2013 7,612.33 -
7,612.33 798.52 03/2023 03/2023
03/2023
7 SIARMAL OCP (40.00MTY) - [N06000113
5/2014 3,756.36 -
3,756.36 620.94 03/2026 -
03/2026
8 KHADIA EXPANSION OPENCAST PROJECT(4 TO 10 MTPA,6MTPA INCREMENTAL) - [N06000091
6/2011 1,131.28 -
1,131.28 148.45 03/2018 -
03/2018
Total 19,913.94 -
19,705.44 2,562.81
PETROLEUM 9 INSTALLATION OF DIESEL HYDROTREATMENT UNIT (DHT)
AND ASSOCIATED FACILITIES - [N16000205 5/2015 2,443.00
- 2,443.00 - 12/2017
- 12/2017
10 INTEGRATED REFINERY EXPANSION PROJECT - [N16000143
3/2012 14,225.00 -
16,504.00 10,044.66 05/2016 -
05/2016
11 DIESEL HYDROTREATOR - [N16000207
7/2015 1,031.37 -
1,031.37 12.72 01/2018 -
01/2018
12 NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAY - [N16000204
8/2015 2,818.88 -
2,818.88 - 03/2019 -
03/2019
13 GAMJI REDEVELOPMENT PROJECT - [N16000202
5/2015 1,671.22 -
1,881.22 - 11/2019 -
11/2019
14 ADDITIONAL DEVELOPMENT OF VASAI EAST FIELD - [N16000183
3/2014 2,476.82 -
2,476.82 599.26 12/2018 -
12/2018
15 MH NORTH REDEVELOPMENT PHASE III - [N16000188
6/2014 5,706.47 -
5,813.25 2,689.65 05/2017 05/2017
05/2017
16 PIPELINE REPLACEMENT PROJECT -4 - [N16000203
2/2015 2,899.93 -
2,098.43 641.31 05/2017 -
05/2017
17 POLYPROPYLENE PLANT AT PARADIP REFINERY - [N16000179
3/2014 3,150.00 -
3,150.00 111.66 09/2017 -
09/2017
Total 36,422.69 -
38,216.97 14,099.26
POWER 18 LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MW
- [N18000142 7/2012 1,527.00
- 1,527.00 143.00 08/2017
- 08/2017
19 DARLIPALLI STPP STAGE-I (2X800 MW) - [N18000176
2/2014 12,532.44 -
12,532.44 2,500.00 08/2018 -
08/2018
20 PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) - [N18000172
10/2014 8,112.12 -
8,112.12 120.00 04/2020 -
04/2020
(January 2016)
Date of Commissioning
(Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure (Rs. crore)
Original/ Revised
Antici Pated
1 2 3 4 5 6 7 8
21 NPGCPL-NABINAGAR STPP - JV (3X660 MW) - [N18000192
1/2013 12,964.60 -
12,964.60 4,914.20 01/2018 -
01/2018
22 TRANSMISSION SYSTEM STRENGTHENING IN WR-NR TRANSMISSION CORRIDOR FOR IPPS IN CHHATTISGARH - [N18000168
6/2014 5,151.37 -
5,151.37 703.00 03/2018 -
03/2018
23 GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART B - [N18000196
4/2015 3,705.61 -
3,705.61 194.60 04/2018 -
04/2018
24 GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME (ISTS) - PART A - [N18000197
4/2015 1,479.30 -
1,479.30 78.90 04/2017 -
04/2017
25 CREATION OF 400/220 KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-A) - [N18000188
3/2015 1,394.52 -
1,394.52 1.70 05/2017 -
05/2017
26 INSTALLATION OF STATCOMS IN WESTERN REGION - [N18000185
3/2015 1,071.24 -
1,071.24 0.10 09/2017 -
09/2017
27 TRANSMISSION SYSTEM ASSOCIATED WITH MAUDA STAGE-II - [N18000153
9/2013 1,575.30 -
1,575.30 709.90 05/2016 -
05/2016
28 WARDHA-HYDERABAD 765 KV LINK - [N18000183
1/2015 3,662.02 -
3,662.02 338.80 05/2018 -
05/2018
29 TANDA TPP STAGE-II (2X660 MW) - [N18000175
9/2014 9,188.98 -
9,188.98 1,000.00 03/2019 -
03/2019
30 GADARWARA SUPER THERMAL POWER PROJECT STAGE-I - [N18000151
3/2013 11,638.55 -
11,638.55 4,856.00 09/2017 -
09/2017
31 RAMMAM-III HEPP (3X40 MW) - [N18000178
9/2014 1,381.84 -
1,381.84 157.00 09/2019 -
09/2019
32 KHARGONE STPP STAGE I (1320 MW) - [N18000205
3/2015 9,870.51 -
9,870.51 - 09/2019 -
09/2019
33 NORTH KARANPURA STPP (3X660 MW) - [N18000177
2/2014 14,366.58 -
14,366.58 2,349.00 02/2019 -
02/2019
34 INTER-REGIONAL SYSTEM STRENGTHENING SCHEME IN WR AND NR (PART-B) - [N18000179
12/2014 6,517.36 -
6,517.36 301.90 04/2018 -
04/2018
35 GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART C - [N18000200
7/2015 2,247.37 -
2,247.37 16.00 07/2018 -
07/2018
36 LARA SUPER THERMAL POWER PROJECT STAGE-I (2 X 800 MW) - [N18000140
12/2012 11,846.00 -
11,846.00 5,564.00 06/2017 -
06/2017
37 SYSTEM STRENGTHENING XXIV IN SOUTHERN REGION - [N18000208
1/2016 1,455.47 -
1,455.47 - 07/2018 -
07/2018
38 FGUTPP, UNCHAHAR STAGE-IV (1X500 MW) - [N18000174
7/2013 3,363.12 -
3,363.12 1,018.00 12/2016 -
12/2016
Total 125,051.30 -
125,051.30 24,966.10
RAILWAYS 39 DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY
AND MOHARI-TANTPUR & TANPUR-BANSI PAHARPUR - [N22000158
4/2010 622.41 -
2,030.50 3.61 02/2019 -
02/2019
40 GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC) - [N22000148
4/2011 1,176.09 -
3,845.60 2.33 02/2020 -
02/2020
Total 1,798.50 -
5,876.10 5.94
ROAD TRANSPORT AND HIGHWAYS 41 FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1A
- [N24000471 12/2015 2,168.66
- 2,168.66 - 06/2019
- 06/2019
(January 2016)
Date of Commissioning
(Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure (Rs. crore)
Original/ Revised
Antici Pated
1 2 3 4 5 6 7 8
42 FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120 - [N24000349
5/2015 1,387.11 -
1,387.11 - 11/2017 -
11/2017
43 FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA - [N24000496
6/2015 1,012.90 -
1,012.90 - 03/2016 -
03/2016
44 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION - [N24000462
5/2014 1,655.01 -
1,655.01 - 08/2016 -
08/2016
45 FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A - [N24000488
12/2015 2,136.97 -
2,136.97 - 12/2018 -
12/2018
46 FOUR LANING OF SULTANPUR TO VARANASI (PKG-I) - [N24000493
1/2016 1,027.53 -
1,027.53 - 06/2018 -
06/2018
47 4 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785) - [N24000463
12/2015 1,083.00 -
1,083.00 - 06/2018 -
06/2018
48 FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM) - [N24000232
11/2013 1,916.79 -
1,916.79 1,202.43 11/2016 -
11/2016
49 4 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9 - [N24000233
4/2014 1,266.60 -
1,266.60 - 09/2016 -
09/2016
50 FOUR LANING OF AURANGABAD - YEDISHI - [N24000508
7/2015 1,871.34 -
1,871.34 830.19 01/2018 -
01/2018
Total 15,525.91 -
15,525.91 2,032.62
STEEL 51 EXPANSION OF GUA ORE MINES WITH BENEFICIATION
FACILITIES AND INSTALLATION OF PELLET PLANT - [N12000097
2/2014 4,749.00 -
4,749.00 2.61 09/2017 -
09/2017
52 INSTALLATION OF NEW HOT STRIP MILL AT RSP - [N12000094
4/2015 3,127.30 -
3,127.30 297.93 04/2018 -
04/2018
53 MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANT - [N12000096
5/2015 1,154.18 -
1,154.18 28.20 12/2017 -
12/2017
54 NEW SINTER PLANT AT BOKARO STEEL PLANT - [N12000095
3/2015 1,034.01 -
1,034.01 - 10/2017 -
10/2017
Total 10,064.49 -
10,064.49 328.74
URBAN DEVELOPMENT 55 REDEVELOPMENT OF EAST KIDWAI NAGAR
- [N28000080 6/2012 4,264.00
- 4,264.00 1,055.27 11/2019
- 11/2019
56 NAGPUR METRO RAIL - [N28000085
8/2014 8,680.00 -
8,680.00 74.92 03/2018 -
03/2018
57 ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHI - [N28000071
10/2013 1,219.21 -
1,219.21 - 07/2017 -
07/2017
Total 14,163.21 -
14,163.21 1,130.19
Grand Total 222,940.04 228,603.42 45,125.66
Annexure - V Details of Ongoing Projects having Cost Overruns w.r.t. to Original Schedule
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overruns
(%)
1 2 3 4 5 6 7 8 ATOMIC ENERGY 1 PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500
MWE) - [020100044 09/2003 3,492.00
- 5,677.00 09/2010
- 09/2016 62.57
2 KUDANKULAM APP (NPCIL) - [020100040
12/2001 13,171.00 -
22,462.00 12/2008 -
05/2016 70.54
Total 16,663.00 -
28,139.00
COAL 3 ADRIYALA SHAFT PROJECT
- [N06000016 12/2009 212.34
- 1,228.39 03/2013
- 03/2016 478.50
Total 212.34 -
1,228.39
HEAVY INDUSTRY 4 NATIONAL AUTOMOTIVE TESTING AND RD
INFRASTRUCTURE PROJECT (NATRIP) - [N20000001
04/2011 1,718.00 -
3,827.30 09/2011 -
12/2017 122.78
Total 1,718.00 -
3,827.30
PETROCHEMICALS 5 ASSAM GAS CRACKER PROJECT
- [N16000106 04/2006 5,460.61
- 9,965.00 04/2012
- 12/2015 82.49
Total 5,460.61 -
9,965.00
PETROLEUM 6 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR
- [N16000169 01/2006 993.00
- 1,693.00 01/2012
- 05/2016 70.49
7 INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS - [N16000172
05/2013 4,124.35 -
4,941.49 04/2016 -
12/2017 19.81
8 MH NORTH REDEVELOPMENT PHASE III - [N16000188
06/2014 5,706.47 -
5,813.25 05/2017 -
05/2017 1.87
9 GAMJI REDEVELOPMENT PROJECT - [N16000202
05/2015 1,671.22 -
1,881.22 11/2019 -
11/2019 12.57
10 CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS) - [N16000128
03/2011 861.79 -
1,256.72 05/2013 -
04/2016 45.83
11 PARADIP REFINERY PROJECT - [N16000058
02/2009 29,777.00 -
34,555.00 11/2012 -
02/2016 16.05
12 INTEGRATED DEVELOPMENT OF B-127 FIELDS - [N16000131
12/2011 2,059.63 -
2,665.65 03/2015 -
05/2016 29.42
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overruns
(%)
1 2 3 4 5 6 7 8 13 INTEGRATED REFINERY EXPANSION PROJECT
- [N16000143 03/2012 14,225.00
- 16,504.00 05/2016
- 05/2016 16.02
14 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE - [N16000157
01/2006 732.00 -
1,227.00 10/2011 -
03/2016 67.62
15 UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE - [N18000148
09/2012 871.35 -
1,200.00 03/2015 -
08/2016 37.72
Total 61,021.81 -
71,737.33
POWER
16 PARBATI HEP (4X200 MW) (NHPC) II - [180100210
09/2002 3,919.59 -
8,398.76 09/2009 -
12/2018 114.28
17 SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) - [180100221
09/2003 6,285.33 -
18,063.89 09/2010 -
- 187.40
18 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) - [180100243
09/2005 1,061.38 -
2,193.08 09/2009 -
09/2016 106.63
19 NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECT - [N18000066
02/2009 11,130.19 -
13,762.80 08/2013 -
12/2017 23.65
20 TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS. - [N18000080
02/2010 2,144.00 -
2,932.88 12/2012 -
12/2016 36.79
21 TAPOVAN-VISHNUGAD HEP (4X130MW) - [N18000014
11/2006 2,978.48 -
3,846.30 03/2013 -
12/2018 29.14
22 BONGAIGAON THERMAL POWER PROJECT - [N18000041
01/2008 4,375.35 -
6,749.18 09/2011 -
03/2017 54.25
23 BOKARO THERMAL POWER STATION-A - [N18000199
08/2006 2,313.00 4,139.00
4,237.67 12/2011 -
03/2016 83.21
24 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202
04/2007 4,122.00 8,781.00
9,606.82 02/2011 -
01/2017 133.06
25 KAMENG HYDROELECTRIC PROJECT (NEEPCO) - [180100239
12/2004 2,496.90 -
6,085.84 12/2009 06/2016
06/2016 143.74
26 TEHRI PUMPED STORAGE PLANT(1000MW) - [N18000010
07/2006 1,657.00 -
2,978.86 02/2016 -
09/2019 79.77
27 PARE HYDRO ELECTRIC PROJECT - [N18000045
12/2008 573.99 -
1,262.27 08/2013 -
07/2016 119.91
28 SYSTEM STRENGTHENING IN NORTH/WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARH - [N18000116
12/2011 1,746.65 -
2,228.71 08/2014 -
06/2016 27.60
29 KISHANGANGA HEP (3X110 MW) - [N18000031
01/2009 3,642.04 -
5,751.47 01/2016 -
11/2016 57.92
30 KUNADANKULAM APP TRANS SYSTEM (PGCIL) - [180100258
05/2005 1,779.29 -
2,187.32 11/2008 -
12/2016 22.93
31 BARH STPP(3X660MW) NTPC - [180100242
02/2005 8,692.97 -
15,095.67 01/2011 -
05/2018 73.65
32 TUIRIAL HYDRO ELECTRIC PROJECT (60MW) - [N18000119
07/1998 368.72 -
1,381.71 07/2006 02/2015
10/2016 274.73
33 TRIPURA GAS BASED POWER PROJECT - [N18000071
07/2009 421.01 -
1,007.57 07/2013 -
01/2016 139.32
Total 59,707.89 -
107,770.80
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overruns
(%)
1 2 3 4 5 6 7 8 RAILWAYS
34 NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR - [220100135
04/1983 36.80 274.41
1,336.57 - -
03/2019 3,531.98
35 KATIHAR - JOGBANI (GC)(NEFR) - [220100247
09/2001 492.98 -
1,727.27 12/2010 -
03/2018 250.37
36 QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) - [220100263
03/1998 280.00 -
1,122.00 - -
- 300.71
37 KOTLPALLI-NARASAPUR (NL) (SCR) - [220100265
12/2001 330.00 -
1,047.00 - -
- 217.27
38 TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP) - [220100268
03/2000 1,049.69 -
3,404.92 12/2006 -
- 224.37
39 BANKURA - DAMODAR (GC) (SER) - [220100277
03/1998 111.90 -
2,371.85 03/2005 12/2008
12/2019 2,019.62
40 HARIDASPUR-PARADEEP(NL) - [220100285
04/1996 301.64 -
1,185.64 - 09/2009
- 293.06
41 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307
04/2002 921.00 -
3,040.00 03/2009 -
03/2016 230.08
42 RAMGANJMUNDI-BHOPAL (NL),WCR - [220100314
04/2001 470.92 727.13
1,225.90 - -
03/2017 160.32
43 CHHINDWARA - NAGPUR (GC)(SECR) - [220100324
04/2005 383.79 -
1,101.16 - -
03/2017 186.92
44 SUKINDA ROAD - ANGUL (NL)(ECOR) - [220100325
04/1998 183.23 -
1,202.70 02/2015 -
- 556.39
45 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI - [N22000079
09/2007 404.19 -
1,383.45 - -
- 242.28
46 TIDIVANAM-NAGARI (NL) - [N22000085
09/2006 456.00 -
1,080.00 - -
- 136.84
47 BHAIRABI SAIRONG, NL, NEFR - [N22000100
04/2008 619.34 -
2,820.25 04/2014 -
03/2018 355.36
48 RATLAM-MHOW-KHANDWA-AKOLA (GC) - [N22000120
04/2008 603.04 -
1,421.25 03/2012 -
- 135.68
49 WARDHA-NANDED MAHARASHTRA - [N22000231
04/2008 499.30 -
2,501.05 - -
- 400.91
50 TUMKUR-CHITRADURGA-DAVENGERE NL - [N22000256
04/2011 913.00 -
1,801.01 - -
- 97.26
51 MUNIRABAD (GINGERA) -RAICHUR NL - [N22000257
04/2007 179.65 -
1,350.91 - -
- 651.97
52 KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION - [N22000261
04/2012 1,054.35 -
2,200.00 - -
- 108.66
53 AKOLA-KHANDWA GC AKOLA-AKOT - [N22000263
04/2008 184.26 -
2,000.00 - -
- 985.42
54 BHANUPALI-BILASPUR BERI NL - [N22000273
04/2008 1,046.88 -
2,966.99 - -
- 183.41
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overruns
(%)
1 2 3 4 5 6 7 8 55 RAYADURGA-TUMKUR NL
- [N22000279 04/2007 970.34
- 1,743.00 -
- - 79.63
56 GADAG-WADI NL - [N22000299
04/2013 1,117.00 -
1,922.00 - -
- 72.07
57 QUILON-TIRUNELVELI - TRICHENDUR, TENKASI - [N22000303
04/1999 460.94 -
1,030.00 01/1999 -
- 123.46
58 AHMEDNAGAR-PARLI VAIJNATH(NL) CR - [220100181
02/1997 514.68 -
2,820.00 - -
- 447.91
59 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164
03/1996 495.44 -
1,781.98 03/2004 -
03/2016 259.68
60 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201
09/1997 1,500.00 -
4,996.19 04/2008 12/2011
06/2017 233.08
61 LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) - [220100232
09/1998 247.66 -
3,500.00 05/2008 -
- 1,313.23
62 JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR - [220100240
04/1997 501.69 335.77
1,043.56 03/2012 -
- 108.01
63 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266
04/2000 733.00 -
2,531.34 12/2008 -
03/2018 245.34
64 KHURDA ROAD-BOLANGIR(NL)ECOR - [220100284
04/1994 470.21 -
1,995.25 - -
- 324.33
65 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288
04/2003 727.56 -
6,570.75 03/2011 -
03/2019 803.12
66 PATNA GANGA BRIDGE (NL), ECR - [220100308
04/2001 624.47 -
2,921.00 10/2007 -
12/2015 367.76
67 NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124
04/2006 850.00 -
2,973.42 03/2015 -
03/2020 249.81
68 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092
04/2008 5,300.00 -
7,986.04 03/2014 -
03/2019 50.68
69 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127
04/1996 1,676.31 -
5,500.00 03/2009 -
03/2016 228.10
70 AGARTALA SABROOM, NL, NEFR - [N22000099
04/2008 813.34 -
2,876.00 03/2014 -
03/2018 253.60
71 SEVOK RANGPO, NEFR - [N22000102
04/2008 1,339.48 -
4,190.00 12/2015 -
03/2020 212.81
72 KANPUR KASGANJ MATHURA(GC) NER - [220100197
03/1997 677.97 1,062.36
1,651.54 - -
03/2018 143.60
73 NANGALDAM-TALWARA(NL),NR - [220100188
03/1981 450.00 -
2,100.00 07/2012 -
- 366.67
74 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133
03/1995 2,500.00 -
20,000.00 11/2002 -
12/2017 700.00
75 UTRATIA-ZAFRABAD, NR (LINE DOUBLING) - [N22000088
04/2006 325.00 -
2,434.00 03/2010 -
- 648.92
76 GONDIA-JABALPUR(GC),(SECR) - [220100186
02/1997 386.30 -
1,544.40 03/1998 -
12/2019 299.79
77 HOWRAH-AMTA-CHAMPADANGA NL (SER) - [220100208
04/1974 393.46 154.30
1,026.00 03/2007 03/2007
03/2015 160.76
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overruns
(%)
1 2 3 4 5 6 7 8 78 TAMLUK DIGHA,LINE DOUBLING (SER)
- [N22000097 03/1984 293.97
- 1,428.00 06/2005
- 12/2019 385.76
79 HUBLI-ANKOLA(NL),SWR - [220100193
04/1997 227.00 -
2,135.00 - -
- 840.53
80 GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM) - [N22000345
04/1997 836.26 -
1,072.51 - -
- 28.25
81 HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR - [220100183
02/1997 295.00 -
1,289.92 - -
- 337.26
82 BANGLORE - SATYAMANGALAM (NL)(SWR) - [220100274
04/1996 138.00 -
1,382.78 - -
- 902.01
83 SAMBALPUR-TALCHER DOUBLING - [N22000315
03/2011 679.27 -
1,111.99 - -
- 63.70
84 KIRANDUL - JAGDALPUR DOUBLING - [N22000318
12/2012 826.57 -
1,143.60 - -
03/2018 38.35
85 ANGAMALI-SABARIMALA (N.L.)(SR) - [220100252
10/1998 550.00 -
1,566.00 - -
- 184.73
86 RATLAM-DUNGARPUR VIA BANSWARA (NL) - [N22000147
04/2011 2,082.75 -
3,500.00 - -
- 68.05
87 GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC) - [N22000148
04/2011 1,176.09 -
3,845.60 02/2020 -
02/2020 226.98
88 DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR & TANPUR-BANSI PAHARPUR - [N22000158
04/2010 622.41 -
2,030.50 02/2019 -
02/2019 226.23
89 DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRA - [N22000160
04/2010 553.63 -
1,009.00 - -
12/2019 82.25
90 NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING - [N22000183
04/2013 1,798.00 -
1,887.90 - -
03/2019 5.00
91 CHENNAI-CUDDALORE VIA MAMALLAPURAM - [N22000185
04/2008 523.52 -
1,200.00 - -
- 129.22
92 SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDUR - [N22000186
04/2013 839.00 -
1,500.00 - -
- 78.78
93 VILLUPURAM-DINDIGUL WITH ELECTRIFICATION - [N22000189
04/2008 822.39 -
1,280.83 - -
- 55.74
94 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194
04/1999 895.00 -
1,242.25 03/2007 -
03/2016 38.80
95 DIMAPUR-TIZIT NL - [N22000196
04/2013 4,274.00 -
4,487.70 - -
03/2020 5.00
96 NEW BG LINE FROM BYRNIHAT TO SHILLONG - [N22000205
04/2010 4,083.02 -
5,307.90 - -
03/2020 30.00
97 NEW JALPAIGURI-SILIGURI-NEW BONGAIGAON INCLUDING BR. LINE AND MM FOR CHALSA-NAXAL& RAJABHATKHOWA-JAI - [N22000209
04/1999 523.17 -
1,653.55 - -
03/2018 216.06
Total 55,635.86 -
163,501.42
ROAD TRANSPORT AND HIGHWAYS
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overruns
(%)
1 2 3 4 5 6 7 8 98 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM)
- [N24000133 05/2009 1,108.00
- 2,288.00 11/2011
- 06/2016 106.50
Total 1,108.00 -
2,288.00
STEEL
99 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA - [N12000101
05/2005 768.88 1,060.00
1,060.00 02/2014 -
03/2016 37.86
Total 768.88 -
1,060.00
URBAN DEVELOPMENT
100 BANGALORE METRO RAIL PROJECT - [N28000008
05/2006 6,395.00 -
13,845.01 06/2011 -
06/2016 116.50
Total 6,395.00 -
13,845.01
Grand Total 208,691.39 403,362.25
Annexure - VI Details of Delayed Projects w.r.t. Original and Revised Schedule
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 ATOMIC ENERGY
1 KUDANKULAM APP (NPCIL) - [020100040]NPCIL,TAMIL NADU
12/2001 13,171.00 17,270.00
22,462.00 21,077.00 12/2008 10/2013
05/2016 89 70.54
2 PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE) - [020100044]BHAVNI,TAMIL NADU
09/2003 3,492.00 -
5,677.00 5,150.14 09/2010 -
09/2016 72 62.57
3 KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4 - [N02000010]NPCIL,GUJARAT
10/2009 11,459.00 -
11,459.00 7,715.00 12/2015 10/2016
11/2018 35 0
4 RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW) - [N02000027]NPCIL,RAJASTHAN
10/2009 12,320.00 -
12,320.00 5,513.00 12/2016 03/2017
12/2019 36 0
Total 40,442.00 -
51,918.00 39,455.14
COAL
5 GEVRA EXPANSION OCP (SECL) (25-35) MTY - [060100093]SECL,CHHATISGARH
06/2010 2,675.67 -
2,675.67 1,990.05 03/2014 -
03/2016 24 0
6 DIPKA EXPANSION OCP (SECL) (20-25) MTY - [060100094]SECL,CHHATISGARH
12/2009 1,943.66 -
1,943.66 1,713.30 03/2014 -
03/2016 24 0
7 ADRIYALA SHAFT PROJECT - [N06000016]SCCL,TELANGANA
12/2009 212.34 1,228.39
1,228.39 866.79 03/2013 09/2012
03/2016 36 478.5
8 NEYVELI NEW THERMAL POWER PROJECT(2X500 MW) - [N06000095]NLC,TAMIL NADU
06/2011 5,907.11 -
5,907.11 1,373.77 12/2015 04/2018
04/2018 28 0
9 SONEPUR BAZARI (COMB) OCP (8.0 MTY) - [N06000109]ECL,WEST BENGAL
08/2012 1,055.05 -
1,055.05 202.22 03/2018 -
06/2018 3 0
10 MOONIDIH XV SEAM UG - [N06000098]BCCL,JHARKHAND
08/2011 1,230.27 -
1,230.27 47.76 04/2015 04/2019
04/2019 48 0
11 EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA) - [N06000138]NLC,TAMIL NADU
04/2013 1,458.17 -
1,458.17 14.59 06/2015 -
08/2019 50 0
Total 14,482.27 -
15,498.32 6,208.48
MINES
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 12 EXPANSION OF MALANJKHAND
MINE-DEVELOPMENT OF UNDERGROUND MINE UNDER EXISTING OPEN CAST MINE OF CAPAC - [N10000007]HCL,MADHYA PRADESH
09/2011 1,856.00 -
1,176.00 4.59 09/2017 -
04/2020 31 -36.64 Delay in grant of statutory clearances i.e.
environmental clearance, clearance from standing
committee of NBWL.
Total 1,856.00 -
1,176.00 4.59
STEEL
13 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA - [N12000101]HSCL,KARNATAKA
05/2005 768.88 1,060.00
1,060.00 1,070.97 02/2014 -
03/2016 25 37.86
14 EXPANSION OF BHILAI STEEL PLANT - [N12000057]SAIL,CHHATISGARH
08/2010 17,265.00 -
17,265.00 15,516.00 03/2013 03/2016
06/2016 39 0
15 NMDC INTEGRATED STEEL PLANT - [N12000086]NMDC,CHHATISGARH
01/2010 15,525.00 -
15,525.00 8,493.78 05/2015 12/2016
12/2016 19 0
Total 33,558.88 -
33,850.00 25,080.75
PETROLEUM
16 DEVELOPMENT OF WO-16 CLUSTER FIELDS - [N16000105]ONGC,MULTI STATE
06/2010 2,523.00 2,523.00
2,523.00 1,792.85 01/2014 12/2015
01/2016 24 0
17 PARADIP REFINERY PROJECT - [N16000058]IOCL,ODISHA
02/2009 29,777.00 34,555.00
34,555.00 31,052.90 11/2012 11/2013
02/2016 39 16.05
18 DE-BOTTLENECKING OF SMPL - [N16000089]IOCL,MAHARASHTRA
12/2009 1,584.00 -
1,584.00 1,399.90 08/2015 -
03/2016 7 0
19 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE - [N16000157]ISPRL,KARNATAKA
01/2006 732.00 1,227.00
1,227.00 1,074.73 10/2011 -
03/2016 53 67.62 issues faced with local elements in the RoU.
20 CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS) - [N16000128]ONGC,MAHARASHTRA
03/2011 861.79 1,256.72
1,256.72 995.12 05/2013 04/2016
04/2016 35 45.83
21 PARADIP-RAIPUR- RANCHI PIPELINE - [N16000088]IOCL,MULTI STATE
08/2009 1,793.00 -
1,793.00 1,294.55 09/2012 -
05/2016 44 0
22 INTEGRATED DEVELOPMENT OF B-127 FIELDS - [N16000131]ONGC,MAHARASHTRA
12/2011 2,059.63 2,665.65
2,665.65 1,323.77 03/2015 05/2016
05/2016 14 29.42
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 23 STRATEGIC CRUDE OIL
STORAGE PROJECT AT PADUR - [N16000169]ISPRL,KERALA
01/2006 993.00 1,693.00
1,693.00 1,447.43 01/2012 -
05/2016 52 70.49 Progress is slow due to heavy rains during the
period, RoU issue 24 UPGRADATION OF CRUDE OIL
PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE - [N18000148]OIL,ASSAM
09/2012 871.35 -
1,200.00 537.65 03/2015 11/2015
08/2016 17 37.72 space constraint in few locations, obstructions,
retendering, poor performance of contractor,
torrential rain, delay in award
25 RESID UPGRADATION PROJECT - [N16000184]CPCL,TAMIL NADU
02/2011 3,110.36 -
3,110.36 1,395.63 11/2015 07/2016
11/2016 12 0
26 ASSAM RENEWAL PROJECT FOR GROUP A - [N16000061]ONGC,ASSAM
03/2009 2,465.15 2,378.89
2,378.89 1,795.13 03/2013 03/2016
03/2017 48 -3.5
27 DEVELOPMENT OF C-26 CLUSTER FIELDS - [N16000133]ONGC,MAHARASHTRA
03/2012 2,592.17 2,592.17
2,592.17 832.22 05/2014 03/2017
03/2017 34 0
28 INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS - [N16000172]ONGC,MULTI STATE
05/2013 4,124.35 4,941.49
4,941.49 549.78 04/2016 12/2017
12/2017 20 19.81
29 DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERY - [N16000175]IOCL,WEST BENGAL
03/2014 3,076.00 -
3,076.00 188.44 09/2017 03/2018
12/2017 3 0
30 PHUPLUR-HALDIA PIPELINE PROJECT PHASE-I - [N16000072]GAIL,MULTI STATE
07/2009 3,957.00 3,561.00
3,561.00 26.81 01/2013 -
12/2018 71 -10.01
31 DAMAN DEVELOPMENT PROJECT - [N16000198]ONGC,D & N HAVELI
08/2014 6,086.08 -
6,086.08 592.92 05/2019 03/2020
03/2020 10 0
Total 66,605.88 -
74,243.36 46,299.83
POWER
32 TRIPURA GAS BASED POWER PROJECT - [N18000071]NEEPCO,TRIPURA
07/2009 421.01 1,007.57
1,007.57 958.83 07/2013 01/2016
01/2016 30 139.32
33 NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXI - [N18000095]PGCIL,MULTI STATE
08/2010 1,677.57 -
1,677.57 1,447.42 04/2013 -
02/2016 34 0 Severe ROW problem in western UP.
34 SYSTEM STRENGTHENING IN NR FOR SASAN AND MUNDRA (UMPP) - [N18000081]PGCIL,MULTI STATE
12/2009 1,216.83 -
1,216.83 1,062.99 08/2012 -
03/2016 43 0 Contractual problem.
35 TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-B - [N18000099]PGCIL,MULTI STATE
03/2011 1,585.12 -
1,585.12 1,578.86 11/2013 -
03/2016 28 0 Delayed land acquisition & severe ROW problem.
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 36 TR SYSTEM FOR PHASE-I
GENERATION PROJECTS IN JHARKHAND AND WEST BENGAL-PART-A2 - [N18000113]PGCIL,MULTI STATE
12/2011 2,422.66 -
2,422.66 2,372.26 08/2014 -
03/2016 19 0 Delay in land acquisition for sub station & ROW
problem.
37 TRANSMISSION SYSTEM ASSOCIATED WITH KRISHNAPATNAM UMPP-PART B - [N18000122]PGCIL,MULTI STATE
02/2012 1,927.16 -
1,927.16 1,585.67 10/2014 -
03/2016 17 0 Severe ROW problem.
38 KBUNL-MUZAFFARPUR TPP STAGE-II- SUBSIDIARY (2X195 MW) - [N18000191]NTPC,BIHAR
03/2010 3,984.03 -
3,984.03 3,178.09 01/2013 -
03/2016 38 0 - Delay in completion of Project due to delay in land acquisition of Ash Dyke and
ROU of MUW corridor. - Non performance of civil, Swyd, CHP, AHP agencies
39 BOKARO THERMAL POWER STATION-A - [N18000199]DVC,JHARKHAND
08/2006 2,313.00 4,139.00
4,237.67 3,088.00 12/2011 -
03/2016 51 83.21 - Shifting of old switch yard. Frequent interuption due to labour unrest aggravated delay in completion of the
work. - Space constraint to
faciltate construction activity to preserve heritage old power house building of
Bokaro -A. -Contractual issues.
- Delay in construction of 400 KV BTPS - KTPS
transmission line by PGCIL due to forest land
clearance. 40 KAMENG HYDROELECTRIC
PROJECT (NEEPCO) - [180100239]NEEPCO,ARUNACHAL PRADESH
12/2004 2,496.90 6,085.84
6,085.84 4,362.53 12/2009 06/2016
06/2016 78 143.74
41 ESTABLISHMENT OF POOLING STATIONS AT CHAMPA AND RAIGARH FOR IPP GENERATION PROJECT IN CHHATTISGARH - [N18000101]PGCIL,CHHATISGARH
05/2011 1,961.87 -
1,961.87 1,798.15 05/2014 -
06/2016 25 0 Delayed land acquisition for Champa S/stn.
42 COMMON SYSTEM ASSOCIATED WITH COASTAL ENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED L - [N18000103]PGCIL,TAMIL NADU
09/2011 1,940.13 -
1,940.13 1,938.06 09/2014 -
06/2016 21 0 Contractual issues & severe ROW problem in Karnataka.
43 TRANSMISSION SYSTEM STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARH - [N18000112]PGCIL,CHHATISGARH
11/2011 2,127.51 -
2,127.51 2,319.63 07/2014 -
06/2016 23 0 Severe ROW problem & forest clearance awaited.
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 44 SYSTEM STRENGTHENING IN
NORTH/WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARH - [N18000116]PGCIL,CHHATISGARH
12/2011 1,746.65 2,228.71
2,228.71 1,475.53 08/2014 12/2015
06/2016 22 27.6 Forest clearance awaited.
45 SYSTEM STRENTHENING IN RAIPUR WARDHA CORRIDOR FOR IPP PROJECTS IN CHHATTISGARH - [N18000117]PGCIL,CHHATISGARH
01/2012 1,422.85 -
1,422.85 1,391.42 01/2015 -
06/2016 17 0 Forest clearance awaited.
46 WR-NR HVDC INTERCONNECTOR FOR IPP PROJECTS IN CHHATTISGARH - [N18000125]PGCIL,CHHATISGARH
03/2012 9,569.76 -
9,569.76 5,724.59 06/2015 -
06/2016 12 0 Delay in land acquisition of Champa HVDC terminal & forest clearance awaited.
47 TR. SYS. FOR PHASE-I PROJ. IN JHARKHAN AND WEST BENGAL PART-B - [N18000129]PGCIL,MULTI STATE
02/2012 3,201.44 -
3,201.44 2,996.11 10/2014 -
06/2016 20 0 Final forest clearance awaited. Permission to work
obtained in Jan 16.
48 EASTERN REGION STRENGTHENING SCHEME-V - [N18000155]PGCIL,MULTI STATE
10/2013 1,364.52 -
1,364.52 434.44 04/2016 -
06/2016 2 0 Delayed land acquisition & ROW problem in
Jharkhand. 49 PARE HYDRO ELECTRIC
PROJECT - [N18000045]NEEPCO,ARUNACHAL PRADESH
12/2008 573.99 1,262.27
1,262.27 1,093.23 08/2013 07/2016
07/2016 35 119.91
50 COMMON SYSTEM ASSOCIATED WITH EAST COAST ENERGY PVT. LTD. AND NCC POWER PROJECTS LTD. LTOA GENERATI - [N18000145]PGCIL,MULTI STATE
06/2012 1,909.24 -
1,909.24 1,016.53 06/2015 -
08/2016 14 0 Contractual issue.
51 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) - [180100243]NHPC,WEST BENGAL
09/2005 1,061.38 -
2,193.08 1,956.52 09/2009 -
09/2016 84 106.63 1. Initial delay in handing over of forest land & start of
work 2. Bandh/ closure by locals ,
political outfits like GJMM and its effect
3. Due to inordinate delay and extended stay, BOQ rates become unworkable and resulted in cash deficit
of Civil Contractor. 4. Delay in award of E&M
contract due to clarification regarding participation of
Chinese firm 52 TUIRIAL HYDRO ELECTRIC
PROJECT (60MW) - [N18000119]NEEPCO,MIZORAM
07/1998 368.72 1,381.71
1,381.71 951.92 07/2006 10/2016
10/2016 123 274.73
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 53 KISHANGANGA HEP (3X110 MW)
- [N18000031]NHPC,JAMMU AND KASHMIR
01/2009 3,642.04 -
5,751.47 4,402.95 01/2016 -
11/2016 10 57.92 Rehabilitation & Resettlement Plan is
pending for approval with J&K State Govt.
54 KUNADANKULAM APP TRANS SYSTEM (PGCIL) - [180100258]PGCIL,TAMIL NADU
05/2005 1,779.29 2,187.32
2,187.32 1,903.55 11/2008 01/2016
12/2016 97 22.93 Severe ROW problem in Kerala.
55 TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECT - [N18000061]PGCIL,MULTI STATE
10/2008 4,824.12 -
4,824.12 4,237.58 10/2012 -
12/2016 50 0 Severe ROW problem & forest clearance awaited.
56 TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS. - [N18000080]PGCIL,MULTI STATE
02/2010 2,144.00 2,932.88
2,932.88 2,283.80 12/2012 12/2016
12/2016 48 36.79 Contractual issues & forest clearance awaited.
57 MOUDA STPP STAGE 2 - [N18000132]NTPC,MAHARASHTRA
03/2012 7,921.47 -
7,921.47 4,904.00 09/2016 -
12/2016 3 0 - Delay in supplies & slow progress in erection activities of Steam
Generator (M/s BHEL). - Slow progress of work in Main Plant civil Package
(M/s IVRCL) 58 COMMON SYS. ASSOCIATED
WITH EAST COAST ENERGY PVT LTD AND NCC POWER PROJECTS LTD LTOA GEN PART- B - [N18000144]PGCIL,MULTI STATE
03/2013 2,514.88 -
2,514.88 1,043.56 12/2015 -
12/2016 12 0 Huge forest involvement & severe ROW problem.
59 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202]DVC,WEST BENGAL
04/2007 4,122.00 8,781.00
9,606.82 1,353.36 02/2011 -
01/2017 71 133.06 - Frequent local issues/ resistance by land losers.
- Supply of defective equipments and delay in replacement of same by
RIL. - Dismantling and
reconstruction of MDBFP Foundation.
-Damage of imported insulation material and
delay in its replacement. 60 BONGAIGAON THERMAL POWER
PROJECT - [N18000041]NTPC,ASSAM
01/2008 4,375.35 6,749.18
6,749.18 5,719.00 09/2011 -
03/2017 66 54.25 -Inadequate deployment of manpower & resources by
M/s BHEL and its sub-agencies have affected the
erection/commissioning progress of U#1
61 TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER - [N18000077]PGCIL,WEST BENGAL
04/2010 4,404.57 -
4,404.57 2,405.85 01/2015 -
03/2017 26 0 Gen. project delayed. Forest clearance awaited.
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 62 EASTERN REGION
STRENGTHENING SCHEME-III - [N18000100]PGCIL,MULTI STATE
07/2010 1,272.80 -
1,272.80 1,244.23 11/2012 -
03/2017 52 0 Delay in land acquisition & ROW problem.
63 KUDGI STPP STAGE 1 - [N18000131]NTPC,KARNATAKA
01/2012 15,166.19 -
15,166.19 10,171.00 01/2017 -
03/2017 2 0 - NGT issue – work stopped from 17.03.14 to 01.04.14 - Work stoppage due to
agitation against the project (5.07.14 to 22.07.14) -Delay in supply of
Generator Stator of U#2 & 3 (M/s Toshiba)
64 SOLAPUR STPP - [N18000133]NTPC,MAHARASHTRA
03/2012 9,395.18 -
9,395.18 5,881.00 11/2016 -
08/2017 9 0 - Delay of 12 months in Engg. & supplies by BGR
which has led to a consequent delay of 12
months in erection. 65 BRBCL-NABINAGAR TPP- JV
(4X250 MW) - [N18000190]NTPC,BIHAR
01/2007 5,353.00 -
5,353.00 5,298.06 05/2014 -
09/2017 40 0 - Delay in balance land acquisition
- Law & order problem 66 MUNPL-MEJA TPP - JV (2X660
MW) - [N18000193]NTPC,UTTAR PRADESH
04/2012 9,750.89 -
9,750.89 4,529.23 12/2016 -
09/2017 9 0 Delay of 12 months in Engg. & supplies by BGR which has led to a consequent delay of 12 months in
erection. 67 NORTH- EAST NORTH WESTERN
INTERCONNECTOR I PROJECT - [N18000066]PGCIL,MULTI STATE
02/2009 11,130.19 13,762.80
13,762.80 11,463.30 08/2013 12/2017
12/2017 52 23.65 Gen. project delayed & law & order problem in NER.
68 BARH STPP(3X660MW) NTPC - [180100242]NTPC,BIHAR
02/2005 8,692.97 15,095.67
15,095.67 11,183.00 01/2011 10/2014
05/2018 88 73.65 - Non performance of Russian agency M/s TPE &
M/s PM. - TPE stopped work from
Oct’2013 and the contract of M/s TPE was terminated on
14.01.15. - Award of balance works on “as is where is basis in done in Jan’16. Schedule
for U#1 commissioning is 16 months i.e. May’17 and subsequent units at 6
months interval.
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 69 PARBATI HEP (4X200 MW)
(NHPC) II - [180100210]NHPC,HIMACHAL PRADESH
09/2002 3,919.59 -
8,398.76 5,398.46 09/2009 -
12/2018 111 114.28 1. Init
ial delay in start of Dam works due to delay in
Revised Forest clearance 2.
Burial of TBM during Nov, 06. Heavy ingress of water with
silt from TBM face. Treatment of shear zone,
3. Back hill slope failure of Power
House three times, 4.
Ban on use of aggregates by Hon’ble High Court, Shimla
70 TAPOVAN-VISHNUGAD HEP (4X130MW) - [N18000014]NTPC,UTTARAKHAND
11/2006 2,978.48 3,846.30
3,846.30 2,699.00 03/2013 -
12/2018 69 29.14 - Unprecedented flood in Uttarakhand during Aug'12
and Jun'13 damaging cofferdam and approach
roads. TBM stuck up thrice & L&T Alpine JV did not
perform leading to termination of contract.
- Head Race Tunnel (HRT) Package is under retender. NIT done in May’15, Price
bid opened in Nov’15 . 71 TEHRI PUMPED STORAGE
PLANT(1000MW) - [N18000010]THDCIL,UTTARAKHAND
07/2006 1,657.00 2,978.86
2,978.86 1,603.73 02/2016 09/2019
09/2019 43 79.77 1.4.67 Ha. land diversion case for dumping area at
Village Chopra. 2.Cash flow problem with
the contractor. 72 VISHNUGAD PIPALKOTI HYDRO
ELECTRIC PROJECT - [N18000042]THDCIL,UTTARAKHAND
08/2008 2,491.58 -
2,491.58 789.89 06/2013 -
12/2019 78 0 Post Award: 1. Minor hindrances by local
villagers.
Total 152,827.93 -
189,112.28 131,245.33
HEAVY INDUSTRY
73 NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP) - [N20000001]NATIS,MULTI STATE
04/2011 1,718.00 -
3,827.30 - 09/2011 -
12/2017 75 122.78 NATRIP is a temporary organization is the major
hurdle of the project. NATRIP is first of its kind of
project for which no train manpower was available in
the country. Total 1,718.00
- 3,827.30 .00
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 RAILWAYS
74 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164]MRTP,MAHARASHTRA
03/1996 495.44 495.44
1,781.98 440.08 03/2004 -
03/2016 144 259.68
75 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307]ECR,BIHAR
04/2002 921.00 3,040.00
3,040.00 1,834.31 03/2009 -
03/2016 84 230.08
76 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127]NFR,ASSAM
04/1996 1,676.31 -
5,500.00 4,769.59 03/2009 -
03/2016 84 228.1
77 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194]NFR,TRIPURA
04/1999 895.00 -
1,242.25 1,047.10 03/2007 -
03/2016 108 38.8
78 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP) - [N22000108]RVNL,WEST BENGAL
04/2010 2,397.72 -
2,397.72 204.56 03/2016 -
06/2016 3 0 Work hampered due to encroachment on Railway land along the proposed
metro alignment.
79 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201]NFR,ASSAM
09/1997 1,500.00 4,996.19
4,996.19 4,102.70 04/2008 12/2011
06/2017 110 233.08
80 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133]NR,JAMMU AND KASHMIR
03/1995 2,500.00 -
20,000.00 10,722.72 11/2002 -
12/2017 181 700
81 KATIHAR - JOGBANI (GC)(NEFR) - [220100247]NFR,BIHAR
09/2001 492.98 -
1,727.27 743.74 12/2010 -
03/2018 87 250.37 Work affected due to fund constraint.
82 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266]NFR,MULTI STATE
04/2000 733.00 733.00
2,531.34 1,732.43 12/2008 -
03/2018 111 245.34 Work is affected due to land problems. State Govt. has
been requested to expedite handing over of land to
Railways for early commissioning of the line.
83 AGARTALA SABROOM, NL, NEFR - [N22000099]NFR,TRIPURA
04/2008 813.34 813.34
2,876.00 823.83 03/2014 -
03/2018 48 253.6 Supreme court approval is required for NBWL
clearance of 9.94 Hect Trishna Wild life Sanctuary.
84 BHAIRABI SAIRONG, NL, NEFR - [N22000100]NFR,MIZORAM
04/2008 619.34 619.34
2,820.25 199.31 04/2014 03/2015
03/2018 47 355.36
85 EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKE - [N22000135]MRTP,WEST BENGAL
03/2013 4,874.58 -
4,874.58 1,911.65 03/2016 -
06/2018 27 0
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 86 NEW WORK FOR
CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH. - [N22000111]RVNL,WEST BENGAL
04/2010 2,913.51 -
2,095.20 619.56 03/2016 -
12/2018 33 -28.09 Non-handing over of land of Joka Depot
87 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288]NFR,MANIPUR
04/2003 727.56 727.56
6,570.75 2,787.99 03/2011 03/2014
03/2019 96 803.12
88 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092]MRTP,MAHARASHTRA
04/2008 5,300.00 6,821.29
7,986.04 2,443.62 03/2014 03/2019
03/2019 60 50.68 Fund constraint affecting the progress of projects.
89 GONDIA-JABALPUR(GC),(SECR) - [220100186]SECR,MULTI STATE
02/1997 386.30 -
1,544.40 - 03/1998 -
12/2019 261 299.79
90 BANKURA - DAMODAR (GC) (SER) - [220100277]SER,WEST BENGAL
03/1998 111.90 1,039.29
2,371.85 486.25 03/2005 12/2008
12/2019 177 2019.62 Local disturbance and fund constraint affected the work
progress. 91 TAMLUK DIGHA,LINE DOUBLING
(SER) - [N22000097]SER,WEST BENGAL
03/1984 293.97 1,013.74
1,428.00 466.36 06/2005 07/2011
12/2019 174 385.76 In Kanthi-Egra section land acquisition is kept in
abeyance due to insufficient funds and no interest
showing by the State Govt. 92 SEVOK RANGPO, NEFR -
[N22000102]NFR,SIKKIM 04/2008 1,339.48
1,339.48 4,190.00 88.56 12/2015
- 03/2020 51 212.81 Delay in land acquisition
affected work progress in Rongchong and Kalimpong
(West Bengal). 93 NEW LINE FROM DIMAPUR TO
ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124]NFR,NAGALAND
04/2006 850.00 -
2,973.42 10.44 03/2015 03/2020
03/2020 60 249.81 Land acquisition is pending.
94 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP) - [N22000110]RVNL,WEST BENGAL
04/2010 3,951.98 -
3,161.58 878.29 03/2016 -
12/2020 57 -20 land aquisition problem
Total 33,793.41 -
86,108.82 36,313.09
ROAD TRANSPORT AND
HIGHWAYS
95 GURGAON - KOTPUTLI - JAIPUR (SIX LANE) - [N24000477]DORTH,RAJASTHAN
02/2008 1,673.70 -
1,673.70 - 10/2011 -
01/2016 51 0
96 FOUR LANING OF GWALIOR-SHIVPURI - [N24000494]DORTH,MADHYA PRADESH
05/2013 1,055.00 -
1,055.00 - 11/2015 -
01/2016 2 0
97 GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTION - [N24000125]NHAI,GUJARAT
03/2010 1,509.10 -
1,509.10 - 09/2012 -
02/2016 41 0
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11 98 INDORE-JHABUA-GUJRAT/MP -
[N24000136]NHAI,MADHYA PRADESH
10/2010 1,175.00 -
1,175.00 - 04/2013 -
03/2016 35 0
99 MURADABAD-BAREILY - [N24000154]NHAI,UTTAR PRADESH
04/2010 1,267.00 -
1,267.00 2,425.00 06/2013 -
03/2016 33 0
100 4 LANING OF NAGPUR-BETUL - [N24000155]NHAI,MULTI STATE
02/2011 2,498.76 -
2,498.76 - 08/2014 -
03/2016 19 0
101 BEAWAR PALI PINDWARA - [N24000199]NHAI,RAJASTHAN
12/2011 2,388.51 -
2,388.00 2,301.00 06/2014 -
03/2016 21 -.02
102 SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWAR - [N24000205]NHAI,MULTI STATE
12/2011 1,047.00 -
1,047.00 - 06/2014 -
03/2016 21 0
103 FOUR LANING OF ORISSA CHATTISHGARH BORDER - [N24000218]NHAI,MULTI STATE
02/2013 1,232.00 -
1,232.00 927.19 08/2015 -
03/2016 7 0
104 FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTION - [N24000481]NHAI,CHHATISGARH
02/2013 1,232.00 -
1,232.00 - 08/2015 -
03/2016 7 0
105 GHAZIABAD-ALIGARH NH-91 - [N24000170]NHAI,UTTAR PRADESH
02/2011 1,141.00 -
1,141.00 1,911.64 08/2013 -
04/2016 32 0
106 DELHI AGRA APPROVED LENGTH 180.0 KM - [N24000224]NHAI,MULTI STATE
10/2012 1,928.22 -
1,928.22 822.96 04/2015 -
04/2016 12 0
107 NASHRI- CHANANI - [N24000162]NHAI,JAMMU AND KASHMIR
05/2011 2,159.00 -
2,159.00 - 06/2015 -
05/2016 11 0
108 6-LANING OF DHANKUNI-KHARAGPUR SECTION - [N24000206]NHAI,WEST BENGAL
04/2012 1,396.18 -
1,396.18 2,287.44 09/2014 -
05/2016 20 0
109 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM) - [N24000133]NHAI,HARYANA
05/2009 1,108.00 -
2,288.00 3,619.94 11/2011 -
06/2016 55 106.5
110 QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00 - [N24000161]NHAI,JAMMU AND KASHMIR
07/2010 1,987.00 -
1,987.00 - 07/2015 -
06/2016 11 0
111 JAMMU-UDHAMPUR KM.27.5 TO KM.67.00 - [N24000163]NHAI,JAMMU AND KASHMIR
07/2010 1,813.76 -
1,813.76 - 07/2013 -
06/2016 35 0
112 4 LANNING OF AHMEDABAD TO GODHARA - [N24000167]NHAI,GUJARAT
12/2010 1,008.50 -
1,008.50 - 06/2013 -
06/2016 36 0
113 SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547 - [N24000183]NHAI,ANDHRA PRADESH
11/2011 1,535.00 -
1,535.00 2,478.63 05/2014 -
06/2016 25 0
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11
114 SRINAGAR TO BANIHAL - [N24000189]NHAI,JAMMU AND KASHMIR
06/2011 1,100.70 -
1,100.70 - 06/2014 -
06/2016 24 0
115 ETAWAH CHAKERI - [N24000219]NHAI,UTTAR PRADESH
03/2013 1,573.00 -
1,573.00 1,840.00 09/2015 -
06/2016 9 0
116 AHMEDABAD TO VADODARA SECTION - [N24000222]NHAI,GUJARAT
01/2013 2,125.24 -
2,125.24 - 12/2015 -
06/2016 6 0
117 CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KM - [N24000145]NHAI,ANDHRA PRADESH
11/2010 1,585.00 -
1,585.00 1,050.90 05/2013 -
08/2016 39 0
118 4-LANING OF FARAKA-RAIGANJ - [N24000202]NHAI,MULTI STATE
02/2011 1,078.84 -
1,078.84 - 08/2013 -
08/2016 36 0
119 WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50 - [N24000230]NHAI,MAHARASHTRA
05/2013 1,348.20 -
1,348.20 1,267.57 02/2014 -
08/2016 30 0
120 FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASS - [N24000509]NHAI,MAHARASHTRA
04/2010 1,170.52 -
1,170.52 1,579.15 06/2012 -
08/2016 50 0
121 PANIKHOLI-RIMOLI - [N24000197]NHAI,ODISHA
03/2012 1,410.00 -
1,410.00 - 09/2014 -
10/2016 25 0
122 PUNE-SATARA(NH-4) - [N24000156]NHAI,MAHARASHTRA
10/2010 1,724.55 -
1,724.55 1,742.94 03/2013 -
12/2016 45 0
123 SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46 - [N24000172]NHAI,TAMIL NADU
09/2011 1,250.00 -
1,250.00 - 12/2013 -
12/2016 36 0
124 BAREILY-SITAPUR (NH-24) - [N24000200]NHAI,UTTAR PRADESH
03/2011 1,046.00 -
1,046.00 425.65 09/2013 -
12/2016 39 0
125 WALAJAPET POONAMALEE KM 106.8 TO KM 13.8 - [N24000228]NHAI,TAMIL NADU
06/2013 1,287.95 -
1,287.95 - 11/2015 -
03/2017 16 0
126 VARANASI-AURANGABAD KM.786 TO KM.978.40 - [N24000182]NHAI,MULTI STATE
09/2011 2,848.00 -
2,848.00 504.51 03/2014 -
04/2017 37 0
127 RANCHI-RARGA-JAMSETHPUR - [N24000215]NHAI,MULTI STATE
12/2012 1,479.00 -
1,479.00 461.94 06/2015 -
05/2017 23 0
Total 50,181.73 -
51,361.22 25,646.46
TELECOMMUNICATIONS
128 NETWORK FOR SPECTRUM - [N26000101]DOT,MULTI STATE
03/2012 13,334.00 -
13,334.00 1,360.00 07/2015 -
03/2017 20 0
(January 2016)
Date of
Commissioning (Month/Year)
S.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Anticip ated Cost (Rs. crore)
Cumulative Expenditure (Rs. crore)
Original / Revised
Antici Pated
Time
Overrun (Months)
Cost
Overrun (%)
Reasons for Delay (As Reported by
Project Implementing
Agencies) 1 2 3 4 5 6 7 8 9 10 11
129 NETWORK FOR SPECTRUM (NFS) OFC LAYING PROJECT, PACKAGE F AND G, A PART OF INTELLIGENT FIBER OPTIC C - [N26000102]ITI,MULTI STATE
09/2014 2,111.17 -
2,011.17 1,360.00 09/2014 -
03/2017 30 -4.74
Total 15,445.17 -
15,345.17 2,720.00
URBAN DEVELOPMENT
130 BANGALORE METRO RAIL PROJECT - [N28000008]MRTP,KARNATAKA
05/2006 6,395.00 11,609.00
13,845.01 13,525.81 06/2011 12/2015
06/2016 60 116.5 Difficult geological condition , slow progress to aviod damages to structure in densly populated area
131 CHENNAI METRO RAIL LTD (PHASE 1) - [N28000084]CMRL,TAMIL NADU
02/2009 14,600.00 14,600.00
14,600.00 11,786.98 12/2015 -
08/2016 8 0
132 DELHI MRTS PHASE-III - [N28000056]DMRCL,DELHI
09/2011 38,585.00 -
38,585.00 20,172.80 03/2016 -
12/2016 9 0 Rehabilitation & Resettlement, Land
acquistion and Delay in technical approval from M/o Railways delays the project.
133 BANGALORE METRO RAIL PROJECT PHASE-2 - [N28000058]BMRCL,KARNATAKA
02/2014 26,405.14 26,405.01
26,405.01 217.54 02/2019 03/2020
03/2020 13 0
Total 85,985.14 -
93,435.02 45,703.13
Grand Total 496,896.41 615,875.49 358,676.80
Annexure - VII Details of Ongoing Projects having Time and Cost Overruns w.r.t Original Schedule
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost (Rs. crore)
Anticipated Cost
(Rs.crore)
Original / Revised
Antici Pated
Cost Overruns
(%)
T.O.R.s (in
months) 1 2 3 4 5 6 7 8 9 ATOMIC ENERGY
1 PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE) - [020100044
09/2003 3,492.00 -
5,677.00 09/2010 -
09/2016 62.57 72
2 KUDANKULAM APP (NPCIL) - [020100040
12/2001 13,171.00 -
22,462.00 12/2008 -
05/2016 70.54 89
Total 16,663.00 -
28,139.00
COAL
3 ADRIYALA SHAFT PROJECT - [N06000016
12/2009 212.34 -
1,228.39 03/2013 -
03/2016 478.50 36
Total 212.34 -
1,228.39
HEAVY INDUSTRY
4 NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP) - [N20000001
04/2011 1,718.00 -
3,827.30 09/2011 -
12/2017 122.78 75
Total 1,718.00 -
3,827.30
PETROLEUM
5 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE - [N16000157
01/2006 732.00 -
1,227.00 10/2011 -
03/2016 67.62 53
6 CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS) - [N16000128
03/2011 861.79 -
1,256.72 05/2013 -
04/2016 45.83 35
7 UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE - [N18000148
09/2012 871.35 -
1,200.00 03/2015 -
08/2016 37.72 17
8 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR - [N16000169
01/2006 993.00 -
1,693.00 01/2012 -
05/2016 70.49 52
9 INTEGRATED DEVELOPMENT OF B-127 FIELDS - [N16000131
12/2011 2,059.63 -
2,665.65 03/2015 -
05/2016 29.42 14
10 INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS - [N16000172
05/2013 4,124.35 -
4,941.49 04/2016 -
12/2017 19.81 20
11 PARADIP REFINERY PROJECT - [N16000058
02/2009 29,777.00 -
34,555.00 11/2012 -
02/2016 16.05 39
Total 39,419.12 -
47,538.86
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost (Rs. crore)
Anticipated Cost
(Rs.crore)
Original / Revised
Antici Pated
Cost Overruns
(%)
T.O.R.s (in
months) 1 2 3 4 5 6 7 8 9 POWER
12 TUIRIAL HYDRO ELECTRIC PROJECT (60MW) - [N18000119
07/1998 368.72 -
1,381.71 07/2006 02/2015
10/2016 274.73 123
13 TRIPURA GAS BASED POWER PROJECT - [N18000071
07/2009 421.01 -
1,007.57 07/2013 -
01/2016 139.32 30
14 PARE HYDRO ELECTRIC PROJECT - [N18000045
12/2008 573.99 -
1,262.27 08/2013 -
07/2016 119.91 35
15 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) - [180100243
09/2005 1,061.38 -
2,193.08 09/2009 -
09/2016 106.63 84
16 TEHRI PUMPED STORAGE PLANT(1000MW) - [N18000010
07/2006 1,657.00 -
2,978.86 02/2016 -
09/2019 79.77 43
17 SYSTEM STRENGTHENING IN NORTH/WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARH - [N18000116
12/2011 1,746.65 -
2,228.71 08/2014 -
06/2016 27.60 22
18 KUNADANKULAM APP TRANS SYSTEM (PGCIL) - [180100258
05/2005 1,779.29 -
2,187.32 11/2008 -
12/2016 22.93 97
19 TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS. - [N18000080
02/2010 2,144.00 -
2,932.88 12/2012 -
12/2016 36.79 48
20 BOKARO THERMAL POWER STATION-A - [N18000199
08/2006 2,313.00 4,139.00
4,237.67 12/2011 -
03/2016 83.21 51
21 KAMENG HYDROELECTRIC PROJECT (NEEPCO) - [180100239
12/2004 2,496.90 -
6,085.84 12/2009 06/2016
06/2016 143.74 78
22 TAPOVAN-VISHNUGAD HEP (4X130MW) - [N18000014
11/2006 2,978.48 -
3,846.30 03/2013 -
12/2018 29.14 69
23 KISHANGANGA HEP (3X110 MW) - [N18000031
01/2009 3,642.04 -
5,751.47 01/2016 -
11/2016 57.92 10
24 PARBATI HEP (4X200 MW) (NHPC) II - [180100210
09/2002 3,919.59 -
8,398.76 09/2009 -
12/2018 114.28 111
25 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202
04/2007 4,122.00 8,781.00
9,606.82 02/2011 -
01/2017 133.06 71
26 BONGAIGAON THERMAL POWER PROJECT - [N18000041
01/2008 4,375.35 -
6,749.18 09/2011 -
03/2017 54.25 66
27 BARH STPP(3X660MW) NTPC - [180100242
02/2005 8,692.97 -
15,095.67 01/2011 -
05/2018 73.65 88
28 NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECT - [N18000066
02/2009 11,130.19 -
13,762.80 08/2013 -
12/2017 23.65 52
Total 53,422.56 -
89,706.91
RAILWAYS
29 BANKURA - DAMODAR (GC) (SER) - [220100277
03/1998 111.90 -
2,371.85 03/2005 12/2008
12/2019 2,019.62 177
30 TAMLUK DIGHA,LINE DOUBLING (SER) - [N22000097
03/1984 293.97 -
1,428.00 06/2005 -
12/2019 385.76 174
31 GONDIA-JABALPUR(GC),(SECR) - [220100186
02/1997 386.30 -
1,544.40 03/1998 -
12/2019 299.79 261
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost (Rs. crore)
Anticipated Cost
(Rs.crore)
Original / Revised
Antici Pated
Cost Overruns
(%)
T.O.R.s (in
months) 1 2 3 4 5 6 7 8 9 32 KATIHAR - JOGBANI (GC)(NEFR)
- [220100247 09/2001 492.98
- 1,727.27 12/2010
- 03/2018 250.37 87
33 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164
03/1996 495.44 -
1,781.98 03/2004 -
03/2016 259.68 144
34 BHAIRABI SAIRONG, NL, NEFR - [N22000100
04/2008 619.34 -
2,820.25 04/2014 -
03/2018 355.36 47
35 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288
04/2003 727.56 -
6,570.75 03/2011 -
03/2019 803.12 96
36 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266
04/2000 733.00 -
2,531.34 12/2008 -
03/2018 245.34 111
37 AGARTALA SABROOM, NL, NEFR - [N22000099
04/2008 813.34 -
2,876.00 03/2014 -
03/2018 253.60 48
38 NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124
04/2006 850.00 -
2,973.42 03/2015 -
03/2020 249.81 60
39 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194
04/1999 895.00 -
1,242.25 03/2007 -
03/2016 38.80 108
40 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307
04/2002 921.00 -
3,040.00 03/2009 -
03/2016 230.08 84
41 SEVOK RANGPO, NEFR - [N22000102
04/2008 1,339.48 -
4,190.00 12/2015 -
03/2020 212.81 51
42 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201
09/1997 1,500.00 -
4,996.19 04/2008 12/2011
06/2017 233.08 110
43 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127
04/1996 1,676.31 -
5,500.00 03/2009 -
03/2016 228.10 84
44 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133
03/1995 2,500.00 -
20,000.00 11/2002 -
12/2017 700.00 181
45 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092
04/2008 5,300.00 -
7,986.04 03/2014 -
03/2019 50.68 60
Total 19,655.62 -
73,579.74
ROAD TRANSPORT AND HIGHWAYS
46 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM) - [N24000133
05/2009 1,108.00 -
2,288.00 11/2011 -
06/2016 106.50 55
Total 1,108.00 -
2,288.00
STEEL
47 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA - [N12000101
05/2005 768.88 1,060.00
1,060.00 02/2014 -
03/2016 37.86 25
Total 768.88 -
1,060.00
URBAN DEVELOPMENT
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original / Revised
Cost (Rs. crore)
Anticipated Cost
(Rs.crore)
Original / Revised
Antici Pated
Cost Overruns
(%)
T.O.R.s (in
months) 1 2 3 4 5 6 7 8 9 48 BANGALORE METRO RAIL PROJECT
- [N28000008 05/2006 6,395.00
- 13,845.01 06/2011
- 06/2016 116.50 60
Total 6,395.00 -
13,845.01
Grand Total 139,362.52 261,213.21
Annexure - VIII Details of Projects Without Date of Commissioning
Date of Commissioning
(Month/Year) SI.No
Project
Date of Approval
(Month/Year)
Original / Revised
Cost (Rs. crore)
Original / Revised
Anticipated
1 2 3 4 5 6 PETROCHEMICALS
1 ASSAM GAS CRACKER PROJECT - [N16000106]BCPL,ASSAM 04/2006 5,460.61 8,920.00
04/2012 12/2013
12/2015
Total 5,460.61 -
PETROLEUM
2 KOCHI-KOOTANAD BANGALORE MANGALORE PIPELINE PROJECT - [N16000129]GAIL,MULTI STATE
06/2009 2,915.00 -
12/2012 -
06/2015
3 AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPUR - [N16000193]IOCL,MULTI STATE
01/2015 1,823.00 -
- -
-
4 PARADIP HYDERABAD PIPLEINE - [N16000194]IOCL,MULTI STATE 01/2015 2,321.00 -
- -
-
Total 7,059.00 -
POWER
5 SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) - [180100221]NHPC,ARUNACHAL PRADESH
09/2003 6,285.33 -
09/2010 -
-
Total 6,285.33 -
RAILWAYS
6 HOWRAH-AMTA-CHAMPADANGA NL (SER) - [220100208]SER,WEST BENGAL
04/1974 393.46 393.46
03/2007 03/2007
03/2015
7 PATNA GANGA BRIDGE (NL), ECR - [220100308]ECR,BIHAR 04/2001 624.47 -
10/2007 12/2012
12/2015
8 LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) - [220100232]WCR,MULTI STATE
09/1998 247.66 3,500.00
05/2008 -
-
9 PALANPUR-SAMAKHAYALI (DL) - [N22000144]WR,GUJARAT 04/2013 1,266.89 -
- -
-
10 KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION - [N22000261]SCR,MULTI STATE
04/2012 1,054.35 2,200.00
- -
-
11 GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM) - [N22000345],UTTAR PRADESH
04/1997 836.26 -
- -
-
12 UTRATIA-ZAFRABAD, NR (LINE DOUBLING) - [N22000088]NR,UTTAR PRADESH
04/2006 325.00 2,434.00
03/2010 -
-
13 AHMEDNAGAR-PARLI VAIJNATH(NL) CR - [220100181]CR,MAHARASHTRA
02/1997 514.68 -
- -
-
14 HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR - [220100183]SWR,KARNATAKA
02/1997 295.00 -
- -
-
15 NANGALDAM-TALWARA(NL),NR - [220100188]NR,MULTI STATE 03/1981 450.00 -
07/2012 -
-
Date of
Commissioning (Month/Year)
SI.No
Project
Date of Approval
(Month/Year)
Original / Revised
Cost (Rs. crore)
Original / Revised
Anticipated
1 2 3 4 5 6 16 HUBLI-ANKOLA(NL),SWR - [220100193]SWR,KARNATAKA 04/1997 227.00
997.58 - -
-
17 KODERMA-RANCHI VIA BARKAKANA (NL),ECR - [220100222]ECR,JHARKHAND
03/1999 2,957.21 -
07/2005 -
-
18 JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR - [220100240]ECR,BIHAR
04/1997 501.69 501.69
03/2012 -
-
19 ANGAMALI-SABARIMALA (N.L.)(SR) - [220100252]SR,KERALA 10/1998 550.00 517.70
- -
-
20 QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) - [220100263]SR,MULTI STATE
03/1998 280.00 -
- -
-
21 KOTLPALLI-NARASAPUR (NL) (SCR) - [220100265]SCR,ANDHRA PRADESH
12/2001 330.00 -
- -
-
22 TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP) - [220100268]MRTP,WEST BENGAL
03/2000 1,049.69 3,385.14
12/2006 -
-
23 TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ER - [220100272]ER,WEST BENGAL
04/2000 1,188.91 -
- 12/2009
-
24 BANGLORE - SATYAMANGALAM (NL)(SWR) - [220100274]SWR,KARNATAKA
04/1996 138.00 -
- -
-
25 KHURDA ROAD-BOLANGIR(NL)ECOR - [220100284]ECOR,ODISHA 04/1994 470.21 -
- -
-
26 HARIDASPUR-PARADEEP(NL) - [220100285]RVNL,ODISHA 04/1996 301.64 -
- 09/2009
-
27 SUKINDA ROAD - ANGUL (NL)(ECOR) - [220100325]RVNL,ODISHA 04/1998 183.23 -
02/2015 -
-
28 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI - [N22000079]SR,TAMIL NADU
09/2007 404.19 -
- -
-
29 TIDIVANAM-NAGARI (NL) - [N22000085]SR,TAMIL NADU 09/2006 456.00 -
- -
-
30 BARDHAMAN-KATWA (GC) - [N22000091]ER,WEST BENGAL 04/2007 1,106.62 -
12/2010 -
-
31 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP) - [N22000109]RVNL,WEST BENGAL
04/2010 2,298.42 -
03/2014 -
-
32 RATLAM-MHOW-KHANDWA-AKOLA (GC) - [N22000120]WR,MADHYA PRADESH
04/2008 603.04 -
03/2012 -
-
33 UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR) - [N22000122]WR,GUJARAT
04/2008 1,389.62 -
03/2014 -
-
34 CHOTTAUDEPUR-DHAR(NL) - [N22000138]WR,MULTI STATE 04/2007 1,347.26 -
- -
-
35 DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL) - [N22000139]WR,MULTI STATE
04/2007 1,640.04 -
- -
-
36 RATLAM-DUNGARPUR VIA BANSWARA (NL) - [N22000147]NWR,MULTI STATE
04/2011 2,082.75 -
- -
-
37 CHENNAI-CUDDALORE VIA MAMALLAPURAM - [N22000185]SR,MULTI STATE
04/2008 523.52 -
- -
-
38 SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDUR - [N22000186]SR,TAMIL NADU
04/2013 839.00 -
- -
-
39 VILLUPURAM-DINDIGUL WITH ELECTRIFICATION - [N22000189]SR,MULTI STATE
04/2008 822.39 -
- -
-
40 WARDHA-NANDED MAHARASHTRA - [N22000231]CR,MAHARASHTRA
04/2008 499.30 -
- -
-
Date of
Commissioning (Month/Year)
SI.No
Project
Date of Approval
(Month/Year)
Original / Revised
Cost (Rs. crore)
Original / Revised
Anticipated
1 2 3 4 5 6 41 TUMKUR-CHITRADURGA-DAVENGERE NL -
[N22000256]SWR,KARNATAKA 04/2011 913.00
- - -
-
42 MUNIRABAD (GINGERA) -RAICHUR NL - [N22000257]SWR,KARNATAKA
04/2007 179.65 -
- -
-
43 MANUGURU-RAMAGUNDAM - [N22000259]SCR,TELANGANA 04/2013 1,112.00 -
- -
-
44 AKOLA-KHANDWA GC AKOLA-AKOT - [N22000263]SCR,MULTI STATE
04/2008 184.26 -
- -
-
45 DELHI-SOHNA-NUH-FIROZPUR-JHIRKA-ALWAR - [N22000271]NR,MULTI STATE
04/2013 1,239.00 -
- -
-
46 BHANUPALI-BILASPUR BERI NL - [N22000273]NR,HIMACHAL PRADESH
04/2008 1,046.88 -
- -
-
47 RAYADURGA-TUMKUR NL - [N22000279]SWR,MULTI STATE 04/2007 970.34 -
- -
-
48 NADIKUDE-SRI KALAHASTI - [N22000286]SCR,ANDHRA PRADESH 04/2011 1,313.48 -
- -
-
49 KADAPA-BANGALORE (NL), KADAPA-PENDLIMARRI PH-I - [N22000288]SCR,MULTI STATE
04/2008 2,050.00 -
- -
-
50 HOSPET-HUBLI-LONDA-VASCODAGAMA DL - [N22000297]SWR,KARNATAKA
04/2010 2,127.00 -
- -
-
51 GADAG-WADI NL - [N22000299]SWR,KARNATAKA 04/2013 1,117.00 -
- -
-
52 QUILON-TIRUNELVELI - TRICHENDUR, TENKASI - [N22000303]SR,TAMIL NADU
04/1999 460.94 -
01/1999 -
-
53 SAMBALPUR-TALCHER DOUBLING - [N22000315]ECOR,ODISHA 03/2011 679.27 -
- -
-
54 HUBLI- CHIKJAJUR - [N22000325]SWR,KARNATAKA 03/2015 1,900.00 -
- -
-
55 MIRAJ-LONDA - [N22000327]SWR,MULTI STATE 03/2015 1,830.00 -
- -
-
56 HOTGI-KUDGI-GADAG - [N22000333]SWR,MULTI STATE 03/2015 1,618.00 -
- -
-
Total 46,938.32 -
ROAD TRANSPORT AND HIGHWAYS
57 2 LANING OF SHILLONG NONGSTOIN SECTION OF NH 44 AND NONGSTOIN TURA STATE ROAD UNDER PHASE A OF SA - [N24000390]PWD,MEGHALAYA
12/2010 1,494.48 -
02/2011 -
02/2011
58 SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502 - [N24000131]NHAI,MULTI STATE
02/2009 1,693.75 -
08/2011 -
-
59 NEW 4 LANE ELEVATED ROAD FROM CHENNAI AIRPORT-MADURAVOYAL NH NO.4 - [N24000139]NHAI,TAMIL NADU
09/2010 1,655.00 -
09/2013 -
-
60 YADGIRI-WARANGAL OF NH 202(NEW NH 163) UNDER NHDP-IV - [N24000235]NHAI,TELANGANA
04/2014 1,123.17 -
- -
-
61 WIDENING OF 2(TWO) LANING OF LONGLENG-CHANTONGYA ROAD, MON-TAMLU-MERANGKONG ROAD, PHEK- PFUTSERO ROA - [N24000315]PWD,NAGALAND
12/2010 1,296.00 -
02/2011 -
-
62 4 LANING OF AMRAVATI - CHIKHLI (PKG-I) - [N24000425]NHAI,MAHARASHTRA
07/2015 2,288.18 -
- -
-
63 4 LANING OF BAHARAGORA - SINGHARA - [N24000427]NHAI,ODISHA
07/2015 1,282.94 -
- -
-
Date of
Commissioning (Month/Year)
SI.No
Project
Date of Approval
(Month/Year)
Original / Revised
Cost (Rs. crore)
Original / Revised
Anticipated
1 2 3 4 5 6 64 4 LANING OF FAGNE - MAH-GUJ BORDER ( PKG-3) -
[N24000439]NHAI,MAHARASHTRA 07/2015 1,885.74
- - -
-
65 8 LANING OF MUKARBA CHOWK TO PANIPAT - [N24000449]NHAI,HARYANA
07/2015 2,128.72 -
- -
-
66 6 LANING OF AGRA - ETAWAH BYPASS - [N24000452]NHAI,UTTAR PRADESH
07/2015 1,657.20 -
- -
-
67 4 LANING OF GUNA TO BIAORA - [N24000458]NHAI,MADHYA PRADESH
06/2015 1,012.90 -
- -
-
68 FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31 - [N24000480]NHAI,BIHAR
12/2015 1,041.10 -
- -
-
69 FOUR LANING OF YADGIRI - WARANGAL - [N24000486]NHAI,WEST BENGAL
12/2015 1,423.96 -
- -
-
70 FOUR LANING OF HOSPET - CHITRADURGA - [N24000490]NHAI,KARNATAKA
01/1991 1,388.00 -
- -
-
71 FOUR LANING OF BIAORA –DEWAS SECTION OF NH-3 FROM KM 426.100 TO KM 566.450 IN THE STATE OF MADHYA PR - [N24000505]NHAI,MADHYA PRADESH
06/2015 1,583.79 -
- -
-
72 FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31 - [N24000507]NHAI,BIHAR
01/1991 1,167.45 -
- -
-
Total 24,122.38 -
SHIPPING AND PORTS
73 SETHUSAMUDRAM SHIP CHANNEL PROJECT - [250100175]PORT TRUST,TAMIL NADU
06/2005 2,427.40 -
10/2008 -
-
Total 2,427.40 -
URBAN DEVELOPMENT
74 MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ) - [N28000086]MMRCL,MAHARASHTRA
07/2013 23,136.00 -
01/2015 -
12/2015
Total 23,136.00 -
Grand Total 115,429.04
Annexure - IX Details of Projects Without Original Date of Commissioning
(January 2016)
Date of
Commissioning (Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised Cost
(Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure (Rs. crore)
Original /
Revised
Antici Pated
Delay w.r.t.
Original (in months)
Milestones Achieved/
Total
1 2 3 4 5 6 7 8 9 10 RAILWAYS
1 RAMGANJMUNDI-BHOPAL (NL),WCR - [220100314]WCR,MADHYA PRADESH
04/2001 470.92 727.13
1,225.90 257.59 - -
03/2017 - 0/0
2 CHHINDWARA - NAGPUR (GC)(SECR) - [220100324]SECR,MADHYA PRADESH
04/2005 383.79 663.67
1,101.16 194.91 - -
03/2017 - 0/0
3 KANPUR KASGANJ MATHURA(GC) NER - [220100197]NER,UTTAR PRADESH
03/1997 677.97 1,062.36
1,651.54 1,621.40 - -
03/2018 - 0/0
4 NEW JALPAIGURI-SILIGURI-NEW BONGAIGAON INCLUDING BR. LINE AND MM FOR CHALSA-NAXAL& RAJABHATKHOWA-JAI - [N22000209]NFR,MULTI STATE
04/1999 523.17 380.60
1,653.55 1,040.11 - -
03/2018 - 0/0
5 KIRANDUL - JAGDALPUR DOUBLING - [N22000318]ECOR,CHHATISGARH
12/2012 826.57 -
1,143.60 189.12 - -
03/2018 - 0/0
6 NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR - [220100135]NFR,WEST BENGAL
04/1983 36.80 36.38
1,336.57 255.55 - -
03/2019 - 0/0
7 NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING - [N22000183]NFR,MULTI STATE
04/2013 1,798.00 1,798.00
1,887.90 - - -
03/2019 - 0/0
8 DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRA - [N22000160]SER,MULTI STATE
04/2010 553.63 651.17
1,009.00 7.50 - -
12/2019 - 0/0
9 DIMAPUR-TIZIT NL - [N22000196]NFR,NAGALAND
04/2013 4,274.00 -
4,487.70 - - -
03/2020 - 0/0
10 NEW BG LINE FROM BYRNIHAT TO SHILLONG - [N22000205]NFR,MEGHALAYA
04/2010 4,083.02 -
5,307.90 7.79 - 03/2016
03/2020 48(R3) 0/0
11 VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM) - [N22000313]RVNL,ANDHRA PRADESH
03/2012 1,503.71 -
1,503.71 175.26 - -
03/2020 - 0/0
Total 15,131.58 -
22,308.53 3,749.23 0/0
ROAD TRANSPORT AND HIGHWAYS
12 SIX-LANING OF BARWA ADDA-PANAGARH - [N24000515]NHAI,WEST BENGAL
04/2014 1,665.00 -
1,665.00 994.21 - -
09/2016 - 0/0
13 FOUR LANING OF KAITHAL - RAJASTHAN BORDER - [N24000487]NHAI,HARYANA
07/2015 1,393.00 -
1,393.00 876.68 - -
01/2018 - 0/0
Total 3,058.00 -
3,058.00 1,870.89 0/0
Grand Total 18,189.58 25,366.53 5,620.12 0/0
Annexure - X Details of Projects Without Milestones w.r.t. Original Schedule
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 COAL
1 MADANNAGAR OPENCAST PROJECT - [N06000140]SECL,CHHATISGARH 10/2015 1,875.32 -
03/2024 -
03/2024 0/0
Total 1,875.32 -
0/0
MINES
2 EXPANSION OF MALANJKHAND MINE-DEVELOPMENT OF UNDERGROUND MINE UNDER EXISTING OPEN CAST MINE OF CAPAC - [N10000007]HCL,MADHYA PRADESH
09/2011 1,856.00 -
09/2017 -
04/2020 0/0
Total 1,856.00 -
0/0
STEEL
3 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA - [N12000101]HSCL,KARNATAKA
05/2005 768.88 1,060.00
02/2014 -
03/2016 0/0
4 EXPANSION OF GUA ORE MINES WITH BENEFICIATION FACILITIES AND INSTALLATION OF PELLET PLANT - [N12000097]SAIL,JHARKHAND
02/2014 4,749.00 -
09/2017 -
09/2017 0/0
5 NEW SINTER PLANT AT BOKARO STEEL PLANT - [N12000095]SAIL,JHARKHAND 03/2015 1,034.01 -
10/2017 -
10/2017 0/0
6 MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANT - [N12000096]SAIL,JHARKHAND
05/2015 1,154.18 -
12/2017 -
12/2017 0/0
7 INSTALLATION OF NEW HOT STRIP MILL AT RSP - [N12000094]SAIL,ODISHA 04/2015 3,127.30 -
04/2018 -
04/2018 0/0
Total 10,833.37 -
0/0
PETROLEUM
8 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE - [N16000157]ISPRL,KARNATAKA
01/2006 732.00 1,227.00
10/2011 -
03/2016 0/0
9 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR - [N16000169]ISPRL,KERALA 01/2006 993.00 1,693.00
01/2012 -
05/2016 0/0
10 PIPELINE REPLACEMENT PROJECT -4 - [N16000203]ONGC,MAHARASHTRA 02/2015 2,899.93 2,098.43
05/2017 -
05/2017 0/0
11 POLYPROPYLENE PLANT AT PARADIP REFINERY - [N16000179]IOCL,ODISHA 03/2014 3,150.00 -
09/2017 -
09/2017 0/0
12 DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERY - [N16000175]IOCL,WEST BENGAL
03/2014 3,076.00 -
09/2017 03/2018
12/2017 0/0
13 INSTALLATION OF DIESEL HYDROTREATMENT UNIT (DHT) AND ASSOCIATED FACILITIES - [N16000205]BPCL,MAHARASHTRA
05/2015 2,443.00 -
12/2017 -
12/2017 0/0
14 DIESEL HYDROTREATOR - [N16000207]NRL,ASSAM 07/2015 1,031.37 -
01/2018 -
01/2018 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 15 MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-III -
[N16000197]ONGC,MAHARASHTRA 11/2014 6,068.80
- 04/2019
- 03/2019 0/0
16 NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAY - [N16000204]ONGC,MAHARASHTRA
08/2015 2,818.88 -
03/2019 -
03/2019 0/0
17 GAMJI REDEVELOPMENT PROJECT - [N16000202]ONGC,GUJARAT 05/2015 1,671.22 1,881.22
11/2019 -
11/2019 0/0
18 DAMAN DEVELOPMENT PROJECT - [N16000198]ONGC,D & N HAVELI 08/2014 6,086.08 -
05/2019 03/2020
03/2020 0/0
19 AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPUR - [N16000193]IOCL,MULTI STATE
01/2015 1,823.00 -
- -
- 0/0
20 PARADIP HYDERABAD PIPLEINE - [N16000194]IOCL,MULTI STATE 01/2015 2,321.00 -
- -
- 0/0
Total 35,114.28 -
0/0
POWER
21 BOKARO THERMAL POWER STATION-A - [N18000199]DVC,JHARKHAND 08/2006 2,313.00 4,139.00
12/2011 -
03/2016 0/0
22 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202]DVC,WEST BENGAL
04/2007 4,122.00 8,781.00
02/2011 -
01/2017 0/0
23 INSTALLATION OF STATCOMS IN WESTERN REGION - [N18000185]PGCIL,MULTI STATE
03/2015 1,071.24 -
09/2017 -
09/2017 0/0
24 GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART C - [N18000200]PGCIL,MULTI STATE
07/2015 2,247.37 -
07/2018 -
07/2018 0/0
25 SYSTEM STRENGTHENING XXIV IN SOUTHERN REGION - [N18000208]PGCIL,MULTI STATE
01/2016 1,455.47 -
07/2018 -
07/2018 0/0
26 PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) - [N18000172]CVPPPL,JAMMU AND KASHMIR
10/2014 8,112.12 -
04/2020 -
04/2020 0/0
27 SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) - [180100221]NHPC,ARUNACHAL PRADESH
09/2003 6,285.33 -
09/2010 -
- 0/0
Total 25,606.53 -
0/0
HEAVY INDUSTRY
28 NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP) - [N20000001]NATIS,MULTI STATE
04/2011 1,718.00 -
09/2011 -
12/2017 0/0
Total 1,718.00 -
0/0
RAILWAYS
29 HOWRAH-AMTA-CHAMPADANGA NL (SER) - [220100208]SER,WEST BENGAL 04/1974 393.46 393.46
03/2007 03/2007
03/2015 0/0
30 PATNA GANGA BRIDGE (NL), ECR - [220100308]ECR,BIHAR 04/2001 624.47 -
10/2007 12/2012
12/2015 0/0
31 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164]MRTP,MAHARASHTRA
03/1996 495.44 495.44
03/2004 -
03/2016 0/0
32 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307]ECR,BIHAR 04/2002 921.00 3,040.00
03/2009 -
03/2016 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 33 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL
PROJECT - [N22000127]NFR,ASSAM 04/1996 1,676.31
- 03/2009
- 03/2016 0/0
34 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194]NFR,TRIPURA 04/1999 895.00 -
03/2007 -
03/2016 0/0
35 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP) - [N22000108]RVNL,WEST BENGAL
04/2010 2,397.72 -
03/2016 -
06/2016 0/0
36 RAMGANJMUNDI-BHOPAL (NL),WCR - [220100314]WCR,MADHYA PRADESH 04/2001 470.92 727.13
- -
03/2017 0/0
37 CHHINDWARA - NAGPUR (GC)(SECR) - [220100324]SECR,MADHYA PRADESH 04/2005 383.79 663.67
- -
03/2017 0/0
38 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201]NFR,ASSAM 09/1997 1,500.00 4,996.19
04/2008 12/2011
06/2017 0/0
39 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133]NR,JAMMU AND KASHMIR
03/1995 2,500.00 -
11/2002 -
12/2017 0/0
40 KANPUR KASGANJ MATHURA(GC) NER - [220100197]NER,UTTAR PRADESH 03/1997 677.97 1,062.36
- -
03/2018 0/0
41 KATIHAR - JOGBANI (GC)(NEFR) - [220100247]NFR,BIHAR 09/2001 492.98 -
12/2010 -
03/2018 0/0
42 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266]NFR,MULTI STATE
04/2000 733.00 733.00
12/2008 -
03/2018 0/0
43 AGARTALA SABROOM, NL, NEFR - [N22000099]NFR,TRIPURA 04/2008 813.34 813.34
03/2014 -
03/2018 0/0
44 BHAIRABI SAIRONG, NL, NEFR - [N22000100]NFR,MIZORAM 04/2008 619.34 619.34
04/2014 03/2015
03/2018 0/0
45 NEW JALPAIGURI-SILIGURI-NEW BONGAIGAON INCLUDING BR. LINE AND MM FOR CHALSA-NAXAL& RAJABHATKHOWA-JAI - [N22000209]NFR,MULTI STATE
04/1999 523.17 380.60
- -
03/2018 0/0
46 KIRANDUL - JAGDALPUR DOUBLING - [N22000318]ECOR,CHHATISGARH 12/2012 826.57 -
- -
03/2018 0/0
47 EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKE - [N22000135]MRTP,WEST BENGAL
03/2013 4,874.58 -
03/2016 -
06/2018 0/0
48 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH. - [N22000111]RVNL,WEST BENGAL
04/2010 2,913.51 -
03/2016 -
12/2018 0/0
49 DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR & TANPUR-BANSI PAHARPUR - [N22000158]NCR,MULTI STATE
04/2010 622.41 2,030.50
02/2019 -
02/2019 0/0
50 NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR - [220100135]NFR,WEST BENGAL
04/1983 36.80 36.38
- -
03/2019 0/0
51 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288]NFR,MANIPUR 04/2003 727.56 727.56
03/2011 03/2014
03/2019 0/0
52 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092]MRTP,MAHARASHTRA
04/2008 5,300.00 6,821.29
03/2014 03/2019
03/2019 0/0
53 NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING - [N22000183]NFR,MULTI STATE
04/2013 1,798.00 1,798.00
- -
03/2019 0/0
54 GONDIA-JABALPUR(GC),(SECR) - [220100186]SECR,MULTI STATE 02/1997 386.30 -
03/1998 -
12/2019 0/0
55 BANKURA - DAMODAR (GC) (SER) - [220100277]SER,WEST BENGAL 03/1998 111.90 1,039.29
03/2005 12/2008
12/2019 0/0
56 TAMLUK DIGHA,LINE DOUBLING (SER) - [N22000097]SER,WEST BENGAL 03/1984 293.97 1,013.74
06/2005 07/2011
12/2019 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 57 DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRA - [N22000160]SER,MULTI
STATE 04/2010 553.63
651.17 - -
12/2019 0/0
58 GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC) - [N22000148]NCR,MULTI STATE
04/2011 1,176.09 3,845.60
02/2020 -
02/2020 0/0
59 SEVOK RANGPO, NEFR - [N22000102]NFR,SIKKIM 04/2008 1,339.48 1,339.48
12/2015 -
03/2020 0/0
60 NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124]NFR,NAGALAND
04/2006 850.00 -
03/2015 03/2020
03/2020 0/0
61 DIMAPUR-TIZIT NL - [N22000196]NFR,NAGALAND 04/2013 4,274.00 -
- -
03/2020 0/0
62 NEW BG LINE FROM BYRNIHAT TO SHILLONG - [N22000205]NFR,MEGHALAYA 04/2010 4,083.02 -
- 03/2016
03/2020 0/0
63 VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM) - [N22000313]RVNL,ANDHRA PRADESH
03/2012 1,503.71 -
- -
03/2020 0/0
64 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP) - [N22000110]RVNL,WEST BENGAL
04/2010 3,951.98 -
03/2016 -
12/2020 0/0
65 LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) - [220100232]WCR,MULTI STATE 09/1998 247.66 3,500.00
05/2008 -
- 0/0
66 PALANPUR-SAMAKHAYALI (DL) - [N22000144]WR,GUJARAT 04/2013 1,266.89 -
- -
- 0/0
67 KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION - [N22000261]SCR,MULTI STATE
04/2012 1,054.35 2,200.00
- -
- 0/0
68 GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM) - [N22000345],UTTAR PRADESH
04/1997 836.26 -
- -
- 0/0
69 UTRATIA-ZAFRABAD, NR (LINE DOUBLING) - [N22000088]NR,UTTAR PRADESH 04/2006 325.00 2,434.00
03/2010 -
- 0/0
70 AHMEDNAGAR-PARLI VAIJNATH(NL) CR - [220100181]CR,MAHARASHTRA 02/1997 514.68 -
- -
- 0/0
71 HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR - [220100183]SWR,KARNATAKA
02/1997 295.00 -
- -
- 0/0
72 NANGALDAM-TALWARA(NL),NR - [220100188]NR,MULTI STATE 03/1981 450.00 -
07/2012 -
- 0/0
73 HUBLI-ANKOLA(NL),SWR - [220100193]SWR,KARNATAKA 04/1997 227.00 997.58
- -
- 0/0
74 KODERMA-RANCHI VIA BARKAKANA (NL),ECR - [220100222]ECR,JHARKHAND 03/1999 2,957.21 -
07/2005 -
- 0/0
75 JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR - [220100240]ECR,BIHAR 04/1997 501.69 501.69
03/2012 -
- 0/0
76 ANGAMALI-SABARIMALA (N.L.)(SR) - [220100252]SR,KERALA 10/1998 550.00 517.70
- -
- 0/0
77 KOTLPALLI-NARASAPUR (NL) (SCR) - [220100265]SCR,ANDHRA PRADESH 12/2001 330.00 -
- -
- 0/0
78 TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP) - [220100268]MRTP,WEST BENGAL
03/2000 1,049.69 3,385.14
12/2006 -
- 0/0
79 TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ER - [220100272]ER,WEST BENGAL 04/2000 1,188.91 -
- 12/2009
- 0/0
80 BANGLORE - SATYAMANGALAM (NL)(SWR) - [220100274]SWR,KARNATAKA 04/1996 138.00 -
- -
- 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 81 KHURDA ROAD-BOLANGIR(NL)ECOR - [220100284]ECOR,ODISHA 04/1994 470.21
- - -
- 0/0
82 HARIDASPUR-PARADEEP(NL) - [220100285]RVNL,ODISHA 04/1996 301.64 -
- 09/2009
- 0/0
83 SUKINDA ROAD - ANGUL (NL)(ECOR) - [220100325]RVNL,ODISHA 04/1998 183.23 -
02/2015 -
- 0/0
84 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI - [N22000079]SR,TAMIL NADU
09/2007 404.19 -
- -
- 0/0
85 TIDIVANAM-NAGARI (NL) - [N22000085]SR,TAMIL NADU 09/2006 456.00 -
- -
- 0/0
86 BARDHAMAN-KATWA (GC) - [N22000091]ER,WEST BENGAL 04/2007 1,106.62 -
12/2010 -
- 0/0
87 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP) - [N22000109]RVNL,WEST BENGAL
04/2010 2,298.42 -
03/2014 -
- 0/0
88 RATLAM-MHOW-KHANDWA-AKOLA (GC) - [N22000120]WR,MADHYA PRADESH 04/2008 603.04 -
03/2012 -
- 0/0
89 UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR) - [N22000122]WR,GUJARAT
04/2008 1,389.62 -
03/2014 -
- 0/0
90 CHOTTAUDEPUR-DHAR(NL) - [N22000138]WR,MULTI STATE 04/2007 1,347.26 -
- -
- 0/0
91 DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL) - [N22000139]WR,MULTI STATE
04/2007 1,640.04 -
- -
- 0/0
92 RATLAM-DUNGARPUR VIA BANSWARA (NL) - [N22000147]NWR,MULTI STATE 04/2011 2,082.75 -
- -
- 0/0
93 CHENNAI-CUDDALORE VIA MAMALLAPURAM - [N22000185]SR,MULTI STATE 04/2008 523.52 -
- -
- 0/0
94 SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDUR - [N22000186]SR,TAMIL NADU
04/2013 839.00 -
- -
- 0/0
95 VILLUPURAM-DINDIGUL WITH ELECTRIFICATION - [N22000189]SR,MULTI STATE 04/2008 822.39 -
- -
- 0/0
96 WARDHA-NANDED MAHARASHTRA - [N22000231]CR,MAHARASHTRA 04/2008 499.30 -
- -
- 0/0
97 TUMKUR-CHITRADURGA-DAVENGERE NL - [N22000256]SWR,KARNATAKA 04/2011 913.00 -
- -
- 0/0
98 MUNIRABAD (GINGERA) -RAICHUR NL - [N22000257]SWR,KARNATAKA 04/2007 179.65 -
- -
- 0/0
99 MANUGURU-RAMAGUNDAM - [N22000259]SCR,TELANGANA 04/2013 1,112.00 -
- -
- 0/0
100 AKOLA-KHANDWA GC AKOLA-AKOT - [N22000263]SCR,MULTI STATE 04/2008 184.26 -
- -
- 0/0
101 DELHI-SOHNA-NUH-FIROZPUR-JHIRKA-ALWAR - [N22000271]NR,MULTI STATE 04/2013 1,239.00 -
- -
- 0/0
102 BHANUPALI-BILASPUR BERI NL - [N22000273]NR,HIMACHAL PRADESH 04/2008 1,046.88 -
- -
- 0/0
103 RAYADURGA-TUMKUR NL - [N22000279]SWR,MULTI STATE 04/2007 970.34 -
- -
- 0/0
104 NADIKUDE-SRI KALAHASTI - [N22000286]SCR,ANDHRA PRADESH 04/2011 1,313.48 -
- -
- 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7
105 KADAPA-BANGALORE (NL), KADAPA-PENDLIMARRI PH-I - [N22000288]SCR,MULTI STATE
04/2008 2,050.00 -
- -
- 0/0
106 HOSPET-HUBLI-LONDA-VASCODAGAMA DL - [N22000297]SWR,KARNATAKA 04/2010 2,127.00 -
- -
- 0/0
107 GADAG-WADI NL - [N22000299]SWR,KARNATAKA 04/2013 1,117.00 -
- -
- 0/0
108 QUILON-TIRUNELVELI - TRICHENDUR, TENKASI - [N22000303]SR,TAMIL NADU 04/1999 460.94 -
01/1999 -
- 0/0
109 SAMBALPUR-TALCHER DOUBLING - [N22000315]ECOR,ODISHA 03/2011 679.27 -
- -
- 0/0
110 HUBLI- CHIKJAJUR - [N22000325]SWR,KARNATAKA 03/2015 1,900.00 -
- -
- 0/0
111 MIRAJ-LONDA - [N22000327]SWR,MULTI STATE 03/2015 1,830.00 -
- -
- 0/0
112 HOTGI-KUDGI-GADAG - [N22000333]SWR,MULTI STATE 03/2015 1,618.00 -
- -
- 0/0
Total 97,381.81 -
0/0
ROAD TRANSPORT AND HIGHWAYS
113 2 LANING OF SHILLONG NONGSTOIN SECTION OF NH 44 AND NONGSTOIN TURA STATE ROAD UNDER PHASE A OF SA - [N24000390]PWD,MEGHALAYA
12/2010 1,494.48 -
02/2011 -
02/2011 0/0
114 GURGAON - KOTPUTLI - JAIPUR (SIX LANE) - [N24000477]DORTH,RAJASTHAN 02/2008 1,673.70 -
10/2011 -
01/2016 0/0
115 FOUR LANING OF GWALIOR-SHIVPURI - [N24000494]DORTH,MADHYA PRADESH 05/2013 1,055.00 -
11/2015 -
01/2016 0/0
116 INDORE-JHABUA-GUJRAT/MP - [N24000136]NHAI,MADHYA PRADESH 10/2010 1,175.00 -
04/2013 -
03/2016 0/0
117 MURADABAD-BAREILY - [N24000154]NHAI,UTTAR PRADESH 04/2010 1,267.00 -
06/2013 -
03/2016 0/0
118 4 LANING OF NAGPUR-BETUL - [N24000155]NHAI,MULTI STATE 02/2011 2,498.76 -
08/2014 -
03/2016 0/0
119 BEAWAR PALI PINDWARA - [N24000199]NHAI,RAJASTHAN 12/2011 2,388.51 -
06/2014 -
03/2016 0/0
120 SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWAR - [N24000205]NHAI,MULTI STATE
12/2011 1,047.00 -
06/2014 -
03/2016 0/0
121 FOUR LANING OF ORISSA CHATTISHGARH BORDER - [N24000218]NHAI,MULTI STATE
02/2013 1,232.00 -
08/2015 -
03/2016 0/0
122 FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTION - [N24000481]NHAI,CHHATISGARH
02/2013 1,232.00 -
08/2015 -
03/2016 0/0
123 FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA - [N24000496]NHAI,MADHYA PRADESH
06/2015 1,012.90 -
03/2016 -
03/2016 0/0
124 GHAZIABAD-ALIGARH NH-91 - [N24000170]NHAI,UTTAR PRADESH 02/2011 1,141.00 -
08/2013 -
04/2016 0/0
125 DELHI AGRA APPROVED LENGTH 180.0 KM - [N24000224]NHAI,MULTI STATE 10/2012 1,928.22 -
04/2015 -
04/2016 0/0
126 NASHRI- CHANANI - [N24000162]NHAI,JAMMU AND KASHMIR 05/2011 2,159.00 -
06/2015 -
05/2016 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7
127 6-LANING OF DHANKUNI-KHARAGPUR SECTION - [N24000206]NHAI,WEST BENGAL 04/2012 1,396.18 -
09/2014 -
05/2016 0/0
128 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM) - [N24000133]NHAI,HARYANA 05/2009 1,108.00 -
11/2011 -
06/2016 0/0
129 QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00 - [N24000161]NHAI,JAMMU AND KASHMIR
07/2010 1,987.00 -
07/2015 -
06/2016 0/0
130 JAMMU-UDHAMPUR KM.27.5 TO KM.67.00 - [N24000163]NHAI,JAMMU AND KASHMIR 07/2010 1,813.76 -
07/2013 -
06/2016 0/0
131 SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547 - [N24000183]NHAI,ANDHRA PRADESH
11/2011 1,535.00 -
05/2014 -
06/2016 0/0
132 SRINAGAR TO BANIHAL - [N24000189]NHAI,JAMMU AND KASHMIR 06/2011 1,100.70 -
06/2014 -
06/2016 0/0
133 ETAWAH CHAKERI - [N24000219]NHAI,UTTAR PRADESH 03/2013 1,573.00 -
09/2015 -
06/2016 0/0
134 CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KM - [N24000145]NHAI,ANDHRA PRADESH
11/2010 1,585.00 -
05/2013 -
08/2016 0/0
135 4-LANING OF FARAKA-RAIGANJ - [N24000202]NHAI,MULTI STATE 02/2011 1,078.84 -
08/2013 -
08/2016 0/0
136 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION - [N24000462]NHAI,KARNATAKA
05/2014 1,655.01 -
08/2016 -
08/2016 0/0
137 FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASS - [N24000509]NHAI,MAHARASHTRA
04/2010 1,170.52 -
06/2012 -
08/2016 0/0
138 4 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9 - [N24000233]NHAI,TELANGANA
04/2014 1,266.60 -
09/2016 -
09/2016 0/0
139 SIX-LANING OF BARWA ADDA-PANAGARH - [N24000515]NHAI,WEST BENGAL 04/2014 1,665.00 -
- -
09/2016 0/0
140 PANIKHOLI-RIMOLI - [N24000197]NHAI,ODISHA 03/2012 1,410.00 -
09/2014 -
10/2016 0/0
141 FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM) - [N24000232]NHAI,HIMACHAL PRADESH
11/2013 1,916.79 -
11/2016 -
11/2016 0/0
142 PUNE-SATARA(NH-4) - [N24000156]NHAI,MAHARASHTRA 10/2010 1,724.55 -
03/2013 -
12/2016 0/0
143 SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46 - [N24000172]NHAI,TAMIL NADU
09/2011 1,250.00 -
12/2013 -
12/2016 0/0
144 BAREILY-SITAPUR (NH-24) - [N24000200]NHAI,UTTAR PRADESH 03/2011 1,046.00 -
09/2013 -
12/2016 0/0
145 WALAJAPET POONAMALEE KM 106.8 TO KM 13.8 - [N24000228]NHAI,TAMIL NADU 06/2013 1,287.95 -
11/2015 -
03/2017 0/0
146 VARANASI-AURANGABAD KM.786 TO KM.978.40 - [N24000182]NHAI,MULTI STATE 09/2011 2,848.00 -
03/2014 -
04/2017 0/0
147 RANCHI-RARGA-JAMSETHPUR - [N24000215]NHAI,MULTI STATE 12/2012 1,479.00 -
06/2015 -
05/2017 0/0
148 FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120 - [N24000349]NHAI,TAMIL NADU
05/2015 1,387.11 -
11/2017 -
11/2017 0/0
149 FOUR LANING OF KAITHAL - RAJASTHAN BORDER - [N24000487]NHAI,HARYANA 07/2015 1,393.00 -
- -
01/2018 0/0
150 FOUR LANING OF AURANGABAD - YEDISHI - [N24000508]NHAI,MAHARASHTRA 07/2015 1,871.34 -
01/2018 -
01/2018 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7
151 4 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785) - [N24000463]NHAI,WEST BENGAL
12/2015 1,083.00 -
06/2018 -
06/2018 0/0
152 FOUR LANING OF SULTANPUR TO VARANASI (PKG-I) - [N24000493]NHAI,UTTAR PRADESH
01/2016 1,027.53 -
06/2018 -
06/2018 0/0
153 FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A - [N24000488]NHAI,JAMMU AND KASHMIR
12/2015 2,136.97 -
12/2018 -
12/2018 0/0
154 FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1A - [N24000471]NHAI,JAMMU AND KASHMIR
12/2015 2,168.66 -
06/2019 -
06/2019 0/0
155 NEW 4 LANE ELEVATED ROAD FROM CHENNAI AIRPORT-MADURAVOYAL NH NO.4 - [N24000139]NHAI,TAMIL NADU
09/2010 1,655.00 -
09/2013 -
- 0/0
156 YADGIRI-WARANGAL OF NH 202(NEW NH 163) UNDER NHDP-IV - [N24000235]NHAI,TELANGANA
04/2014 1,123.17 -
- -
- 0/0
157 WIDENING OF 2(TWO) LANING OF LONGLENG-CHANTONGYA ROAD, MON-TAMLU-MERANGKONG ROAD, PHEK- PFUTSERO ROA - [N24000315]PWD,NAGALAND
12/2010 1,296.00 -
02/2011 -
- 0/0
158 4 LANING OF AMRAVATI - CHIKHLI (PKG-I) - [N24000425]NHAI,MAHARASHTRA 07/2015 2,288.18 -
- -
- 0/0
159 4 LANING OF BAHARAGORA - SINGHARA - [N24000427]NHAI,ODISHA 07/2015 1,282.94 -
- -
- 0/0
160 4 LANING OF FAGNE - MAH-GUJ BORDER ( PKG-3) - [N24000439]NHAI,MAHARASHTRA
07/2015 1,885.74 -
- -
- 0/0
161 8 LANING OF MUKARBA CHOWK TO PANIPAT - [N24000449]NHAI,HARYANA 07/2015 2,128.72 -
- -
- 0/0
162 6 LANING OF AGRA - ETAWAH BYPASS - [N24000452]NHAI,UTTAR PRADESH 07/2015 1,657.20 -
- -
- 0/0
163 4 LANING OF GUNA TO BIAORA - [N24000458]NHAI,MADHYA PRADESH 06/2015 1,012.90 -
- -
- 0/0
164 FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31 - [N24000480]NHAI,BIHAR 12/2015 1,041.10 -
- -
- 0/0
165 FOUR LANING OF YADGIRI - WARANGAL - [N24000486]NHAI,WEST BENGAL 12/2015 1,423.96 -
- -
- 0/0
166 FOUR LANING OF HOSPET - CHITRADURGA - [N24000490]NHAI,KARNATAKA 01/1991 1,388.00 -
- -
- 0/0
167 FOUR LANING OF BIAORA –DEWAS SECTION OF NH-3 FROM KM 426.100 TO KM 566.450 IN THE STATE OF MADHYA PR - [N24000505]NHAI,MADHYA PRADESH
06/2015 1,583.79 -
- -
- 0/0
168 FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31 - [N24000507]NHAI,BIHAR
01/1991 1,167.45 -
- -
- 0/0
Total 85,203.23 -
0/0
SHIPPING AND PORTS
169 SETHUSAMUDRAM SHIP CHANNEL PROJECT - [250100175]PORT TRUST,TAMIL NADU
06/2005 2,427.40 -
10/2008 -
- 0/0
Total 2,427.40 -
0/0
TELECOMMUNICATIONS
170 NETWORK FOR SPECTRUM - [N26000101]DOT,MULTI STATE 03/2012 13,334.00 -
07/2015 -
03/2017 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 Total 13,334.00
- 0/0
URBAN DEVELOPMENT
171 MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ) - [N28000086]MMRCL,MAHARASHTRA
07/2013 23,136.00 -
01/2015 -
12/2015 0/0
172 DELHI MRTS PHASE-III - [N28000056]DMRCL,DELHI 09/2011 38,585.00 -
03/2016 -
12/2016 0/0
173 KOCHI METRO RAIL PROJECT - [N28000081]KMRCL,KERALA 07/2012 5,181.79 -
07/2017 -
06/2017 0/0
174 ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHI - [N28000071]CPWD,DELHI
10/2013 1,219.21 -
07/2017 -
07/2017 0/0
175 NAGPUR METRO RAIL - [N28000085]NMRCL,MAHARASHTRA 08/2014 8,680.00 -
03/2018 -
03/2018 0/0
176 BANGALORE METRO RAIL PROJECT PHASE-2 - [N28000058]BMRCL,KARNATAKA 02/2014 26,405.14 26,405.01
02/2019 03/2020
03/2020 0/0
Total 103,207.14 -
0/0
Grand Total 378,557.08 0/0
Annexure - XI List of Projects Ahead of Schedule w.r.t. Latest Schedule
(January 2016)
Date of Commissioning
SI.No
Project
Date of Approval
Original / Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
1 2 3 4 5 6 7 8 PETROLEUM
1 DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERY - [N16000175
3/2014 3,076.00 -
3,076.00 188.44 09/2017 03/2018
12/2017
Total 3,076.00 -
3,076.00 188.44
URBAN DEVELOPMENT
2 KOCHI METRO RAIL PROJECT - [N28000081
7/2012 5,181.79 -
5,181.79 2,562.95 07/2017 -
06/2017
Total 5,181.79 -
5,181.79 2,562.95
PETROLEUM
3 MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-III - [N16000197
11/2014 6,068.80 -
6,068.80 648.01 04/2019 -
03/2019
Total 6,068.80 -
6,068.80 648.01
Grand Total 14,326.59 14,326.59 3,399.40
Annexure - XII List of Projects on schedule w.r.t. Latest Schedule
(January 2016) Date of
Commissioning
SI.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original /Revised
Antici Pated
1 2 3 4 5 6 7 8 COAL
1 AMLOHRI EPR (NCL) (6 MTY , INCR.) - [N06000010
12/2009 1,352.04 -
1,143.54 809.04 03/2016 -
03/2016
2 RAMPUR BATURA OCP (4.0 MTY) - [N06000049
8/2015 1,186.64 -
1,186.64 1.33 03/2023 -
03/2023
3 MADANNAGAR OPENCAST PROJECT - [N06000140
10/2015 1,875.32 -
1,875.32 - 03/2024 -
03/2024
4 GARJANBAHAL OCP - [N06000117
11/2014 1,375.38 -
1,375.38 179.10 03/2021 -
03/2021
5 KHADIA EXPANSION OPENCAST PROJECT(4 TO 10 MTPA,6MTPA INCREMENTAL) - [N06000091
6/2011 1,131.28 -
1,131.28 148.45 03/2018 -
03/2018
6 SIARMAL OCP (40.00MTY) - [N06000113
5/2014 3,756.36 -
3,756.36 620.94 03/2026 -
03/2026
7 PELMA OCP(15.00MTY) - [N06000045
11/2014 1,624.59 -
1,624.59 5.43 03/2023 03/2023
03/2023
8 KUSMUNDA EXPN.OCP(SECL)(15-50)MTY - [N06000008
8/2013 7,612.33 -
7,612.33 798.52 03/2023 03/2023
03/2023
9 MOONIDIH XV SEAM UG - [N06000098
8/2011 1,230.27 -
1,230.27 47.76 04/2015 04/2019
04/2019
10 NEYVELI NEW THERMAL POWER PROJECT(2X500 MW) - [N06000095
6/2011 5,907.11 -
5,907.11 1,373.77 12/2015 04/2018
04/2018
Total 27,051.32 -
26,842.82 3,984.34
PETROLEUM
11 CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS) - [N16000128
3/2011 861.79 -
1,256.72 995.12 05/2013 04/2016
04/2016
12 DAMAN DEVELOPMENT PROJECT - [N16000198
8/2014 6,086.08 -
6,086.08 592.92 05/2019 03/2020
03/2020
13 INTEGRATED DEVELOPMENT OF B-127 FIELDS - [N16000131
12/2011 2,059.63 -
2,665.65 1,323.77 03/2015 05/2016
05/2016
14 INSTALLATION OF DIESEL HYDROTREATMENT UNIT (DHT) AND ASSOCIATED FACILITIES - [N16000205
5/2015 2,443.00 -
2,443.00 - 12/2017 -
12/2017
15 DIESEL HYDROTREATOR - [N16000207
7/2015 1,031.37 -
1,031.37 12.72 01/2018 -
01/2018
16 NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAY - [N16000204
8/2015 2,818.88 -
2,818.88 - 03/2019 -
03/2019
17 GAMJI REDEVELOPMENT PROJECT - [N16000202
5/2015 1,671.22 -
1,881.22 - 11/2019 -
11/2019
(January 2016) Date of
Commissioning
SI.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original /Revised
Antici Pated
1 2 3 4 5 6 7 8 18 ADDITIONAL DEVELOPMENT OF VASAI EAST FIELD
- [N16000183 3/2014 2,476.82
- 2,476.82 599.26 12/2018
- 12/2018
19 MH NORTH REDEVELOPMENT PHASE III - [N16000188
6/2014 5,706.47 -
5,813.25 2,689.65 05/2017 05/2017
05/2017
20 INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDS - [N16000172
5/2013 4,124.35 -
4,941.49 549.78 04/2016 12/2017
12/2017
21 DEVELOPMENT OF C-26 CLUSTER FIELDS - [N16000133
3/2012 2,592.17 -
2,592.17 832.22 05/2014 03/2017
03/2017
22 PIPELINE REPLACEMENT PROJECT -4 - [N16000203
2/2015 2,899.93 -
2,098.43 641.31 05/2017 -
05/2017
23 POLYPROPYLENE PLANT AT PARADIP REFINERY - [N16000179
3/2014 3,150.00 -
3,150.00 111.66 09/2017 -
09/2017
24 INTEGRATED REFINERY EXPANSION PROJECT - [N16000143
3/2012 14,225.00 -
16,504.00 10,044.66 05/2016 -
05/2016
Total 52,146.71 -
55,759.08 18,393.07
POWER
25 TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS. - [N18000080
2/2010 2,144.00 -
2,932.88 2,283.80 12/2012 12/2016
12/2016
26 LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MW - [N18000142
7/2012 1,527.00 -
1,527.00 143.00 08/2017 -
08/2017
27 DARLIPALLI STPP STAGE-I (2X800 MW) - [N18000176
2/2014 12,532.44 -
12,532.44 2,500.00 08/2018 -
08/2018
28 FGUTPP, UNCHAHAR STAGE-IV (1X500 MW) - [N18000174
7/2013 3,363.12 -
3,363.12 1,018.00 12/2016 -
12/2016
29 NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECT - [N18000066
2/2009 11,130.19 -
13,762.80 11,463.30 08/2013 12/2017
12/2017
30 TRANSMISSION SYSTEM STRENGTHENING IN WR-NR TRANSMISSION CORRIDOR FOR IPPS IN CHHATTISGARH - [N18000168
6/2014 5,151.37 -
5,151.37 703.00 03/2018 -
03/2018
31 TANDA TPP STAGE-II (2X660 MW) - [N18000175
9/2014 9,188.98 -
9,188.98 1,000.00 03/2019 -
03/2019
32 GADARWARA SUPER THERMAL POWER PROJECT STAGE-I - [N18000151
3/2013 11,638.55 -
11,638.55 4,856.00 09/2017 -
09/2017
33 RAMMAM-III HEPP (3X40 MW) - [N18000178
9/2014 1,381.84 -
1,381.84 157.00 09/2019 -
09/2019
34 PARE HYDRO ELECTRIC PROJECT - [N18000045
12/2008 573.99 -
1,262.27 1,093.23 08/2013 07/2016
07/2016
35 KHARGONE STPP STAGE I (1320 MW) - [N18000205
3/2015 9,870.51 -
9,870.51 - 09/2019 -
09/2019
36 TEHRI PUMPED STORAGE PLANT(1000MW) - [N18000010
7/2006 1,657.00 -
2,978.86 1,603.73 02/2016 09/2019
09/2019
37 NORTH KARANPURA STPP (3X660 MW) - [N18000177
2/2014 14,366.58 -
14,366.58 2,349.00 02/2019 -
02/2019
38 TUIRIAL HYDRO ELECTRIC PROJECT (60MW) - [N18000119
7/1998 368.72 -
1,381.71 951.92 07/2006 10/2016
10/2016
(January 2016) Date of
Commissioning
SI.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original /Revised
Antici Pated
1 2 3 4 5 6 7 8 39 INTER-REGIONAL SYSTEM STRENGTHENING SCHEME
IN WR AND NR (PART-B) - [N18000179
12/2014 6,517.36 -
6,517.36 301.90 04/2018 -
04/2018
40 GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME (ISTS) - PART A - [N18000197
4/2015 1,479.30 -
1,479.30 78.90 04/2017 -
04/2017
41 CREATION OF 400/220 KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-A) - [N18000188
3/2015 1,394.52 -
1,394.52 1.70 05/2017 -
05/2017
42 INSTALLATION OF STATCOMS IN WESTERN REGION - [N18000185
3/2015 1,071.24 -
1,071.24 0.10 09/2017 -
09/2017
43 TRANSMISSION SYSTEM ASSOCIATED WITH MAUDA STAGE-II - [N18000153
9/2013 1,575.30 -
1,575.30 709.90 05/2016 -
05/2016
44 KAMENG HYDROELECTRIC PROJECT (NEEPCO) - [180100239
12/2004 2,496.90 -
6,085.84 4,362.53 12/2009 06/2016
06/2016
45 WARDHA-HYDERABAD 765 KV LINK - [N18000183
1/2015 3,662.02 -
3,662.02 338.80 05/2018 -
05/2018
46 TRIPURA GAS BASED POWER PROJECT - [N18000071
7/2009 421.01 -
1,007.57 958.83 07/2013 01/2016
01/2016
47 GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART B - [N18000196
4/2015 3,705.61 -
3,705.61 194.60 04/2018 -
04/2018
48 GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART C - [N18000200
7/2015 2,247.37 -
2,247.37 16.00 07/2018 -
07/2018
49 LARA SUPER THERMAL POWER PROJECT STAGE-I (2 X 800 MW) - [N18000140
12/2012 11,846.00 -
11,846.00 5,564.00 06/2017 -
06/2017
50 SYSTEM STRENGTHENING XXIV IN SOUTHERN REGION - [N18000208
1/2016 1,455.47 -
1,455.47 - 07/2018 -
07/2018
51 NPGCPL-NABINAGAR STPP - JV (3X660 MW) - [N18000192
1/2013 12,964.60 -
12,964.60 4,914.20 01/2018 -
01/2018
52 PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) - [N18000172
10/2014 8,112.12 -
8,112.12 120.00 04/2020 -
04/2020
Total 143,843.11 -
154,463.23 47,683.44
RAILWAYS
53 DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR & TANPUR-BANSI PAHARPUR - [N22000158
4/2010 622.41 -
2,030.50 3.61 02/2019 -
02/2019
54 GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC) - [N22000148
4/2011 1,176.09 -
3,845.60 2.33 02/2020 -
02/2020
55 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092
4/2008 5,300.00 -
7,986.04 2,443.62 03/2014 03/2019
03/2019
56 NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124
4/2006 850.00 -
2,973.42 10.44 03/2015 03/2020
03/2020
Total 7,948.50 -
16,835.56 2,460.00
(January 2016) Date of
Commissioning
SI.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original /Revised
Antici Pated
1 2 3 4 5 6 7 8 ROAD TRANSPORT AND HIGHWAYS
57 FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1A - [N24000471
12/2015 2,168.66 -
2,168.66 - 06/2019 -
06/2019
58 FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA - [N24000496
6/2015 1,012.90 -
1,012.90 - 03/2016 -
03/2016
59 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION - [N24000462
5/2014 1,655.01 -
1,655.01 - 08/2016 -
08/2016
60 FOUR LANING OF AURANGABAD - YEDISHI - [N24000508
7/2015 1,871.34 -
1,871.34 830.19 01/2018 -
01/2018
61 4 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9 - [N24000233
4/2014 1,266.60 -
1,266.60 - 09/2016 -
09/2016
62 FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM) - [N24000232
11/2013 1,916.79 -
1,916.79 1,202.43 11/2016 -
11/2016
63 FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A - [N24000488
12/2015 2,136.97 -
2,136.97 - 12/2018 -
12/2018
64 FOUR LANING OF SULTANPUR TO VARANASI (PKG-I) - [N24000493
1/2016 1,027.53 -
1,027.53 - 06/2018 -
06/2018
65 4 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785) - [N24000463
12/2015 1,083.00 -
1,083.00 - 06/2018 -
06/2018
66 FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120 - [N24000349
5/2015 1,387.11 -
1,387.11 - 11/2017 -
11/2017
Total 15,525.91 -
15,525.91 2,032.62
STEEL
67 EXPANSION OF GUA ORE MINES WITH BENEFICIATION FACILITIES AND INSTALLATION OF PELLET PLANT - [N12000097
2/2014 4,749.00 -
4,749.00 2.61 09/2017 -
09/2017
68 MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANT - [N12000096
5/2015 1,154.18 -
1,154.18 28.20 12/2017 -
12/2017
69 INSTALLATION OF NEW HOT STRIP MILL AT RSP - [N12000094
4/2015 3,127.30 -
3,127.30 297.93 04/2018 -
04/2018
70 NEW SINTER PLANT AT BOKARO STEEL PLANT - [N12000095
3/2015 1,034.01 -
1,034.01 - 10/2017 -
10/2017
71 NMDC INTEGRATED STEEL PLANT - [N12000086
1/2010 15,525.00 -
15,525.00 8,493.78 05/2015 12/2016
12/2016
Total 25,589.49 -
25,589.49 8,822.52
URBAN DEVELOPMENT
72 REDEVELOPMENT OF EAST KIDWAI NAGAR - [N28000080
6/2012 4,264.00 -
4,264.00 1,055.27 11/2019 -
11/2019
(January 2016) Date of
Commissioning
SI.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original /Revised
Antici Pated
1 2 3 4 5 6 7 8 73 NAGPUR METRO RAIL
- [N28000085 8/2014 8,680.00
- 8,680.00 74.92 03/2018
- 03/2018
74 BANGALORE METRO RAIL PROJECT PHASE-2 - [N28000058
2/2014 26,405.14 -
26,405.01 217.54 02/2019 03/2020
03/2020
75 ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHI - [N28000071
10/2013 1,219.21 -
1,219.21 - 07/2017 -
07/2017
Total 40,568.35 -
40,568.22 1,347.73
Grand Total 312,673.39 335,584.31 84,723.72
Annexure - XIII List of ongoing projects having cost overrun w.r.t. to revised schedule
(January 2016)
Date of
Commissioning
S.No
Project
Date of Approval
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overrun
(%)
1 2 3 4 5 6 7 8 ATOMIC ENERGY 1 PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500
MWE) - [020100044 09/2003 3,492.00
- 5,677.00 09/2010
- 09/2016 62.57
2 KUDANKULAM APP (NPCIL) - [020100040
12/2001 13,171.00 -
22,462.00 12/2008 -
05/2016 70.54
Total 16,663.00 -
28,139.00
HEAVY INDUSTRY 3 NATIONAL AUTOMOTIVE TESTING AND RD
INFRASTRUCTURE PROJECT (NATRIP) - [N20000001
04/2011 1,718.00 -
3,827.30 09/2011 -
12/2017 122.78
Total 1,718.00 -
3,827.30
PETROCHEMICALS 4 ASSAM GAS CRACKER PROJECT
- [N16000106 04/2006 5,460.61
- 9,965.00 04/2012
- 12/2015 82.49
Total 5,460.61 -
9,965.00
PETROLEUM 5 INTEGRATED REFINERY EXPANSION PROJECT
- [N16000143 03/2012 14,225.00
- 16,504.00 05/2016
- 05/2016 16.02
6 UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE - [N18000148
09/2012 871.35 -
1,200.00 03/2015 -
08/2016 37.72
Total 15,096.35 -
17,704.00
POWER 7 PARBATI HEP (4X200 MW) (NHPC) II
- [180100210 09/2002 3,919.59
- 8,398.76 09/2009
- 12/2018 114.28
8 SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) - [180100221
09/2003 6,285.33 -
18,063.89 09/2010 -
- 187.40
9 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) - [180100243
09/2005 1,061.38 -
2,193.08 09/2009 -
09/2016 106.63
10 BOKARO THERMAL POWER STATION-A - [N18000199
08/2006 2,313.00 4,139.00
4,237.67 12/2011 -
03/2016 83.21
11 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202
04/2007 4,122.00 8,781.00
9,606.82 02/2011 -
01/2017 133.06
12 KISHANGANGA HEP (3X110 MW) - [N18000031
01/2009 3,642.04 -
5,751.47 01/2016 -
11/2016 57.92
Total
21,343.34 -
48,251.69
(January 2016)
Date of
Commissioning
S.No
Project
Date of Approval
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overrun
(%)
1 2 3 4 5 6 7 8 RAILWAYS
13 NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR - [220100135
04/1983 36.80 274.41
1,336.57 - -
03/2019 3,531.98
14 KATIHAR - JOGBANI (GC)(NEFR) - [220100247
09/2001 492.98 -
1,727.27 12/2010 -
03/2018 250.37
15 QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) - [220100263
03/1998 280.00 -
1,122.00 - -
- 300.71
16 KOTLPALLI-NARASAPUR (NL) (SCR) - [220100265
12/2001 330.00 -
1,047.00 - -
- 217.27
17 TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP) - [220100268
03/2000 1,049.69 -
3,404.92 12/2006 -
- 224.37
18 BANKURA - DAMODAR (GC) (SER) - [220100277
03/1998 111.90 -
2,371.85 03/2005 12/2008
12/2019 2,019.62
19 HARIDASPUR-PARADEEP(NL) - [220100285
04/1996 301.64 -
1,185.64 - 09/2009
- 293.06
20 RAMGANJMUNDI-BHOPAL (NL),WCR - [220100314
04/2001 470.92 727.13
1,225.90 - -
03/2017 160.32
21 CHHINDWARA - NAGPUR (GC)(SECR) - [220100324
04/2005 383.79 -
1,101.16 - -
03/2017 186.92
22 SUKINDA ROAD - ANGUL (NL)(ECOR) - [220100325
04/1998 183.23 -
1,202.70 02/2015 -
- 556.39
23 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI - [N22000079
09/2007 404.19 -
1,383.45 - -
- 242.28
24 TIDIVANAM-NAGARI (NL) - [N22000085
09/2006 456.00 -
1,080.00 - -
- 136.84
25 BHAIRABI SAIRONG, NL, NEFR - [N22000100
04/2008 619.34 -
2,820.25 04/2014 -
03/2018 355.36
26 RATLAM-MHOW-KHANDWA-AKOLA (GC) - [N22000120
04/2008 603.04 -
1,421.25 03/2012 -
- 135.68
27 WARDHA-NANDED MAHARASHTRA - [N22000231
04/2008 499.30 -
2,501.05 - -
- 400.91
28 TUMKUR-CHITRADURGA-DAVENGERE NL - [N22000256
04/2011 913.00 -
1,801.01 - -
- 97.26
29 MUNIRABAD (GINGERA) -RAICHUR NL - [N22000257
04/2007 179.65 -
1,350.91 - -
- 651.97
30 AKOLA-KHANDWA GC AKOLA-AKOT - [N22000263
04/2008 184.26 -
2,000.00 - -
- 985.42
31 BHANUPALI-BILASPUR BERI NL - [N22000273
04/2008 1,046.88 -
2,966.99 - -
- 183.41
32 RAYADURGA-TUMKUR NL - [N22000279
04/2007 970.34 -
1,743.00 - -
- 79.63
33 GADAG-WADI NL - [N22000299
04/2013 1,117.00 -
1,922.00 - -
- 72.07
34 QUILON-TIRUNELVELI - TRICHENDUR, TENKASI - [N22000303
04/1999 460.94 -
1,030.00 01/1999 -
- 123.46
(January 2016)
Date of
Commissioning
S.No
Project
Date of Approval
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overrun
(%)
1 2 3 4 5 6 7 8 35 AHMEDNAGAR-PARLI VAIJNATH(NL) CR
- [220100181 02/1997 514.68
- 2,820.00 -
- - 447.91
36 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164
03/1996 495.44 -
1,781.98 03/2004 -
03/2016 259.68
37 JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR - [220100240
04/1997 501.69 335.77
1,043.56 03/2012 -
- 108.01
38 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266
04/2000 733.00 -
2,531.34 12/2008 -
03/2018 245.34
39 KHURDA ROAD-BOLANGIR(NL)ECOR - [220100284
04/1994 470.21 -
1,995.25 - -
- 324.33
40 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288
04/2003 727.56 -
6,570.75 03/2011 -
03/2019 803.12
41 PATNA GANGA BRIDGE (NL), ECR - [220100308
04/2001 624.47 -
2,921.00 10/2007 -
12/2015 367.76
42 NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) - [N22000124
04/2006 850.00 -
2,973.42 03/2015 -
03/2020 249.81
43 MUMBAI URBAN TRANSPORT PROJECT PHASE-II - [N22000092
04/2008 5,300.00 -
7,986.04 03/2014 -
03/2019 50.68
44 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127
04/1996 1,676.31 -
5,500.00 03/2009 -
03/2016 228.10
45 AGARTALA SABROOM, NL, NEFR - [N22000099
04/2008 813.34 -
2,876.00 03/2014 -
03/2018 253.60
46 SEVOK RANGPO, NEFR - [N22000102
04/2008 1,339.48 -
4,190.00 12/2015 -
03/2020 212.81
47 KANPUR KASGANJ MATHURA(GC) NER - [220100197
03/1997 677.97 1,062.36
1,651.54 - -
03/2018 143.60
48 NANGALDAM-TALWARA(NL),NR - [220100188
03/1981 450.00 -
2,100.00 07/2012 -
- 366.67
49 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133
03/1995 2,500.00 -
20,000.00 11/2002 -
12/2017 700.00
50 GONDIA-JABALPUR(GC),(SECR) - [220100186
02/1997 386.30 -
1,544.40 03/1998 -
12/2019 299.79
51 HOWRAH-AMTA-CHAMPADANGA NL (SER) - [220100208
04/1974 393.46 154.30
1,026.00 03/2007 03/2007
03/2015 160.76
52 TAMLUK DIGHA,LINE DOUBLING (SER) - [N22000097
03/1984 293.97 -
1,428.00 06/2005 -
12/2019 385.76
53 HUBLI-ANKOLA(NL),SWR - [220100193
04/1997 227.00 -
2,135.00 - -
- 840.53
54 GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM) - [N22000345
04/1997 836.26 -
1,072.51 - -
- 28.25
55 HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR - [220100183
02/1997 295.00 -
1,289.92 - -
- 337.26
56 BANGLORE - SATYAMANGALAM (NL)(SWR) - [220100274
04/1996 138.00 -
1,382.78 - -
- 902.01
(January 2016)
Date of
Commissioning
S.No
Project
Date of Approval
Original / Revised
Cost(Rs crore)
Anticipated Cost
(Rs.crore)
Original/ Revised
Antici Pated
Cost Overrun
(%)
1 2 3 4 5 6 7 8 57 SAMBALPUR-TALCHER DOUBLING
- [N22000315 03/2011 679.27
- 1,111.99 -
- - 63.70
58 KIRANDUL - JAGDALPUR DOUBLING - [N22000318
12/2012 826.57 -
1,143.60 - -
03/2018 38.35
59 ANGAMALI-SABARIMALA (N.L.)(SR) - [220100252
10/1998 550.00 -
1,566.00 - -
- 184.73
60 RATLAM-DUNGARPUR VIA BANSWARA (NL) - [N22000147
04/2011 2,082.75 -
3,500.00 - -
- 68.05
61 DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRA - [N22000160
04/2010 553.63 -
1,009.00 - -
12/2019 82.25
62 NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLING - [N22000183
04/2013 1,798.00 -
1,887.90 - -
03/2019 5.00
63 CHENNAI-CUDDALORE VIA MAMALLAPURAM - [N22000185
04/2008 523.52 -
1,200.00 - -
- 129.22
64 SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDUR - [N22000186
04/2013 839.00 -
1,500.00 - -
- 78.78
65 VILLUPURAM-DINDIGUL WITH ELECTRIFICATION - [N22000189
04/2008 822.39 -
1,280.83 - -
- 55.74
66 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194
04/1999 895.00 -
1,242.25 03/2007 -
03/2016 38.80
67 DIMAPUR-TIZIT NL - [N22000196
04/2013 4,274.00 -
4,487.70 - -
03/2020 5.00
68 NEW BG LINE FROM BYRNIHAT TO SHILLONG - [N22000205
04/2010 4,083.02 -
5,307.90 - -
03/2020 30.00
69 NEW JALPAIGURI-SILIGURI-NEW BONGAIGAON INCLUDING BR. LINE AND MM FOR CHALSA-NAXAL& RAJABHATKHOWA-JAI - [N22000209
04/1999 523.17 -
1,653.55 - -
03/2018 216.06
Total 49,789.35 -
141,455.13
ROAD TRANSPORT AND HIGHWAYS
70 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM) - [N24000133
05/2009 1,108.00 -
2,288.00 11/2011 -
06/2016 106.50
Total 1,108.00 -
2,288.00
URBAN DEVELOPMENT 71 BANGALORE METRO RAIL PROJECT
- [N28000008 05/2006 6,395.00
- 13,845.01 06/2011
- 06/2016 116.50
Total 6,395.00 -
13,845.01
Grand Total 117,573.65 265,475.13
Annexure- XIV List of Delayed Projects w.r.t. Latest Schedule
(January 2016)
Date of Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 ATOMIC ENERGY 1 KUDANKULAM APP (NPCIL) -
[020100040]NPCIL,TAMIL NADU 12/2001 13,171.00
17,270.00 22,462.00 21,077.00 12/2008
10/2013 05/2016 89 31
2 PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE) - [020100044]BHAVNI,TAMIL NADU
09/2003 3,492.00 -
5,677.00 5,150.14 09/2010 -
09/2016 72 -
3 KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4 - [N02000010]NPCIL,GUJARAT
10/2009 11,459.00 -
11,459.00 7,715.00 12/2015 10/2016
11/2018 35 25
4 RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW) - [N02000027]NPCIL,RAJASTHAN
10/2009 12,320.00 -
12,320.00 5,513.00 12/2016 03/2017
12/2019 36 33
Total 40,442.00 -
51,918.00 39,455.14
COAL 5 GEVRA EXPANSION OCP (SECL) (25-35) MTY -
[060100093]SECL,CHHATISGARH 06/2010 2,675.67
- 2,675.67 1,990.05 03/2014
- 03/2016 24 -
6 DIPKA EXPANSION OCP (SECL) (20-25) MTY - [060100094]SECL,CHHATISGARH
12/2009 1,943.66 -
1,943.66 1,713.30 03/2014 -
03/2016 24 -
7 ADRIYALA SHAFT PROJECT - [N06000016]SCCL,TELANGANA
12/2009 212.34 1,228.39
1,228.39 866.79 03/2013 09/2012
03/2016 36 42
8 SONEPUR BAZARI (COMB) OCP (8.0 MTY) - [N06000109]ECL,WEST BENGAL
08/2012 1,055.05 -
1,055.05 202.22 03/2018 -
06/2018 3 -
9 EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA) - [N06000138]NLC,TAMIL NADU
04/2013 1,458.17 -
1,458.17 14.59 06/2015 -
08/2019 50 -
Total 7,344.89 -
8,360.94 4,786.95
MINES
10 EXPANSION OF MALANJKHAND MINE-DEVELOPMENT OF UNDERGROUND MINE UNDER EXISTING OPEN CAST MINE OF CAPAC - [N10000007]HCL,MADHYA PRADESH
09/2011 1,856.00 -
1,176.00 4.59 09/2017 -
04/2020 31 -
Total 1,856.00 -
1,176.00 4.59
STEEL
11 CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGA - [N12000101]HSCL,KARNATAKA
05/2005 768.88 1,060.00
1,060.00 1,070.97 02/2014 -
03/2016 25 -
12 EXPANSION OF BHILAI STEEL PLANT - [N12000057]SAIL,CHHATISGARH
08/2010 17,265.00 -
17,265.00 15,516.00 03/2013 03/2016
06/2016 39 3
Total 18,033.88 -
18,325.00 16,586.97
PETROLEUM
(January 2016) Date of
Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 13 DEVELOPMENT OF WO-16 CLUSTER FIELDS -
[N16000105]ONGC,MULTI STATE 06/2010 2,523.00
2,523.00 2,523.00 1,792.85 01/2014
12/2015 01/2016 24 1
14 PARADIP REFINERY PROJECT - [N16000058]IOCL,ODISHA
02/2009 29,777.00 34,555.00
34,555.00 31,052.90 11/2012 11/2013
02/2016 39 27
15 DE-BOTTLENECKING OF SMPL - [N16000089]IOCL,MAHARASHTRA
12/2009 1,584.00 -
1,584.00 1,399.90 08/2015 -
03/2016 7 -
16 STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALORE - [N16000157]ISPRL,KARNATAKA
01/2006 732.00 1,227.00
1,227.00 1,074.73 10/2011 -
03/2016 53 -
17 PARADIP-RAIPUR- RANCHI PIPELINE - [N16000088]IOCL,MULTI STATE
08/2009 1,793.00 -
1,793.00 1,294.55 09/2012 -
05/2016 44 -
18 STRATEGIC CRUDE OIL STORAGE PROJECT AT PADUR - [N16000169]ISPRL,KERALA
01/2006 993.00 1,693.00
1,693.00 1,447.43 01/2012 -
05/2016 52 -
19 UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINE - [N18000148]OIL,ASSAM
09/2012 871.35 -
1,200.00 537.65 03/2015 11/2015
08/2016 17 9
20 RESID UPGRADATION PROJECT - [N16000184]CPCL,TAMIL NADU
02/2011 3,110.36 -
3,110.36 1,395.63 11/2015 07/2016
11/2016 12 4
21 ASSAM RENEWAL PROJECT FOR GROUP A - [N16000061]ONGC,ASSAM
03/2009 2,465.15 2,378.89
2,378.89 1,795.13 03/2013 03/2016
03/2017 48 12
22 PHUPLUR-HALDIA PIPELINE PROJECT PHASE-I - [N16000072]GAIL,MULTI STATE
07/2009 3,957.00 3,561.00
3,561.00 26.81 01/2013 -
12/2018 71 -
Total 47,805.86 -
53,625.25 41,817.58
POWER
23 NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXI - [N18000095]PGCIL,MULTI STATE
08/2010 1,677.57 -
1,677.57 1,447.42 04/2013 -
02/2016 34 -
24 SYSTEM STRENGTHENING IN NR FOR SASAN AND MUNDRA (UMPP) - [N18000081]PGCIL,MULTI STATE
12/2009 1,216.83 -
1,216.83 1,062.99 08/2012 -
03/2016 43 -
25 TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-B - [N18000099]PGCIL,MULTI STATE
03/2011 1,585.12 -
1,585.12 1,578.86 11/2013 -
03/2016 28 -
26 TR SYSTEM FOR PHASE-I GENERATION PROJECTS IN JHARKHAND AND WEST BENGAL-PART-A2 - [N18000113]PGCIL,MULTI STATE
12/2011 2,422.66 -
2,422.66 2,372.26 08/2014 -
03/2016 19 -
27 TRANSMISSION SYSTEM ASSOCIATED WITH KRISHNAPATNAM UMPP-PART B - [N18000122]PGCIL,MULTI STATE
02/2012 1,927.16 -
1,927.16 1,585.67 10/2014 -
03/2016 17 -
28 KBUNL-MUZAFFARPUR TPP STAGE-II- SUBSIDIARY (2X195 MW) - [N18000191]NTPC,BIHAR
03/2010 3,984.03 -
3,984.03 3,178.09 01/2013 -
03/2016 38 -
29 BOKARO THERMAL POWER STATION-A - [N18000199]DVC,JHARKHAND
08/2006 2,313.00 4,139.00
4,237.67 3,088.00 12/2011 -
03/2016 51 -
30 ESTABLISHMENT OF POOLING STATIONS AT CHAMPA AND RAIGARH FOR IPP GENERATION PROJECT IN CHHATTISGARH - [N18000101]PGCIL,CHHATISGARH
05/2011 1,961.87 -
1,961.87 1,798.15 05/2014 -
06/2016 25 -
(January 2016) Date of
Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 31 COMMON SYSTEM ASSOCIATED WITH
COASTAL ENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED L - [N18000103]PGCIL,TAMIL NADU
09/2011 1,940.13 -
1,940.13 1,938.06 09/2014 -
06/2016 21 -
32 TRANSMISSION SYSTEM STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARH - [N18000112]PGCIL,CHHATISGARH
11/2011 2,127.51 -
2,127.51 2,319.63 07/2014 -
06/2016 23 -
33 SYSTEM STRENGTHENING IN NORTH/WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARH - [N18000116]PGCIL,CHHATISGARH
12/2011 1,746.65 2,228.71
2,228.71 1,475.53 08/2014 12/2015
06/2016 22 6
34 SYSTEM STRENTHENING IN RAIPUR WARDHA CORRIDOR FOR IPP PROJECTS IN CHHATTISGARH - [N18000117]PGCIL,CHHATISGARH
01/2012 1,422.85 -
1,422.85 1,391.42 01/2015 -
06/2016 17 -
35 WR-NR HVDC INTERCONNECTOR FOR IPP PROJECTS IN CHHATTISGARH - [N18000125]PGCIL,CHHATISGARH
03/2012 9,569.76 -
9,569.76 5,724.59 06/2015 -
06/2016 12 -
36 TR. SYS. FOR PHASE-I PROJ. IN JHARKHAN AND WEST BENGAL PART-B - [N18000129]PGCIL,MULTI STATE
02/2012 3,201.44 -
3,201.44 2,996.11 10/2014 -
06/2016 20 -
37 EASTERN REGION STRENGTHENING SCHEME-V - [N18000155]PGCIL,MULTI STATE
10/2013 1,364.52 -
1,364.52 434.44 04/2016 -
06/2016 2 -
38 COMMON SYSTEM ASSOCIATED WITH EAST COAST ENERGY PVT. LTD. AND NCC POWER PROJECTS LTD. LTOA GENERATI - [N18000145]PGCIL,MULTI STATE
06/2012 1,909.24 -
1,909.24 1,016.53 06/2015 -
08/2016 14 -
39 TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) - [180100243]NHPC,WEST BENGAL
09/2005 1,061.38 -
2,193.08 1,956.52 09/2009 -
09/2016 84 -
40 KISHANGANGA HEP (3X110 MW) - [N18000031]NHPC,JAMMU AND KASHMIR
01/2009 3,642.04 -
5,751.47 4,402.95 01/2016 -
11/2016 10 -
41 KUNADANKULAM APP TRANS SYSTEM (PGCIL) - [180100258]PGCIL,TAMIL NADU
05/2005 1,779.29 2,187.32
2,187.32 1,903.55 11/2008 01/2016
12/2016 97 11
42 TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECT - [N18000061]PGCIL,MULTI STATE
10/2008 4,824.12 -
4,824.12 4,237.58 10/2012 -
12/2016 50 -
43 MOUDA STPP STAGE 2 - [N18000132]NTPC,MAHARASHTRA
03/2012 7,921.47 -
7,921.47 4,904.00 09/2016 -
12/2016 3 -
44 COMMON SYS. ASSOCIATED WITH EAST COAST ENERGY PVT LTD AND NCC POWER PROJECTS LTD LTOA GEN PART- B - [N18000144]PGCIL,MULTI STATE
03/2013 2,514.88 -
2,514.88 1,043.56 12/2015 -
12/2016 12 -
45 RAGHUNATHPUR THERMAL POWER STATION PHASE-I - [N18000202]DVC,WEST BENGAL
04/2007 4,122.00 8,781.00
9,606.82 1,353.36 02/2011 -
01/2017 71 -
46 BONGAIGAON THERMAL POWER PROJECT - [N18000041]NTPC,ASSAM
01/2008 4,375.35 6,749.18
6,749.18 5,719.00 09/2011 -
03/2017 66 -
47 TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER - [N18000077]PGCIL,WEST BENGAL
04/2010 4,404.57 -
4,404.57 2,405.85 01/2015 -
03/2017 26 -
48 EASTERN REGION STRENGTHENING SCHEME-III - [N18000100]PGCIL,MULTI STATE
07/2010 1,272.80 -
1,272.80 1,244.23 11/2012 -
03/2017 52 -
49 KUDGI STPP STAGE 1 - [N18000131]NTPC,KARNATAKA
01/2012 15,166.19 -
15,166.19 10,171.00 01/2017 -
03/2017 2 -
(January 2016) Date of
Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 50 SOLAPUR STPP -
[N18000133]NTPC,MAHARASHTRA 03/2012 9,395.18
- 9,395.18 5,881.00 11/2016
- 08/2017 9 -
51 BRBCL-NABINAGAR TPP- JV (4X250 MW) - [N18000190]NTPC,BIHAR
01/2007 5,353.00 -
5,353.00 5,298.06 05/2014 -
09/2017 40 -
52 MUNPL-MEJA TPP - JV (2X660 MW) - [N18000193]NTPC,UTTAR PRADESH
04/2012 9,750.89 -
9,750.89 4,529.23 12/2016 -
09/2017 9 -
53 BARH STPP(3X660MW) NTPC - [180100242]NTPC,BIHAR
02/2005 8,692.97 15,095.67
15,095.67 11,183.00 01/2011 10/2014
05/2018 88 43
54 PARBATI HEP (4X200 MW) (NHPC) II - [180100210]NHPC,HIMACHAL PRADESH
09/2002 3,919.59 -
8,398.76 5,398.46 09/2009 -
12/2018 111 -
55 TAPOVAN-VISHNUGAD HEP (4X130MW) - [N18000014]NTPC,UTTARAKHAND
11/2006 2,978.48 3,846.30
3,846.30 2,699.00 03/2013 -
12/2018 69 -
56 VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT - [N18000042]THDCIL,UTTARAKHAND
08/2008 2,491.58 -
2,491.58 789.89 06/2013 -
12/2019 78 -
Total 134,036.12 -
159,700.35 108,527.99
HEAVY INDUSTRY
57 NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP) - [N20000001]NATIS,MULTI STATE
04/2011 1,718.00 -
3,827.30 - 09/2011 -
12/2017 75 -
Total 1,718.00 -
3,827.30 .00
RAILWAYS
58 BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) - [220100164]MRTP,MAHARASHTRA
03/1996 495.44 495.44
1,781.98 440.08 03/2004 -
03/2016 144 -
59 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307]ECR,BIHAR
04/2002 921.00 3,040.00
3,040.00 1,834.31 03/2009 -
03/2016 84 -
60 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127]NFR,ASSAM
04/1996 1,676.31 -
5,500.00 4,769.59 03/2009 -
03/2016 84 -
61 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194]NFR,TRIPURA
04/1999 895.00 -
1,242.25 1,047.10 03/2007 -
03/2016 108 -
62 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP) - [N22000108]RVNL,WEST BENGAL
04/2010 2,397.72 -
2,397.72 204.56 03/2016 -
06/2016 3 -
63 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201]NFR,ASSAM
09/1997 1,500.00 4,996.19
4,996.19 4,102.70 04/2008 12/2011
06/2017 110 66
64 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133]NR,JAMMU AND KASHMIR
03/1995 2,500.00 -
20,000.00 10,722.72 11/2002 -
12/2017 181 -
65 KATIHAR - JOGBANI (GC)(NEFR) - [220100247]NFR,BIHAR
09/2001 492.98 -
1,727.27 743.74 12/2010 -
03/2018 87 -
66 NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR - [220100266]NFR,MULTI STATE
04/2000 733.00 733.00
2,531.34 1,732.43 12/2008 -
03/2018 111 -
67 AGARTALA SABROOM, NL, NEFR - [N22000099]NFR,TRIPURA
04/2008 813.34 813.34
2,876.00 823.83 03/2014 -
03/2018 48 -
68 BHAIRABI SAIRONG, NL, NEFR - [N22000100]NFR,MIZORAM
04/2008 619.34 619.34
2,820.25 199.31 04/2014 03/2015
03/2018 47 36
(January 2016) Date of
Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 69 EAST WEST METRO CORRIDOR FROM
HOWRAH MAIDAN TO SALT LAKE - [N22000135]MRTP,WEST BENGAL
03/2013 4,874.58 -
4,874.58 1,911.65 03/2016 -
06/2018 27 -
70 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH. - [N22000111]RVNL,WEST BENGAL
04/2010 2,913.51 -
2,095.20 619.56 03/2016 -
12/2018 33 -
71 JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) - [220100288]NFR,MANIPUR
04/2003 727.56 727.56
6,570.75 2,787.99 03/2011 03/2014
03/2019 96 60
72 GONDIA-JABALPUR(GC),(SECR) - [220100186]SECR,MULTI STATE
02/1997 386.30 -
1,544.40 - 03/1998 -
12/2019 261 -
73 BANKURA - DAMODAR (GC) (SER) - [220100277]SER,WEST BENGAL
03/1998 111.90 1,039.29
2,371.85 486.25 03/2005 12/2008
12/2019 177 132
74 TAMLUK DIGHA,LINE DOUBLING (SER) - [N22000097]SER,WEST BENGAL
03/1984 293.97 1,013.74
1,428.00 466.36 06/2005 07/2011
12/2019 174 101
75 SEVOK RANGPO, NEFR - [N22000102]NFR,SIKKIM
04/2008 1,339.48 1,339.48
4,190.00 88.56 12/2015 -
03/2020 51 -
76 NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP) - [N22000110]RVNL,WEST BENGAL
04/2010 3,951.98 -
3,161.58 878.29 03/2016 -
12/2020 57 -
Total 27,643.41 -
75,149.36 33,859.03
ROAD TRANSPORT AND HIGHWAYS
77 GURGAON - KOTPUTLI - JAIPUR (SIX LANE) - [N24000477]DORTH,RAJASTHAN
02/2008 1,673.70 -
1,673.70 - 10/2011 -
01/2016 51 -
78 FOUR LANING OF GWALIOR-SHIVPURI - [N24000494]DORTH,MADHYA PRADESH
05/2013 1,055.00 -
1,055.00 - 11/2015 -
01/2016 2 -
79 GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTION - [N24000125]NHAI,GUJARAT
03/2010 1,509.10 -
1,509.10 - 09/2012 -
02/2016 41 -
80 INDORE-JHABUA-GUJRAT/MP - [N24000136]NHAI,MADHYA PRADESH
10/2010 1,175.00 -
1,175.00 - 04/2013 -
03/2016 35 -
81 MURADABAD-BAREILY - [N24000154]NHAI,UTTAR PRADESH
04/2010 1,267.00 -
1,267.00 2,425.00 06/2013 -
03/2016 33 -
82 4 LANING OF NAGPUR-BETUL - [N24000155]NHAI,MULTI STATE
02/2011 2,498.76 -
2,498.76 - 08/2014 -
03/2016 19 -
83 BEAWAR PALI PINDWARA - [N24000199]NHAI,RAJASTHAN
12/2011 2,388.51 -
2,388.00 2,301.00 06/2014 -
03/2016 21 -
84 SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWAR - [N24000205]NHAI,MULTI STATE
12/2011 1,047.00 -
1,047.00 - 06/2014 -
03/2016 21 -
85 FOUR LANING OF ORISSA CHATTISHGARH BORDER - [N24000218]NHAI,MULTI STATE
02/2013 1,232.00 -
1,232.00 927.19 08/2015 -
03/2016 7 -
86 FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTION - [N24000481]NHAI,CHHATISGARH
02/2013 1,232.00 -
1,232.00 - 08/2015 -
03/2016 7 -
87 GHAZIABAD-ALIGARH NH-91 - [N24000170]NHAI,UTTAR PRADESH
02/2011 1,141.00 -
1,141.00 1,911.64 08/2013 -
04/2016 32 -
88 DELHI AGRA APPROVED LENGTH 180.0 KM - [N24000224]NHAI,MULTI STATE
10/2012 1,928.22 -
1,928.22 822.96 04/2015 -
04/2016 12 -
(January 2016) Date of
Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 89 NASHRI- CHANANI - [N24000162]NHAI,JAMMU
AND KASHMIR 05/2011 2,159.00
- 2,159.00 - 06/2015
- 05/2016 11 -
90 6-LANING OF DHANKUNI-KHARAGPUR SECTION - [N24000206]NHAI,WEST BENGAL
04/2012 1,396.18 -
1,396.18 2,287.44 09/2014 -
05/2016 20 -
91 PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM) - [N24000133]NHAI,HARYANA
05/2009 1,108.00 -
2,288.00 3,619.94 11/2011 -
06/2016 55 -
92 QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00 - [N24000161]NHAI,JAMMU AND KASHMIR
07/2010 1,987.00 -
1,987.00 - 07/2015 -
06/2016 11 -
93 JAMMU-UDHAMPUR KM.27.5 TO KM.67.00 - [N24000163]NHAI,JAMMU AND KASHMIR
07/2010 1,813.76 -
1,813.76 - 07/2013 -
06/2016 35 -
94 4 LANNING OF AHMEDABAD TO GODHARA - [N24000167]NHAI,GUJARAT
12/2010 1,008.50 -
1,008.50 - 06/2013 -
06/2016 36 -
95 SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547 - [N24000183]NHAI,ANDHRA PRADESH
11/2011 1,535.00 -
1,535.00 2,478.63 05/2014 -
06/2016 25 -
96 SRINAGAR TO BANIHAL - [N24000189]NHAI,JAMMU AND KASHMIR
06/2011 1,100.70 -
1,100.70 - 06/2014 -
06/2016 24 -
97 ETAWAH CHAKERI - [N24000219]NHAI,UTTAR PRADESH
03/2013 1,573.00 -
1,573.00 1,840.00 09/2015 -
06/2016 9 -
98 AHMEDABAD TO VADODARA SECTION - [N24000222]NHAI,GUJARAT
01/2013 2,125.24 -
2,125.24 - 12/2015 -
06/2016 6 -
99 CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KM - [N24000145]NHAI,ANDHRA PRADESH
11/2010 1,585.00 -
1,585.00 1,050.90 05/2013 -
08/2016 39 -
100 4-LANING OF FARAKA-RAIGANJ - [N24000202]NHAI,MULTI STATE
02/2011 1,078.84 -
1,078.84 - 08/2013 -
08/2016 36 -
101 WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50 - [N24000230]NHAI,MAHARASHTRA
05/2013 1,348.20 -
1,348.20 1,267.57 02/2014 -
08/2016 30 -
102 FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASS - [N24000509]NHAI,MAHARASHTRA
04/2010 1,170.52 -
1,170.52 1,579.15 06/2012 -
08/2016 50 -
103 PANIKHOLI-RIMOLI - [N24000197]NHAI,ODISHA 03/2012 1,410.00 -
1,410.00 - 09/2014 -
10/2016 25 -
104 PUNE-SATARA(NH-4) - [N24000156]NHAI,MAHARASHTRA
10/2010 1,724.55 -
1,724.55 1,742.94 03/2013 -
12/2016 45 -
105 SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46 - [N24000172]NHAI,TAMIL NADU
09/2011 1,250.00 -
1,250.00 - 12/2013 -
12/2016 36 -
106 BAREILY-SITAPUR (NH-24) - [N24000200]NHAI,UTTAR PRADESH
03/2011 1,046.00 -
1,046.00 425.65 09/2013 -
12/2016 39 -
107 WALAJAPET POONAMALEE KM 106.8 TO KM 13.8 - [N24000228]NHAI,TAMIL NADU
06/2013 1,287.95 -
1,287.95 - 11/2015 -
03/2017 16 -
108 VARANASI-AURANGABAD KM.786 TO KM.978.40 - [N24000182]NHAI,MULTI STATE
09/2011 2,848.00 -
2,848.00 504.51 03/2014 -
04/2017 37 -
109 RANCHI-RARGA-JAMSETHPUR - [N24000215]NHAI,MULTI STATE
12/2012 1,479.00 -
1,479.00 461.94 06/2015 -
05/2017 23 -
Total 50,181.73 -
51,361.22 25,646.46
TELECOMMUNICATIONS
(January 2016) Date of
Commissioning
S.No
Project
Date of Approval
Original/ Revised
Cost (Rs. crore)
Anticipated Cost
(Rs. crore)
Cumulative Expenditure
Cost (Rs. crore)
Original / Revised
Anticipated
Delay w.r.t. original
(in months)
Delay w.r.t. Revised
(in months)
1 2 3 4 5 6 7 8 9 10 110 NETWORK FOR SPECTRUM -
[N26000101]DOT,MULTI STATE 03/2012 13,334.00
- 13,334.00 1,360.00 07/2015
- 03/2017 20 -
111 NETWORK FOR SPECTRUM (NFS) OFC LAYING PROJECT, PACKAGE F AND G, A PART OF INTELLIGENT FIBER OPTIC C - [N26000102]ITI,MULTI STATE
09/2014 2,111.17 -
2,011.17 1,360.00 09/2014 -
03/2017 30 -
Total 15,445.17 -
15,345.17 2,720.00
URBAN DEVELOPMENT
112 BANGALORE METRO RAIL PROJECT - [N28000008]MRTP,KARNATAKA
05/2006 6,395.00 11,609.00
13,845.01 13,525.81 06/2011 12/2015
06/2016 60 6
113 CHENNAI METRO RAIL LTD (PHASE 1) - [N28000084]CMRL,TAMIL NADU
02/2009 14,600.00 14,600.00
14,600.00 11,786.98 12/2015 -
08/2016 8 -
114 DELHI MRTS PHASE-III - [N28000056]DMRCL,DELHI
09/2011 38,585.00 -
38,585.00 20,172.80 03/2016 -
12/2016 9 -
Total 59,580.00 -
67,030.01 45,485.59
Grand Total 404,087.06 505,818.60 318,890.30
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
ATOMIC ENERGY
COAL
HEAVY INDUSTRY
MINES
PETROLEUM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW) KAKRAPAR ATOMIC POWER PROJECT - 3 AND4 KUDANKULAM APP (NPCIL) PROTOTYPE FAST BREEDER REACTOR(BHAVINI, 500 MWE)
NEYVELI NEW THERMAL POWERPROJECT(2X500 MW) MOONIDIH XV SEAM UG GEVRA EXPANSION OCP (SECL) (25-35)MTY ADRIYALA SHAFT PROJECT EXPANSION OF MINE-I (LEASE AREA) ANDMINE-I A (3.0 TO 7.0 MTPA) DIPKA EXPANSION OCP (SECL) (20-25)MTY
NATIONAL AUTOMOTIVE TESTING AND RDINFRASTRUCTURE PROJECT (NATRIP)
EXPANSION OF MALANJKHAND MINE-DEVELOPMENT OF UNDERGROUND MINE UNDEREXISTING OPEN CAST MINE OF CAPAC
UPGRADATION OF CRUDE OIL PUMPSTATIONS OF NAHARKATIYA-BARAUNI CRUDEOIL TRUNK PIPELINE STRATEGIC CRUDE OIL STORAGE PROJECTAT MANGALORE DEVELOPMENT OF C-26 CLUSTER FIELDS PARADIP REFINERY PROJECT
10/2009
10/2009
12/2001
09/2003
06/2011
08/2011
06/2010
12/2009
04/2013
12/2009
04/2011
09/2011
09/2012
01/2006
03/2012
02/2009
12/2016
12/2015
12/2008
09/2010
12/2015
04/2015
03/2014
03/2013
06/2015
03/2014
09/2011
09/2017
03/2015
10/2011
05/2014
11/2012
12/2019
11/2018
05/2016
09/2016
04/2018
04/2019
03/2016
03/2016
08/2019
03/2016
12/2017
04/2020
08/2016
03/2016
03/2017
02/2016
12320
11459
13171
3492
5907.11
1230.27
2675.67
212.34
1458.17
1943.66
1718
1856
871.35
732
2592.17
29777
NPCIL
NPCIL
NPCIL
BHAVNI
NLC
BCCL
SECL
SCCL
NLC
SECL
NATIS
HCL
OIL
ISPRL
ONGC
IOCL
36
35
89
72
28
48
24
36
50
24
75
31
17
53
34
39
Sn
Sn
Sn
Sn
Sn
Project
Project
Project
Project
Project
DOA
DOA
DOA
DOA
DOA
DOC Original
DOC Original
DOC Original
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
DOC Anticipated
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
TOR (Months)
TOR (Months)
TOR (Months)
Agency
Agency
Agency
Agency
Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
POWER
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
ASSAM RENEWAL PROJECT FOR GROUP A DEVELOPMENT OF WO-16 CLUSTER FIELDS STRATEGIC CRUDE OIL STORAGE PROJECTAT PADUR INTEGRATED DEVELOPMENT OF VASHISTAAND S-1 FIELDS RESID UPGRADATION PROJECT DAMAN DEVELOPMENT PROJECT PHUPLUR-HALDIA PIPELINE PROJECTPHASE-I CONVERSION OF RIG SAGAR SAMRAT TOMOBILE OFFSHORE PRODUCTION UNIT(MOPS) PARADIP-RAIPUR- RANCHI PIPELINE DE-BOTTLENECKING OF SMPL INTEGRATED DEVELOPMENT OF B-127FIELDS
COMMON SYSTEM ASSOCIATED WITH EASTCOAST ENERGY PVT. LTD. AND NCC POWERPROJECTS LTD. LTOA GENERATISOLAPUR STPP COMMON SYS. ASSOCIATED WITH EASTCOAST ENERGY PVT LTD AND NCC POWERPROJECTS LTD LTOA GEN PART- B TRANSMISSION SYSTEM ASSOCIATED WITHKRISHNAPATNAM UMPP-PART B TUIRIAL HYDRO ELECTRIC PROJECT (60MW) BRBCL-NABINAGAR TPP- JV (4X250 MW) KBUNL-MUZAFFARPUR TPP STAGE-II-SUBSIDIARY (2X195 MW) MUNPL-MEJA TPP - JV (2X660 MW) BOKARO THERMAL POWER STATION-A RAGHUNATHPUR THERMAL POWER STATIONPHASE-I VISHNUGAD PIPALKOTI HYDRO ELECTRICPROJECT
03/2009
06/2010
01/2006
05/2013
02/2011
08/2014
07/2009
03/2011
08/2009
12/2009
12/2011
06/2012
03/2012
03/2013
02/2012
07/1998
01/2007
03/2010
04/2012
08/2006
04/2007
08/2008
03/2013
01/2014
01/2012
04/2016
11/2015
05/2019
01/2013
05/2013
09/2012
08/2015
03/2015
06/2015
11/2016
12/2015
10/2014
07/2006
05/2014
01/2013
12/2016
12/2011
02/2011
06/2013
03/2017
01/2016
05/2016
12/2017
11/2016
03/2020
12/2018
04/2016
05/2016
03/2016
05/2016
08/2016
08/2017
12/2016
03/2016
10/2016
09/2017
03/2016
09/2017
03/2016
01/2017
12/2019
2465.15
2523
993
4124.35
3110.36
6086.08
3957
861.79
1793
1584
2059.63
1909.24
9395.18
2514.88
1927.16
368.72
5353
3984.03
9750.89
2313
4122
2491.58
ONGC
ONGC
ISPRL
ONGC
CPCL
ONGC
GAIL
ONGC
IOCL
IOCL
ONGC
PGCIL
NTPC
PGCIL
PGCIL
NEEPCO
NTPC
NTPC
NTPC
DVC
DVC
THDCIL
48
24
52
20
12
10
71
35
44
7
14
14
9
12
17
123
40
38
9
51
71
78
Sn
Sn
Project
Project
DOA
DOA
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
Agency
Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
TR SYSTEM FOR PHASE-I GENERATIONPROJECTS IN JHARKHAND AND WESTBENGAL-PART-A2 KAMENG HYDROELECTRIC PROJECT (NEEPCO) COMMON SYSTEM ASSOCIATED WITH COASTALENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED LESTABLISHMENT OF POOLING STATIONS ATCHAMPA AND RAIGARH FOR IPP GENERATIONPROJECT IN CHHATTISGARH TAPOVAN-VISHNUGAD HEP (4X130MW) BONGAIGAON THERMAL POWER PROJECT EASTERN REGION STRENGTHENING SCHEME-III TEHRI PUMPED STORAGE PLANT(1000MW) TRANSMISSION SYSTEM STRENGTHENING INWESTERN PART OF WR FOR IPPSGENERATION PROJECTS IN CHATTISGARH PARE HYDRO ELECTRIC PROJECT SYSTEM STRENGTHENING IN NORTH/WESTPART OF WR FOR IPP PROJECTS INCHATTISGARH KISHANGANGA HEP (3X110 MW) KUNADANKULAM APP TRANS SYSTEM (PGCIL) BARH STPP(3X660MW) NTPC SYSTEM STRENTHENING IN RAIPUR WARDHACORRIDOR FOR IPP PROJECTS INCHHATTISGARH PARBATI HEP (4X200 MW) (NHPC) II TEESTA LOW DAM HEP, STAGE-IV (4X40MW) (NHPC) TR. SYSTEM ASSOCIATED WITH MUNDRAULTRA MEGA POWER PROJECT NORTHERN REGION SYSTEM STRENGTHENINGSCHEME-XXI TRANSMISSION SYSTEM FOR TRANSFER OFPOWER FROM GEN.PROJ IN SIKKIM TONR/WR PART-B TRANSMISSION SYSTEM FOR DEVELOPMENTOF POOLING STN. IN NR PART OF WESTBENGAL AND TRANSFER OF POWER NORTH- EAST NORTH WESTERNINTERCONNECTOR I PROJECT SYSTEM STRENGTHENING IN NR FOR SASANAND MUNDRA (UMPP)
12/2011
12/2004
09/2011
05/2011
11/2006
01/2008
07/2010
07/2006
11/2011
12/2008
12/2011
01/2009
05/2005
02/2005
01/2012
09/2002
09/2005
10/2008
08/2010
03/2011
04/2010
02/2009
12/2009
08/2014
12/2009
09/2014
05/2014
03/2013
09/2011
11/2012
02/2016
07/2014
08/2013
08/2014
01/2016
11/2008
01/2011
01/2015
09/2009
09/2009
10/2012
04/2013
11/2013
01/2015
08/2013
08/2012
03/2016
06/2016
06/2016
06/2016
12/2018
03/2017
03/2017
09/2019
06/2016
07/2016
06/2016
11/2016
12/2016
05/2018
06/2016
12/2018
09/2016
12/2016
02/2016
03/2016
03/2017
12/2017
03/2016
2422.66
2496.9
1940.13
1961.87
2978.48
4375.35
1272.8
1657
2127.51
573.99
1746.65
3642.04
1779.29
8692.97
1422.85
3919.59
1061.38
4824.12
1677.57
1585.12
4404.57
11130.19
1216.83
PGCIL
NEEPCO
PGCIL
PGCIL
NTPC
NTPC
PGCIL
THDCIL
PGCIL
NEEPCO
PGCIL
NHPC
PGCIL
NTPC
PGCIL
NHPC
NHPC
PGCIL
PGCIL
PGCIL
PGCIL
PGCIL
PGCIL
19
78
21
25
69
66
52
43
23
35
22
10
97
88
17
111
84
50
34
28
26
52
43
Sn Project DOA
DOC Original
DOC Anticipated
Cost Original(Rs. crore)
TOR (Months)Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
RAILWAYS
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
TRANSMISSION SYSTEM ASSOCIATED WITHPALLATANA GBPP and BPTS. TRIPURA GAS BASED POWER PROJECT WR-NR HVDC INTERCONNECTOR FOR IPPPROJECTS IN CHHATTISGARH TR. SYS. FOR PHASE-I PROJ. INJHARKHAN AND WEST BENGAL PART-B
CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR AGARTALA SABROOM, NL, NEFR MUMBAI URBAN TRANSPORT PROJECT PHASE-II JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) KATIHAR - JOGBANI (GC)(NEFR) BANKURA - DAMODAR (GC) (SER) RAIL-CUM-ROAD BRIDGE AT MUNGER (NL),ECR BHAIRABI SAIRONG, NL, NEFR NEW WORK FOR CONSTRUCTION OF METRORAILWAY FROM JOKA TO BINOY BADALDINESH BAGH. BELAPUR-SEAWOOD-URAN ELECTRIFIEDDOUBLE LINE(MTP) BPUTRA BRIDGE AT BOGIBIL AND LINKLINES NEFR NEW MAYNAGURI TO JOGIGHOPA VIACHANGRABANDHA (NL),NEFR NEW LINE FROM DIMAPUR TOZUBZA(KOHIMA) NATIONAL PROJECT (NEFR) LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT SEVOK RANGPO, NEFR NEW WORK FOR CONSTRUCTION OF METRORAILWAY FROM NSCB AIRPORT TO NEWGARIA VIA RAJARHAT (MTP)
02/2010
07/2009
03/2012
02/2012
04/1999
03/1995
04/2008
04/2008
04/2003
09/2001
03/1998
04/2002
04/2008
04/2010
03/1996
09/1997
04/2000
04/2006
04/1996
04/2008
04/2010
12/2012
07/2013
06/2015
10/2014
03/2007
11/2002
03/2014
03/2014
03/2011
12/2010
03/2005
03/2009
04/2014
03/2016
03/2004
04/2008
12/2008
03/2015
03/2009
12/2015
03/2016
12/2016
01/2016
06/2016
06/2016
03/2016
12/2017
03/2018
03/2019
03/2019
03/2018
12/2019
03/2016
03/2018
12/2018
03/2016
06/2017
03/2018
03/2020
03/2016
03/2020
12/2020
2144
421.01
9569.76
3201.44
895
2500
813.34
5300
727.56
492.98
111.9
921
619.34
2913.51
495.44
1500
733
850
1676.31
1339.48
3951.98
PGCIL
NEEPCO
PGCIL
PGCIL
NFR
NR
NFR
MRTP
NFR
NFR
SER
ECR
NFR
RVNL
MRTP
NFR
NFR
NFR
NFR
NFR
RVNL
48
30
12
20
108
181
48
60
96
87
177
84
47
33
144
110
111
60
84
51
57
Sn
Sn
Project
Project
DOA
DOA
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
Agency
Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
ROAD TRANSPORT AND HIGHWAYS
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
EAST WEST METRO CORRIDOR FROM HOWRAHMAIDAN TO SALT LAKE GONDIA-JABALPUR(GC),(SECR) TAMLUK DIGHA,LINE DOUBLING (SER)
FOUR LANING FROM MPMAHARASHTRA BORDERTO NAGPUR IC KAMPTEE KANOON ANDNAGPUR BYPASS GHAZIABAD-ALIGARH NH-91 SIX LANNING OF KRISHNAGIRI-WALAJHAPET SECTION KM.0.00 TOKM.148.3 NH-46 VARANASI-AURANGABAD KM.786 TOKM.978.40 SIX LANNING OF NELLORE-CHILKALURIPETKM.1182.802 TO KM.1366.547 PANIKHOLI-RIMOLI BEAWAR PALI PINDWARA BAREILY-SITAPUR (NH-24) 4-LANING OF FARAKA-RAIGANJ SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWAR PANIPAT-JALANDHAR 6 LANE(KM 96 TO387.1 KM) WALAJAPET POONAMALEE KM 106.8 TO KM13.8 WIDENING OF KHED-SINNAR STRETCH OFPUNE NASHIK SECTION OF NH-50 MURADABAD-BAREILY PUNE-SATARA(NH-4) CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KM GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTION INDORE-JHABUA-GUJRAT/MP
03/2013
02/1997
03/1984
04/2010
02/2011
09/2011
09/2011
11/2011
03/2012
12/2011
03/2011
02/2011
12/2011
05/2009
06/2013
05/2013
04/2010
10/2010
11/2010
03/2010
10/2010
03/2016
03/1998
06/2005
06/2012
08/2013
12/2013
03/2014
05/2014
09/2014
06/2014
09/2013
08/2013
06/2014
11/2011
11/2015
02/2014
06/2013
03/2013
05/2013
09/2012
04/2013
06/2018
12/2019
12/2019
08/2016
04/2016
12/2016
04/2017
06/2016
10/2016
03/2016
12/2016
08/2016
03/2016
06/2016
03/2017
08/2016
03/2016
12/2016
08/2016
02/2016
03/2016
4874.58
386.3
293.97
1170.52
1141
1250
2848
1535
1410
2388.51
1046
1078.84
1047
1108
1287.95
1348.2
1267
1724.55
1585
1509.1
1175
MRTP
SECR
SER
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
27
261
174
50
32
36
37
25
25
21
39
36
21
55
16
30
33
45
39
41
35
Sn
Sn
Project
Project
DOA
DOA
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
Agency
Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
STEEL
TELECOMMUNICATIONS
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
4 LANNING OF AHMEDABAD TO GODHARA 4 LANING OF NAGPUR-BETUL QUAZIGUND-BANIHAL KM.220.00 TOKM.188.00 NASHRI- CHANANI JAMMU-UDHAMPUR KM.27.5 TO KM.67.00 SRINAGAR TO BANIHAL RANCHI-RARGA-JAMSETHPUR 6-LANING OF DHANKUNI-KHARAGPURSECTION FOUR LANING OF ORISSA CHATTISHGARHBORDER ETAWAH CHAKERI AHMEDABAD TO VADODARA SECTION DELHI AGRA APPROVED LENGTH 180.0 KM GURGAON - KOTPUTLI - JAIPUR (SIXLANE) FOUR LANING OF ORISSA/CHATTISGARHBORDER - AURANG SECTION
NMDC INTEGRATED STEEL PLANT CONSTRUCTION OF MEDICAL COLLEGE ANDHOSPITAL AT GULBARGA EXPANSION OF BHILAI STEEL PLANT
NETWORK FOR SPECTRUM NETWORK FOR SPECTRUM (NFS) OFC LAYINGPROJECT, PACKAGE F AND G, A PART OFINTELLIGENT FIBER OPTIC C
12/2010
02/2011
07/2010
05/2011
07/2010
06/2011
12/2012
04/2012
02/2013
03/2013
01/2013
10/2012
02/2008
02/2013
01/2010
05/2005
08/2010
03/2012
09/2014
06/2013
08/2014
07/2015
06/2015
07/2013
06/2014
06/2015
09/2014
08/2015
09/2015
12/2015
04/2015
10/2011
08/2015
05/2015
02/2014
03/2013
07/2015
09/2014
06/2016
03/2016
06/2016
05/2016
06/2016
06/2016
05/2017
05/2016
03/2016
06/2016
06/2016
04/2016
01/2016
03/2016
12/2016
03/2016
06/2016
03/2017
03/2017
1008.5
2498.76
1987
2159
1813.76
1100.7
1479
1396.18
1232
1573
2125.24
1928.22
1673.7
1232
15525
768.88
17265
13334
2111.17
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
NHAI
DORTH
NHAI
NMDC
HSCL
SAIL
DOT
ITI
36
19
11
11
35
24
23
20
7
9
6
12
51
7
19
25
39
20
30
Sn
Sn
Sn
Project
Project
Project
DOA
DOA
DOA
DOC Original
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
TOR (Months)
Agency
Agency
Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
Annexure - XV
URBAN DEVELOPMENT
123
124
125
126
DELHI MRTS PHASE-III BANGALORE METRO RAIL PROJECT PHASE-2 BANGALORE METRO RAIL PROJECT CHENNAI METRO RAIL LTD (PHASE 1)
09/2011
02/2014
05/2006
02/2009
03/2016
02/2019
06/2011
12/2015
12/2016
03/2020
06/2016
08/2016
38585
26405.14
6395
14600
DMRCL
BMRCL
MRTP
CMRL
9
13
60
8
Sn Project DOA
DOC Original
DOC Anticipated
Cost Original(Rs. crore)
TOR (Months)Agency
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING COST OVERRUNS OF MORE THAN Rs. 100 CRORE
DOA -> Date of Approval
DOC -> date of Commissioning
Annexure - XVI
ATOMIC ENERGY
COAL
HEAVY INDUSTRY
PETROCHEMICALS
PETROLEUM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
PROTOTYPE FAST BREEDER REACTOR (BHAVINI,500 MWE) KUDANKULAM APP (NPCIL)
ADRIYALA SHAFT PROJECT
NATIONAL AUTOMOTIVE TESTING AND RDINFRASTRUCTURE PROJECT (NATRIP)
ASSAM GAS CRACKER PROJECT
STRATEGIC CRUDE OIL STORAGE PROJECT ATPADUR INTEGRATED DEVELOPMENT OF VASHISTA ANDS-1 FIELDS MH NORTH REDEVELOPMENT PHASE III INTEGRATED DEVELOPMENT OF B-127 FIELDS UPGRADATION OF CRUDE OIL PUMP STATIONSOF NAHARKATIYA-BARAUNI CRUDE OIL TRUNKPIPELINE STRATEGIC CRUDE OIL STORAGE PROJECT ATMANGALORE INTEGRATED REFINERY EXPANSION PROJECT PARADIP REFINERY PROJECT CONVERSION OF RIG SAGAR SAMRAT TO MOBILEOFFSHORE PRODUCTION UNIT(MOPS) GAMJI REDEVELOPMENT PROJECT
BHAVNI
NPCIL
SCCL
NATIS
BCPL
ISPRL
ONGC
ONGC
ONGC
OIL
ISPRL
BPCL
IOCL
ONGC
ONGC
09/2003
12/2001
12/2009
04/2011
04/2006
01/2006
05/2013
06/2014
12/2011
09/2012
01/2006
03/2012
02/2009
03/2011
05/2015
3492
13171
212.34
1718
5460.61
993
4124.35
5706.47
2059.63
871.35
732
14225
29777
861.79
1671.22
5677
22462
1228.39
3827.3
9965
1693
4941.49
5813.25
2665.65
1200
1227
16504
34555
1256.72
1881.22
2185
9291
1016.05
2109.3
4504.39
700
817.14
106.78
606.02
328.65
495
2279
4778
394.93
210
Sn
Sn
Sn
Sn
Sn
Project
Project
Project
Project
Project
Agency
Agency
Agency
Agency
Agency
DOA
DOA
DOA
DOA
DOA
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
09/2010
12/2008
03/2013
09/2011
04/2012
01/2012
04/2016
05/2017
03/2015
03/2015
10/2011
05/2016
11/2012
05/2013
11/2019
DOC Original
DOC Original
DOC Original
DOC Original
DOC Original
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING COST OVERRUNS OF MORE THAN Rs. 100 CRORE
DOA -> Date of Approval
DOC -> date of Commissioning
Annexure - XVI
POWER
RAILWAYS
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
PARBATI HEP (4X200 MW) (NHPC) II SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) TEESTA LOW DAM HEP, STAGE-IV (4X40 MW)(NHPC) TRANSMISSION SYSTEM ASSOCIATED WITHPALLATANA GBPP and BPTS. NORTH- EAST NORTH WESTERN INTERCONNECTORI PROJECT BARH STPP(3X660MW) NTPC KUNADANKULAM APP TRANS SYSTEM (PGCIL) KISHANGANGA HEP (3X110 MW) SYSTEM STRENGTHENING IN NORTH/WEST PARTOF WR FOR IPP PROJECTS IN CHATTISGARH PARE HYDRO ELECTRIC PROJECT TEHRI PUMPED STORAGE PLANT(1000MW) KAMENG HYDROELECTRIC PROJECT (NEEPCO) RAGHUNATHPUR THERMAL POWER STATIONPHASE-I BOKARO THERMAL POWER STATION-A TRIPURA GAS BASED POWER PROJECT TUIRIAL HYDRO ELECTRIC PROJECT (60MW) BONGAIGAON THERMAL POWER PROJECT TAPOVAN-VISHNUGAD HEP (4X130MW)
NEW BG RLY LINE FROM EKLAKHI-BALURGHATINCLUDING GAZOLE-ITAHAR(NL),NEFR KATIHAR - JOGBANI (GC)(NEFR) QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) KOTLPALLI-NARASAPUR (NL) (SCR)
NHPC
NHPC
NHPC
PGCIL
PGCIL
NTPC
PGCIL
NHPC
PGCIL
NEEPCO
THDCIL
NEEPCO
DVC
DVC
NEEPCO
NEEPCO
NTPC
NTPC
NFR
NFR
SR
SCR
09/2002
09/2003
09/2005
02/2010
02/2009
02/2005
05/2005
01/2009
12/2011
12/2008
07/2006
12/2004
04/2007
08/2006
07/2009
07/1998
01/2008
11/2006
04/1983
09/2001
03/1998
12/2001
3919.59
6285.33
1061.38
2144
11130.19
8692.97
1779.29
3642.04
1746.65
573.99
1657
2496.9
4122
2313
421.01
368.72
4375.35
2978.48
36.8
492.98
280
330
8398.76
18063.89
2193.08
2932.88
13762.8
15095.67
2187.32
5751.47
2228.71
1262.27
2978.86
6085.84
9606.82
4237.67
1007.57
1381.71
6749.18
3846.3
1336.57
1727.27
1122
1047
4479.17
11778.56
1131.7
788.88
2632.61
6402.7
408.03
2109.43
482.06
688.28
1321.86
3588.94
5484.82
1924.67
586.56
1012.99
2373.83
867.82
1299.77
1234.29
842
717
Sn
Sn
Project
Project
Agency
Agency
DOA
DOA
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
09/2009
09/2010
09/2009
12/2012
08/2013
01/2011
11/2008
01/2016
08/2014
08/2013
02/2016
12/2009
02/2011
12/2011
07/2013
07/2006
09/2011
03/2013
N.A.
12/2010
N.A.
N.A.
DOC Original
DOC Original
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING COST OVERRUNS OF MORE THAN Rs. 100 CRORE
DOA -> Date of Approval
DOC -> date of Commissioning
Annexure - XVI
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
TOLLYGANJ-GARIA WITH EXTENSION TO DUMDUM-NOAPARA AND NOAPARA-NSCBAIRPORT(MTP) BANKURA - DAMODAR (GC) (SER) HARIDASPUR-PARADEEP(NL) RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR RAMGANJMUNDI-BHOPAL (NL),WCR CHHINDWARA - NAGPUR (GC)(SECR) SUKINDA ROAD - ANGUL (NL)(ECOR) MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU'PONDI'-AGASTIYAMPALLI TIDIVANAM-NAGARI (NL) BHAIRABI SAIRONG, NL, NEFR NEW JALPAIGURI-SILIGURI-NEW BONGAIGAONINCLUDING BR. LINE AND MM FOR CHALSA-NAXAL& RAJABHATKHOWA-JAINEW BG LINE FROM BYRNIHAT TO SHILLONG DIMAPUR-TIZIT NL CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA VILLUPURAM-DINDIGUL WITH ELECTRIFICATION SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TOIRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDUR CHENNAI-CUDDALORE VIA MAMALLAPURAM DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRA DHOLPUR-SIRMUTTRA WITH EXTENSION TOGANGAPURCITY AND MOHARI-TANTPUR &TANPUR-BANSI PAHARPUR GWALIOR-SEOPURKALA WITH EXTENSION TOKOTA (GC) RATLAM-DUNGARPUR VIA BANSWARA (NL) LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT MUMBAI URBAN TRANSPORT PROJECT PHASE-II
MRTP
SER
RVNL
ECR
WCR
SECR
RVNL
SR
SR
NFR
NFR
NFR
NFR
NFR
SR
SR
SR
SER
NCR
NCR
NWR
NFR
MRTP
03/2000
03/1998
04/1996
04/2002
04/2001
04/2005
04/1998
09/2007
09/2006
04/2008
04/1999
04/2010
04/2013
04/1999
04/2008
04/2013
04/2008
04/2010
04/2010
04/2011
04/2011
04/1996
04/2008
1049.69
111.9
301.64
921
470.92
383.79
183.23
404.19
456
619.34
523.17
4083.02
4274
895
822.39
839
523.52
553.63
622.41
1176.09
2082.75
1676.31
5300
3404.92
2371.85
1185.64
3040
1225.9
1101.16
1202.7
1383.45
1080
2820.25
1653.55
5307.9
4487.7
1242.25
1280.83
1500
1200
1009
2030.5
3845.6
3500
5500
7986.04
2355.23
2259.95
884
2119
754.98
717.37
1019.47
979.26
624
2200.91
1130.38
1224.88
213.7
347.25
458.44
661
676.48
455.37
1408.09
2669.51
1417.25
3823.69
2686.04
Sn Project Agency DOA
Cost Original(Rs.crore)
Cost Anticipated(Rs.crore)
CostOverrun(Rs.crore)
12/2006
03/2005
N.A.
03/2009
N.A.
N.A.
02/2015
N.A.
N.A.
04/2014
N.A.
N.A.
N.A.
03/2007
N.A.
N.A.
N.A.
N.A.
02/2019
02/2020
N.A.
03/2009
03/2014
DOC Original
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING COST OVERRUNS OF MORE THAN Rs. 100 CRORE
DOA -> Date of Approval
DOC -> date of Commissioning
Annexure - XVI
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA)NATIONAL PROJECT (NEFR) PATNA GANGA BRIDGE (NL), ECR JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) KHURDA ROAD-BOLANGIR(NL)ECOR NEW MAYNAGURI TO JOGIGHOPA VIACHANGRABANDHA (NL),NEFR JAYANAGAR-DARBHANGA-NARKATIAGANJ(GC),ECR LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) ANGAMALI-SABARIMALA (N.L.)(SR) KIRANDUL - JAGDALPUR DOUBLING SAMBALPUR-TALCHER DOUBLING BANGLORE - SATYAMANGALAM (NL)(SWR) HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR GONDA GORAKHPUR LOOP WITH ANAND NAGARNAUTANWA GC (260 KM) HUBLI-ANKOLA(NL),SWR TAMLUK DIGHA,LINE DOUBLING (SER) HOWRAH-AMTA-CHAMPADANGA NL (SER) GONDIA-JABALPUR(GC),(SECR) UTRATIA-ZAFRABAD, NR (LINE DOUBLING) UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR NANGALDAM-TALWARA(NL),NR KANPUR KASGANJ MATHURA(GC) NER SEVOK RANGPO, NEFR AGARTALA SABROOM, NL, NEFR
NFR
ECR
NFR
ECOR
NFR
ECR
WCR
SR
ECOR
ECOR
SWR
SWR
SWR
SER
SER
SECR
NR
NR
NR
NER
NFR
NFR
04/2006
04/2001
04/2003
04/1994
04/2000
04/1997
09/1998
10/1998
12/2012
03/2011
04/1996
02/1997
04/1997
04/1997
03/1984
04/1974
02/1997
04/2006
03/1995
03/1981
03/1997
04/2008
04/2008
850
624.47
727.56
470.21
733
501.69
247.66
550
826.57
679.27
138
295
836.26
227
293.97
393.46
386.3
325
2500
450
677.97
1339.48
813.34
2973.42
2921
6570.75
1995.25
2531.34
1043.56
3500
1566
1143.6
1111.99
1382.78
1289.92
1072.51
2135
1428
1026
1544.4
2434
20000
2100
1651.54
4190
2876
2123.42
2296.53
5843.19
1525.04
1798.34
541.87
3252.34
1016
317.03
432.72
1244.78
994.92
236.25
1908
1134.03
632.54
1158.1
2109
17500
1650
973.57
2850.52
2062.66
Sn Project Agency DOA
Cost Original(Rs.crore)
Cost Anticipated(Rs.crore)
CostOverrun(Rs.crore)
03/2015
10/2007
03/2011
N.A.
12/2008
03/2012
05/2008
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
06/2005
03/2007
03/1998
03/2010
11/2002
07/2012
N.A.
12/2015
03/2014
DOC Original
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING COST OVERRUNS OF MORE THAN Rs. 100 CRORE
DOA -> Date of Approval
DOC -> date of Commissioning
Annexure - XVI
ROAD TRANSPORT AND HIGHWAYS
STEEL
URBAN DEVELOPMENT
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
BPUTRA BRIDGE AT BOGIBIL AND LINK LINESNEFR BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLELINE(MTP) AHMEDNAGAR-PARLI VAIJNATH(NL) CR QUILON-TIRUNELVELI - TRICHENDUR, TENKASI GADAG-WADI NL RAYADURGA-TUMKUR NL BHANUPALI-BILASPUR BERI NL AKOLA-KHANDWA GC AKOLA-AKOT KAZIPET-VIJAYAWADA 3RD LINE WITHELECTRIFICATION MUNIRABAD (GINGERA) -RAICHUR NL TUMKUR-CHITRADURGA-DAVENGERE NL WARDHA-NANDED MAHARASHTRA RATLAM-MHOW-KHANDWA-AKOLA (GC)
PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1KM)
CONSTRUCTION OF MEDICAL COLLEGE ANDHOSPITAL AT GULBARGA
BANGALORE METRO RAIL PROJECT
NFR
MRTP
CR
SR
SWR
SWR
NR
SCR
SCR
SWR
SWR
CR
WR
NHAI
HSCL
MRTP
09/1997
03/1996
02/1997
04/1999
04/2013
04/2007
04/2008
04/2008
04/2012
04/2007
04/2011
04/2008
04/2008
05/2009
05/2005
05/2006
1500
495.44
514.68
460.94
1117
970.34
1046.88
184.26
1054.35
179.65
913
499.3
603.04
1108
768.88
6395
4996.19
1781.98
2820
1030
1922
1743
2966.99
2000
2200
1350.91
1801.01
2501.05
1421.25
2288
1060
13845.01
3496.19
1286.54
2305.32
569.06
805
772.66
1920.11
1815.74
1145.65
1171.26
888.01
2001.75
818.21
1180
291.12
7450.01
Sn
Sn
Sn
Sn
Project
Project
Project
Project
Agency
Agency
Agency
Agency
DOA
DOA
DOA
DOA
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Original(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
Cost Anticipated(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
CostOverrun(Rs.crore)
04/2008
03/2004
N.A.
01/1999
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
03/2012
11/2011
02/2014
06/2011
DOC Original
DOC Original
DOC Original
DOC Original
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE AND COST OVERRUNS OFRs.100 CRORE AND ABOVE
COR -> Cost Overrun
Annexure - XVII
ATOMIC ENERGY
COAL
HEAVY INDUSTRY
PETROLEUM
POWER
1
2
3
4
5
6
7
8
9
10
11
12
KUDANKULAM APP (NPCIL) PROTOTYPE FAST BREEDER REACTOR(BHAVINI, 500 MWE)
ADRIYALA SHAFT PROJECT
NATIONAL AUTOMOTIVE TESTINGAND RD INFRASTRUCTURE PROJECT(NATRIP)
UPGRADATION OF CRUDE OIL PUMPSTATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNKPIPELINE STRATEGIC CRUDE OIL STORAGEPROJECT AT MANGALORE INTEGRATED DEVELOPMENT OFVASHISTA AND S-1 FIELDS STRATEGIC CRUDE OIL STORAGEPROJECT AT PADUR PARADIP REFINERY PROJECT CONVERSION OF RIG SAGAR SAMRATTO MOBILE OFFSHORE PRODUCTIONUNIT(MOPS) INTEGRATED DEVELOPMENT OF B-127 FIELDS
TRIPURA GAS BASED POWERPROJECT
12/2001
09/2003
12/2009
04/2011
09/2012
01/2006
05/2013
01/2006
02/2009
03/2011
12/2011
07/2009
12/2008
09/2010
03/2013
09/2011
03/2015
10/2011
04/2016
01/2012
11/2012
05/2013
03/2015
07/2013
05/2016
09/2016
03/2016
12/2017
08/2016
03/2016
12/2017
05/2016
02/2016
04/2016
05/2016
01/2016
NPCIL
BHAVNI
SCCL
NATIS
OIL
ISPRL
ONGC
ISPRL
IOCL
ONGC
ONGC
NEEPCO
89
72
36
75
17
53
20
52
39
35
14
30
Sn
Sn
Sn
Sn
Sn
Project
Project
Project
Project
Project
DOA
DOA
DOA
DOA
DOA
DOC Original
DOC Original
DOC Original
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
DOC Anticipated
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
TOR (Months)
TOR (Months)
TOR (Months)
Agency
Agency
Agency
Agency
Agency
1,3171.00
3492.00
212.34
1718.00
871.35
732.00
4124.35
993.00
2,9777.00
861.79
2059.63
421.01
2,2462.00
5677.00
1228.39
3827.30
1200.00
1227.00
4941.49
1693.00
3,4555.00
1256.72
2665.65
1007.57
Cost Anticipated(Rs. crore)
Cost Anticipated(Rs. crore)
Cost Anticipated(Rs. crore)
Cost Anticipated(Rs. crore)
Cost Anticipated(Rs. crore)
9291
2185
1016.05
2109.3
328.65
495
817.14
700
4778
394.93
606.02
586.56
COR(Rs.crore)
COR(Rs.crore)
COR(Rs.crore)
COR(Rs.crore)
COR(Rs.crore)
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE AND COST OVERRUNS OFRs.100 CRORE AND ABOVE
COR -> Cost Overrun
Annexure - XVII
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
KISHANGANGA HEP (3X110 MW) KAMENG HYDROELECTRIC PROJECT(NEEPCO) TAPOVAN-VISHNUGAD HEP(4X130MW) BONGAIGAON THERMAL POWERPROJECT BOKARO THERMAL POWER STATION-A RAGHUNATHPUR THERMAL POWERSTATION PHASE-I PARE HYDRO ELECTRIC PROJECT TEHRI PUMPED STORAGEPLANT(1000MW) SYSTEM STRENGTHENING INNORTH/WEST PART OF WR FOR IPPPROJECTS IN CHATTISGARH KUNADANKULAM APP TRANS SYSTEM(PGCIL) PARBATI HEP (4X200 MW) (NHPC)II TEESTA LOW DAM HEP, STAGE-IV(4X40 MW) (NHPC) NORTH- EAST NORTH WESTERNINTERCONNECTOR I PROJECT TRANSMISSION SYSTEM ASSOCIATEDWITH PALLATANA GBPP and BPTS. BARH STPP(3X660MW) NTPC TUIRIAL HYDRO ELECTRIC PROJECT(60MW)
01/2009
12/2004
11/2006
01/2008
08/2006
04/2007
12/2008
07/2006
12/2011
05/2005
09/2002
09/2005
02/2009
02/2010
02/2005
07/1998
01/2016
12/2009
03/2013
09/2011
12/2011
02/2011
08/2013
02/2016
08/2014
11/2008
09/2009
09/2009
08/2013
12/2012
01/2011
07/2006
11/2016
06/2016
12/2018
03/2017
03/2016
01/2017
07/2016
09/2019
06/2016
12/2016
12/2018
09/2016
12/2017
12/2016
05/2018
10/2016
NHPC
NEEPCO
NTPC
NTPC
DVC
DVC
NEEPCO
THDCIL
PGCIL
PGCIL
NHPC
NHPC
PGCIL
PGCIL
NTPC
NEEPCO
10
78
69
66
51
71
35
43
22
97
111
84
52
48
88
123
Sn Project DOA
DOC Original
DOC Anticipated
Cost Original(Rs. crore)
TOR (Months)
Agency
3642.04
2496.90
2978.48
4375.35
2313.00
4122.00
573.99
1657.00
1746.65
1779.29
3919.59
1061.38
1,1130.19
2144.00
8692.97
368.72
5751.47
6085.84
3846.30
6749.18
4237.67
9606.82
1262.27
2978.86
2228.71
2187.32
8398.76
2193.08
1,3762.80
2932.88
1,5095.67
1381.71
Cost Anticipated(Rs. crore)
2109.43
3588.94
867.82
2373.83
1924.67
5484.82
688.28
1321.86
482.06
408.03
4479.17
1131.7
2632.61
788.88
6402.7
1012.99
COR(Rs.crore)
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE AND COST OVERRUNS OFRs.100 CRORE AND ABOVE
COR -> Cost Overrun
Annexure - XVII
RAILWAYS
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
CONSTRUCTION OF NL FROMKUMARGHAT-AGARTALA UDHAMPUR-SRINAGAR-BARAMULLA(NL),NR AGARTALA SABROOM, NL, NEFR MUMBAI URBAN TRANSPORT PROJECTPHASE-II JIRIBAM TO IMPHAL(TUPUI)(NL)(NEFR) BPUTRA BRIDGE AT BOGIBIL ANDLINK LINES NEFR KATIHAR - JOGBANI (GC)(NEFR) BANKURA - DAMODAR (GC) (SER) RAIL-CUM-ROAD BRIDGE AT MUNGER(NL), ECR BHAIRABI SAIRONG, NL, NEFR BELAPUR-SEAWOOD-URANELECTRIFIED DOUBLE LINE(MTP) NEW MAYNAGURI TO JOGIGHOPA VIACHANGRABANDHA (NL),NEFR NEW LINE FROM DIMAPUR TOZUBZA(KOHIMA) NATIONAL PROJECT(NEFR) LUMDING-SILCHAR JIRIBAM,BADARPUR-BARAIGRAM KUMARGHATNATIONAL PROJECT SEVOK RANGPO, NEFR GONDIA-JABALPUR(GC),(SECR) TAMLUK DIGHA,LINE DOUBLING(SER)
04/1999
03/1995
04/2008
04/2008
04/2003
09/1997
09/2001
03/1998
04/2002
04/2008
03/1996
04/2000
04/2006
04/1996
04/2008
02/1997
03/1984
03/2007
11/2002
03/2014
03/2014
03/2011
04/2008
12/2010
03/2005
03/2009
04/2014
03/2004
12/2008
03/2015
03/2009
12/2015
03/1998
06/2005
03/2016
12/2017
03/2018
03/2019
03/2019
06/2017
03/2018
12/2019
03/2016
03/2018
03/2016
03/2018
03/2020
03/2016
03/2020
12/2019
12/2019
NFR
NR
NFR
MRTP
NFR
NFR
NFR
SER
ECR
NFR
MRTP
NFR
NFR
NFR
NFR
SECR
SER
108
181
48
60
96
110
87
177
84
47
144
111
60
84
51
261
174
Sn Project DOA
DOC Original
DOC Anticipated
Cost Original(Rs. crore)
TOR (Months)
Agency
895.00
2500.00
813.34
5300.00
727.56
1500.00
492.98
111.90
921.00
619.34
495.44
733.00
850.00
1676.31
1339.48
386.30
293.97
1242.25
2,0000.00
2876.00
7986.04
6570.75
4996.19
1727.27
2371.85
3040.00
2820.25
1781.98
2531.34
2973.42
5500.00
4190.00
1544.40
1428.00
Cost Anticipated(Rs. crore)
347.25
17500
2062.66
2686.04
5843.19
3496.19
1234.29
2259.95
2119
2200.91
1286.54
1798.34
2123.42
3823.69
2850.52
1158.1
1134.03
COR(Rs.crore)
DOA -> Date of Approval
DOC -> Date of Commissioning
TOR -> Time Overrun
DETAILS OF CENTRAL SECTOR PROJECTS SHOWING TIME OVERRUNS OF 6 MONTHS AND MORE AND COST OVERRUNS OFRs.100 CRORE AND ABOVE
COR -> Cost Overrun
Annexure - XVII
ROAD TRANSPORT AND HIGHWAYS
STEEL
URBAN DEVELOPMENT
46
47
48
PANIPAT-JALANDHAR 6 LANE(KM 96TO 387.1 KM)
CONSTRUCTION OF MEDICALCOLLEGE AND HOSPITAL ATGULBARGA
BANGALORE METRO RAIL PROJECT
05/2009
05/2005
05/2006
11/2011
02/2014
06/2011
06/2016
03/2016
06/2016
NHAI
HSCL
MRTP
55
25
60
Sn
Sn
Sn
Project
Project
Project
DOA
DOA
DOA
DOC Original
DOC Original
DOC Original
DOC Anticipated
DOC Anticipated
DOC Anticipated
Cost Original(Rs. crore)
Cost Original(Rs. crore)
Cost Original(Rs. crore)
TOR (Months)
TOR (Months)
TOR (Months)
Agency
Agency
Agency
1108.00
768.88
6395.00
2288.00
1060.00
1,3845.01
Cost Anticipated(Rs. crore)
Cost Anticipated(Rs. crore)
Cost Anticipated(Rs. crore)
1180
291.12
7450.01
COR(Rs.crore)
COR(Rs.crore)
COR(Rs.crore)
Annexure- XVIII Details of 20 Railways Projects [ as identified by Ministry of Railways vide letter
no. 2011/w-1 /Genl / MoSPI dated 28/10/2015 ] to be monitored at MoSPI level
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 RAILWAYS
1 PATNA GANGA BRIDGE (NL), ECR - [220100308]ECR,BIHAR 04/2001 624.47 -
2,921.00
10/2007 12/2012
12/2015 0/0
2 RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR - [220100307]ECR,BIHAR 04/2002 921.00 3,040.00 3,040.00
03/2009 -
03/2016 0/0
3 LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECT - [N22000127]NFR,ASSAM
04/1996 1,676.31 -
5,500.00
03/2009 -
03/2016 0/0
4 CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA - [N22000194]NFR,TRIPURA 04/1999 895.00 -
1,242.25
03/2007 -
03/2016 0/0
5 BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR - [220100201]NFR,ASSAM 09/1997 1,500.00 4,996.19 4,996.19
04/2008 12/2011
06/2017 0/0
6 UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR - [220100133]NR,JAMMU AND KASHMIR
03/1995 2,500.00 -
20,000.00
11/2002 -
12/2017 0/0
7 KANPUR KASGANJ MATHURA(GC) NER - [220100197]NER,UTTAR PRADESH 03/1997 677.97 1,062.36 1,651.54
- -
03/2018 0/0
8 KIRANDUL - JAGDALPUR DOUBLING - [N22000318]ECOR,CHHATISGARH 12/2012 826.57 -
1,143.60
- -
03/2018 0/0
9 GONDIA-JABALPUR(GC),(SECR) - [220100186]SECR,MULTI STATE 02/1997 386.30 -
1,544.40
03/1998 -
12/2019 0/0
10 LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) - [220100232]WCR,MULTI STATE 09/1998 247.66 3,500.00 3,500.00
05/2008 -
- 0/0
11 PALANPUR-SAMAKHAYALI (DL) - [N22000144]WR,GUJARAT 04/2013 1,266.89 -
1,266.89
- -
- 0/0
12 KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION - [N22000261]SCR,MULTI STATE
04/2012 1,054.35 2,200.00 2,200.00
- -
- 0/0
13 GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM) - [N22000345],UTTAR PRADESH
04/1997 836.26 -
1,072.51
- -
- 0/0
14 UTRATIA-ZAFRABAD, NR (LINE DOUBLING) - [N22000088]NR,UTTAR PRADESH 04/2006 325.00 2,434.00 2,434.00
03/2010 -
- 0/0
(January 2016)
Date of Commissioning
(Month/Year)
SI.No
Project
Date of Approval (Month/ Year)
Original/ Revised
Cost (Rs. crore)
Original / Revised
Antici Pated
Milestones Achieved/
Total 1 2 3 4 5 6 7 15 KODERMA-RANCHI VIA BARKAKANA (NL),ECR - [220100222]ECR,JHARKHAND 03/1999 2,957.21
- 2,957.21
07/2005 -
- 0/0
16 HARIDASPUR-PARADEEP(NL) - [220100285]RVNL,ODISHA 04/1996 301.64 -
1,185.64
- 09/2009
- 0/0
17 SUKINDA ROAD - ANGUL (NL)(ECOR) - [220100325]RVNL,ODISHA 04/1998 183.23 -
1,202.70
02/2015 -
- 0/0
18 VILLUPURAM-DINDIGUL WITH ELECTRIFICATION - [N22000189]SR,MULTI STATE 04/2008 822.39 -
1,280.83
- -
- 0/0
19 HOSPET-HUBLI-LONDA-VASCODAGAMA DL - [N22000297]SWR,KARNATAKA 04/2010 2,127.00 -
2,127.00
- -
- 0/0
20 SAMBALPUR-TALCHER DOUBLING - [N22000315]ECOR,ODISHA 03/2011 679.27 -
1,111.99
- -
- 0/0
Total 20,808.52 -
0/0
Grand Total 20,808.52 0/0
Details of Worst 10 Cases of Time Overruns
DOC -> date of commissioning
TOR -> Time Overrun
1
2
3
4
5
6
7
8
9
10
GONDIA-JABALPUR(GC),(SECR) UDHAMPUR-SRINAGAR-BARAMULLA(NL),NR BANKURA - DAMODAR (GC) (SER) TAMLUK DIGHA,LINE DOUBLING (SER) BELAPUR-SEAWOOD-URAN ELECTRIFIEDDOUBLE LINE(MTP) TUIRIAL HYDRO ELECTRIC PROJECT(60MW) NEW MAYNAGURI TO JOGIGHOPA VIACHANGRABANDHA (NL),NEFR PARBATI HEP (4X200 MW) (NHPC) II BPUTRA BRIDGE AT BOGIBIL AND LINKLINES NEFR CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALA
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
POWER
RAILWAYS
POWER
RAILWAYS
RAILWAYS
03/1998
11/2002
03/2005
06/2005
03/2004
07/2006
12/2008
09/2009
04/2008
03/2007
12/2019
12/2017
12/2019
12/2019
03/2016
10/2016
03/2018
12/2018
06/2017
03/2016
261
181
177
174
144
123
111
111
110
108
Sn Project Sector
DOC Original
DOC Anticipated
TOR(Months)
Annexure- XIX
Details of Worst 10 Cases of Cost Overruns
DOC -> date of commissioning
TOR -> Time Overrun
1
2
3
4
5
6
7
8
9
10
NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR BANKURA - DAMODAR (GC) (SER) LALITPUR-SATNA-REWA-SINGRULI NL,(NCR) AKOLA-KHANDWA GC AKOLA-AKOT BANGLORE - SATYAMANGALAM (NL)(SWR) HUBLI-ANKOLA(NL),SWR JIRIBAM TO IMPHAL(TUPUI)(NL)(NEFR) UDHAMPUR-SRINAGAR-BARAMULLA(NL),NR MUNIRABAD (GINGERA) -RAICHUR NL UTRATIA-ZAFRABAD, NR (LINEDOUBLING)
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
RAILWAYS
36.80
111.90
247.66
184.26
138.00
227.00
727.56
2500.00
179.65
325.00
1336.57
2371.85
3500.00
2000.00
1382.78
2135.00
6570.75
2,0000.00
1350.91
2434.00
3531.98
2019.62
1313.23
985.42
902.01
840.53
803.12
700.00
651.97
648.92
Sn Project Sector
Cost Original
Cost Anticipated COR(%)
04/1983
03/1998
09/1998
04/2008
04/1996
04/1997
04/2003
03/1995
04/2007
04/2006
DOA
Annexure- XX