7030 - data sheets

12
 API 653 Certification Data Sheets MSTS  1 October 2013  Answer Reference Documents 1 Fitness for Service (FFS) 2 Risked Based Inspection 3 Low Pressure Storage Tanks 4 Cathodic Protection 5 Tank Bottom Linings 6 Welding on In-Service Equipment containing Flammables 7 NDE Procedure Guidelines 8 Acceptance Standards for RT’s of Welds 9 Alternative evaluation for pits and LTA’s  10 Welder Qualification 11 Weld Procedure Qualification 12 Impact Testing Method and Equipment Requirements 13 Requirem ent for new welding electrodes 14 NDE Personnel Qualification (RT & UT Flaw Detection) 15 API 650 Appendix for Frangible Roofs 16 API 650 Appendix for Hot Tanks Answer Class Abbreviations 1 API 653 S cope (Alteration, Inspe ction, Repair, Re construction) 2 API 653 AI’s Employer (Jurisdiction, User, Insurance company, Contractor) 3 API 653 Repair Organization (authorized by Jurisdiction, Owner, Contractor)

Upload: brian-case

Post on 04-Nov-2015

13 views

Category:

Documents


0 download

DESCRIPTION

API 653 Data sheets for exam

TRANSCRIPT

  • API 653 Certification Data Sheets

    MSTS 1 October 2013

    Answer Reference Documents

    1 Fitness for Service (FFS)

    2 Risked Based Inspection

    3 Low Pressure Storage Tanks

    4 Cathodic Protection

    5 Tank Bottom Linings

    6 Welding on In-Service Equipment containing Flammables

    7 NDE Procedure Guidelines

    8 Acceptance Standards for RTs of Welds

    9 Alternative evaluation for pits and LTAs

    10 Welder Qualification

    11 Weld Procedure Qualification

    12 Impact Testing Method and Equipment Requirements

    13 Requirement for new welding electrodes

    14 NDE Personnel Qualification (RT & UT Flaw Detection)

    15 API 650 Appendix for Frangible Roofs

    16 API 650 Appendix for Hot Tanks

    Answer Class Abbreviations

    1 API 653 Scope (Alteration, Inspection, Repair, Reconstruction)

    2 API 653 AIs Employer (Jurisdiction, User, Insurance company, Contractor)

    3 API 653 Repair Organization (authorized by Jurisdiction, Owner,

    Contractor)

  • API 653 Certification Data Sheets

    MSTS 2 October 2013

    Answer Dimensions

    1 Definitions - Length of shell-to-bottom weld that if repaired is

    considered a major repair or alteration

    2 Linings - Typically anchor profile of steel surface required for the

    installation of a tank bottom lining

    3 Welds - Maximum undercut of a vertical weld & nozzle weld

    4 Welds - Maximum undercut of a horizontal weld

    5 Welds - Maximum diameter of a surface porosity cluster

    6 Weld Qualification - Max allowed discontinuity in a Bend Test

    7 Nameplates - Minimum size of nameplate letters

    8 Bottoms - Minimum external projection of bottom plate on an existing

    tank (from toe of shell-to-bottom FW)

    9 Reconstruction - Max amount of peaking allowed in vert welds

    10 Shell Calcs When calculating tmin for shell LTA, minimum distance

    away from a weld where E is always 1.0

    11 Shell Patch - Minimum overlap of shell lap-patch used to cover a hole

    (edge of hole to edge of patch)

    12 NDE - When performing a PT examination, minimum distance to clean

    beyond the area to be examined

    13 NDE - When performing a MT examination, minimum distance to clean

    beyond the area to be examined

    14 Reconstruction - Maximum amount of banding allowed in a horizontal

    welds

    15 Bottoms - Minimum overlap required for single-welded lap joints

    16 Bottoms - Minimum external projection of bottom plate on a new tank

    17 Vacuum Box - Minimum overlap of previously test surfaces when using

    a vacuum box

    18 Bottom Patch - Minimum overlap of bottom lap-patch used to cover

    corroded area (edge of corrosion to edge of patch)

    19 Bottom Patch - Minimum distance bottom lap-patch fillet weld to the

    nearest existing bottom weld

    20 Shell Patch - Minimum radius of a shell lap-patch

    21 Reconstruction - If reusing bottom plates, min distance to cut from

    existing bottom welds (if plates are not deseamed)

    22 Reconstruction - If reusing roof plates, min distance to cut from

    existing roof welds (if plates are not deseamed)

  • API 653 Certification Data Sheets

    MSTS 3 October 2013

    Answer Dimensions (continued)

    23 Shell Pitting - Maximum allowed vertical length of pits on a tank shell

    24 Bottom Pitting - Maximum allowed length of pits in the critical zone

    that can be repaired by weld-buildup

    25 Bottoms - Radial length of critical zone measured from shell

    26 Bottoms Suggested pad thickness

    27 Welds - Min distance between clusters of surface porosity

    28 Shell Patch - Minimum dimension of a shell lap-patch

    29 Shell Patch - Minimum radius of a shell flush-patch

    30 Shell Calcs When calculating tmin for shell LTA, minimum distance

    away from a rivet where E is always 1.0

    31 Bottom Patch - Minimum size of bottom lap-patch that does NOT

    cross a bottom seam

    32 Bottom Patch - Minimum distance between a bottom lap-patch and the

    shell for patches that do NOT extend to the shell

    33 Reconstruction - If reusing shell plates, min distance to cut from

    existing shell welds (if plates are not deseamed)

    34 RT - Minimum diagnostic length of a RT for vertical or horizontal

    welds

    35 Weld Qualification - Minimum length of RT when qualifying a welder

    with RT using a coupon or 1st production weld

    36 Weld Qualification - Minimum length of RT when qualifying a welding

    operator with RT of a test coupon

    37 Shell Patch Minimum distance to overlap a shell weld when using a

    lap-patch

    38 Corrosion Area to dig when checking for soil-to-air corrosion

    39 NDE Distance of eye-to-part to count as a Visual Exam

    40 Vacuum Box - Typical size of a vacuum box

    41 Shell Patch - Minimum dimension of a shell flush-patch

    42 Bottoms - Minimum dimension that a 3-lap joint can be from: other 3-

    laps, the shell, or annular plate joints

    43 Bottom Patch - Minimum dimension of bottom lap-patch that crosses a

    bottom seam

    44 Foundations - Suggested height above grade for new tank bottoms

  • API 653 Certification Data Sheets

    MSTS 4 October 2013

    Answer Dimensions (continued)

    45 Shell Patch - When adding a shell flush-patch that extends to a

    horizontal shell weld, minimum distance to cut the horizontal weld

    past the new vertical welds

    46 Shell Patch - Dimension of a shell flush-patch that is considered

    either a major repair or alteration

    47 Definition - Dimension of a shell vertical weld if repaired or replaced

    is considered a major repair or alteration

    48 Bottom Patch Max width of bottom patch in the critical zone

    49 Bottoms - Minimum radial width of annular plate (distance between

    shell and nearest bottom fillet weld)

    50 NDE Max distance of eye-to-part to count as a Visual Exam

    51 Hot Tap - Minimum height of liquid above new nozzle during the hot

    tap operation

    52 Weld Qualification - Minimum length of RT when qualifying a welding

    operator with RT of first production weld

    53 NDE - Length of sweep board used when checking for banding or

    peaking

    54 Welds - Maximum distance between welder ID stamps on a tank weld

    55 Shell Patch - Maximum size of shell lap-patch (vertical & horizontal

    dimensions)

    56 Settlement - Maximum distance between tank settlement survey

    points across the inside of the tank

    57 Roofs Maximum shunt spacing on floating roof

    58 Settlement - Maximum distance between tank settlement survey

    points around the outside diameter of the tank

    59 NDE - Maximum distance between RTs in horizontal welds when

    welding to existing shell plates

    60 CP Typical tank size for Galvanic CP systems

    61 Shell Calcs - Tank diameter when variable point design method should

    always be used to calc shell minimum thickness

    62 Shell Minimum offset between vertical welds in adjacent courses

    63 Bottoms Minimum size of bottom welds

  • API 653 Certification Data Sheets

    MSTS 5 October 2013

    Answer Line Sizes

    1 Repad - Nozzle size that never requires a repad

    2

    Repairs On existing tank, new nozzle must use insert plate if shell is

    over thick and shell material does not meet current MDMT

    requirements

    3 RT - Maximum pipe size when using a RT elliptical shot (double-wall

    technique, double-wall view)

    4 Hot Tap - Maximum nozzle size that can be hot tapped when course

    thickness is > and shell has unknown toughness

    5 Definition - When adding a new nozzle, nozzle size to be considered a

    major alteration

    Answer Percentages

    1 RT Film Density - Limits of weld as compared to the IQI (range)

    2 AI Amount of time inspector must be involved in inspection activities

    - required to maintain API 653 certification

    3 RT Reconstruction - % to of weld intersections (new welds to old

    welds) to be RTd

    4 Maximum relative humidity when performing abrasive blasting for tank

    bottom linings

    5 Maximum relative humidity when installing tank bottom linings

    6 % to RT when installing a new insert plate with a nozzle into an

    existing shell plate

    7

  • API 653 Certification Data Sheets

    MSTS 6 October 2013

    Answer Temperatures

    1 Reconstruction - Base metal temp where welding is not allowed

    2 Reconstruction - Base metal temp when hand-warm pre-heat is

    required

    3 Linings - Minimum temp when performing abrasive blasting

    4 Linings - Minimum temp when installing tank bottom linings

    5 Corrosion The corrosion rate of steel tank bottoms may double with

    this rise in temperature

    6 UT Calibration - Calibration Block must be within what temperature of

    the part to be examined

    7 Vacuum Box - Standard temperature range for VB exam

    8 PT - Standard temperature range for a PT exam

    9 Impact Test - Design metal temperature that requires weld procedure

    used for vertical welds to be impacted tested

    10 Brittle - Tank metal temperature where brittle fracture is NOT a

    concern

    11 Bottom Lap Patches - Metal temp where lap-patches are NOT allowed

    in critical zone on SS tank

    12 Intervals - If tank product solidify below this temperature, the code

    maximum interval rules do not apply

    13 Preheat - Approximate temp of a required hand-warm pre-heat

    14 Corrosion - Temperature when high strength caustic causes serious

    corrosion in CS and 300 SS

    15 Preheat - Required pre-heat temperature for shell welds over 1.5

    thick during Reconstruction

    16 Bottom Lap Patches - Metal temperature where lap-patches are NOT

    allowed in the critical zone on CS tanks

    17 Temperature Range for API 650 App M

    18 Corrosion - Most aggressive temperature range for CUI. Range for

    API 575 and API 571

    19 Preheat - Minimum pre-heat temperature, when pre-heat is

    substituted for PWHT

    20 Maximum temperature for UT readings

    21 PWHT Temperature

    22

  • API 653 Certification Data Sheets

    MSTS 7 October 2013

    Answer Thicknesses

    1 Linings - Thickness of a thin film lining

    2 Bottom - Minimum allowed bottom plate thickness when there is a

    Reinforced Liner that is > 0.050 thick

    3 Bottom - Minimum allowed bottom plate thickness when there is a

    means to Detect and Contain a leak

    4 Roofs - Minimum allowed average thickness of corroded roof plate

    5 Shell - Minimum arbitrary shell thickness (used when calculated

    minimum thickness is below this number)

    6 Bottom - Minimum allowed thickness of bottom plate at toe of the

    external shell-to-bottom fillet weld

    7 Bottom - Minimum allowed bottom plate thickness away from critical

    zone or an annular plate

    8 Bottom - Minimum allowed plate thickness in critical zone that can

    be repaired by weld-buildup

    9 Roof Rim - Minimum allowed roof rim thickness

    10 Roof - Minimum thickness of new roof plate (cone & floating)

    11 Roof Rim - Minimum thickness of new roof rim

    12 Bottom - Normal minimum thickness of new bottom plate

    13 Bottom Patch - Maximum thickness of lap-patch in critical zone

    14 Brittle - Thickness when brittle fracture is NOT a concern

    15 Shell Patch Max shell thickness when lap-patches are allowed

    16 Shell Patch Maximum patch thickness for a shell lap-patch

    17 Weld Qualification When can UT be used in lieu of RT to Qualify a

    Welder/Welding Operator

    18 NDE - When welding existing shell plate. Thickness that requires

    100% examination by RT and MT or PT.

    19 NDE - Plate thickness which requires 100% of verticals weld to be

    radiographed

    20 Reconstruction - Shell plate thickness that requires all welds to be

    preheated to at least 200 oF.

    21 Shell Pits - Minimum remaining thickness allowed below a pit

  • API 653 Certification Data Sheets

    MSTS 8 October 2013

    Answer Time Intervals

    1 Vacuum Box - Minimum duration of each vacuum-testing exam

    2 NDE - Minimum time an examiner should be in a darkened area prior

    to using a black light for MT & PT exams

    3 NDE - Final interpretation of a PT exam after application of developer

    (time range)

    4 Testing - Minimum time to let oil to penetrate when performing a

    diesel oil test of shell-to-bottom weld

    5 Testing - Minimum duration for a tank hydrotest to be held at full

    height

    6 NDE - Max Calibrating Interval - Permanent magnet MT Yoke

    7 Intervals - Maximum Interval - Routine In-Service inspection

    8 CP - Maximum Interval - Routine check of CP impressed current

    sources

    9 NDE - Max Calibrating Interval - RT densitometer

    10 Reconstruction - Maximum allowed age of last thickness readings,

    used to design a reconstructed tank

    11 Weld Qualification Maximum Time - Welder or operator maintains

    qualifications for a welding process without using that process

    12 NDE - Max Calibrating Interval - Electromagnetic MT Yoke

    13 CP - Maximum Interval - Detailed check of CP impressed current

    facilities

    14 CP - Maximum Interval - CP surveys (field potential measurements)

    15 NDE - Minimum Time - To keep RTs acquired during tank repairs and

    reconstructions

    16 Vac Box Max Test Interval - Jaeger 2 eye test for VB oper

    17 NDE Max Test Interval - Jaeger 2 eye test for PT/ MT tech

    18 AI Time period between API AI recertification

    19 Intervals - Maximum Interval - UT readings of a tank shell when the

    corrosion rate is unknown

    20 Intervals - Maximum Interval - External Inspection

    21 AI Time period between API AI on-line recertification

    22 Intervals - Maximum Interval - Initial Internal Inspection (without

    RBI or other special situations)

  • API 653 Certification Data Sheets

    MSTS 9 October 2013

    Answer Time Intervals (continued)

    23 RBI - Maximum Interval - RBI reassessments

    24 Intervals - Maximum Interval - UT readings of a tank shell when the

    corrosion rate is known

    25 Intervals - Maximum Interval - Internal Inspection when the

    corrosion rate is known (without RBI assessment)

    26 Linings - Typical life of a properly applied tank lining

    27 NDE - Max Calibrating Interval - Check the light intensity of a black

    light used in a MT or PT exam

    Answer Pressures

    1 Scope - Maximum internal pressure for tanks in API 650 & 653

    2 Vacuum Box - Normal vacuum required when vacuum testing

    3 Pressure Test - Pressure used when air testing the shell-to-bottom

    weld

    4 Pressure Test - Pressure used when air testing a repad

    5 Scope - Maximum internal pressure for tanks in API 620

    Answer Slopes

    1 Minimum slope of normal tank bottom

    2 Minimum slope of cone roof tank (for water runoff)

    3 Maximum roof slope on tanks > 50 diameter (if roof is considered to

    be fragible)

    4 Maximum taper (steepest slope) allowed for an insert plate

    5

  • API 653 Certification Data Sheets

    MSTS 10 October 2013

    Answer Miscellaneous Numbers

    1 Roofs - Maximum amount of primary seal that can be removed for

    repair while tank is still in service

    2 NDE - Minimum number of RTs required on a circular shell

    replacement plate

    3 FFS Current joint efficiency E in API 650

    4 FFS Joint Efficiency E Calculating tmin for an LTA, when LTA is

    away from rivets by > 6

    5 FFS Joint Efficiency E Calculating tmin for an LTA, when LTA is

    away from weld by greater of: 1 or 2t

    6 Reconstruction - Number of sets of center punch marks located on

    top and bottom edges of each shell piece

    7 Weld Qualification - Number of tension tests to qualify a WPS

    8 Weld Qualification - Number of bend tests to qualify a welder or

    welding operator in welding positions 1G-4G

    9 NDE - Minimum # of exposures to RT 360o of a weld using a double-

    wall technique, double-wall view (elliptical shot)

    10 NDE - RT film Density Range - allowed for the weld & IQI when using

    a gamma ray source

    11 NDE - Minimum # of exposures to RT 360o of a weld using a double-

    wall technique, single-wall view

    12 Impact Test - Number of test bars required in each set of impact

    test specimens

    13 NDE - When using a shim under a hole-type IQI, the number of sides

    of the IQI that must be seen in the RT image

    14 Hot Tap - Minimum number of UT readings around the circumference

    of a new hot tapped nozzle

    15 Weld Qualification - Number of bend tests to qualify a WPS

    16 Weld Qualification - Number of bend tests required to qualify a

    welder in welding positions 5G & 6G

    17 FFS - Corrosion Averaging in a Shell LTA - Minimum # of UT readings

    to take on each designated vertical line.

    18 NDE - Minimum number of RTs required on a square or rectangular

    shell replacement plate

    19 Settlement - Minimum number of settlement points around

    circumference

    20

    21

    22

  • API 653 Certification Data Sheets

    MSTS 11 October 2013

    Answer Miscellaneous Other

    1 Reconstructed Maximum allowed out-of-plumbness

    2 Corrosion pH level that causes corrosion to increase

    3 Corrosion Chloride level where pitting on steel begins

    4 NDE - Weight used to check magnetic strength of an AC yoke

    5 Grounding - Maximum electrical resistance permitted from tank to earth

    6 NDE Min angle of eye-to-part to count as a Visual Exam

    7 NDE - Weight used to check magnetic strength of a DC yoke

    8 NDE - Minimum light intensity when performing non-fluorescent MT or PT exams

    9 Vacuum Box - Minimum light intensity when performing vacuum testing

    10 NDE - Minimum black light intensity when performing fluorescent MT or PT exams

    11 Brittle Shell stress when brittle fracture is NOT a concern

    12 NDE - Hole size that must be visible in RT when using a hole-type IQI

    13 Weld Qualification - Maximum allowed thickness on a WPS based on the plate thickness (T) of a PQR test coupon

    14 Weld Qualification The all-position test coupon

    15 NDE - Lead letter used during RT to check for backscatter radiation

    16 NDE - Lead letter used during RT to indicate a film-side IQI

    17 NDE - Lead letter used during RT to indicate a repaired weld

    18 Repairs Material where pre-heat can be substituted for a required PWHT

    19 Repairs Materials where control deposition welding can be substituted for a required PWHT

    20 Hot Taps Nozzle thickness for hot tapped nozzles

  • API 653 Certification Data Sheets

    MSTS 12 October 2013

    Miscellaneous Other (continued)

    21 Repairs Welding processes that can be used when substituting Preheat or Controlled Deposition welding for a required PWHT

    22 Corrosion In a corrosion cell, the part that corrodes

    23 Corrosion In a corrosion cell, the part that doesnt corrode

    24 Linings Minimum surface prep prior to applying lining

    25 Weld Qualification Rejectable in RT when qualifying a welder

    26