1 nyngan solar plant community consultative committee august 2014 date: 1 august 2014
TRANSCRIPT
2
Agenda
2
1 Welcome August CCC
3
4
5
Review previous minutes
Overview of project status (AGL and First Solar)
Project planning
Construction community fund
6 Next meeting and close
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
4
2. Review actions from previous meeting
Action item CCC meeting Status
AGL to send an example application form to CCC.
June 2014 Closed
AGL to progress the shopfront display June 2014 Open
AGM to provide more information about using the land acquired for native vegetation preservation for training purposes.
June 2014 Closed
AGL to investigate if additional traffic signage is required.
June 2014 Closed
LT to investigate issue around football players and rosters.
June 2014 Closed
RH to send received applications to KRo. June 2014 Closed
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
5
2. Confirmation of June 2014 minutes
› Any comments to the June minutes?
› Accept as accurate record of meeting?
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
6
> Presentation title
> Author
> Date (Verdana 10pt)
Overview of project status
• Adam Mackett (AGL)• Bruce Smith (First Solar)
7
2. AGL overview of project status
Current progress on the Nyngan Solar Plant:
› Project on track for completion in June 2015
› Solar Plant launch on Wednesday, 30 July 2014
› Ten times bigger than the current largest solar PV plant in Australia.
› 250 hectares 134 SCGs› 1.35 millions modules› 200km of electrical cabling
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
8
2. AGL overview of project status
Current progress on the Nyngan Solar Plant connection:
› Connection works are mechanically complete.» 132kV transmission line (Essential Energy)» 132kV Switchyard (Essential Energy» 132kV Substation (AGL)
› Energisation of the 132kV transmission line has been moved from 2 Aug 2014 to 30 Aug 2014
› Interface works with First Solar’s 33kV Switchyard are progressing 132/33kV transformer energisation
› Communication works in the Nyngan 66kV (town) substation).
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
9
2. First Solar overview of project status
Current progress on the Nyngan Solar Plant
› 40,000 of the 140,000 steel posts have been installed
› 19,000 of the 140,000 tilt brackets have been installed
› Table installation underway
› 250,000 of the 1,350,000 panels have been delivered
› 18 of the 77 PCS (Power Conversion Station) units and 1 of the 4 PVCS (Photovoltaic Combiner Switchgear) units have been delivered
› Operations and maintenance buildings have been installed
› Table installation has commenced
› Electrical work underway – underground cabling and combiner boxes
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
12
2. First Solar overview of project statusLocal community and employment
As of end of July 2014, the Joint Venture between WBHO and Probuild Civil has approximately 110 personnel on site – of which 1/3 are local/regional (35)
›First Solar Contacts:
›Bruce Smith Michael Law
›Project Manager Construction Manager
›Mob: 0428 199 241 Mob: 0417 369 921
›E: [email protected] E: [email protected]
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
17
4. Project planning
First Module Installation event, 30 July 2014
Attendees included:› The Hon, Kevin Humphries MP (NSW), Minister for
Natural Resources, Lands & Water› Mark Coulton MP, Federal Member for Parkes› Leslie Williams MP, NSW Parliamentary Secretary
for Renewable Energy› Ray Donald (Mayor Bogan Shire Council)
Community Feedback
Any comments or questions from the CCC or observers?
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
20
5. Community Fund
Update on the Community Fund
AGL is finalising detailsApplicants will be notified of the outcome of their applications in week commencing 11 August
Community Fund Panel processAny feedback on the process?
> Nyngan Solar Project
> AGL Energy
> 1 August 2014
22
6. Any other business
› Questions from observers?
› AGL and First Solar will be at the Nyngan Ag Expo this Saturday, so feel free to drop by for a chat.