Indian Transmission network

TRANSCRIPT

Page 1: Y K Sehgal Transmission Development-India
Page 2: Y K Sehgal Transmission Development-India

Installed Capacity : 159,400 MW

Peak Power Demand : 118,000 MW

Peak availability : 103,000 MW

Present Power Scenario

• Infrastructure growth remains the overriding priority for IndiaPower Sector has a pivotal role to play

Present Supply Scenario

Generation MixThermal 102450 MW(64%) Central

State

Private

TOTAL 159400 MW 159400 MW

50992 MW (32%)

Hydro 36860 MW (23%) 79394 MW (50%)

Nuclear 4560 MW(3%) 29014 MW (18%)

RES 15530 MW(10%)

Page 3: Y K Sehgal Transmission Development-India

• Transmission network spread geographically over 3.3 million sq kms

• 765kV/400kV lines: 1,00,916 ckms

• 220kV lines: 1,28,000 ckms

• HVDC Bipole (±500kV) : 7,500 ckms

• National Grid – Inter-regional capacity: 20,800MW

Transmission Network - Present

SOUTHERN REGION

WESTERNREGION

EASTERN REGION

NORTHERN REGION

NORTH-EASTERN REGION

1

2

The‘Electrical’Regions

Page 4: Y K Sehgal Transmission Development-India

• 400kV Backbone Trans. Network - about 60,500 ckm(220kV: 10,000 ckm)

• Overlaying 765kV AC and 500kV HVDC system - about 7,000 ckm

• Substations 400kV & above –131 nos. with 89,000 MVA

• 2 nos. HVDC Bipole (4000 MW) and 4 nos HVDC Back to Back System (3000 MW)

POWER MAP OF INDIA POWERGRID Transmission Network - Present

World’s 3rd largest Transmission Network

Page 5: Y K Sehgal Transmission Development-India

KOTA

MALANPUR

AURAIYA

AGRA

NR

GORAKHPUR

BALIA

SAHUPURI

MW500

SALAKATIBIHARSHARIFF

SASARAM

PATNA

MUZAFFARPUR

MALDA

BIRPARA

BONGAIGAON

NER

UJJAIN

KOLHAPUR

PONDA

SR

CHANDRAPUR

BELGAUMNAGJHARI

GWALIOR

WR

1000

U.SILERU

MW

KORBAVINDHYACHAL

RAIPUR

BALIMELA

ERBUDHIPADAR

1000

TALCHERROURKELA

DEHRI

GAZUWAKA

MW

KANKAROLI

ZERDA

SIPAT RANCHI

Inter-regional capacity : 20,800MW

National Grid - Present

Page 6: Y K Sehgal Transmission Development-India

Inter-regional capacity : >32,000 MW

National Grid – A Continuing Process

National Grid – By 2012

Page 7: Y K Sehgal Transmission Development-India

36874

2860026783

14400 15043

57000

0

10000

20000

30000

40000

50000

60000

Central Sector State Sector Private Sector

XI Plan

XII Plan

Change in Generation Profile

Total

36874 (47%) 26783(34%) 15043(19%) 78700

28600 (28%) 14400(15%) 57000 (57%) 100000

XI

XII

Page 8: Y K Sehgal Transmission Development-India

Unevenly dispersed energy resources

Hydro in NER & NR

Coal in ER

Integration of energy resources through high capacity National Grid - a must

NR

WR

SR

ERNER

Ennore

KudankulamKayamkulam

Partabpur

Talcher/Ib Valley

Vindhyachal

Korba

LEGEND

Coal

Hydro

Lignite

Coastal

Nuclear

VizagSimhadri

Kaiga

Tarapur

Mangalore

Krishnapatnam

RAPP

SIKKIM

MYA

NMM

AR

CHICKEN NECK

Cuddalore

SRI LANKACOLOMBO

NEPALBHUTAN

DESHBANGLA

South Madras

Pipavav

Generation Load-Centre

Kolkata

Bhubaneswar

PatnaLucknow

Delhi

Mumbai

Chennai

Bangalore

Bhopal

Guwahati

Jammu

Ludhiana

Jaipur

Gandhinagar

Indore

Raipur

Thiruvananthapuram

Kozhikode

Hyderabad

Energy Resource Map

Page 9: Y K Sehgal Transmission Development-India

Jharkhand –6500 MW

NER –5000 MW

Orissa –23,000 MW

T.N.–10,000 MW

Generation Profile of IPPs

AP–24,000 MW

Chhattisgarh.–58,000 MW

Page 10: Y K Sehgal Transmission Development-India

Open Access in Transmission

Generation de-license

Power purchase through Tariff-based competitive bidding

Destination of power transfer not firmed-up when generation project is envisaged

New Regime of Power Sector

Page 11: Y K Sehgal Transmission Development-India

Change in generation profileQuantity

Location of the generation project

Scarce Right of Way

Complex dynamism due to high technologyReactive Power Management

Control of power flow

Implementation in time

Shortage of skilled manpower

Need of New Initiatives in Transmission

Page 12: Y K Sehgal Transmission Development-India

Cluster of Demand areas

Cluster of Generation

pockets

High Capacity Corridors

Need to be developed in Phases depending upon progress of generation projects

Page 13: Y K Sehgal Transmission Development-India

Creation of high Capacity Transmission Corridor

Minimum cost per MW transfer

Optimal Transmission losses

Minimization of Right of Way

Protection of flora & fauna

Strengthening of National Grid

Challenges in Transmission Development

Page 14: Y K Sehgal Transmission Development-India

Technology

Page 15: Y K Sehgal Transmission Development-India

High Voltage line

Increase the capacity of trans. corridor through HSIL/re-conductoring with HTLS /Upgradation

Utilisation of transmission lines upto full thermal

capacity – Series capacitors, SVC, FACTS

Optimization of Tower design – tall tower, multi-ckt. tower

GIS substation

EHVAC : 400kV 765kV 1200kVHVDC : ±500kV ±800kV

Technology being Adopted

Page 16: Y K Sehgal Transmission Development-India

1977 1990 2000 2012 2016

Voltage (kV)

Year

220kV400kV

500kVHVDC

765kV800kVHVDC

Increase in Transmission voltage

Complexities with high voltage AC system• Reactive Power Management• Availability of switchgear• Corona Loss• Sustainability of grid during contingencies

Voltage Upgradation1200kV

Page 17: Y K Sehgal Transmission Development-India

Development Plan

Page 18: Y K Sehgal Transmission Development-India

NEYVELI

RAICHUR

RAMAGUNDAM

VIJAYAWADA

CHANDRAPUR

KORADI

KORBAKORBA(W)

VINDHYACHAL

SATPURA

RIHAND

ANPARA OBRA

RENGALI

FARAKKA

KAHAL-

TALCHER

MUNIRABAD

N'SAGAR

URI

MAITHON

MADRAS

TEHRI

DHAULIGANGA

CHAMERA

N.JHAKRI

AURAIYA

KAIGA

MADURAI

UDUMALPET TRICHY

SALEM

BANGALORE

CUDDAPAH

GOOTY

HYDERABAD GAZUWAKA

ASOJ

DHULEBHILAI

ITARSI

JAIPUR

KANPUR LUCKNOW

JEYPORE

J

JEERAT

DURGAPUR

NORTH TRICHUR

KISHENPUR

WAGOORA

MOGA

BHIWANI

BIHAR-

KHAMMAM

BAREILLY

HISSAR

NALLAGARH

PANIPAT

MALERKOTLA

DEHGAM

INDRAVATI

DADRI

JAMSHEDPUR

LEGEND

BALLABGARH

BAWANA

MURADNAGAR

MANDAULAMEERUT

BASSI(RSEB)

PANKI

JALANDHAR

IIIII

GANDHAR

STPS

DULHASTIPAMPORE

SALALI&II

JAMMUSARNA HAMIRPUR

SIUL

PONG

RAPP-B

ANTA

DAUSA

CHITTORGARH

UDAIPUR

KOLAR

BAHOOR

KAYAMKULAM

PALLOM

EDAMON

KOLASIBAGARTALA

AGARTALA GPP

MALDA

KUMARGHAT

BADARPUR IMPHAL

JIRIBAMAIZWAL

ZEMABAWK

HAFLONG

LOKTAK

KAMENG

RAMMAM

SILIGURI

PURNEA KHLIEHRIAT

CHUKHA

BONGAIGAON BIRPARA

DALKHOLA

SAMAGURI

BALIPARATEZPUR

KOPILI DIMAPUR

DOYANGMARIANI

ITANAGAR

KHANDONG

MISA

RANGANADI

GOHPUR

ZIRO

DEOMALIKATHALGUR

KAKRAPAR

BHARUCH

KAWAS

NAVSARIVALTHAN

NAGDA

VAPI

HOSUR

SHARIF

MERAMUNDALI

BARIPADA

STPS

KOLAGHAT

ALLAHABAD

SINGRAULI

LUDHIANA PATIALA

KAITHAL

BUDHI-PADAR

NELLORE

KURNOOLNARENDRA

KOLHAPUR

MAPUSA

TRIVANDRUM

BHIWADI

SATNA

UNNAO

GORAKHPUR(PG)

MUZAFARPUR

TALAB H U T A N

SEONI

FATEHBAD

MAINPURI

SIPAT

KHANDWA

RAJGARH

SSAROVAR

BOISARTARAPUR

DAVANGERE HIRIYUR

GAON

SUBHASGRAM

AMRITSAR

BHATAPARA

WARANGAL

ALAMANTHI

MALEKOTTAYUR

PONDICHERRY

PUGALUR

MYSORE

KOZIKODE

DELHI

KUDANKULAM

TIRUNELVELI

MUVATTAPUZHA

BARHPATNAMAU

(PG)

(UP)

(UP)

KOTA RAPP-C&DKANKROLI

PARBATI

KOLDAM

PALLATANAGBPP

RANCHI

AKOLA

URI-II

-II

BAHDURGARH

JODHPUR

KISHENGANGA

ARASUR

MAHBOOB NAGAR

SOLAPUR(PG)

PARLI(N)PUNE

LONIKHAND

KALWA

B'SPUR

DAMOH

KARAMSADLIMBDI

RANCHODPURAZERDA

KARAD

SOLAPUR

BHILWARA

MERTA

ALISTONG

WAMPOH

-III

GANGTOK

MELLI

TALGUPPA

HASSAN

KARAIKUDI

VEMAGIRI

PARLI

RAJKOT

NAVI MUMBAI

KHADOLI

SHUJALPUR

KHARADPADA

MAGARWADA

AMARGARH

CHANDAKA

TEESTA-V

RANGIT

NKSTPP

FATEHPUR

BISHWANATH

LOWERSUBANSIRI

BHINMAL

GURGAON

RAMPUR

SILCHARMAITHON RBSASAN

MUNDRA

JETPURAMRELI

MUMBAI LOC

BHADRAWATI

BYRNIHAT

SONIPAT

K'WANGTOO

BACHCHAU

GAYA

TUTICORIN JV

KRISHNAPATANAM UMPP

NORTH CHENNAI JV

SIKAR

RATANGARH

BASPA

PANCHKULA POOLING STN

JATTI KALAN

LUCKNOW

BAREILLY

DASUYA

MAHRANIBAGHGNOIDA

KODERMA

BOKARO

MEJIA

FROM SIKKIMMELLI

BEHRAMPUR

PUNE

A'BAD

NEEMRANAMANESAR

DEHRADUNBAGPAT

GAJWEL

TILAIYYA

ROORKEE

SAHARANPURROORKEE

KASHIPUR

SASARAM

VARANASI

WR POOL

ANGUL

PADGHEAURANGABAD

RAIPURRAIGARH

WARDHA

INDORE

GWALIOR

BINA

JABALPUR POOL

JABALPUR DHARAMJAYGARH

JHARSUGUDA

CHAMPA

KISHANGANJ

AGRA

Transmission Corridor for Chhattisgarh IPP's (Corridor - V)

BHOPAL

JAIPUR

JHARKHANDPOOL

CHARIALIALIPURDUAR

PUNATSANGCHU-I

Transmission Corridor for Orissa IPP's (Corridor - I)Transmission Corridor for Jharkhand IPP's (Corridor - II)

Transmission Corridor for Tuticorin IPP's (Corridor - VII)

Transmission Corridor for Sikkim IPP's (Corridor - III)

NABINAGAR

EAST COAST

KRISHNAPATANAM IPP

BANGALORE

BANG_NEW

CHEYYUR UMPP

Transmission Corridor for Krishnapatnam IPP's (Corridor - VI)

TIRUVALAM

CUDDALORE

KURUKSHETRA

VADODRA

BALIA

B'SAHAR

ORAI

Transmission Corridor for Chhattisgarh & MP IPP's (Corridor - IV

PIRANA

Transmission Corridor for Srikakulam IPP's (Corridor - VIII)Transmission Corridor for Southern Region IPP's (Corridor - IX)

High Capacity Transmission Corridor

Page 19: Y K Sehgal Transmission Development-India

Planned to enhance the National Grid capacity progressively to about -

National Grid – A Continuing Process

2080032000

75000

0

20000

40000

60000

80000

Present By 2011-12 By 2016-17

Strengthening National Grid

Page 20: Y K Sehgal Transmission Development-India

Road Map for Indian Power System

• 400kV Transmission System – Present Backbone

• 765kV Transmission system – 2700 ckm under operation, about 7000 ckm under different stages of execution

• 765kV transmission lines are mostly double circuit

• HVDC system - ±800kV 6000MW NER- Agra under execution

• 1200kV AC Transmission System – under development : expected operation by 2016-17

Road Map for Transmission

Page 21: Y K Sehgal Transmission Development-India

Plan Target

Page 22: Y K Sehgal Transmission Development-India

POWERGRID 11th Plan Target

Item 11th Plan Target

Achieved So far(Mar’10)

Balance

Transmission line 400kV & above (Ckm)

35500

45

56000

Investment (USD billion)

12 5.6(2.3)

6.4

18400(5515)

17100

No.of EHV substations(400kV & above)

27(7)

18

MVA capacity 30080(10290)

25920

(*) Achieved in 2009-10

Page 23: Y K Sehgal Transmission Development-India

POWERGRID Transmission Augmentation Plan(Next 7-8 years)

Item Estimated Addition Programmein 12th Plan (2102-16)

Transmission line 400kV/765kV & above (Ckm)

80,000 – 90,000

No.of EHV substations (400kV & above)

90-100

MVA capacity 150,000 – 170,000

• Estimated Investment : About USD 22 billion

Page 24: Y K Sehgal Transmission Development-India

Transmission Lines : 80,000 – 90,000 Ckt.kms

+ 500kV/800kV HVDC: 5,000 – 6,000 ckt km

765 kV AC : 30,000 – 35,000 ckt km

400kV AC : 45000 – 50,000 ckt. km

New Substations – 90 - 100 Nos.

765/400kV : 35 – 40 Nos.

400/220/132kV : 55 - 60 Nos.

1200/765/400kV : 1 – 2 Nos.

Transformation Capacity (MVA)- 1,50,000 – 1,70,000 MVA765/400kV : 80,000 – 90,000 MVA

400/220/132kV : 70,000 – 80,000 MVA

Series Compensation : 22 nos. on 400kV lines

POWERGRID Physical Target(Next 7-8years)

Page 25: Y K Sehgal Transmission Development-India
Page 26: Y K Sehgal Transmission Development-India

Interconnection with Neighbouring Countries

Page 27: Y K Sehgal Transmission Development-India

INTERCONNECTION OF INDIA WITH BANGLADESH

Page 28: Y K Sehgal Transmission Development-India

India & Bangladesh InterconnectionIndia & Bangladesh Interconnection• Asynchronous Interconnection between the two

countries agreed in a meeting between Indian Delegation and BPDB & PGCB officials, Bangladesh on November 24, 2009 at Dhaka.

• Scope of Interconnection :– Establishment of 400kV Sw. Stn. at

Baharampur(India) by LILO of Farakka-Jeerat400kV S/c line

– Baharampur(India) –Ishurdi/Bheramara(Bangladesh) 400kV D/c line.

– Installation of HVDC back-to-back station (400/230 kV) at Ishurdi/ Bheramara(Bangladesh).

• The target date of commissioning is July, 2012.

Page 29: Y K Sehgal Transmission Development-India

Interconnection between India & Bangladesh GridsInterconnection between India & Bangladesh Grids

• Purpose :–Exchange of Power between

India and Bangladesh

• Interconnection :– Baharampur(India)-

Bheramara(Bangladesh) 400kV D/c line

–500MW HVDC B/b stn at Bheramara(Bangladesh)

• Type of connection :–Asynchronous(HVDC)

• Transfer Capacity :– 500MW (upgradable to

1000MW)

GOALPARA33.2 MVA

KHULNADOMJUR

LILUAH

HOWRAH(WB)

JOKA

BUDGEBUDGE

SOUTHERN

BARIPADA

HALDIATAMLUK

FALTA

KOLAGHAT

KRG'PUR(D)

ULUBERIA

KOLAGHAT(D) HWH(D)

HM

LEGEND

BHOLAGALLAMARI

LAKSHMIKANTOPUR

SUBHASGRAMBASIRHATSONARPUR

KASBA

MANGLA13.3 MVA

SOUTH

SATKHIRA

BHANDARIA13.3 MVA

26.6 MVABAGERHAT

KAWKHALI

PATUAKHALI40 MVA

BARISAL82 MVA

230/220kVEXISTING

132kV

FUTUREBANDARBAN

20 MVACOX'S BAZAR

RAUJAN

JULDAHSHAHMIRPUR

126 MVA

Bay of Bengal

HALISHAHAR167 MVA

BURHANUDDIN

63 MVA

82 MVA

HATHAZARI

BAROAULIA

KULSISIKALBAHA

80 MVA

41 MVADOHAZARI

CHANDROGHONA26.6 MVAMADANHAT

82 MVA

KAPTAI

LUNGSEN

TENGA

NBU

LDTEESTA

RAIGANJ

GANGARAMPUR

DALKHOLA(WBSEB)

CH. NAWABGANJ40 MVA

SAGARDIGHI

RAGHUNATHGANJ

DEBAGRAM

KRNAGAR

RANAGHAT

TITAGARH

DPL

ARAMBAG

ARAMBAGBURDWAN

RISHRA

BELMURI

KHANYANBTPS

DURGAPUR

NAGARBIDHAN

MANKAR

BOLPUR

SATGACHIA

KATWA

DHULIAN

RAMPURHAT

BAKRESHWARSAITHIA

GOKARNA

FARRAKA

KHEJURIA

PURNEA

KAHALGAONMALDA

SAMSI

DALKHOLA

KATIHAR

PURNEA(BSEB)(WBSEB)DALKHOLA

LEBONG

RAMMAM

JOYDEVPUR

GHORASAL

ASHUGANJ

MEGHNAGHATMAGURA

40 MVA

KHULNA CENTRAL192 MVA

NOAPARABONGAON

JEERAT

ASHOKNAGAR

DHRMPR

BARASAT

KALYANI JESSORE80 MVA

CHUADANGA

JHENAIDA40 MVA

BOTTAIL82 MVA

MADARIPUR26.6 MVA

GOPALGANJCHANDPUR

40 MVA

AMINBAZAR

FARIDPUR40 MVA

MANIKGANJ41 MVA

HASNABAD

MIRPUR

KALYANPUR

TONGI

ULLON

BASUNDHARA

BOGRA82 MVA

40 MVA

SHAHJAD

SIRAJGANJ

PUR40 MVA

BHERAMARA16.6 MVA

ISHURDIBEHRAMPUR

BEHRAMPUR

53 MVARAJSHAHI

82 MVAPABNA

NATORE40MVA

NIAMATPUR NAOGAON82 MVA

BOGRASOUTH

SRIPUR(MODHUPUR)

TANGAIL82 MVA

BAGHABARIKABIRPUR82 MVA

68 MVA

JAMALPUR82 MVA

82 MVAMYMENSINGH

JIRIBAMKOLASIB100 MVA KHOWAI

TRIPURA

CHOWMOHANI82 MVA

COMILLA

82 MVASOUTH

FENI40 MVA

40 MVA

COMILLANORTH

AGARTALAHARIPURSIDDHIRGANJ

RAMPURAGPP

AGARTALA

AMBASSA

W.PHAILENG

RANGAMATI

KHAGRACHARI

LUNGLEI

MARPARA

SERCHIP

(ZEMABAWK)

MIZORAMAIZWAL

AIZWAL

EASTKANCHANBARI

KISHORGANJ

20 MVASHAHJIBAZAR

50 MVA

B. BARIA

B BARIA

40 MVA

KAMALPUR

SREEMONGAL40 MVA

NETROKONA40 MVA

SYLHET

DULLABCHERA

KAILASHAHAR

KUMARGHAT

DHARMNAGAR

BADARPUR

PANCHGRAM

FENCHUGANJ33 MVA

SYLHET40 MVA

JIRIBAM

PILAPOOL

BONGAIGAON

ASSAM

BORNAGAR

40 MVALALMONIRHAT

PALASHBARI

JOYPURHAT

BALURGHAT 40 MVA

82 MVASAIDPUR

33.4 MVA

BOROPUKURIA

PURBASADIPUR

(2x41+1x20) MVATHAKURGAON

RANGPUR82 MVA

TURA

ALIPURDUAR

SILIGURI

MOINAGURI

PANCHAGARH

BIRPARA

MELLI

BIRPARA(WB)

GOSAIGAON

DHALIGAON

AGIA

SALAKATI

SINGIGAON

CHUKHA

GUWAHATI

NEHU

KYRDEMKULAIUMIAM-4

MEGHALAYANANGAL

BIBRA

40 MVACHATTAK

CHERRAPUNJI

SHILLONG

LONGPI

UMTRU

UMIAM

CHANDRAPUR

KHLIEHRIAT

KHLIEHRIAT

KHANDONG

HAFLONG

KOPILI

BYRNIHAT

JAGIROAD

UMRANGSO

NECHIPHU

RANGIA

AMINGAON

ROWTA TEJPUR

SAMAGURI

MARIANI

BALIPARA GOHPUR

POWER MAP OF BANGLADESH AND INDIA

GANGTOKRANJIT

TEESTA-VTALA

LHAO

KAMENGKHUPI

SURYAMANINAGAR

SILCHAR

400kV at 132kV

PALLATANA

AZARA

Page 30: Y K Sehgal Transmission Development-India

BOGRASOUTH

BHERAMARA

NAOGAON

NIAMATPUR

FARRAKA

SUBHASGRAM

KATWA

GOKARNA

JEERATKHULNA(SOUTH)

BOTTAIL

BAHARAMPUR

CH. NAWABGANJ

RAGHUNATHGANJ

KA

HA

LGA

ON

SAGARDIGHI

RAJSHAHI

BAHARAMPURISHURDI

NATORE

KHEJURIA

FARIDPUR

BAGHABARIGHORASAL

MA

DH

OP

UR

SHAHJADPABNA PUR

SIRAJGANJ

BOGRA

INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS

400 kV230 kV132 kV

THE PROJECTLEGEND

BAKRESHWAR

KOLAGHAT

INDIA400kV D/c

(400 KV)

BANGLADESH

MALDA

DHULIAN

DURGAPUR

ExistingUnder Constr. / Future

JAYPURHAT BARAPUKURIA

Page 31: Y K Sehgal Transmission Development-India

INTERCONNECTION OF INDIA WITH SRI LANKA

Page 32: Y K Sehgal Transmission Development-India

• Installed Capacity : 2411 MW

(Hydro – 50%, Thermal-46% )

• Maximum Demand : 1922MW

• Demand Growth : 8 %

• Hydro potential : 2000 MW, out of which 1000 MW already harnessed

EMBILIPITIYA

MATARA

GALLE

DENIYAYA

SAMANALAWEWA

BALANGODA

MATUGAMA

PANADURA

RANTEMBE

RANDENIGALA

VICTORIA

INGINIYAGALA

AMPARA

BOWATENNA

UKUWELA

KIRIBATHKUMBURA

KOTMALE

WIMALASURENDRABADULLA

N'ELIYA

MADAMPE

BOLAWATTA

THULHIRIYA

KURUNEGALA

VEYANGODA

BIYAGAMA

ORUWALA

KOLONNAWA

KOTUGODA

RATMALANA PANNIPITIYA

TRINCOMALEE

ANURADHAPURA

PUTTALAM HABARANA

RATMALANA

PANNIPITIYA

ORUWALA

BIYAGAMA

FORT

KOLLUPITIYA

KELANITISSA

KOLONNAWA

S'KANDA

132kV : Underground Cable132kV Line

220kV Line

POLPITIYA

NEWLAXAPANA

CANYON

KELANIYA

KOTUGODA

SAPUGASKANDA

KELANITISSA

KHD

KOSGAMA

VAVUNIA

POLONNARUWA

HAMBANTOTA

LAKDANAWI

LAXAPANA

SITHAWAKA

220/132 kV Sub Station 132kV GS Hydro Power Station Thermal Power Station

NEW ANURADHAPURA

Sri Lanka Transmission System

BARGE PS

CHUNNAKAM

KILINOCHCHI

VALACHCHANAI

132kV Line (not in operation)

Sri LankaSri Lanka : Present Power Scenario: Present Power Scenario

Page 33: Y K Sehgal Transmission Development-India

POWER MAP OF INDIA & SRILANKA

AP1

RENIGUNTA

KARWAR

KUDRE

HASSAN

DAVANGERE

TAIL RACE

SHARAVATHI

SIRSI KAIGA

KEMAR

MANGALORE

VARAHI

SHIMOGA

MUKH

TALAGUPPA

BANGALORE

C.DURGA

TIPTURHONALI

KA3

KA2

ANANTAPUR

HIRIYUR

KOLAR

AP3

TN3

HINDUPUR

AP4

CHITTOOR

TN1

NARENDRA

HAVERI

A'WADI

KADRA

KALINADI

PONDATO

KODASALLI

HUBLI KURNOOL

GOOTY

RAICHUR

MUNIRABAD

MUDDANURKRISHNAPATANAM

TN6. VILLUPURAM

KE1. PALAKKADKE2. KANIYAMPETAH

TN2. VINNAMANGALAM

TN4. KRISHNAGIRITN3. HOSUR

TN5. TV MALAI

TN1. THIRUVALEM

TN8. PERAMBULURTN7. SINGARAPET

SRIPERUMBUDUR

SULURPET

NELLORE

ALAMANTHI

ENNORE

KADAPERI

N MADRAS

VIJAYAWADA

NEYVELI EXTN.

PUDUKOTTAI

PARAMAKUDI

VILLUPURAM

KARAIKUDI

NEYVELI

BRAHMAPURAM

KOZHIKODE

KALAMASSERI

IDUKKI

PALLOM

KAYAMKULAM

EDAMON

TRIVANDRUM

NORTH TRICHUR

KANNUR

L PERIYAR

KASARAKODE

SATHURSABARGIRI

TIRUNELVELI

ZIRCONUM

TUTICORIN

UDUMELPET

TIRUPPUR

THENI

METTUR

MUV'ZHA

THUDIYALURKE1

KE2

PYKARA

KUNDAH

TN10

TN11

TN12

ARASUR

MYSORE

TK HALLI

H HALLI

TN7

TCGODU

PUGALUR

SALEM

MADURAI

INGUR

TN9

TRICHY

TN8

TN5

ATHUR

TN4 TN2

ARANI

TN12. GC PALAYAM

TN10. KADAMPARAITN9. SAMAYAPURAM

TN11. SEMPATTY

LEGEND

ACHARAPAKKAM

PONDICHERRY

BAHOUR

CUDDALORE

P P NALLURMYLADUTHURAI

THANJAVUR

VILLIANNOR

THIRUVARUR

KALPAKKAMSP KOIL

KUDANKULAMNAGARCOIL

400kV lines

132kV lines

MALEKOTTAIYUR

KILINOCHCHI

ANURADHAPURA

KURUNEGALA

KOSGAMA

SITHAWAKA

POLPITIYA

DENIYAYA

S APUGAS-

PANNIPITIYA

ORUWALA

BIYAGAMA

VEYANGODA

THULHIR IYA

PUTTALAM

MATUGAMA

GALLE

KOTUGODABOLAWATTA

KOLONNAWA

RATMALANA

PANADURA

KELANITISSA

MADAMPE

CHUNNAKAM

VALACHCHANAI

SAMANALAWEWA

EMBILIPITIYA

MATARA HAMBANTOTA

POLONNARUWA

BOWATENNA

UKUWELA

VICTORIA

RANDENIGALA

N'ELIYA

BALANGODA

KIRIBATHKUMBU RA

WIMALASURENDRA

KOTMALE

NEW

CANYON

LAXAPANA

HABARANA

RANTEMBEBADULLA

INGIN IYAGALA

AMPARA

TRINCOMALEE

VAVUNIA

NEW ANURADHAPURA

RAICHUR

RAICHUR

N'SAGAR N'SAGAR

FROM TALCHER

-KANDA

LAXAPANA

220kV lines

HVDC BIPOLE

UNDER GROUNDCABLE

AP1. MYDUKURAP2. NANDYALAP3. YERRAGUNTLAAP4. KALIKIRIKA1. HIRIYURKA2. GOWRIBIDANOORKA3. DB PUR

India India –– Sri Lanka Sri Lanka interconnectioninterconnection

• Madurai –Anuradhapura HVDC Bipole Line with :

1x500MW HVDC Terminal (Stage-I) 2x500 MW HVDC Terminal (Stage-II)

Quantum of Power Quantum of Power Exchange : 1000 MWExchange : 1000 MW

Proposed InterconnectionProposed Interconnection

Page 34: Y K Sehgal Transmission Development-India

India : Interconnection with Sri LankaIndia : Interconnection with Sri Lanka

185 Kms

50 Kms

150 Kms

Proposed Route for Interconnection

Madurai

Rameshwaram

Anuradhapura

Talaimannar

Page 35: Y K Sehgal Transmission Development-India

FILTER

TRANSFORMER VALVES

SM REACTOR

OVERHEAD OVERHEADCABLE

Proposed HVDC Interconnection Proposed HVDC Interconnection –– Initial StageInitial Stage

METALIC METALIC RETURN CABLERETURN CABLE

FILTER

Page 36: Y K Sehgal Transmission Development-India

FILTER

TRANSFORMER VALVES

SM REACTOR

OVERHEAD OVERHEADCABLE

Proposed HVDC InterconnectionProposed HVDC Interconnection

METALIC METALIC RETURN CABLERETURN CABLE

OVERHEAD OVERHEADCABLE

FILTER

FILTER

FILTER

Page 37: Y K Sehgal Transmission Development-India

INTERCONNECTION OF INDIA WITH BHUTAN

Page 38: Y K Sehgal Transmission Development-India

• For import of power from Chukha HEP (4x84 MW)

– Chukha – Birpara 220kV 3 ckts

• For import of power from Kurichu HEP (4x15 MW)

– Kuruchu - Geylegphug(Bhutan) – Salakati(NER) 132 kV S/c

• For import of power from Tala HEP (6x170 MW = 1020 MW)

– Tala – Siliguri 400kV 2x D/c line

India India -- Bhutan : Existing InterconnectionsBhutan : Existing Interconnections

Page 39: Y K Sehgal Transmission Development-India

• Hydro Potential in Bhutan : About 21000 MW

• About 11,000MW identified to be implemented in future– Punatsangchu –I : 1200 MW– Punatsangchu –II : 1000 MW– Mangdechu : 720 MW– Sankosh : 4000 MW– Chamkhar Chu -I : 670 MW– Kurigongre : 1800 MW– Amochu : 620 MW– Kholongchu : 486 MW– Wangchu : 900 MW– Bunakha : 180 MW

• Major portion of power from the future generation projects in Bhutan is envisaged to be imported into Indian grid.

• The 1st of the future projects to be commissioned in Bhutan is Punatsangchu-I (1200 MW) in 2014-15.

India India -- Bhutan : Future PotentialBhutan : Future Potential

Page 40: Y K Sehgal Transmission Development-India

India India –– Bhutan InterconnectionBhutan Interconnection

Page 41: Y K Sehgal Transmission Development-India

INTERCONNECTION OF INDIA WITH NEPAL

Page 42: Y K Sehgal Transmission Development-India

India - Nepal : Present Interconnection

Power Scenario in NepalInstalled Capacity : 607MW (Hydro – 91%)Demand : 600 MW

Over 16 links at 132/33/11 kVAbout 50 MW of power being exchangedNet export to Nepal (about 10% of demand of Nepal met from India)

Supply of 70MU/annum from Tanakpur (India) to Nepal

Page 43: Y K Sehgal Transmission Development-India
Page 44: Y K Sehgal Transmission Development-India

India – Nepal : Future• A 400 kV inter-connection (initially op. at 220kV level)

between Muzaffarpur(India) and Dhalkebar(Nepal) planned

• The scheme is to be developed by a private developer (IL&FS) in participation with POWERGRID

• For its implementation, two separate JV companies, one for Indian portion (ILFS, PTC, POWERGRID) and other for Nepalese portion (ILFS, PTC, NEA) are proposed

• Two separate DPRs for Indian and Nepalese portion have been prepared by POWERGRID and submitted to IL&FS in Feb-09 & March-09 respectively

• Formation of Joint Venture is under progress

Page 45: Y K Sehgal Transmission Development-India

India India –– Nepal : FutureNepal : Future

• Hydro Potential of Nepal : about 80,000 MW

• Large potential projects being considered for development and export of power to India

– Karnali - 10,800 MW

– Pancheshwar HEP - 6,500 MW

– Sapta Koshi - 3,300 MW

– Arun HEP - 1,000 MW

– West Seti HEP - 750 MW

– Arun HEP - 685 MW

– U. Marsyangdi – 2 - 600 MW