work packages & estimates

Upload: alex

Post on 05-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/15/2019 Work Packages & Estimates

    1/7

  • 8/15/2019 Work Packages & Estimates

    2/7

  • 8/15/2019 Work Packages & Estimates

    3/7

  • 8/15/2019 Work Packages & Estimates

    4/7

    Managing Engineering & Construction Projects Chapter 3 - Work Packages & Estimates

    Copyright 2001 The Hampton Group, Inc. All rights reserved 50

    ! 7.4m Space Capacity Plant

    ! Site purchased meet JITD 30x30

    ! JITD Specification approved by VPMK

    ! Signed contract with REC

    ! 5 site alternates meet JITD spec

    ! Site location approved by VPOP

    ! Site purchase executed by CFO

    This set of achievements will form the basis for the contract with the Real Estate Consultant (REC) and details the performanceexpectations that will be the core of the contract. We show the development of the 30x30 specifications (within 30 miles of theCanadian border and within 30 miles of the Burlington Airport and additional requirements for the “Just in time delivery.” Then weask the realtor for 5 sites that meet those specs and move on to final approval. By using these achievements we clearlycommunicate our expectations to the realtor and also provide a basis for that professional to estimate the hours required to deliverthem.

    Now let’s look at the subdivision of the next second level achievement into its supporting sub-achievements.

    ! Plant approved for construction by VPOP

    ! Signed contract with Architectural/Engineering firm

    ! Building design approved by VPOP! GC contracted per design spec! City/State/Federal Permits/Approvals Issued

    The approach in the above achievements is similar, with the outside contractor, an architectural/engineering firm, responsible for thefacility design and then executive approvals of their work. Each of these achievements specifies an end result; not all the steps

    necessary to reach that end result. As an example the last achievement on government approval/permits does not tell the individual(probably from the General Contractor) what permits and approvals to get. We’ve laid out the just the end result because that is whatwe will manage. In the supporting project documentation, we’ll maintain a listing of the approvals but only in rare cases would weschedule and track the application process for each permit or approval. Far better to hold people accountable for end results than foractivities.

    Now we’ll move down and look at the detail supporting the third sub-achievement.

    ! Plant structure and systems meet design specs

  • 8/15/2019 Work Packages & Estimates

    5/7

    Managing Engineering & Construction Projects Chapter 3 - Work Packages & Estimates

    Copyright 2001 The Hampton Group, Inc. All rights reserved 51

    ! Site prepared for foundation to meet specs

    ! Foundations set to meet specs

    ! Underground utilities installed to meet specs

    ! Floor set to meet specs

    ! State Inspect. & A/E approve foundation to meet specs

    ! Steel frame & roof 100% to meet specs

    ! Exterior shell & insulation 100% to meet specs

    ! Main Electric Xfmr & Service 100% to meet specs

    ! Rooftop HVAC 100% to meet specs

    ! State Inspect. & A/E approve shell

    ! Rooftop HVAC supply heat to meet specs! Electric distribution in production area to meet specs

    ! Electric distribution system to meet specs

    ! HVAC air distribution production area to meet specs! HVAC air distribution to meet specs! Interior office 100% complete to meet specs

    ! Fire & life safety systems to meet specs! Certificate-of-Occupancy issued by State Inspector! Architect signs-off on As-built docs

    The preceding achievements are all tied to meeting design specifications and inspections. Later we will make the decisions on howmuch additional detail the plan needs. Certain lengthy achievements with durations of more than 6 weeks may be broken down intosmaller work packages for scheduling and tracking purposes. Other short duration achievements may be bundled in one large workpackage for the same purpose.

    Here’s the last set of supporting sub-achievements:

    ! Prod. line 1-2-3 environment meet specs• Air quality exceeds specs

  • 8/15/2019 Work Packages & Estimates

    6/7

  • 8/15/2019 Work Packages & Estimates

    7/7

    Managing Engineering & Construction Projects Chapter 3 - Work Packages & Estimates

    Copyright 2002 The Hampton Group, Inc. All rights reserved 53

    The level of input and output required from the resource (whether from the customer’s staff, the PM’s own organization or acontractor) to complete the package will depend on their level of involvement in the project. We’ll define level of involvement of a

    team resource at three levels.Resource Involvement

    Level ofInvolvement

    Description Work Package ElementsProvided by Resource

    Participation Requires technical judgment for an adaptive solution. Resourceprovides the majority of the work package information.

    70 to 100%

    Vendor Requires evaluation of features & specifications related to scope orwork. Usually provides “Approach”, “Output” and “Issues” elements.

    40 to 60%

    Commodity Output requirements readily available and similar from a multitude ofresources. Usually provides price only.

    10%

    We will rely very heavily on the technical and professional judgments of certain of our team members. Others may be asked only toprovide a price.

    Example of resource involvement levels

    Participation Vendor Commodity Production Engineer

    Architect/Engineer

    General Contractor

    Real Estate Consultant

    Production Equipment Supplier

    Distribution Supervisor

    Raw Material Supplier

    Plumbing Contractor

    Landscape Contractor