weekly progress report update w/e 19 th june 2015
TRANSCRIPT
![Page 1: Weekly progress report Update w/e 19 th June 2015](https://reader036.vdocuments.us/reader036/viewer/2022082610/56649d745503460f94a542dd/html5/thumbnails/1.jpg)
Weekly progress report
Update w/e 19th June 2015
![Page 2: Weekly progress report Update w/e 19 th June 2015](https://reader036.vdocuments.us/reader036/viewer/2022082610/56649d745503460f94a542dd/html5/thumbnails/2.jpg)
High-level project planWeek 1 Week 2 Week 3 Week 4 Week 5
w/c 1 June w/c 8 June w/c 15 June w/c 22 June w/c 29 June
PMO
Service work streams
Enabler work streams
Submission to NCM Team
Agree MLAFL Board
Agree MLAFL Terms of Reference
Develop PID Develop business case template
Develop project plan template
Second meeting with work stream leads
Create initial draft value proposition
Finalise value propositions
Develop project charters for each work stream
Finalise project plans
Meet with work stream leads
Create initial draft project plan
Checkpoint to agree approach
MALFL Board Milestone
Agree submission to NCM team
Submission to NCM Team
Create initial draft value proposition
Agree project charters
Create initial draft project plan
Meet with work stream leads
Finalise value propositions
Finalise project plans
Develop project charters for each work stream
Agree work streams and membership
![Page 3: Weekly progress report Update w/e 19 th June 2015](https://reader036.vdocuments.us/reader036/viewer/2022082610/56649d745503460f94a542dd/html5/thumbnails/3.jpg)
Progress this week
Activity Work stream Progress to date Priorities next week
PMO All Continued to refine and started to complete value propositions for each work stream.
Complete value propositions for each work stream.
All Refined the business case structure based on discussion with the NCM team and input from the MLAFL board.
Write up business plan and implementation plan.
All Finalised work streams and membership.
Continued to build on the initial project plan templates.
Create an interdependencies map for all the work streams.
All Agreed governance, work streams, sponsors and leads, and the sign off process for the business case with MLB.
Service work streams
Prevention and Early Intervention
First draft of final value proposition. Complete value proposition.
Integrated Single point of access
Completed value proposition.
Integrated locality teams First draft of final value proposition. Complete value proposition.
Clinical services review First draft of final value proposition. Complete value proposition.
![Page 4: Weekly progress report Update w/e 19 th June 2015](https://reader036.vdocuments.us/reader036/viewer/2022082610/56649d745503460f94a542dd/html5/thumbnails/4.jpg)
Progress this week
Activity Work stream Progress to date Priorities next week
Enabler work streams
All Work streams finalised.
Meetings arranged for next week.
2-hour meetings scheduled for Tuesday 23rd and Wednesday 24th June – to confirm project plans and provide details regarding activities and costs.
Email and circulate project plans for final comments.
Please note: the workstreams are in the process of being finalised.
![Page 5: Weekly progress report Update w/e 19 th June 2015](https://reader036.vdocuments.us/reader036/viewer/2022082610/56649d745503460f94a542dd/html5/thumbnails/5.jpg)
Milestone tracking
Key milestones Due date RAGRevised date (if slipped) Comments / Mitigation actions
Agree MLAFL board 5/6/2015 G Completed
Agree MLAFL board terms of reference 5/6/2015 G Completed
Develop Implementation Plan template 5/6/2015 G Completed
Develop Business Case template 12/6/2015 G Completed
Agree Work Streams and key membership 12/06/2015 G 17/06/2015 Completed
Initial meeting with service work stream leads 12/06/2015 G 17/06/2015 Completed
Create draft value propositions- service work streams 12/06/2015 A 18/06/2015
Agree Governance Structure 12/06/2015 G Completed
Initial meeting with enabler work stream leads 19/06/2015 A 24/06/2015 Meetings on 23rd and 24th June
Create initial draft project plans – enabler work streams. 19/06/2015 A 24/06/2015
Finalise value propositions – service work streams 26/06/2015 G
Finalise project plans – service work streams 26/06/2015 G
Finalise project plans – enabler work streams 26/06/2015 G
Finalise business case 26/06/2015 G
Approve business case and submit 30/06/2015 G
![Page 6: Weekly progress report Update w/e 19 th June 2015](https://reader036.vdocuments.us/reader036/viewer/2022082610/56649d745503460f94a542dd/html5/thumbnails/6.jpg)
Key risks / issues
RAG status Definition
Red (R) ■ The risk / issue requires immediate remedial action to prevent significant slippage in the timetable OR action is being taken to resolve but is not considered appropriate and/or timely.
Amber (A) ■ The risk / issue has been noted and appropriate action is being taken to resolve to prevent significant slippage in the timetable.
Green (G) ■ The risk/ issue has been noted and appropriate action is being taken to resolve and/or the impact on the timetable is considered minimal.
Workstream Description MitigationRAG last week
RAG this week
Risks
All Given the short timeframes for creation and submission of the business case, failing to attend meeting appointments may result in the deliverability of the Business Case and the Value Proposition being delayed.
Keeping to deadlines and meeting outside of normal hours. n/a R