waste not want not
TRANSCRIPT
Waste Not, Want Not: The Inefficient
Design of Today’s Data CentersChris Crosby, CEO, Compass Datacenters
Who We Are
2
• Compass Datacenters provides dedicated data centers
• Built using our patent pending architecture• Uptime Institute Tier III certified design and constructed
• LEED certified
• Geographically independent• The building is the module
• Simplify Capacity Planning• Growth in 1.2MW Increments
• Control• Ownership or lease
• Operations and security
• Expansion
2
The Big Myth
3
• Myth: Scale is needed to drive out cost
• Truth: Product mentality is needed to drive out cost
Hidden Inefficiencies
Capital
Materials
Land
Natural Resources
4
• How much is your data center? Easy to answer• What is included? Hard to answer
Capital
• Monolithic Modular structures
• $20-$100 million is spent on four walls and a roof
• #1 killer of new projects is the shell to hold the 20 year plan
• A “real” modular solution would allocate capital as
needed
• Freeing funds for other uses until needed
• Not accounting, it’s common sense
5
Land I
• Monolithic facilities aren’t land efficient
• Eliminate the option value
• Ability to use land for other purposes
• Destroys the advantage of an appreciating asset
6
Land II
7
Trees? Who Needs Trees?
Materials
• Lack of standard designs drives materials waste• “Standard” usually just a starting point for customization
discussions
• Reason Uptime checks every facility as part of its process
• How much concrete and steel does it take to build a 100,000 square foot facility?• Does anyone know?
• What is known:• Production of 1 cubic yard of concrete generates 400 lbs of CO2
• Ex: 6” slab on a 200K square foot building requires 3700 yards of concrete
• Production generates 740 tons of CO2
• Production of 1 ton of steel generates 1.9 tons of CO2
• Ex: 440 tons of steel required for a 200K square foot building
• Production generates 840 tons of CO2
8
Resource Inefficiencies
• Water
• Chemical treatment requirements
• Added cost
• Eco impact
9
9
*National Renewable Energy Lab
**James Hamilton, Amazon
“Just because you’re paranoid…”
The Problem is Already Solved
• Expanded ASHRAE Range
• Lessens cooling requirement
• Enhances Airside as an alternative
• Every solution doesn’t have to come from within
10
A Universal Alternative
11
• Even Houston has over 3600 hours
12
• Adiabatic cooling should be perfect in New Mexico
• Hot and dry
• Free cooling benefits in summer and winter
No Adiabatic System: 1877 free cooling hours
With Adiabatic System: 8380 free cooling hours
Check Your Math
13
Free Cooling Hours Estimated Cost Saving - New Mexico
75 F Supply Air - Normal 75F Supply Air - Adiabatic
Mech Hours 6883 380
Mech Cooling kWh 1,720,750 95,000
Mech Cooling $ $99,804 $5,510
Saving $ $94,294
Capital Cost -$500,000
10 year saving $442,935
Energy Cost ($/kWh) 0.058 $/kWh
Cooling Overhead Assumption 0.25
IT kW Load 1250kW
The Actual Cost
14
• Have to include:
• Discounted future savings (NPV)
• System maintenance
• Cost of water and water treatment
• Adiabatic installation results in NPV -$430k
• Power cost $0.058 / kWh
• Water cost $22 per 1,000
Gal
• 7% discount rate
Materials, Land and Capital
• Solving inefficiency requires a productized solution• Built in self-contained increments
• Each is standalone so if you never grow you never need anything else
• Minimize upfront capital requirements
• Preserve the option value of the land
• 100% hardened is the future proof design
• Elements of true standard design• Standard Bill of Materials
• Same for every job
• The facility is built using “kits”
• All quantities pre-determined
• Reduced transportation requirements
• Volume purchase agreements reduce cost
• Reduced disposal requirements
• Standard drawings and processes• More efficient scheduling reduces wasted manpower
• Only deviations are due to local requirements
• We don’t have to reinvent• Many examples (auto industry, aviation, consumer electronics)
15
Data Center Evolution
1616
Customization
• Industry legacy
• Start with a whiteboard each time
Industrialization
• Introduced by Crosby/Smith at Digital
• VPAs, Standard designs
• Some repeatability, supply chain
Productization
• Complete solution – integrated supply chain
• Serves a segment of the market
• Drives out cost, time through lean
• Increases quality, consistent operations
• The Data Center Industry is Here• Can’t Drive Costs Any Lower or Quality Any Higher
• The Required Next Step• Most Providers Can’t Make It
1990’s
2006
2012
Summary
• Most data centers inherently inefficient• Capital
• Land
• Natural Resources
• Materials
• Standard design really isn’t standard• Standard requires:
• Fixed BOM w/ kitted components
• Standard drawings and processes
• Construction and labor efficiency
• Resource inefficient• Water-based cooling is needed for the specialist, not the generalist
• Land inefficiency
• Concrete and steel inefficiency
• Data centers are evolving• Some will not be able to make the “jump”
• We have proof that there is a better way17
18