vlt-min-esp-13520-0186 missionvii paranal 201408 - unige · 6/18! espressoproject! 1.2.1...

18
Name Date Signature Name Date Signature Name Date Signature Name Date Signature ESPRESSO Paranal Mission VII – 201408 Minutes VLTMINESP135200186, Issue 1.0 March 6th, 2015 Prepared Denis Mégevand 06/03/2014 Approved Marco Riva Alexandre Cabral Released Francesco Pepe Centro de Astrofísica da Universidade do Porto Universidade de Lisboa, CAAUL and LOLS INAF, Osservatorio Astronomico di Trieste INAF, Osservatorio Astronomico di Brera Observatory of the University of Geneva Physics Institute, University of Bern Instituto de Astrofísica de Canarias European Southern Observatory

Upload: buinhi

Post on 27-Aug-2019

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

 

Name             Date       Signature  

Name             Date       Signature  

Name             Date       Signature  

Name             Date       Signature  

           

ESPRESSO    

 Paranal  Mission  VII  –  2014-­08  

Minutes  

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0  

March  6th,  2015  

 

 

Prepared   Denis  Mégevand   06/03/2014            Approved   Marco  Riva           Alexandre  Cabral          Released   Francesco  Pepe      

Centro de Astrofísica da Universidade do Porto Universidade de Lisboa, CAAUL and LOLS INAF, Osservatorio Astronomico di Trieste

INAF, Osservatorio Astronomico di Brera Observatory of the University of Geneva

Physics Institute, University of Bern Instituto de Astrofísica de Canarias

European Southern Observatory

Page 2: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

2/18   ESPRESSO  Project  

Change  Record  Issue/Rev.   Date   Section/Page  affected   Reason/Remarks  

0.10   22/08/2014     First  partial  version  0.20   23/08/2014     Second  partial  version  0.30   24/08/2014     Idem  w/  added  pictures  0.40   29/08/2014     Third  partial  version  1.0   06/03/2015     Homogenize  formats  

   Co-­‐authors:    Marco  Riva,  Alexandre  Cabral,  Matteo  Aliverti,  Gaspare  Lo  Curto,  Manuele  Moschetti,  Gerardo  Avila      

   

Page 3: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   3/18    

Table  of  Contents  Chapter  1.   Introduction  ..............................................................................................................................................  5  1.1  Scope  of  the  Document  ........................................................................................................................................................  5  1.2  Documents  ................................................................................................................................................................................  5  1.2.1   Applicable  Documents  ................................................................................................................................................................  6  1.2.2   Reference  Documents  ..................................................................................................................................................................  6  

1.3  Acronyms  and  Abbreviations  ...........................................................................................................................................  6  1.3.1   Acronyms  ..........................................................................................................................................................................................  6  1.3.2   Abbreviations  ..................................................................................................................................................................................  6  

Chapter  2.   Generalities  ...............................................................................................................................................  8  2.1  Scheduled  period  ....................................................................................................................................................................  8  2.2  Teams  ..........................................................................................................................................................................................  8  

Chapter  3.   Minutes  .......................................................................................................................................................  9  3.1  Wednesday  August  20th  .......................................................................................................................................................  9  

Facts  and  Debriefing  .......................................................................................................................................................................................................  9  Issue  of  the  day  ..............................................................................................................................................................................................................  10  Plan  for  03/07  ................................................................................................................................................................................................................  10  

3.2  Thursday  August  21st  ........................................................................................................................................................  11  Debriefing  .........................................................................................................................................................................................................................  11  Issue  of  the  day  ..............................................................................................................................................................................................................  11  Plan  for  22-­‐08  .................................................................................................................................................................................................................  11  

3.3  Friday  August  22nd  ..............................................................................................................................................................  12  Debriefing  .........................................................................................................................................................................................................................  12  Issue  of  the  day:  .............................................................................................................................................................................................................  12  Plan  for  23-­‐08  .................................................................................................................................................................................................................  12  

3.4  Saturday  August  23rd  .........................................................................................................................................................  12  Debriefing  .........................................................................................................................................................................................................................  12  Issue  of  the  day:  .............................................................................................................................................................................................................  13  Plan  for  24-­‐08  .................................................................................................................................................................................................................  13  

3.5  Sunday  August  24th  .............................................................................................................................................................  13  Debriefing  .........................................................................................................................................................................................................................  13  Issue  of  the  day:  .............................................................................................................................................................................................................  13  Plan  for  25-­‐08  .................................................................................................................................................................................................................  14  

3.6  Monday  August  25th  ...........................................................................................................................................................  14  Debriefing  .........................................................................................................................................................................................................................  14  Issue  of  the  day:  .............................................................................................................................................................................................................  14  Plan  for  26-­‐08  .................................................................................................................................................................................................................  14  

3.7  Tuesday  August  26th  ..........................................................................................................................................................  14  Debriefing  .........................................................................................................................................................................................................................  14  Issue  of  the  day:  .............................................................................................................................................................................................................  15  Plan  for  27-­‐08  .................................................................................................................................................................................................................  15  

3.8  Wednesday,  August  27th  ...................................................................................................................................................  15  Debriefing  .........................................................................................................................................................................................................................  15  Issue  of  the  day:  .............................................................................................................................................................................................................  15  Plan  for  28-­‐08  .................................................................................................................................................................................................................  15  

3.9  Thursday,  August  28th  .......................................................................................................................................................  16  Debriefing  .........................................................................................................................................................................................................................  16  Issue  of  the  day:  .............................................................................................................................................................................................................  16  Plan  for  29-­‐08  .................................................................................................................................................................................................................  16  

3.10  Friday,  August  29th  ...........................................................................................................................................................  16  Debriefing  .........................................................................................................................................................................................................................  16  

3.11  Things  raised  pending  on  decision  or  investigated  during  the  mission  ...................................................  16  Chapter  4.   Conclusions  of  the  mission  ...............................................................................................................  18        

Page 4: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

4/18   ESPRESSO  Project  

List  of  Figures  Figure  1  Material  reception  and  transport  to  CCL.  ...............................................................................................................  9    

Page 5: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   5/18    

Chapter  1.     Introduction  

 

1.1    Scope  of  the  Document  After  the  first  mission  launching  the  preparation  activities  in  the  Combined  Coudé  Laboratory  which  took  place  beginning  of  July  2014,  and  during  which  the  plates  for  the  Vacuum  Vessel  and  the  Front-­‐End  Unit  were  installed,  a  second  installation  mission  took  place  in  August  2014,  to  install  the  Front-­‐End  structure  and  the  Coudé  Train  L11  interface  plates,  which  also  are  the  closing  frames  of  the  incoherent  light  ducts  .    This  document  lists  the  actions  undertaken  at  Paranal  by  the  consortium,  during  this  visit  of  August  2014.  It  lists  also  the  various  points  addressed  during  meetings,  with  actions  items  decided  and  decisions  taken.  

1.2    Documents  The  main  applicable  and  reference  documents  are  listed  hereafter.  

Page 6: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

6/18   ESPRESSO  Project  

1.2.1 Applicable  Documents  AD-­1   ESPRESSO  Statement  of  Work   VLT-­‐SOW-­‐ESO-­‐13520-­‐5059   1   01.02.2011  AD-­2   ESPRESSO  Technical  

Specifications  VLT-­‐SPE-­‐ESO-­‐13520-­‐4633   3   01.02.2011  

AD-­3   ESPRESSO  Project  Plan   VLT-­‐PLA-­‐ESP-­‐13520-­‐0007   5   25.03.2013  AD-­4   ESPRESSO  Management  Plan   VLT-­‐PLA-­‐ESP-­‐13520-­‐0015   4   25.03.2013  

1.2.2 Reference  Documents  RD-­1   ESO-­‐Paranal  Observatory  ICD   VLT-­‐ICD-­‐ESO-­‐13529-­‐5412   2   25.03.2013  RD-­2   Upgrades  to  Paranal  

Observatory  Technical  Infrastructure  

VLT-­‐TRE-­‐ESO-­‐13529-­‐5411   2   25.03.2013  

1.3    Acronyms  and  Abbreviations  The  main  acronyms  and  abbreviations  are  listed  hereafter.  

1.3.1 Acronyms  AD   Applicable  Document  AI   Action  Item  CCL   Combined  Coudé  Laboratory  CPR   Computer  Room  CR   Coudé  Room  ESPRESSO   Echelle  Spectrograph  for  Rocky  Exoplanets  and  Stable  Spectroscopic  Observations  FES   Front-­‐End  Structure  FE(U)   Front-­‐End  (Unit)  LFC   Laser  Frequency  Comb  LT   Laser  Tracker  PLO   Paranal  La  Silla  Observatory  PM   Project  Manager,  Progress  Meeting  RD   Reference  Document  SCP   Service  Connection  Point  SE   System  Engineer  TC   Teleconference  UPS   Uninterrupted  Power  Supply  UT   Unit  Telescope  VLT   Very  Large  Telescope  VV   Vacuum  Vessel  WP(M)   Work  Package  (Manager)    

1.3.2 Abbreviations  ACA   Alexandre  Cabral  (ESP)  DME   Denis  Mégevand  (ESP)  FGO   Fréderic  Gonté  (PLO)  

Page 7: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   7/18    FLU   Fernando  Luco  (PLO)  GAV   Gerardo  Avila  (ESO  ESP)  GLC   Gaspare  Lo  Curto  (ESO)  HBA   Hermann  Barrios  (CONYSER,  civil  work)  HUG   Hugo  Guttierez  (CONYSER,  warehouse)  ICO   Igor  Coretti  (ESP)  IHU   Ian  Hughes  (ESP)  MAL   Matteo  Aliverti  (ESP)  MMI   Manuele  Moschetti  (ESP)  MPO   Matteo  Pozzobon  (PLO)  MRI   Marco  Riva  (ESP)  MSC   Marcel  Schroeder  (CONYSER,  warehouse)  MTA   Mario  Tapia  (PLO)  ODI   Oscar  Diaz  (CONYSER,  civil  work)  PBO   Pierre  Bourget  (PLO)  RCA   Robin  Capocci  (PLO)    

Page 8: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

8/18   ESPRESSO  Project  

Chapter  2.     Generalities  This  section  presents  generalities  concerning  the  visit  made  at  Paranal  in  August  2014.  

2.1    Scheduled  period  The  mission  extended  over  the  period  from  August  20th  to  August  29th.    Some  people  attended  partly  the  mission,  due  to  their  schedule  or  to  the  need  of  their  presence.  This  is  indicated  in  the  composition  of  the  team  hereafter.  

2.2    Teams  The  team  attending  this  “plate  installation”  mission  in  Paranal  was  composed,  for  the  consortium,  by:    

• Matteo  Aliverti  (MAL),  Front-­‐End  Unit  WPM,  20.08.14  -­‐  25.08.14  • Gerardo  Avila  (GAV),  Paranal  Interfaces  WPM,  24.08.14  -­‐  30.08.14  • Alexandre  Cabral  (ACA),  Interfaces  Engineer,  Coudé  Train  WPM,  20.08.14  -­‐  29.08.14  • Denis  Mégevand  (DME),  Project  Manager,  20.08.14  -­‐  29.08.14  • Manuele  Moschetti  (MMI),  Front-­‐End  Unit,  20.08.14  -­‐  29.08.14  • Marco  Riva  (MRI),  Deputy  System  Engineer,  20.08.14  -­‐  29.08.14  

 And  for  the  customer  ESO  by:    

• Gaspare  Lo  Curto  (GLC),  Project  Contact,  20.08.14  -­‐  23.08.14    The  ESO  staff  members  and  contratists  met  at  Paranal  were:    

• Pierre  Bourget  (PBO),  engineering;  • Robin  Capocci  (RCA),  security;  • Oscar  Diaz  (ODI)  CONYSER;  • Fréderic  Gonté  (FGO),  instrumentation  enginer,  ESPRESSO  Paranal  contact  person  • Hermann  Barrios  (HBA),  CONYSER;  • Hugo  Guttierez  (HGU),  warehouse;  • Fernando  Luco  (FLU),  civil  engineering;  • Marcel  Schroeder  (MSC),  warehouse;  • Mario  Tapia  (MTA),  responsible  of  the  mechanical  workshop;  

Page 9: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   9/18    

Chapter  3.     Minutes  This  visit  intended  to  be  focused  on  two  subjects,  the  installation  of  the  structure  of  the  Front-­‐End  and  the  installation  of  CT  interface  plates  in  the  CCL,  called  L11  frames.  Nevertheless,  some  discussions  were  foreseen  on  other  subject  like  the  Coude  Train  CREs  and  some  still  open  points  concerning  the  scheduling  of  next  activities,  in  Europe  and  in  Paranal.    The  daily  work  had  as  usual  to  be  scheduled  daily  to  take  into  account  the  presence  and  availabilities  of  the  Paranal  contact  persons,  and  the  constraints  of  the  Paranal  operations.      During  his  presence,  GLC  attended  the  9:00  and  16:30  daily  meetings  to  coordinate  with  Paranal  activities.  After  his  arrival,  GAv  took  avier  this  task.  In  between,  DME  ensured  the  interim.      At  the  end  of  every  day,  we  had  a  debriefing  meeting  to  summarize  the  addressed  points,  the  conclusions,  agree  on  the  conclusions  to  be  reported  in  the  minutes  and  to  prepare  the  plan  for  the  next  day.    This  daily  work  is  reported  in  these  minutes.  They  are  therefore  presented  chronologically,  with  inclusion  of  the  meetings  minutes,  when  relevant.  

3.1    Wednesday  August  20th  

Facts  and  Debriefing  

• Trip  from  Santiago  of  the  following  consortium  members:  o Matteo  Aliverti  o Alexandre  Cabral  o Denis  Mégevand  o Manuele  Moschetti  o Marco  Riva  

• Our  material  arrived  one  day  in  advance,  on  Tuesday  19th.  GLC  received  it  and  managed  the  unloading  and  transportation  to  the  CCL.  

                     

Figure  1  Material  reception  and  transport  to  CCL.  

• Security  induction  course  with  the  security  officer,  Robin  Capocci  (RCO)  for  MMI  and  ACA.  

Page 10: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

10/18   ESPRESSO  Project  

• Got  their  security  material  at  the  warehouse  • We  have  been  assigned  two  cars,  number  75  and  159.  The  159  is  missing,  borrowed  by  the  

contratists.  We  got  the  99  instead.  • GoPro  timelapse  camera  installation  (DME)  • Unpacking  of  the  FEU  structure  (MRI,  MAL,  MMI).  Test  how  to  manipulate  it  with  portable  

crane.  • Calibration  of  the  Laser  Tracker  (LT),  which  was  preliminarily  warmed  up  by  GLC.  • Realigning  of  the  coordinate  system  • Reacquired  the  central  pin  and  some  plates’  holes.  • GLC  and  ACA  had  a  meeting  with  Mario  Tapia  (MTA)    

• Manufacturing  of  the  CT  interface  flanges.  • The  flanges  for  P5,  P6,  P7  L10  and  light  duct  cover  were  presented  and  detailed  to  MTA.  • Mario  remarked  the  need  for  tolerances  to  define  the  manufacturing  strategy  as  well  as  to  

estimate  the  manufacturing  time.  • This  information  is  mandatory  before  moving  forward.  • The   material   to   be   used   (St   1.0038/S235(JR))   is   available   in   Chile,   or   at   least   an  

equivalent  one.  There  is  even  some  stock  for  P5  and  P6  flanges  (to  be  replaced  if  used).  • For  the  profiles  in  P7  and  L10  flanges,  MTA  provided  a  catalog  with  the  profiles  existing  

in   Chile   and   the   CT   team   will   adapt   the   design   to   those   profiles   if   the   decision   to  manufacture  them  in  Paranal  is  taken.  

• MTA  gave  an  estimation  of  required  men-­‐hour  for  the  manufacturing  of  the  parts:  o P5                            15  to      20  men  hours  o P6                            15  to      20  o P7                            35  to      40  o L10                  116  to  138  o Cover              20  to        24  o Others          20  to        25  

• Considering   the   worst   case   and   a   10%   contingency   we   obtain   300  men   hours   for   the  manufacturing  of  these  parts  in  Paranal.  

• The  procurement  of  the  materials  might  take  1  month,  but  some  parts  might  start  earlier  due  to  existing  stock.  

• The  drawings  will  be  detailed  with  all  required  tolerances  for  a  more  accurate  estimation  of  manufacturing  time.  

• The  painting  of  the  parts  (black  mate)  can  be  done  in  Paranal.  The  option  for  the  surface  treatment   shall   be   taken   later   considering   what,   fulfilling   the   requirements,   is   more  appropriate  to  be  done  in  Paranal.  

• The  manpower  in  the  workshop  is  tight.  • Only  15%  of  their  resources  can  be  dedicated  to  projects.    • And  this  must  be  shared  by  all  projects.  • Therefore   it   might   be   more   efficient   to   hire   some   contractors,   possibly   well   known  

personnel  that  already  worked  in  the  workshop.  • Mario  /  Matteo  to  give  indication  on  that.  • They  should  be  contracted  on  a  monthly  basis.  

Issue  of  the  day    

Alex  

Plan  for  03/07  

1. TC  with  FES  manufacturer  

Page 11: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   11/18    

2. Move  LT  to  convergence  point  (Morning)  3. Align  laser  tracker  through  inclinometer  (Morning)  4. Mark  the  feed-­‐through  (Morning)  5. Align  reference  plate  (Morning)  6. Take  measurements  of  CR,  Reference  plate,  Walls,  VV  holes  (Morning)  7. Mount  clock  system  (Morning-­‐Afternoon)  8. Moving  of  the  Laser  Tracker,  recalibration  and  acquisition  of  center  point  (Afternoon)  9. Preliminary  Marking  of  the  holes  through  nominal  position  of  the  laser  tracker  

(Afternoon)  10. Deployment  of  balancer  and  metrology  of  relative  position  of  the  plates  (Afternoon)  

3.2    Thursday  August  21st  

Debriefing    

• 9.30  Check  of  UT2  CR  flange  (Done.  UT  3  and  4  checked  good  result)  • 11.00  ACA,  GLC  and  DME  meeting  with  Pierre  Sansgasset,  Paranal  System  Engineer  

(Done)  • Assemble  alignment  tool  laser,  PRS  200  and  Manta  (Done)  • Mount  alignment  tool  on  ceiling  (Done)  • Mount  clock  alignment  tool  for  FES  (to  be  done)  • Clock  alignment  of  FE  and  lock  of  it  (postponed  to  tomorrow)  • Mount  arms  for  the  clock  (Done)  • Tip  tilt  of  toggling  system  preliminary  check  and  seems  to  be  good  (Done)  • Check  Alex  material  brought  in  the  previous  mission  (partially  done)  • Cut  CR  duct  covers  (Done)  • Measure  L10  diameter  in  the  proper  position  (postponed  to  tomorrow)  • Agreed  of  CT  presentation  of  Alex  to  Paranal  engineers  on  Tuesday  morning  (Done)  • Open  L11  flanges  box  (Done)  • Cross-­‐verification  of  the  L11  template,  frames  and  covers  (ongoing)  

Issue  of  the  day    

• Opening  of  the  L11  flanges  box    • Flanges  not  engraved  

Plan  for  22-­08  

1. Recover  luggage  of  Alex  2. Finalize  the  clock  and  fixation  of  the  structure  3. PRS200  tip  tilt  alignment  4. Laser  pre-­‐alignment  5. Analyze  aperture  on  light  duct  for  ut3  (corridor  and  bodega)  6. Measure  L10  diameter  in  the  proper  position    7. Cross-­‐verification  of  the  L11  template,  frames  and  covers  

Page 12: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

12/18   ESPRESSO  Project  

8. Try  to  detect  the  iron  in  the  wall  9. Discussion  of  management  for  next  months    

3.3    Friday  August  22nd    

Debriefing  

• Recover  luggage  of  Alex  (Done)  • Finalize  the  clock  and  fix  of  structure  (Done)  • PRS200  tip  tilt  alignment  (Done)  • Laser  pre-­‐alignment  (Done  in  tip-­‐tilt)  • Analyze  aperture  on  light  duct  for  ut3  (corridor  and  bodega)  (Done)  • Measure  L10  diameter  in  the  proper  position  (postponed  to  tomorrow)  • Cross-­‐verification  of  the  L11  template,  frames  and  covers  (Done)  • Try  to  detect  the  iron  in  the  wall  (Done)  • Discussion  of  management  for  next  months  (ongoing)  • Measurement  of  UT3  L11  dimension  of  duct  and  iron  detection.  • Contratists  tested  the  vacuum  fixation  for  the  big  driller.  • Contratists  fixed  the  damaged  surface  near  UT4  duct.  • GLC  prepared  the  sending  back  of  the  Laser  Tracker.  • GLC  discussed  with  MPO  concerning  the  point  5  (Duct  aperture).  He  things  it  is  OK  • The  Hilti  threaded  bars  and  resin  is  ordered  for  L11  flanges  fixation.  

Issue  of  the  day:  

• Manuele  computer  fall  down.  

Plan  for  23-­08  

1. Measure  light  duct  at  L10  position  2. Installation  of  the  CR  light  duct  covers  and  targets  3. XY  alignment  of  the  laser  4. Mount  the  pentaprism  and  shine  laser  into  the  tunnels  5. Measure  the  height  of  the  laser  6. Acquire  the  final  reference  of  the  FES  

3.4    Saturday  August  23rd    

Debriefing  

• Measure  light  duct  at  L10  position  (Done)  • Installation  of  the  CR  light  duct  covers  and  targets  (Done)  • XY  alignment  of  the  laser  (Done)  • Mount  the  pentaprism  (Done)  and  shine  laser  into  the  tunnels  (Done)  • Measure  the  height  of  the  laser  (Done)  

Page 13: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   13/18    

• Acquire  the  final  reference  of  the  FES  (not  done,  delayed  to  tomorrow)  • GLC  left  at  16:20  to  Santiago  • Preliminary  clock  encoder  definition  for  all  UTs.  The  alignment  is  done  with  an  error  of  

17  arcsecond  of  tilt  of  the  plane  defined  by  the  four  CR.  This  is  acceptable  but  we  will  try  to  enhance  it  tomorrow  .  

• Management  discussion  to  define  next  missions  and  delta  FDR  schedule.  • The  CT  alignment  sensor  was  tested,  SW  was  debugged.  

Issue  of  the  day:  

• UT3  flange  in  CR  has  one  screw  hole  displaced  by  a  few  mm.    

Plan  for  24-­08  

1. Acquire  the  AS  installed  reference  of  the  FES  2. Improve  the  alignment  of  the  laser  by  shining  to  UT1  and  UT4  CRs  3. Re-­‐center  XY  4. Definition  of  the  clock  encoder  position  for  all  UTs  5. Position  the  pentaprism  height  to  the  mean  height  of  the  CR  duct  centers  6. Preliminary  activities  concerning  the  L11  frames  holes  marking  7. Welcome  Gerardo  

3.5    Sunday  August  24th    

Debriefing  

• Acquire  the  AS  installed  reference  of  the  FES  (almost  done)  • Improve  the  alignment  of  the  laser  by  shining  to  UT1  and  UT4  CRs  (Done)  • Re-­‐center  XY  (Done)  • Definition  of  the  clock  encoder  position  for  all  UTs  (Done  except  UT3)  • Position  the  pentaprism  height  to  the  mean  height  of  the  CR  duct  centers  (postponed)  • Preliminary  activities  concerning  the  L11  frames  holes  marking  (postponed)  • Checking  of  possible  interference  between  template  and  column  (Done:    no  interference)  • Welcome  Gerardo  (Done)  • Visit  of  UWE  • Meeting  with  Frederic  Gonté  

• Run  the  cabling  of  P5-­‐P6  cabinets  along  structure  • Protect  the  P6  mechanism  to  allow  people  to  work  on  M8  without  risks  for  P6.  • No  work  in  Paranal  that  wasn’t  approved  at  a  FDR.  

Issue  of  the  day:  

• UT3  flange  in  CR  has  one  screw  hole  displaced  by  a  few  mm.    • Indexing  issue  solved  • Fluctuation  higher  in  UT4    

Page 14: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

14/18   ESPRESSO  Project  

Plan  for  25-­08  

1. Check  availability  of  contratists  2. UT3  clock  alignment    3. Z  alignment  according  to  measurement  4. Marking  of  the  holes  of  UT3  in  CCL  5. Check  of  UT1,  UT2  and  UT4  6. Marking  plate  position  of  UT1,  UT2  and  UT4  7. Start  drilling  of  plates  holes  8. Acquire  the  height  of  optical  axis  plane  9. @20.30:  seminar  of  Gerardo  on  optical  fibers  

3.6    Monday  August  25th    

Debriefing  

• Check  availability  of  contratists  (Done)  • UT3  clock  alignment  (Done)  • Z  alignment  according  to  measurement  (Done)  • Marking  of  the  holes  of  UT3  in  CCL  (Done)  • Check  of  UT1,  UT2  and  UT4  (Done)  • Mark  of  plates  of  UT1,  UT2  and  UT4  (Done)  • Start  drilling  of  plates  hole  (Done)  • Acquire  the  height  of  optical  axis  plane  (Done)  • @20:30  seminar  of  Gerardo  on  optical  fibers  (Done,  very  nice  demonstrations)  • Goodbye  to  Matteo  (Done)  • Marking  of  plate  position  of  plates  for  plan  C  (Done)  

Issue  of  the  day:  

• Repeatability  of  PRS200  procedure:  to  be  (re-­‐)defined  

Plan  for  26-­08  

1. Start  drilling  with  the  hole  saw  2. Drill  and  fix  UT3  frames  3. 10:00  meeting  with  Paranal  engineers  to  present  and  discuss  the  CT  CREs.  4. Assemble  structure  to  hold  plates  

3.7    Tuesday  August  26th  

Debriefing  

• Start  drilling  with  the  hole  saw  (UT4  and  UT3  done)  • Drill  and  fix  UT3  frames  (Drilling  done,  without  fixing)  • 10:00  meeting  with  Paranal  engineers  to  present  and  discuss  the  CT  CREs  (Done)  

Page 15: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   15/18    

• MPO  remarks  that  threaded  holes  in  the  ducts  would  be  preferable  to  stud  welds  for  attaching  the  covers,  as  they  are  curved.  

• Route  the  cabling  of  the  P7  below  CR  ceiling  rather  than  above  inner  track  floor.  This  implies  not  to  prepare  the  cables  now.  

• SGU  remarked  that  the  change  of  Gerardo  periscope  from  prisms  to  mirrors  should  have  been  also  presented  to  him,  as  a  reviewer  of  the  optics,  and  as  he  will  have  to  make  the  maintenance  of  that.  To  be  followed  and  clarified  with  GLC.  

• The  front  cover  of  P6  was  discussed  and  the  problem  of  the  possible  omission  to  remove  it  after  intervention  was  mentioned  by  MPO.  There  should  be  either  something  automatic  or  a  clear  procedure  to  be  put  in  place  for  this.  

• Assemble  structure  to  hold  plates  (Done)  • Received  Hilti  material  

Issue  of  the  day:  

• Perpendicular  iron  rod  into  the  holes  non  removable  so  decision  taken  to  shorten  sleeves  because  it  will  not  be  possible  to  remove  this  iron  to  9.5  cm.  

• Sleeves  too  big  for  the  holes,  they  will  need  to  be  adjusted.  

Plan  for  27-­08  

1. Test  of  chemical  pumping  2. Adjustment  of  the  sleeves  3. Fixation  of  UT3  and  UT4  frames  4. Completion  of  holes  for  UT1  and  UT2  5. Fixation  of  UT1  and  UT2  frames  if  holes  drilled.  

3.8    Wednesday,  August  27th  

Debriefing  

• Adjustment  of  the  sleeves  (Done  for  UT2,  UT3  and  UT4)  • Fixation  of  UT4  flanges  (Done)  • Fixation  of  UT3  flange  (Done)  • Completion  of  holes  in  UT2  (Done)  • Fixation  of  UT2  flange  (Done)  • Test  of  chemical  pumping  (not  needed)  

Issue  of  the  day:  

• Remaking  of  UT3  short  sleeves,  the  first  cut  didn’t  hold.  It  is  a  good  lesson  learned  for  the  UT1  ones  

Plan  for  28-­08  

1. Finish  holes  in  UT1  2. Adjustment  of  UT1  sleeves  

Page 16: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

16/18   ESPRESSO  Project  

3. Fixation  of  UT1  4. Laser  tracking  of  flanges  5. Protect  and  cover  the  structure  and  the  pentaprism  6. Glue  labels  7. Start  to  order  the  mess  8. I/F  meeting  9. Prepare  software  for  toggling  and  laser  guiding  

3.9    Thursday,  August  28th  

Debriefing  

• Finish  holes  in  UT1  (Done)  • Adjustment  of  UT1  sleeves  (Done)  • Fixation  of  UT1  (Done)  • Laser  tracking  of  flanges  (Done)  • Protect  and  cover  the  structure  and  the  pentaprism  (Done  on  the  pentaprism,)  • Glue  labels  (will  be  done  in  a  next  mission,  after  the  silicon  has  been  put)  • Start  to  order  the  mess  (started)  • I/F  meeting  (postponed  to  the  guesthouse)  • Prepare  software  for  toggling  and  laser  guiding  (started)  

Issue  of  the  day:  

• Collect  enough  bread  for  the  evening  fondue,  where  were  invited  the  contratists.  

Plan  for  29-­08  

1. Cover  the  structure  2. Finish  to  order  stuff,  empty  the  CCL,  clean  everywhere  

3.10    Friday,  August  29th  

Debriefing  

• CCL  was  emptied,  with  the  help  of  the  contratists.  • Structure  covering  and  feet  protected  • LFC  room  was  ordered  and  cleaned  • Trip  to  Santiago  for  the  whole  crew.  

3.11    Things   raised   pending   on   decision   or   investigated   during  the  mission    

• Keep  under  control  the  hole  drilling  strategy:  hybrid  solution  was  chosen  (12  mm  holes  and  mechanical  sleeves  where  possible,  16mm  holes  and  chemical  ones  in  case  of  iron)  

Page 17: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

VLT-­‐MIN-­‐ESP-­‐13520-­‐0186,  Issue  1.0   17/18    

Hybrid  solution  is  not  working  due  to  the  low  accuracy  of  drilling  with  normal  driller,  we  decided  to  come  back  to  the  full  16mm  solution  for  the  UT1,  UT2  and  UT4.  UT3  is  only  a  closing  frames,  positioning  is  not  sensitive,  so  we  used  it  for  the  tests  and  will  leave  an  hybrid  solution.  

 

Page 18: VLT-MIN-ESP-13520-0186 MissionVII Paranal 201408 - UNIGE · 6/18! ESPRESSOProject! 1.2.1 Applicable!Documents! AD61& ESPRESSO!Statement!of!Work! VLT1SOW1ESO11352015059! 1! 01.02.2011!

18/18   ESPRESSO  Project  

Chapter  4.     Conclusions  of  the  mission    The  preparatory  work  for  ESPRESSO  in  the  Observatory  infrastructure  is  multifold  and  touches  a  lot  of  different  locations  in  the  Observatory.  Mainly  the  Combined  Coudé  Laboratory  (CCL),  the  incoherent  light  ducts  to  the  four  UT,  the  four  Coudé  Rooms  (CR)  and  the  structure  of  the  four  UTs.    This  mission  intended  to  touch  only  the  CCL  and  to  achieve  the  following  goals:  

• Install  the  front-­‐end  structure,  align  it.  • Use  the  rotary  stage  of  the  toggling  mechanism  to  shine  the  alignment  laser  in  the  ducts  to  

precisely  define  the  center  of  the  L11  flanges.  • Mark  and  drill  the  holes  for  these  flanges  and  install  them.  

These  three  goals  were  fully  achieved.      Several  Change  Requests  (CRE)  were  submitted  to  the  Observatory  to  adapt  the  infrastructure  of  the  CCL.  They  were  approved  in  early  summer  2014,  and  several  have  already  been  achieved  by  LPO  staff  before  the  first  mission  in  July:  modification  of  the  lights,  relocation  of  the  fire  extinguisher.  In  addition,  LPO  civil  contratists  have  prepared  a  plastic  separation  of  the  CCL  to  allow  civil  work  to  be  done  cleanly    and  without  dust  contamination  of  the  present  instrumentation.  Several  others  have  been  achieved  during  the  July  mission  and  this  one.    The  remainings  will  be  achieved  in  September  by  LPO  staff  and  contracted  enterprise  (pouring  resin  on  the  ground  of  the  CCL),  and  after  the  installation  of  the  thermal  enclosures  foreseen  in  November  (separation  of  the  lights  located  in  the  1T  part  of  the  laboratory).    This  mission  was  very  fruitful,  and  we  must  thank  all  the  involved  people,  consortium  staff  members  that  prepared  properly  the  mission,  found  alternatives  when  problems  were  encountered  and  just  did  the  job  with  efficiency  and  professionalism.    We  also  have  to  underline  the  very  good  collaboration  and  support  we  got  when  needed  from  Paranal  staff,  and  particularly  Paranal  contratists.  Particular  thanks  to  Gaspare  Lo  Curto,  who  acts  very  efficiently  as  our  interface  with  the  Observatory  as  well  as  to  Hermann  Barrios  and  Oscar  Diaz,  who  managed  the  civil  work.